MONTHYEARRA-23-0268, Transmittal of Sixth 10-Year Inservice Testing Interval Program Plan2023-09-29029 September 2023 Transmittal of Sixth 10-Year Inservice Testing Interval Program Plan RA-23-0052, Refuel 32 (O1R32) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval2023-02-22022 February 2023 Refuel 32 (O1R32) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval RA-22-0334, Refuel 31 (O3R31) Steam Generator Tube Inspection Report2022-11-21021 November 2022 Refuel 31 (O3R31) Steam Generator Tube Inspection Report RA-22-0255, Refuel 31 (O3R31) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval2022-08-29029 August 2022 Refuel 31 (O3R31) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval RA-22-0123, Refuel 30 (O2R30) Steam Generator Tube Inspection Report2022-05-26026 May 2022 Refuel 30 (O2R30) Steam Generator Tube Inspection Report RA-22-0066, Refuel 30 (O2R30) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval2022-03-0707 March 2022 Refuel 30 (O2R30) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval RA-19-0396, Refuel 31 (O1R31) Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Reports, Fifth 10-Year ISI Interval2021-02-11011 February 2021 Refuel 31 (O1R31) Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Reports, Fifth 10-Year ISI Interval RA-19-0394, Refuel 29 (O2R29) Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Reports, Fifth 10-Year ISI Interval2020-03-10010 March 2020 Refuel 29 (O2R29) Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Reports, Fifth 10-Year ISI Interval RA-19-0426, Supplement to RA-18-0138, Oconee Unit 3, Refuel 29 (O3R29) Inservice Inspection and Steam Generator Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval2019-12-0909 December 2019 Supplement to RA-18-0138, Oconee Unit 3, Refuel 29 (O3R29) Inservice Inspection and Steam Generator Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval RA-18-0138, Refuel 29 (03R29) Inservice Inspection (ISI) and Steam Generator Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval2018-08-15015 August 2018 Refuel 29 (03R29) Inservice Inspection (ISI) and Steam Generator Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval ONS-2018-020, Refuel 28 (O2R28) In-service Inspection (ISI) and Steam Generator In-service Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval2018-02-26026 February 2018 Refuel 28 (O2R28) In-service Inspection (ISI) and Steam Generator In-service Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval ONS-2017-015, End of Cycle 29 (1 EOC29) Refueling Outage Lnservice Inspection (ISI) and Steam Generator Lnservice Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval2017-02-24024 February 2017 End of Cycle 29 (1 EOC29) Refueling Outage Lnservice Inspection (ISI) and Steam Generator Lnservice Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval ML16232A0662016-08-15015 August 2016 End of Cycle 28 (3EOC28) Refueling Outage In-service Inspection(Isi)And Steam Generator Service Inspection(SG-ISI) Report, Firth 10-Year ISI Interval ONS-2016-014, End of Cycle 27 (2EOC27) Refueling Outage Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval2016-02-10010 February 2016 End of Cycle 27 (2EOC27) Refueling Outage Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval ML15271A3382015-09-30030 September 2015 Review of the Fall 2014 Steam Generator Tube Inservice Inspection Report for Refueling Outage 28 ML15202A0332015-07-15015 July 2015 Fourth Ten-Year Inservice Inspection Plan, Relief Request No. 15-ON-002, Limited Volume Inspections from 1 EOC27 and 2EOC26 Outages ONS-2015-039, Fifth Ten Year Inservice Inspection Interval, Relief Request No. 14-ON-001; Inspection Impracticality of Letdown Cooler Nozzle Inside Radius Sections2015-05-0404 May 2015 Fifth Ten Year Inservice Inspection Interval, Relief Request No. 14-ON-001; Inspection Impracticality of Letdown Cooler Nozzle Inside Radius Sections ONS-2015-037, Fifth Ten Year Inservice Inspection Interval, Relief Request No. 14-ON-002; Alternative Requirements for Specific Residual Heat Removal System Welds2015-05-0404 May 2015 Fifth Ten Year Inservice Inspection Interval, Relief Request No. 14-ON-002; Alternative Requirements for Specific Residual Heat Removal System Welds ML15072A2182015-03-13013 March 2015 Steam Generator In-service Inspection Summary Report Oconee Nuclear Station Unit 1 EOC 28 Fall Outage 2014 ONS-2015-031, End of Cycle 28 (11EOC28) Refueling Outage Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval2015-03-0606 