SNRC-2157, Forwards 1993 Rept of Personnel & Man-Rem by Work & Job Function. 1993 Personnel Exposures Extremely Low as Majority of Radioactivity Removed from Site

From kanterella
Jump to navigation Jump to search
Forwards 1993 Rept of Personnel & Man-Rem by Work & Job Function. 1993 Personnel Exposures Extremely Low as Majority of Radioactivity Removed from Site
ML20063L669
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 02/28/1994
From: Bortz A
LONG ISLAND POWER AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20063L670 List:
References
LSNRC-2157, NUDOCS 9403070269
Download: ML20063L669 (2)


Text

___ _ _ _ _ _

?. ',

! Long Shoreham Nuclear Power Station i Island P.O. Box 628

- Power North Country Road Authonty Wading River, N.Y.11792 i-4 FEB 2 81994 4

LSNRC-2157 4

U. S. Nuclear Regulatory Commission

! ATTN: Document Control Desk Washington, D.C. 20555 Annual Man-Rem Report Shoreham Nuclear Power Station - Unit 1 Docket No. 50-322 Ladies and Gentlemen:

The attached table, entitled, "Shoreham Report of Personnel and Man-Rem by Work and Job Function," is submitted to provide the information required by Technical Specifications 6.8.1.1 and 6.8.1.2.

1993 personnel exposures were extremely low as the majority of Shoreham's radioactivity has been removed from the site. The doses on the attached tables are all based on quarterly thermoluminescent dosimeter (TLD) readings. Each individual TLD reading was broken down and assigned to one or more job functions, depending upon the jobs that the worker performed during the quarter. The doses on this table account for over 80.0% of the total whole-body doses received from external sources, thus satisfying the aggregate requirement of Technical Specification 6.8.1.2.

Included in this report, for information, is the statistical summary of personnel monitoring information required by 10CFR20. 407 (b) . Also, included is a tabulation of the TLD doses  !

for certain departments, divisions and sections of the Long Island Power. Authority Shoreham organization.

For the reporting period of 1/1/93 to 12/31/93, no individual l received a measurable exposure greater than 100 mrem. 1 i

$$8'18SeEos888!22

/f I

R PDR .

\

s, I.SNRd-2157 Page 2 of 2 Should you have any questions, please do not hesitate to call my office.

Very truly yours, l

l A. J. or z Resident Manager l RP/kc )

Attachments l l

cc: L. Bell I C. L. Pittiglio T. T. Martin R. Nimitz I

l l

.n . .- .

. -., , . . . . . . - - - . .-. ,-. .- - _ . -