ML23283A031 | 9 October 2023 | Inservice Testing Program for Pumps and Valves - Part 9: IST Program Refueling Outage Justifications Rev. 4 | Stroke time Time to boil |
NRC-23-0063, Inservice Testing Program for Pumps and Valves - Part 12: IST Program Pump Basis Revision 1 | 9 October 2023 | Inservice Testing Program for Pumps and Valves - Part 12: IST Program Pump Basis Revision 1 | Safe Shutdown Reactor Vessel Water Level Ultimate heat sink Hydrostatic Earthquake Fuel cladding |
ML23283A034 | 9 October 2023 | Inservice Testing Program for Pumps and Valves - Part 11: IST Program Valve Basis Revision 1 | Safe Shutdown Shutdown Margin Reactor Vessel Water Level Loop seal Ultimate heat sink Stroke time Squib FLEX Scram Discharge Volume |
ML23283A032 | 9 October 2023 | Inservice Testing Program for Pumps and Valves - Part 10: IST Program Technical Positions Revision 2 | Safe Shutdown Stroke time |
ML23283A030 | 9 October 2023 | Inservice Testing Program for Pumps and Valves - Part 8: IST Program Cold Shutdown Justifications Rev. 4 | Safe Shutdown Stroke time Cold shutdown justification |
ML23283A029 | 9 October 2023 | Inservice Testing Program for Pumps and Valves - Part 7: IST Program Relief Request Revision 3 | Stroke time Hydrostatic Incorporated by reference Breakaway torque Power Operated Valves Hardened vent Grace period |
ML23283A028 | 9 October 2023 | Inservice Testing Program for Pumps and Valves - Part 6: IST Check Valve Condition Monitoring Plans Rev. 3 | Safe Shutdown Packing leak Ultimate heat sink Stroke time Anchor Darling Temporary Modification |
ML23283A027 | 9 October 2023 | Inservice Testing Program for Pumps and Valves - Part 5: IST Valve Scope Table Revision 4 | Squib |
ML23283A026 | 9 October 2023 | Inservice Testing Program for Pumps and Valves - Part 4: IST Valve Testing Program (Revision 3) | Safe Shutdown Stroke time Cold shutdown justification |
ML23283A023 | 9 October 2023 | Inservice Testing Program Fourth Ten-Year Interval | Safe Shutdown Cold shutdown justification |
ML23283A025 | 9 October 2023 | Inservice Testing Program for Pumps and Valves - Part 3: IST Pump Scope Table (Revision 4) | |
ML23283A024 | 9 October 2023 | Inservice Testing Program for Pumps and Valves - Part 2: IST Pump Testing Program (Revision 3) | |
NRC-23-0056, Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval | 31 August 2023 | Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval | Safe Shutdown Cold shutdown justification |
NRC-23-0030, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval | 5 June 2023 | Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval | Non-Destructive Examination Weld Overlay Hydrostatic Probabilistic Risk Assessment Coatings Nondestructive Examination VT-2 Incorporated by reference Aging Management Scram Discharge Volume Moisture barrier Earthquake Liquid penetrant Dissimilar Metal Weld |
NRC-23-0029, Snubber Program for the Fourth 10-Year Testing Interval | 5 June 2023 | Snubber Program for the Fourth 10-Year Testing Interval | Safe Shutdown High Radiation Area Scaffolding |
NRC-20-0064, Inservice Inspection Summary Report | 3 November 2020 | Inservice Inspection Summary Report | Finite Element Analysis |
NRC-20-0012, Submittal of Valve Relief Requests VRR-010 and VRR-011 for the Inservice Testing Program Fourth 10-Year Interval | 24 January 2020 | Submittal of Valve Relief Requests VRR-010 and VRR-011 for the Inservice Testing Program Fourth 10-Year Interval | Stroke time |
NRC-19-0047, Submittal of Valve Relief Requests for the Inservice Testing Program Fourth 10-Year Interval | 14 June 2019 | Submittal of Valve Relief Requests for the Inservice Testing Program Fourth 10-Year Interval | Stroke time Scram Discharge Volume Power Operated Valves Hardened vent |
NRC-19-0025, Submittal of Valve Relief Requests for the Inservice Testing Program Fourth 10-Year Interval | 29 May 2019 | Submittal of Valve Relief Requests for the Inservice Testing Program Fourth 10-Year Interval | Stroke time Hydrostatic Grace period |
NRC-19-0015, Submittal of Pump Relief Requests for the Inservice Testing Program Fourth 10-Year Interval | 27 March 2019 | Submittal of Pump Relief Requests for the Inservice Testing Program Fourth 10-Year Interval | |
NRC-19-0016, Submittal of the Inservice Inspection / Nondestructive Examination Program Relief Requests for the Fourth Ten-year Interval | 28 February 2019 | Submittal of the Inservice Inspection / Nondestructive Examination Program Relief Requests for the Fourth Ten-year Interval | Hydrostatic Nondestructive Examination VT-2 Finite Element Analysis Aging Management EVT-1 Pressure Boundary Leakage Pressure boundary leak Through-Wall Leak Weak link |
