Semantic search

Jump to navigation Jump to search
 QuarterSiteTitle
05000461/FIN-2018050-022018Q2ClintonFailure to Promptly Identifya Condition Adverse to Quality
05000461/FIN-2018050-012018Q2ClintonFailure to Follow Multiple Procedure
05000461/FIN-2018050-032018Q2ClintonEquipment Operator Rounds Points Inadequate Acceptance Criteria
05000397/FIN-2017008-012017Q1ColumbiaOperators Fail To Follow Reactor Scram Procedure
05000397/FIN-2017008-022017Q1ColumbiaOperators Fail To Follow Procedure Causes RCIC Overspeed Trip
05000397/FIN-2017008-032017Q1ColumbiaInadequate Corrective Actions Causes Failure of HPCS Restricting Orifice Gasket
05000397/FIN-2016009-022017Q1ColumbiaFailure to Conduct Adequate Surveys of a Solid Radwaste Shipment
05000397/FIN-2016009-012017Q1ColumbiaShipment of a Type B Quantity of Radioactive Material in a Type A Package
05000397/FIN-2016009-032017Q1ColumbiaFailure to Label or Provide Written Information for Items Stored in the Spent Fuel Pool
05000397/FIN-2016009-042017Q1ColumbiaFailure to Provide an Accurate Shipping Manifest
05000397/FIN-2016009-052017Q1ColumbiaFailure of the QA program to assure compliance with 10 CFR 61.55 and 10 CFR 61.56
05000397/FIN-2016009-072017Q1ColumbiaFailure to Follow Procedure and Perform a Root Cause Evaluation to Assess the Causes of a Radwaste Shipping Event
05000397/FIN-2016009-082017Q1ColumbiaFailure to Transfer Byproduct Material to a Disposal Facility in Accordance with the Terms of the Facilitys License
05000397/FIN-2016009-092017Q1ColumbiaFailure to Minimize Void Spaces in a Radioactive Waste Package
05000397/FIN-2016009-062017Q1ColumbiaFailure to Update the Final Safety Analysis Report with Changes to Radioactive Waste Processing
05000458/FIN-2015010-042016Q1River BendFailure to Accomplish an Operability Determination In Accordance With Procedures
05000458/FIN-2015010-052016Q1River BendFailure to Identify and Correct an Adverse Condition in a Timely Manner
05000458/FIN-2016009-012016Q1River BendFailure to Follow Procedure While Installing Jumpers for Shutdown Cooling
05000458/FIN-2016009-042016Q1River BendFailure to Adequately Assess Risk During Motor Generator Set Unavailability
05000440/FIN-2016008-022016Q1PerryFailure to Provide Instructions to Completely Vent Reference Legs
05000440/FIN-2016008-032016Q1PerryHardcard Development Failed to Follow Procedure Change Process
05000440/FIN-2016008-042016Q1PerryFailure to Maintain Traceability of Safety Related Fuses
05000458/FIN-2015010-032016Q1River BendFailure to Identify and Correct Circuit Breaker Failure Mechanism
05000458/FIN-2016009-032016Q1River BendFailure to Implement Corrective Actions to Prevent the Recurrence of a Reactor Scram Due to Grid Disturbances
05000458/FIN-2016009-022016Q1River BendFailure to Establish Adequate Procedural Guidance
05000440/FIN-2016008-012016Q1PerryCoincidence Logic to Preclude Spurious Trips of the Offsite Power Source
05000458/FIN-2015010-022016Q1River BendFailure to Adequately Assess Risk During Chiller Unavailability
05000458/FIN-2015010-012016Q1River BendTechnical Specification Allowed Outage Time During Loss of Non-Technical Specification Supported Systems
05000269/FIN-2016008-012015Q4OconeePotential lack of adequacy of the licensees maintenance program to detect substantial degradation of cables and their connections used on Oconee large oil filled stationary transformers
05000336/FIN-2015012-012015Q4MillstoneFailure to Implement Procedural Guidance During a Loss of RCS Inventory
05000336/FIN-2015012-022015Q4MillstoneFailure of the STA to Support the Crew During a Plant Cooldown
05000336/FIN-2015012-032015Q4MillstoneProcedure Failed to Direct Adequate Venting of SDC System
05000483/FIN-2015009-012015Q4CallawayFailure to Verify the Suitability of the Design of the Reverse-Engineered Replacement Controller Cards for the Auxiliary Feedwater Flow Control Valves
05000483/FIN-2015009-022015Q4CallawayFailure to Have an Adequate Procedure for Calibration of the Auxiliary Feedwater Pump Flow Control Valve Potentiometer
05000483/FIN-2015009-032015Q4CallawayFailure to Have an Adequate Post-Maintenance Test for Setting the Motor-Driven Auxiliary Feedwater Flow Control Valve Modutronics Potentiometer
05000483/FIN-2015009-042015Q4CallawayTwo Examples of a Failure to Properly Designate the Significance Level of Callaway Action Requests.
05000483/FIN-2015009-052015Q4CallawayFailure to Determine the Cause and Take Corrective Action to Preclude Repetition for the Inadequate Design of Auxiliary Feedwater Flow Control Valve Modutronics Cards.
05000483/FIN-2015009-062015Q4CallawayFailure to Have an Adequate Procedure for Testing the Torque and Thrust Values for the Auxiliary Feedwater Pump Flow Control Valves
05000483/FIN-2015009-072015Q4CallawayFailure to Identify and Correct Additional Undersized Components on Auxiliary Feedwater System Flow Control Valve Modified Modutronics Controller Cards
05000338/FIN-2015405-012015Q3North AnnaSecurity
05000338/FIN-2015405-022015Q3North AnnaSecurity
05000285/FIN-2015011-012015Q3Fort CalhounFailure to Ensure the Suitability of Replacement Materials during the Design Review Process
05000285/FIN-2015011-022015Q3Fort CalhounFailure to Establish a Technical Basis for Operability of the Auxiliary Feedwater System
05000285/FIN-2015011-032015Q3Fort CalhounFailure to Correct a Non-Conforming Condition Associated with Auxiliary Feedwater Valves
05000458/FIN-2015009-042015Q2River BendFailure to Identify High Reactor Water Level as a Condition Adverse to Quality
05000458/FIN-2015009-052015Q2River BendFailure of the Plant-Referenced Simulator to Demonstrate Expected Plant Response
05000286/FIN-2015010-012015Q2Indian PointFailure to Correct a Degraded Condition of Fire Protection System Solenoid Valve SOV-230-1
05000458/FIN-2015009-022015Q2River BendFailure to Establish Adequate Procedures to Perform Maintenance on Equipment that can Affect Safety-Related Equipment
05000458/FIN-2015009-032015Q2River BendFailure to Provide Adequate Procedures for Post-scram Recovery
05000458/FIN-2015009-062015Q2River BendFailure to Identify and Classify Operator Workarounds that Impacted Scram Recovery Actions