March 2015 End of Cycle 28 (11EOC28) Refueling Outage Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval ONS-2015-031, Oconee, Unit 1 - End of Cycle 28 (11EOC28) Refueling Outage Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval2015-03-0606 March 2015 Oconee, Unit 1 - End of Cycle 28 (11EOC28) Refueling Outage Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Report, Fifth 10-Year ISI Interval ONS-2014-114, End of Cycle 27 (3EOC27) Refueling Outage Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Report, Fourth 10-Year ISI Interval2014-08-12012 August 2014 End of Cycle 27 (3EOC27) Refueling Outage Inservice Inspection (ISI) and Steam Generator Inservice Inspection (SG-ISI) Report, Fourth 10-Year ISI Interval ML14202A0092014-07-15015 July 2014 Fifth Interval Inservice Inspection Plan ONS-2014-098, Oconee, Units 1, 2 and 3 - Fifth Interval Inservice Inspection Plan2014-07-15015 July 2014 Oconee, Units 1, 2 and 3 - Fifth Interval Inservice Inspection Plan ML14202A0102014-06-18018 June 2014 Oconee, Units 1, 2 and 3 - Fifth Interval Inservice Inspection Plan, Attachment a ONS-2014-098, Fifth Inspection Interval Inservice Inspection Pressure Test Plan, Revision 0, Attachment B2014-05-12012 May 2014 Fifth Inspection Interval Inservice Inspection Pressure Test Plan, Revision 0, Attachment B ONS-2014-098, Oconee, Units 1, 2 and 3 - Fifth Inspection Interval Inservice Inspection Pressure Test Plan, Revision 0, Attachment B2014-05-12012 May 2014 Oconee, Units 1, 2 and 3 - Fifth Inspection Interval Inservice Inspection Pressure Test Plan, Revision 0, Attachment B ML14202A0122014-05-12012 May 2014 Fifth Inspection Interval Inservice Inspection Pressure Test Plan, Revision 0, Attachment C ONS-2014-033, End of Cycle 26 Refueling Outage Steam Generator Inservice Inspection Report2014-03-0303 March 2014 End of Cycle 26 Refueling Outage Steam Generator Inservice Inspection Report ML14066A0692014-03-0303 March 2014 End of Cycle 26 Refueling Outage, Inservice Inspection Summary Report; Fourth Ten Year Inspection Interval ML13273A0372013-09-26026 September 2013 Fourth Ten-Year Inservice Inspection Plan, Request for Relief No. 13-ON-001 ML13239A0732013-08-15015 August 2013 End of Cycle (EOC) 26 Refueling Outage Inservice Inspection (ISI) Report, Fourth Ten-Year Inservice Inspection Interval Revision 1 ML13064A4102013-02-27027 February 2013 End of Cycle (EOC) 27 Refueling Outage Inservice Inspection (ISI) Report Fourth Ten-Year Inservice Inspection Interval ML13066A1002013-02-27027 February 2013 End of Cycle (EOC) 27 Refueling Outage Steam Generator Inservice Inspection Report ML12242A5522012-08-27027 August 2012 End of Cycle (EOC) 26 Refueling Outage Inservice Inspection (ISI) Report Fourth Ten-Year Inservice Inspection Interval ML12195A3212012-07-0202 July 2012 Transmittal of Fifth 10 Year Inservice Testing Interval ML12066A1752012-02-29029 February 2012 Fourth Ten-Year Inservice Inspection Plan Request for Relief No. 11-ON-002 ML12048B4102012-02-15015 February 2012 Unit 2 End of Cycle (EOC) 25 Refueling Outage, Inservice Inspection (ISI) Report Fourth Ten-Year Inservice Inspection Interval ML12009A0912011-12-23023 December 2011 Fourth Ten-Year Inservice Inspection Plan Request for Relief No. 11-ON-001 ML11301A1122011-10-26026 October 2011 End of Cycle (EOC) 26 Refueling Outage Steam Generator Inservice Inspection Report ML11257A2612011-09-0707 September 2011 Unit 1 End of Cycle (EOC) 26 Refueling Outage, Inservice Inspection (ISI) Report, Fourth Ten-Year Inservice Inspection Interval ML11124A1312011-04-29029 April 2011 Fourth Ten Year Interval -- Inservice Inspection Plan Request for Relief No. 10-ON-002 ML1105403112011-02-17017 February 2011 EOC 25 Refueling Outage Inservice Inspection Report, Fourth Ten-Year Inservice Inspection Interval ML1105305122011-02-17017 February 2011 EOC25 Refueling Outage Steam Generator Inservice Inspection Report ML1024305292010-08-27027 August 2010 EOC 24 Refueling Outage Inservice Inspection Report, Fourth Ten-Year Inservice Inspection Interval ML1024305302010-08-27027 August 2010 2EOC24 Refueling Outage Steam Generator Inservice Inspection Report ML1009702702010-04-0101 April 2010 EOC25 Refueling Outage, Steam Generator Inservice Inspection Report ML1007704312010-03-11011 March 2010 Third Ten-Year Inservice Test Program Interval, Pump Specific Relief Request No. ON-SRP-HPI-03 ML1006401432010-03-0303 March 2010 Submittal of Steam Generator Inservice Inspection Report Conducted During EOC25 Refueling Outage ML1006401262010-02-0909 February 2010 Inservice Inspection Report, EOC25 Refueling Outage, Fourth Ten-Year Inservice Inspection Interval 2023-09-29