NRC-19-0010, Inservice Inspection Summary Report for Activities Performed at DTE Electric Company'S (DTE) Fermi 2 Nuclear Power Plant During the 19th Refueling Outage in Fall 2018 | 23 January 2019 | Inservice Inspection Summary Report for Activities Performed at DTE Electric Company'S (DTE) Fermi 2 Nuclear Power Plant During the 19th Refueling Outage in Fall 2018 | |
NRC-17-0081, Supplement to Revised Relief Request No. RR-A37, Revision 1, for the Inservice Inspection Program Third 10-Year Interval | 8 December 2017 | Supplement to Revised Relief Request No. RR-A37, Revision 1, for the Inservice Inspection Program Third 10-Year Interval | |
NRC-17-0047, Inservice Inspection Summary Report | 17 July 2017 | Inservice Inspection Summary Report | |
ML16189A218 | 29 June 2016 | BWR Vessel and Internals Project - Vessel Internals Inspection Summaries for Fall 2015 Outages | Weld Overlay VT-2 EVT-1 Pressure Boundary Leakage Dissimilar Metal Weld DM weld |
NRC-16-0001, Request for Relief from ASME OM Code 5-Year Test Interval | 16 March 2016 | Request for Relief from ASME OM Code 5-Year Test Interval | Grace period |
ML16053A185 | 22 February 2016 | Inservice Inspection Summary Report for 17th Refueling Outage in Fall 2015 | |
NRC-15-0027, Submittal of Inservice Testing Program Relief Request PRR-012 for Quarterly Test of Core Spray Pumps | 5 March 2015 | Submittal of Inservice Testing Program Relief Request PRR-012 for Quarterly Test of Core Spray Pumps | |
NRC-14-0024, Inservice Inspection Summary Report | 2 July 2014 | Inservice Inspection Summary Report | |
NRC-13-0040, Submittal of Inservice Testing Program Relief Request PRR-011, for the Third Ten-Year Interval | 7 August 2013 | Submittal of Inservice Testing Program Relief Request PRR-011, for the Third Ten-Year Interval | |
NRC-12-0052, Inservice Inspection Summary Report | 1 August 2012 | Inservice Inspection Summary Report | |
ML12272A055 | 18 May 2012 | Inservice Testing Program, Third Ten-Year Interval, Third Interval Start - February 17, 2010 | Safe Shutdown Packing leak High Radiation Area Ultimate heat sink Stroke time Time to boil Anchor Darling Squib Incorporated by reference Missed surveillance Scram Discharge Volume Cold shutdown justification Grace period |
NRC-11-0006, Inservice Inspection Summary Report During Refueling Outage 14 | 23 February 2011 | Inservice Inspection Summary Report During Refueling Outage 14 | |
NRC-10-0033, Response to Request for Additional Information Regarding Relief Requests PRR-002 and PRR-003 for the Inservice Testing Program Third Ten-Year Interval | 22 April 2010 | Response to Request for Additional Information Regarding Relief Requests PRR-002 and PRR-003 for the Inservice Testing Program Third Ten-Year Interval | |
NRC-10-0004, Submittal of the Inservice Inspection / Nondestructive Examination Program Relief Requests for the Third Ten-year Interval | 20 January 2010 | Submittal of the Inservice Inspection / Nondestructive Examination Program Relief Requests for the Third Ten-year Interval | Mission time Internal Flooding Hydrostatic Probabilistic Risk Assessment Nondestructive Examination VT-2 Large early release frequency Pressure boundary leak |
NRC-08-0012, Inservice Inspection Summary Report for 2007 | 15 February 2008 | Inservice Inspection Summary Report for 2007 | |
NRC-06-0054, Inservice Inspection Summary Report | 2 August 2006 | Inservice Inspection Summary Report | Hydrostatic Coatings Nondestructive Examination VT-2 Scram Discharge Volume Moisture barrier EVT-1 Liquid penetrant Dissimilar Metal Weld DM weld |
NRC-05-0023, Request to Use Later Edition and Addenda of the ASME OM Code for Pressure Relief Valve Testing | 15 April 2005 | Request to Use Later Edition and Addenda of the ASME OM Code for Pressure Relief Valve Testing | Incorporated by reference |
NRC-05-0010, Inservice Inspection Summary Report for 2004 | 25 February 2005 | Inservice Inspection Summary Report for 2004 | Hydrostatic Coatings Anchor Darling Nondestructive Examination VT-2 Scram Discharge Volume Moisture barrier EVT-1 Liquid penetrant Dissimilar Metal Weld DM weld |
NRC-03-0061, Inservice Inspection Summary Report | 8 August 2003 | Inservice Inspection Summary Report | Hydrostatic Anchor Darling Nondestructive Examination VT-2 Scram Discharge Volume Moisture barrier EVT-1 Liquid penetrant Dissimilar Metal Weld DM weld |
NRC-02-0012, Detroit Edison'S Submittal of Inservice Inspection Summary Report for Fermi 2 | 28 February 2002 | Detroit Edison'S Submittal of Inservice Inspection Summary Report for Fermi 2 | Hydrostatic Nondestructive Examination VT-2 Scram Discharge Volume Moisture barrier EVT-1 Liquid penetrant Dissimilar Metal Weld DM weld |