ML20207E663 | 28 January 1999 | Rev 0 to EMECH-0713-1, Operational Assessment of SG Tubing at Beaver Valley Unit 1,Cycle 13 | Nondestructive Examination |
ML20198B902 | 31 December 1998 | BVPS Unit 1 Simulator Four Yr Certification Rept for 1995-1998 | Boric Acid Main transformer failure |
ML20154D500 | 30 September 1998 | Special Rept on Overview of BVPS-1 & BVPS-2 TS Compliance Issues & Corrective Action Taken | Missed surveillance |
ML20155B587 | 28 August 1998 | Non-proprietary Rev 1 to 51-5001925-01, Risk Assessment for Installation of Electrosleeves at BVPS & Callaway Plant | |
ML20135D426 | 31 January 1997 | Criticality Analysis of Beaver Valley Unit 1 Fresh Fuel Racks | Offsite Dose Calculation Manual |
ML20236W741 | 30 December 1996 | Rev 1,change 1 to Performance Demonstration Initiative (PDI) Program Description | Dissimilar Metal Weld |
ML20196B895 | 16 December 1996 | First Amended & Restated Master Decommissioning Trust Agreement Dtd as of 961216 Between Cleveland Electric Illuminating Co & Mellon Bank | |
ML20196B877 | 16 December 1996 | First Amended & Restated Master Decommissioning Trust Agreement Dtd as of 961231 Between Toledo Edison Co & Mellon Bank | |
ML20195C989 | 4 October 1996 | BVPS-2 Containment Penetrations Overpressure Protection Analysis/Review Rept | |
ML20116J077 | 31 July 1996 | Rev 1 to Beaver Valley Unit 1 1996 Alternate Repair Criteria 90 Day Rept | |
ML20116H982 | 30 June 1996 | Fitness-For-Duty Program for Jan-June 1996 | Fitness for Duty |
ML20097C837 | 31 January 1996 | USI A-46 Seismic Evaluation Rept for BVPS Unit 1 | |
ML20097C843 | 31 January 1996 | USI A-46 Relay Evaluation Rept for BVPS Unit 1 | |
ML20095J636 | 31 December 1995 | BVPS Unit 2 Simulator Four Yr Certification Rept 1992 - 1995 | Boric Acid Shutdown Margin |
ML20196B787 | 21 April 1995 | Pennsylvania Power Co Master Decommissioning Trust Agreement for Beaver Valley Power Station & Perry Nuclear Power Plant | |
ML20087G110 | 28 February 1995 | Interim Plugging Criteria Return to Power Ltr Rept | Boric Acid |
ML20080Q344 | 23 February 1995 | Protection Against Malevolent Use of Vehicles at Nuclear Power Plants | Safe Shutdown |
ML20078Q527 | 13 December 1994 | Simulator Four Yr Certification Rept 1991-94 | Boric Acid Main transformer failure |
ML20196B850 | 1 July 1993 | Ohio Edison Co Master Decommissioning Trust Agreement for Perry Nuclear Power Plant Unit One,Perry Nuclear Power Plant Unit Two,Beaver Valley Power Station Unit One & Beaver Valley Power Station Unit Two | |
ML17352A869 | 31 May 1993 | Technical Rept, Assessment of Aging Degradation of Civil/ Structural Features at Selected Operating Nuclear Power Plants. | Boric Acid Coatings Operating Basis Earthquake Tornado Missile Protection Earthquake |
ML20116G589 | 28 September 1992 | SFP Mod for Increased Storage Capacity BVPS Unit 1 | Safe Shutdown Earthquake Hydrostatic Operating Basis Earthquake Nondestructive Examination Finite Element Analysis Design basis earthquake Earthquake Control of Heavy Loads Fuel cladding |
ML20090M528 | 17 March 1992 | Rev 0 to PRA Individual Plant Exam Summary Rept | |
ML20100P958 | 27 January 1992 | Rev 0 to Assessment of Doses in Unit 2 Control Room Due to Locked Rotor Accident at Unit 2 Assuming 18% Failed Fuel | |
ML20090B308 | 31 December 1991 | Control Room X/Q Values for Beaver Valley Power Station | |
ML20087A166 | 30 December 1991 | Simulator Certification Rept,Beaver Valley Power Station, Unit 2 | Boric Acid Shutdown Margin Stroke time Emergency Lighting FLEX Earthquake |