[Table view] Category:Letter type:RA
MONTHYEARRA-23-0325, Submittal of Procedures CSD-EP-HNP-0101-01, 02, CSD-EP-ONS-0101-01, CSD-EP-RNP-0101-01, and EP-RNP-EPLAN-ANNEX2024-01-0808 January 2024 Submittal of Procedures CSD-EP-HNP-0101-01, 02, CSD-EP-ONS-0101-01, CSD-EP-RNP-0101-01, and EP-RNP-EPLAN-ANNEX RA-23-0320, Notification of Deviation from MRP-227, Revision 1-A Baffle-to-Former Bolt Inspection Frequency2023-12-14014 December 2023 Notification of Deviation from MRP-227, Revision 1-A Baffle-to-Former Bolt Inspection Frequency RA-23-0318, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0404 December 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0182, Duke Energy Carolinas, LLC - License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program for a One-Time Extension of the Units 1, 2 and 3 Type a Leak Rate Test Frequency2023-11-16016 November 2023 Duke Energy Carolinas, LLC - License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program for a One-Time Extension of the Units 1, 2 and 3 Type a Leak Rate Test Frequency RA-23-0284, RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0304, Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 2 Cycle 32 (Revision 0)2023-11-14014 November 2023 Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 2 Cycle 32 (Revision 0) RA-23-0281, Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes2023-11-0101 November 2023 Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes RA-23-0275, Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI)2023-10-12012 October 2023 Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI) RA-23-0268, Transmittal of Sixth 10-Year Inservice Testing Interval Program Plan2023-09-29029 September 2023 Transmittal of Sixth 10-Year Inservice Testing Interval Program Plan RA-23-0234, Update to the Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations for Oconee Nuclear Station (ONS)2023-09-28028 September 2023 Update to the Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations for Oconee Nuclear Station (ONS) RA-23-0225, Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes2023-09-20020 September 2023 Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes RA-23-0228, Registration for Use of General License Spent Fuel Cask Number 1752023-09-14014 September 2023 Registration for Use of General License Spent Fuel Cask Number 175 RA-23-0223, Registration for Use of General License Spent Fuel Cask Numbers 173 and 1742023-08-23023 August 2023 Registration for Use of General License Spent Fuel Cask Numbers 173 and 174 RA-23-0222, On-Shift Staffing Analysis (Ossa), Revision 12023-08-23023 August 2023 On-Shift Staffing Analysis (Ossa), Revision 1 RA-23-0211, Reply to a Notice of Violation (NOV) 05000270/2023010-022023-08-17017 August 2023 Reply to a Notice of Violation (NOV) 05000270/2023010-02 RA-23-0154, Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0136, Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0186, Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 2 Cycle 31 (Revision 3)2023-07-18018 July 2023 Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 2 Cycle 31 (Revision 3) RA-23-0184, Registration for Use of General License Spent Fuel Cask Numbers 171 and 1722023-07-10010 July 2023 Registration for Use of General License Spent Fuel Cask Numbers 171 and 172 RA-23-0142, Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require2023-07-0707 July 2023 Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require RA-23-0146, Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI)2023-06-20020 June 2023 Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI) RA-23-0135, Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory2023-06-0707 June 2023 Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory RA-23-0041, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-30030 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations RA-23-0128, Refuel 32 (O1R32) Steam Generator Tube Inspection Report2023-05-18018 May 2023 Refuel 32 (O1R32) Steam Generator Tube Inspection Report RA-23-0018, Relief Request (RA-23-0018) to Utilize Code Case N-853 PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material Susceptible to Primary Water Stress Corrosion Cracking Section XI, Division 12023-05-0404 May 