Issue date | Title | Topic | |
---|---|---|---|
ML20217A086 | 30 April 1998 | Ei Hatch Nuclear Plant,Units 1 & 2,Process for Implementing Technical Requirements of 10CFR54,License Renewal Rule | Safe Shutdown Fire Barrier Anticipated operational occurrence Coatings Incorporated by reference B.5.b Aging Management Fire Protection Program |
ML20138G627 | 19 December 1996 | Rev 11 to ODCM for Ei Hatch Nuclear Plant | |
ML20093G940 | 5 October 1995 | Inservice Insp Program Third 10-Year Interval for Ei Hatch Nuclear Plant Units 1 & 2 | |
ML20092H646 | 24 July 1995 | Ei Hatch Nuclear Plant Units 1 & 2 IST Program | |
ML20086E847 | 19 June 1995 | Rev 0 to Field Disposition Instruction (Fdi) HT2-0121-12900. Fdi Documents Design Requirements & Matl Required to Install Stabilizers for Shroud Horizontal Welds | |
ML20086E831 | 9 June 1995 | Rev 0 to Fabrication Spec 25A5719, Fabrication of Shroud Stabilizer | Nondestructive Examination Liquid penetrant |
ML20086E814 | 6 June 1995 | Rev 1 to Code Design Spec 25A5717, Shroud Stabilizers | Earthquake |
ML20086E812 | 17 May 1995 | Rev 0 to Design Spec 25A5718, Shroud Repair Hardware | Design basis earthquake Earthquake Liquid penetrant |
ML20106A652 | 29 February 1992 | Proposed Rev 3 to Ei Hatch Nuclear Plant Solid Radwaste PCP, Per GL 89-01 | Offsite Dose Calculation Manual Process Control Program |
ML20106A650 | 7 February 1992 | Rev 7 to Ei Hatch Nuclear Plant ODCM, Reflecting Proposed Changes,Per GL 89-01 | Grab sample Offsite Dose Calculation Manual Hydrostatic Annual Radiological Environmental Operating Report Process Control Program Power change |
ML20056B303 | 1 August 1990 | Ei Hatch Nuclear Plant,Units 1 & 2 Inservice Insp Program Second 10-Yr Interval | Stroke time Weld Overlay Hydrostatic Nondestructive Examination VT-2 Scram Discharge Volume Cold shutdown justification Power-Operated Valves Power Operated Valves Liquid penetrant Scaffolding |
ML20149N114 | 4 January 1988 | Revised Second 10-Yr Interval Inservice Insp Program,1980 Edition of ASME Section XI W/Addenda Through Winter 1981 | Stroke time Weld Overlay Hydrostatic Nondestructive Examination VT-2 Cold shutdown justification Power-Operated Valves Power Operated Valves Liquid penetrant |
ML20211H549 | 20 February 1987 | IGSCC-Susceptible Primary Pressure Boundary Stainless Steel Piping & Components Insp/Mitigation Program, 1987 Maint/Refueling Outage | Weld Overlay Liquid penetrant |
ML20245B830 | 10 December 1986 | Rev 0 to SO-OPS-05-1286, Spent Fuel Pool Transfer Canal Gates | |
ML20245B817 | 5 December 1986 | Rev 0 to SO-OPS-02-1286, Processing of Water from Yard Drains | |
ML20245B820 | 5 December 1986 | Rev 0 to SO-OPS-01-1286, Radwaste Discharges. Supporting Documentation Encl | Chernobyl Power change |
ML20203L929 | 1 August 1986 | Rev 0 to Training Procedure 72TR-TRN-002-0S, License Requalification Training Program | Fuel cladding Power change |
ML20137V903 | 5 December 1985 | Rev 1 to Emergency Implementing Procedure 62RP-RAD-009-05, Airborne Radioactivity Concentration Determination | |
ML20076J187 | 8 November 1985 | Rev 2 to Technical Note 20684-EIH, Thermo-Lag 330 Fire Barrier Sys Installation Procedures Manual Prepared for Bechtel Power Corp for Georgia Power Co | Fire Barrier Coatings FLEX |
ML20076J191 | 4 November 1985 | Rev 1 to Technical Note 20684-EIH, Thermo-Lag 330 Fire Barrier Sys Installation Procedures Manual Prepared for Bechtel Power Corp,For Georgia Power Co | Fire Barrier Coatings FLEX |
ML20076J196 | 23 October 1985 | Rev 0 to Technical Note 20684-EIH, Thermo-Lag 330 Fire Barrier Sys Installation Procedures Manual Prepared for Bechtel Power Corp,For Georgia Power Co | Fire Barrier Coatings FLEX |
ML20135F316 | 26 August 1985 | Rev 1 to Emergency Operating Procedures Implementation Plan for Emergency Response Capability Project | Reactor Vessel Water Level |
ML20132E547 | 23 August 1985 | Rev 0 to Engineering Svc Procedure 42EN-ENG-011-OS, Scram/ Transient Reporting | Scram Discharge Volume |
ML20209F239 | 1 July 1985 | Recirculation,Rhr & Reactor Water Cleanup Sys Piping Weld Joint Insp/Mitigation Program for 1985 Maint/ Refueling Outage | Weld Overlay Liquid penetrant |
ML20128A056 | 25 June 1985 | Inservice Insp Program,1980 Edition of ASME Section XI W/Addenda Through Winter 1981 | Safe Shutdown Stroke time Weld Overlay Hydrostatic Nondestructive Examination VT-2 Power Operated Valves Liquid penetrant |
ML20126E833 | 11 June 1985 | Emergency Plan Implementing Procedures & Deleted Title Sheets,Including Procedures HNP-8007 Re Decontamination of Clothing & Hats & HNP-8004 Re Dosimetry Issuance & Tracking | Process Control Program |
