ML22209A060 | 28 July 2022 | 2022 Inservice Inspection Summary Report | |
GNRO-2021/00014, Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency | 1 June 2021 | Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency | Missed surveillance Power-Operated Valves |
GNRO-2019/00014, Snubber Testing Program for Fourth Inspection Interval | 13 March 2019 | Snubber Testing Program for Fourth Inspection Interval | |
GNRO-2018/00054, Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval | 30 November 2018 | Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval | Nondestructive Examination VT-2 Liquid penetrant Pressure Boundary Leakage |
GNRO-2018/00047, Submittal of 2018 Inservice Inspection Summary Report | 16 October 2018 | Submittal of 2018 Inservice Inspection Summary Report | |
GNRO-2017/00039, Steam Dryer Visual Inspection Results for the First Two Scheduled Refueling Outages | 30 June 2017 | Steam Dryer Visual Inspection Results for the First Two Scheduled Refueling Outages | |
GNRO-2016/00033, Submittal of 2016 Inservice Inspection Summary Report | 20 June 2016 | Submittal of 2016 Inservice Inspection Summary Report | Squib FLEX |
GNRO-2014/00043, Inservice Inspection Summary Report | 12 June 2014 | Inservice Inspection Summary Report | |
GNRO-2012/00110, Submittal of Inservice Inspection Summary Report | 11 September 2012 | Submittal of Inservice Inspection Summary Report | Weld Overlay Finite Element Analysis |
GNRO-2009/00070, Supplement to Request to Use Portion of Later Edition to the American Society of Mechanical Engineers Code for Operation and Maintenance of Nuclear Power Plants for Main Steam Safety Relief Valve Inservice Testing | 14 December 2009 | Supplement to Request to Use Portion of Later Edition to the American Society of Mechanical Engineers Code for Operation and Maintenance of Nuclear Power Plants for Main Steam Safety Relief Valve Inservice Testing | Incorporated by reference |
CNRO-2009-00002, Relief Request CEP-ISI-011 for Third 120 Month Inservice Inspection Interval | 4 March 2009 | Relief Request CEP-ISI-011 for Third 120 Month Inservice Inspection Interval | |
GNRO-2009/00004, Inservice Inspection Summary Report | 19 January 2009 | Inservice Inspection Summary Report | |
GNRO-2008/00071, Inservice Inspection (ISI) Program Third 10-Year Interval, Rev. 0 | 29 October 2008 | Inservice Inspection (ISI) Program Third 10-Year Interval, Rev. 0 | Hydrostatic Nondestructive Examination VT-2 Incorporated by reference Aging Management Large early release frequency Scaffolding |
GNRO-2008/00057, Transmittal of Inservice Inspection Program Third 10-Year Interval, Revision 0 | 31 July 2008 | Transmittal of Inservice Inspection Program Third 10-Year Interval, Revision 0 | |
ML081570002 | 27 June 2008 | Relief Request GGNS-ISI-004 to Extend 2nd 10-Year Inservice Inspection Interval 4 Months Beyond 1-year Extension Allowed by ASME Code | Incorporated by reference Dissimilar Metal Weld DM weld |
CNRO-2008-00016, Relief Requests for Third 120 Month Inservice Testing Interval | 20 May 2008 | Relief Requests for Third 120 Month Inservice Testing Interval | Hydrostatic Nondestructive Examination VT-2 Scaffolding |
1CAN030804, Revised Relief Request for 10 Year Update to the 120 Month Inservice Testing Interval, Arkansas Nuclear One, Unit 1 | 13 March 2008 | Revised Relief Request for 10 Year Update to the 120 Month Inservice Testing Interval, Arkansas Nuclear One, Unit 1 | Safe Shutdown Ultimate heat sink |
CNRO-2007-00044, Unit 1 and Arkansas Nuclear One, Units 1 & 2 - Inservice Testing Plan | 30 November 2007 | Unit 1 and Arkansas Nuclear One, Units 1 & 2 - Inservice Testing Plan | Safe Shutdown Boric Acid High Radiation Area Ultimate heat sink Stroke time Abnormal operational transient Cold shutdown justification Power-Operated Valves Power Operated Valves Scaffolding Unidentified leakage |
CNRO-2007-00042, Entergy Operations, Inc. - Relief Requests for 10 Year Updates to the 120 Month Inservice Testing Intervals | 29 November 2007 | Entergy Operations, Inc. - Relief Requests for 10 Year Updates to the 120 Month Inservice Testing Intervals | Safe Shutdown Ultimate heat sink |
GNRO-2007/00046, Inservice Inspection Summary Report | 10 July 2007 | Inservice Inspection Summary Report | |
GNRO-2006/00044, Corrections to Inservice Inspection Summary Report | 10 August 2006 | Corrections to Inservice Inspection Summary Report | |
GNRO-2006/00002, Lnservice Inspection Summary Report for Grand Gulf Nuclear Station Unit 1 | 13 January 2006 | Lnservice Inspection Summary Report for Grand Gulf Nuclear Station Unit 1 | |
GNRO-2004/00019, Transmittal of Inservice Inspection Summary Reports | 8 March 2004 | Transmittal of Inservice Inspection Summary Reports | Hydrostatic VT-2 |
ML040490179 | 18 December 2003 | to CEP-IST-2, Inservice Testing Plan, Entergy Nuclear South Central Engineering Programs | |
GNRO-2003/00022, Boiling Water Reactor (BWR) Feedwater Nozzle Inservice Inspection Report for Grand Gulf Nuclear Station | 2 April 2003 | Boiling Water Reactor (BWR) Feedwater Nozzle Inservice Inspection Report for Grand Gulf Nuclear Station | |
CNRO-2003-00009, Entergy Operations, Referenced Paper for Request to Use ASME Code Case N-663 | 14 March 2003 | Entergy Operations, Referenced Paper for Request to Use ASME Code Case N-663 | |