2023 Relief Request (RA-23-0018) to Utilize Code Case N-853 PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material Susceptible to Primary Water Stress Corrosion Cracking Section XI, Division 1 RA-23-0111, Withdrawal of License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-04-27027 April 2023 Withdrawal of License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies RA-23-0104, Response to Request for Additional Information (RAI) Regarding Oconee Unit 3, Refuel 31 (O3R31) Steam Generator Tube Inspection Report2023-04-26026 April 2023 Response to Request for Additional Information (RAI) Regarding Oconee Unit 3, Refuel 31 (O3R31) Steam Generator Tube Inspection Report RA-23-0047, Duke Energy Annual Radiological Environmental Operating Report - 20222023-04-26026 April 2023 Duke Energy Annual Radiological Environmental Operating Report - 2022 RA-23-0044, Aduke Energy Annual Report of Changes Pursuant to 10 CFR 50.462023-04-26026 April 2023 Aduke Energy Annual Report of Changes Pursuant to 10 CFR 50.46 RA-23-0099, Subsequent License Renewal Application Second Annual Amendment to the License Renewal Application2023-04-25025 April 2023 Subsequent License Renewal Application Second Annual Amendment to the License Renewal Application RA-23-0046, Annual Radioactive Effluent Release Report - 20222023-04-24024 April 2023 Annual Radioactive Effluent Release Report - 2022 RA-22-0292, License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-04-0404 April 2023 License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies RA-23-0036, Biennial Decommissioning Financial Assurance Reports2023-03-30030 March 2023 Biennial Decommissioning Financial Assurance Reports RA-23-0040, Onsite Property Insurance Coverage2023-03-30030 March 2023 Onsite Property Insurance Coverage RA-23-0039, 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2023-03-30030 March 2023 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums RA-23-0037, Duke Energy - Decommissioning Funding Plan for Independent Spent Fuel Storage Installations (Isfsis)2023-03-30030 March 2023 Duke Energy - Decommissioning Funding Plan for Independent Spent Fuel Storage Installations (Isfsis) RA-23-0051, Response to Request for Additional Information (RAI) Regarding Proposed Alternative to Use American Society of Mechanical Engineers Code Case N-752, Risk-Informed Categorization and Treatment for Repair/Replacement Activities2023-03-0909 March 2023 Response to Request for Additional Information (RAI) Regarding Proposed Alternative to Use American Society of Mechanical Engineers Code Case N-752, Risk-Informed Categorization and Treatment for Repair/Replacement Activities RA-23-0052, Refuel 32 (O1R32) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval2023-02-22022 February 2023 Refuel 32 (O1R32) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval RA-22-0257, Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-02-17017 February 2023 Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) RA-22-0091, Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2023-02-16016 February 2023 Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RA-23-0001, Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI2023-02-0202 February 2023 Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI RA-22-0118, License Amendment Request to Revise Restrictive Technical Specification Surveillance Requirement Frequencies2023-02-0101 February 2023 License Amendment Request to Revise Restrictive Technical Specification Surveillance Requirement Frequencies RA-22-0256, Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2023-01-23023 January 2023 Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) RA-22-0335, Submittal of 30-Day Report Per 10CFR26.719(c)(1) - Unsatisfactory Performance of a Health & Human Services Certified Lab2022-12-0505 December 2022 Submittal of 30-Day Report Per 10CFR26.719(c)(1) - Unsatisfactory Performance of a Health & Human Services Certified Lab RA-22-0334, Refuel 31 (O3R31) Steam Generator Tube Inspection Report2022-11-21021 November 2022 Refuel 31 (O3R31) Steam Generator Tube Inspection Report RA-22-0329, Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 1 Cycle 33 (Revision 0 and Revision 1)2022-11-11011 November 2022 Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 1 Cycle 33 (Revision 0 and Revision 1) RA-22-0285, Subsequent License Renewal - Appendix E Environmental Report Supplement 22022-11-0707 November 2022 Subsequent