ML20116D440 | 23 April 1985 | Revised Emergency Procedures HNP-8109 Re Continuous Air Monitors Models AM-3D & AM-33-1,HNP-8122 Re Radiation Monitor Model RM-16 & HNP-8146 Re Rascal Portable Rate Meter-Scaler/Model PRS-1 Operation & Calibr | |
ML20245B791 | 17 April 1985 | Rev 0 to 10AC-MGR-04-0, Deficiency Control Sys. Supporting Documentation Encl | |
ML20107G142 | 15 February 1985 | Revised Emergency Implementing Procedures,Including Rev 3 to HNP-8161 Re Eberline Model PCM-1 Portable Monitor Operation & Calibr & Rev 2 to HNP-8036 Re Waste Classification & Manifest Reporting Resin Shipments | |
ML20215F737 | 26 December 1984 | Rev 1 to Administrative Control Procedure 40AC-FPX01-0, Fire Protection Program. Portions of Procedures 34AB-OPS-056-1S & 34AB-OPS-056-2S Encl | Safe Shutdown Fire Barrier Fire Protection Program Fire Watch |
ML20101B055 | 17 December 1984 | Rev 5 to Emergency Plan Implementing Procedure HNP-8134, Whole Body Counter Sys | |
ML20108E092 | 29 November 1984 | Rev 10 to Procedure Data Package HNP-1-3980-1, Kinemetrics SMA-3 | Safe Shutdown Operating Basis Earthquake Design basis earthquake Earthquake |
ML20107H570 | 31 October 1984 | Detailed Control Room Design Review Program Plan | Safe Shutdown Reactor Vessel Water Level Nondestructive Examination |
ML20155C896 | 30 September 1984 | Rev 1 to Offsite Dose Calculation Manual | Grab sample Offsite Dose Calculation Manual |
ML20155C884 | 30 September 1984 | Rev 1 to Solid Radwaste Process Control Program | Process Control Program |
ML20098G340 | 30 September 1984 | Offsite Dose Calculation Manual | Grab sample Offsite Dose Calculation Manual |
ML20098G338 | 30 September 1984 | Solid Radwaste Process Control Program | Process Control Program |
ML20108E074 | 13 June 1984 | Rev 10 to Procedure HNP-1-3980-M, Seismic Instrumentation Functional Test & Calibr | Earthquake |
ML20084H497 | 1 May 1984 | Rev 0 to Procedures Generation Package for Emergency Operating Procedures,Including plant-specific Technical Guidelines for Units 1 & 2,plant-specific Writers Guide & Implementation Plan for Emergency Response Project | Reactor Vessel Water Level Scram Discharge Volume |
ML20086U413 | 29 February 1984 | Vendor Equipment Technical Info Program, Per Generic Ltr 83-28,Section 2.2.2,final Draft | Safe Shutdown Probabilistic Risk Assessment |
ML20087N910 | 26 January 1984 | Public Version of Transmittal & Title Page to Deleted Emergency Plan Implementing Procedures,Including Procedure HNP-8031 Re Determination of Specific Activity of Spent Resin & Curie Contents of Liner & 840322 Memo | |
ML20087M791 | 25 January 1984 | Public Version of Transmittal & Title Pages of Deleted Emergency Plan Implementing Procedures HNP-8019, Insp of Steel Radwaste Shipping Drums & HNP-8422, Handling & Loading of Chem-Nuclear Cask & 840322 Memo | |
ML20087M932 | 20 January 1984 | Public Version of Rev 7 to Emergency Plan Implementing Procedure HNP-8101, Teletector Model 6112B/D Operation & Calibr & Jm Felton 840322 Release Memo | |
ML20081B673 | 18 January 1984 | Public Version of Rev 0 to Emergency Plan Implementing Procedure HNP-8161, Eberline Model PCM-1 Portal Monitor & Rev 17 to HNP-8008, Radiation Work Permit & Jm Felton 830307 Release Memo | |
ML20087P019 | 13 January 1984 | Public Version of Revised Emergency Plan Implementing Procedures,Including Procedures HNP-8038 Re Waste Classification & Manifest Reporting & HNP-8042 Re Radiological Work Practices & 840326 Memo | |
ML20079H901 | 7 December 1983 | Public Version of Revised Emergency Plan Implementing Procedures,Including Procedures HNP-8035 Re Pulmonary Function Screening Program & HNP-8016 Re Shipment of Radioactive Matl | |
ML20093D488 | 31 October 1983 | Public Version of Revised Emergency Plan Implementing Procedures,Including HNP-4858, Naturally Occurring Phenomenon & HNP-8108, Pocket Dosimeter Use & Performance Test. W/831031 & 840709 Release Memo | High winds Earthquake Scaffolding Power change |
ML20108E049 | 28 October 1983 | Rev 4 to Procedure HNP-4858, Naturally Occurring Phenomenon | High winds Earthquake Scaffolding Power change |
ML20080L065 | 12 October 1983 | Rev 1 to Procedure HNP-4848, Determination of Extent of Core Damage Under Accident Conditions | Reactor Vessel Water Level Fuel cladding |
ML20081L946 | 12 October 1983 | Public Version of Revised Emergency Plan Implementing Procedures,Including Procedures HNP-4827 Re Offsite Radiological Environ Monitoring During Emergencies & HNP-4852 Re Offsite Dose Estimation |