ML20094G752 | 4 September 1991 | Offsite Dose Consequences of Locked Rotor Accident at Unit 2 w/18% Failed Fuel Analysis | |
ML20079L176 | 31 August 1991 | Plant Safety Evaluation for Beaver Valley Power Station, Unit 2,VANTAGE 5H Fuel Upgrade, for Aug 1991 | |
ML20079A967 | 31 May 1991 | Evaluation of Adequacy of Existing Neutron Flux Instrumentation for NUREG-0737,Suppl 1 | Shutdown Margin Post Accident Monitoring |
ML20067E400 | 17 January 1991 | Evaluation of Main Feedwater Piping Misalignment & Steam Generator Nozzle Cracking Final Rept | Unanalyzed Condition Loop seal Earthquake |
ML20066C486 | 18 December 1990 | Simulator Certification Rept | |
ML20077Q324 | 30 November 1990 | Development of Pressure-Temp Limit Curves for Loop Isolated from Reactor Vessel:Beaver Valley Units 1 & 2 | |
ML20246E828 | 4 May 1989 | Dcrdr Second Supplemental Summary Rept | Emergency Lighting |
ML20246K454 | 30 April 1989 | Plant Safety Evaluation for Beaver Valley Power Station Unit 1 Fuel Upgrade & Increased Peaking Factors. Related Info,Including Recommended Mods to Facility Fsar,Encl | Boric Acid Shutdown Margin Design basis earthquake Earthquake Fuel cladding Power change |
ML20065G872 | 23 August 1988 | Moisture Separator-Reheater Status Rept | |
ML20153G258 | 31 March 1988 | Criticality Analysis of Beaver Valley Unit 2 Fuel Racks | |
ML20195H737 | 5 January 1988 | Dcrdr Supplemental Rept | Boric Acid Emergency Lighting Backfit |
ML20239A011 | 30 June 1987 | Mellon Bank Corp 1987 Second Quarter Rept | |
ML20239A025 | 30 June 1987 | Pnc Financial Corp Rept to Shareholders Second Quarter 870630 | Safe Shutdown NJPDES Incorporated by reference Systematic Assessment of Licensee Performance Exemption Request Earthquake |
ML20239A006 | 30 June 1987 | First Chicago Corp 1987 Second Quarter Rept | |
ML20215D894 | 11 June 1987 | Technical Review Rept,Nrc Region I Insp 50-412/87-34,Review of Beaver Valley Power Station Unit 2 Tech Specs,Onsite Activities Conducted 870330-0410 | Safe Shutdown Boric Acid Ultimate heat sink Stroke time Power Operated Valves Offsite Circuit |
ML20214V192 | 31 May 1987 | Evaluation of RCS for Elimination of Primary Component Support Snubbers | Design basis earthquake Earthquake |
ML20214V195 | 31 May 1987 | RCS Leakage Detection Assessment for Elimination of RCS Main Loop Pipe Break Protective Devices | Boric Acid Pressure Boundary Leakage |
ML20214K349 | 11 May 1987 | Engineering Assurance Corrective Action Status Rept, In-Depth Technical Audits | |
ML20206E473 | 31 March 1987 | Nonproprietary Addl Info on Beaver Valley Power Station Unit 2 SER Confirmatory Issue 032 | |
ML20206T079 | 31 March 1987 | Amend 5 to Failure Modes & Effects Analyses Rept | |
ML20205F988 | 26 March 1987 | Rev 1 to Books 1-3 to Mechanical Equipment Qualification File 651-01, Environ Qualification of Mechanical Equipment | Hydrostatic |
ML20205G022 | 24 March 1987 | Rev 4 to Mechanical Equipment Qualification File 091-01 to Environ Qualification of Mechanical Equipment. W/Four Oversize Encls | |
ML20205G031 | 24 March 1987 | Rev 5 to Mechanical Equipment Qualification File 001-09 to Environ Qualification of Mechanical Equipment | Coast down |
ML20214R264 | 13 March 1987 | Draft SER Addressing Qualification & Documentation of Isolators as Acceptable Interface Devices Between Class 1E Instrumentation & non-Class 1E Spds,Per NUREG-0737,Suppl 1. Devices Acceptable | |
ML20207Q031 | 31 January 1987 | Dcrdr Supplemental Summary Rept | Emergency Lighting |