License Renewal - Appendix E Environmental Report Supplement 2 RA-22-0313, Emergency Action Level (EAL) Technical Basis Document, Revision 4, EAL Wallchart, Revision 3 and Alternate TSC and OSC Renovations2022-10-27027 October 2022 Emergency Action Level (EAL) Technical Basis Document, Revision 4, EAL Wallchart, Revision 3 and Alternate TSC and OSC Renovations RA-22-0270, Response to Request for Additional Information Regarding License Amendment Request to Address Technical Specifications Mode Change Limitations2022-10-0707 October 2022 Response to Request for Additional Information Regarding License Amendment Request to Address Technical Specifications Mode Change Limitations RA-22-0192, Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4a2022-09-0202 September 2022 Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4a 2024-01-08
[Table view] |
Text
Shawn K. Gibby Vice President Nuclear Engineering 526 South Church Street, EC-07H Charlotte, NC 28202 704-519-5138 Shawn.Gibby@duke-energy.com RA-22-0255 10 CFR 50.55a August 29, 2022 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Oconee Nuclear Station, Unit 3 Docket No. 50-287 Renewed License No. DPR-55
Subject:
Oconee Unit 3, Refuel 31 (O3R31) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval Pursuant to the 2007 Edition through the 2008 Addenda of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI, IWA-6000, Duke Energy Carolinas, LLC is providing its Inservice Inspection (ISI) summary pertaining to the 31st refueling outage (O3R31) for Oconee Nuclear Station (ONS) Unit 3.
The Enclosure to this letter contains the O3R31 ISI summary report.
This submittal contains no regulatory commitments. Please refer any questions regarding this submittal to Ryan Treadway, Director - Nuclear Fleet Licensing, at 980-373-5873.
Sincerely, Shawn K. Gibby Vice President - Nuclear Engineering JLV
Enclosure:
Inservice Inspection Summary Report Unit 3 Oconee Spring 2022 Refueling Outage O3R31 (Outage 4)
U.S. Nuclear Regulatory Commission Page 2 RA-22-0255 cc: (with Enclosure)
Ms. Laura Dudes Administrator, Region II U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Avenue NE, Suite 1200 Atlanta, GA 30303-1257 Mr. Shawn Williams NRC Senior Project Manager Oconee Nuclear Station Mr. Jared Nadel NRC Senior Resident Inspector Oconee Nuclear Station
Enclosure to RA-22-0255 Enclosure Inservice Inspection Summary Report Unit 3 Oconee Spring 2022 Refueling Outage O3R31 (Outage 4)
DUKE ENERGY INSERVICE INSPECTION
SUMMARY
REPORT UNIT 3 OCONEE SPRING 2022 REFUELING OUTAGE O3R31 (Outage 4)
Location: Highway 130/183, Seneca, SC 29672 NRC Docket No. 50-287 Commercial Service Date: December 16, 1974 Owner: Duke Energy 526 South Church St.
Charlotte, NC 28201-1006 Revision 0 Originated By: Date Austin C. Keller Checked By: Date Angela Staller Approved By: Date Mark A. Pyne
CASE N-532-5 FORM OAR-1 OWNER'S ACTIVITY REPORT Report Number O3R31 Plant Oconee Nuclear Station, Highway 130/183, Seneca, SC 29672 Unit No. 3 Commercial service date 12/16/1974 Refueling outage no. O3R31 (if applicable)
Current inspection interval Fifth Inspection Interval (ISI), Third Inspection Interval (Containment ISI)
(1st, 2nd, 3rd, 4th, other)
Second & Third Inspection Period (ISI) & Third Inspection Period (Containment)
Current inspection period See Attachment A for details (1st, 2nd, 3rd)
Edition and Addenda of Section XI applicable to the inspection plans ASME Section XI 2007 Edition through 2008 Addenda Date and revision of inspection plans See Attachment A Edition and Addenda of Section XI applicable to repair/replacement activities, if different than the inspection plans Same as above The following Code Cases are permitted by the Augmented ISI, ISI, and Pressure Test Plans, 5th Interval: N-513-3,N-513-4, N-532-4, N-532-5, N-586-1, N-600, N-613-1, N-613-2, N-639, N-643-2, N-648-1, N-648-2, N-651, N-663, N-705, N-706-1, N-711-1, N-712, N-716-1, N-722-1, N-729-6, N-731, N-735, N-765, N-770-5, N-771, N-775, N-776, N-786-1, N-798, Code Cases used for inspection N-800, N-805, N-823, N-823-1, N-825, N-831, N-843, N-845, N-853, &
and evaluation: N-854 (if applicable)
CERTIFICATE OF CONFORMANCE I certify that (a) the statements made in this report are correct; (b) the examinations and tests meet the Inspection Plan as required by the ASME Code,Section XI; and (c) the repair/replacement activities and evaluations supporting the completion of O3R31 conform to the requirements of Section XI.
(refueling outage number)
Signed Austin C. Keller, ISI Program Owner Date 08/16/2022 CERTIFICATE OF INSERVICE INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of South Carolina and employed by Bureau Veritas Inspection and Insurance Company of Lynn, MA have knowledge and belief, the Owner has performed all activities represented by this report in accordance with the requirements of Section XI.
By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair/replacement activities and evaluation described in this report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection.
Commissions 13048, 201, AI, IS, N, I, C, R National Board, State, Province, and Endorsements Mark E. Zurbuch Page 1 of 5
CASE N-532-5 Date Attachment A Oconee Unit 3 Refueling Outage 31, Inservice Inspection Report The Oconee Nuclear Station Unit 3 Fifth Ten Year Inservice Inspection (ISI) Plan complies with 10CFR50.55a(g), which implements, by reference, the American Society of Mechanical Engineers (ASME)
Boiler and Pressure Vessel Code,Section XI, 2007 Edition with 2008 Addenda.
Per RIS 2004-12, Letter RA-20-0262, NRC Accession Number ML20260H325 and approval NRC Accession Number ML20300A206, the NRC staff concluded that the use of subparagraph IWA-4540(b) of the 2017 Edition of the ASME B&PV Code,Section XI, is acceptable for Oconee Unit 3.
Per RIS 2004-16, Letter RA-20-0263, NRC Accession Number ML20260H326 and approval NRC Accession Number ML21113A013, the NRC staff concluded that the use of subparagraph IWA-4340 of the 2017 Edition of the ASME B&PV Code,Section XI, is acceptable for Oconee Unit 3.
Per RIS 2004-12, Letter RA-20-0191, NRC Accession Number ML20265A028 and approval NRC Accession Number ML21029A335, the NRC staff concluded that the use of paragraphs IWA-5120, IWA-5213, IWA-5241, IWA-5242, and IWA-5250 of the 2017 Edition of the ASME B&PV Code,Section XI, is acceptable for Oconee Unit 3.
This summary report is being submitted pursuant to the reporting requirements of ASME Section XI, IWA-6000 as amended by ASME Code Case N-532-Requirements and Inservice Inspection Summary Report Preparation and Submission Section XI, Division Contained within this summary report are the form OAR-Code Case N-532-5 for Oconee Nuclear Station during cycle 31 and Refueling Outage 31 (O3R31).
O3R31 is the first outage of the third ISI period in the fifth inspection interval. For ISI examinations Period 2 was extended by 12 months (as permitted by IWA-2430(c)(3)) to 07/15/2022. This allowed for selected placeholder outage (O3R31a) was added to Period 2 to track the scheduling and completion of examinations performed during O3R31 that are to be credited for Period 2. Only those examinations scheduled for O3R31a shall be credited for Period 2 compliance. In no case was any one exam credited for both periods.
For Containment ISI examinations O3R31 is the first outage of the third Containment period in the third inspection interval.
This report includes all Repair/Replacement activities from May 10, 2020 through May 30, 2022, Cycle 31.
Date and Revision of Inservice Inspection Plans:
I. Fifth Interval Inservice Inspection Plans
- 1. The following documents comprise the Oconee Nuclear Station 5 th Interval Inservice Inspection Plan for ONS Unit 3 (Class 1, 2, and 3 Components):
- a. ISI Plan - Fifth Interval Inservice Inspection Plan, Oconee Nuclear Station Units 1, 2, & 3 and Keowee Hydro Station Units 1 & 2, Document #OISI-0169.10-0050-ISI PLAN, Rev.
1, dated 2/22/2021.
Page 2 of 5
CASE N-532-5
- b. ISI Schedule Fifth Ten-Year Interval Inservice Inspection Schedule Oconee Nuclear Station Unit 3, Document #OISI-0169.10-0050-Unit 3, Rev. 1, dated 2/26/2021.
- 2. The following document comprises the Oconee Nuclear Station 5th Interval Inservice Inspection Pressure Test Plan for ONS Unit 3:
- a. Oconee Nuclear Station - Fifth Inspection Interval Inservice Inspection PT (Pressure Test) Plan General Requirements Units 1, 2, and 3, Document #OISI-0169.20-0050-PTPLAN, Rev. 8, dated 7/21/2022.
II. Fifth Interval Augmented Inservice Inspection Plan
- 1. The following document comprises the Oconee Nuclear Station 5th Interval Augmented Inservice Inspection Plan and Schedule for Unit 3:
- a. Oconee Nuclear Station - Augmented Inservice Inspection NDE Plan - General Requirements and Units Detail Listing, Document #OISI-0169.10-0050 - AUG-ISI, Rev. 7, dated 1/19/2021.
III. Third Interval Containment Inservice Inspection Plan
- 1. The following document comprises the Oconee Nuclear Station 3rd Interval Containment Inservice Inspection Plan for Unit 3 (Class MC):
- a. Third Interval Containment Inservice Inspection Plan Oconee Nuclear Station Units 1, 2,
& 3, Document #O-ISIC3-62-0001, Rev. 9, dated 05/1/2022.
Page 3 of 5
CASE N-532-5 TABLE 1 ITEMS WITH FLAWS OR RELEVANT CONDITIONS THAT REQUIRED EVALUATION FOR CONTINUED SERVICE Examination Category and Item Description Evaluation Description Item Number Areas identified in NCR #02428399 Boric acid residue was found during ISI C-H / C7.10 were evaluated by Engineering and Pressure Test Zone, O3HPI-2A found to be acceptable.
Areas identified in NCR #02428404 Boric acid residue was found during ISI C-H / C7.10 were evaluated by Engineering and Pressure Test Zone, O3HPI-2B found to be acceptable.
Areas identified in NCR #02428080 Relevant conditions were identified during ISI C-H / C7.10 were inspected and resolved per WO Pressure Test Zone, O3RCMU-1 20537520.
Areas identified in NCR #02366873 Boric acid residue was found during ISI C-H / C7.10 were evaluated by Engineering and Pressure Test Zone, I3HPI-4 found to be acceptable.
Areas identified in NCR #02367446 Boric acid residue was found during ISI C-H / C7.10 were evaluated by Engineering and Pressure Test Zone, I3HPI-7 found to be acceptable.
Areas identified in NCR #02374063 Boric acid residue was found during ISI C-H / C7.10 were evaluated by Engineering and Pressure Test Zone, I3RBS-1 found to be acceptable.
Areas identified in NCR #02374413 Boric acid residue was found during ISI C-H / C7.10 were evaluated by Engineering and Pressure Test Zone, I3HPI-1 found to be acceptable.
Areas identified in NCR #02379143 Boric acid residue was found during ISI C-H / C7.10 were evaluated by Engineering and Pressure Test Zone, I3LPI-1 found to be acceptable.
Areas identified in NCR #02375976 Boric acid residue was found during ISI D-B / D2.10 were evaluated by Engineering and Pressure Test Zone, I3SF-2 found to be acceptable.
Indications identified in NCR #02426502 ISI Summary No. O3-08773. VT-1 were evaluated by Engineering and examination of 3-SCV-011 revealed pitting of found to be acceptable for continued E-C / E4.11 the liner plate exceeding 10% nominal wall service per IWE-3122.3. The liner plate loss. in this area was re-coated during O3R31 per WO 20208696.
Page 4 of 5
CASE N-532-5 TABLE 2 ABSTRACT OF REPAIR/REPLACEMENT ACTIVITIES REQUIRED FOR CONTINUED SERVICE Repair /
Code Item Description Description of Work Date Completed Replacement Class Plan Number Encapsulate wall thinning 3 U3 CCW Inlet piping per IWA-4340 2017 Edition 5/17/2022 20395451-01 Reference RA-20-0263 Perform weld repair of 3 0FO-FL-004B cracked filter bracket 6/18/2020 20405673-02 support Replace cuno filter housing 3 0LPS-FL-0027 10/1/2020 20426301-01 due to crack Remove defect and 3 U3 CCW Inlet piping encapsulate through wall 5/20/2022 20476280-45 hole 1 3RC-HX-000A Plug SG tubes 5/16/2022 20476408-17 1 3RC-HX-000B Plug SG tubes 5/16/2022 20476409-17 Replace piping/fittings due 3 3RC-HX-0018 piping 5/24/2022 20535005-01 to through wall leak Page 5 of 5