RA-18-010, Supplement to Relief Request for Extension of Torus Examinations

From kanterella
(Redirected from RA-18-010)
Jump to navigation Jump to search
Supplement to Relief Request for Extension of Torus Examinations
ML18024A230
Person / Time
Site: Oyster Creek
Issue date: 01/24/2018
From: Jim Barstow
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RA-18-010
Download: ML18024A230 (2)


Text

Exelon Generation 10 CFR 50.55a RA-18-010 January 24, 2018 U.S. Nuclear Regulatory Commission AITN: Document Control Desk Washington, DC 20555-0001 Oyster Creek Nuclear Generating Station Renewed Facility Operating License No. DPR-16 NRC Docket No. 50-219

Subject:

Supplement to Relief Request for Extension of Torus Examinations

References:

1. Exelon Generation Company, LLC letter to USNRC, Submittal of Relief Request for Extension of Torus Examinations in Accordance with 10 CFR 50.55a(z)(1 ), dated December 19, 2017 (ML17353A008)
2. Exelon Generation Company, LLC letter to USNRC, "Permanent Cessation of Operations at Oyster Creek Nuclear Generating Station," dated January 7, 2011 In Reference 1, Exelon Generation Company, LLC (EGG) requested relief for Oyster Creek Nuclear Generating Station (Oyster Creek) from the current examination requirements of Containment Shell (Torus) performed in accordance with American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI "Rules for lnservice Inspection of Nuclear Power Plant Components", Subsection IWE, to allow a 16-month extension for the torus visual inspections currently required to be performed in the OC1 R27 Refuel Outage (September 2018). Reference 1 requested this relief under the provisions of 10 CFR 50.55a(z)(1) as a proposed alternative that would provide an acceptable level of safety.

The purpose of this letter is to provide a supplement to Reference 1 to revise the basis for the subject relief request from 10 CFR 50.55a(z)(1) to 10 CFR 50.55a(z)(2) since compliance with the specified requirements of 10 CFR50.55a would result in hardship without a compensating increase in the level of quality and safety.

As described in Reference 2, Oyster Creek plans to permanently shutdown on December 31, 2019. The proposed relief request (Reference 1) extends the torus examinations from the OC1 R27 Refuel Outage (September 2018) to January 31, 2020, at which time the plant is expected to be in the permanently shutdown condition. EGG has evaluated the extensive resources required for planning and execution of torus desludging as well as the worker radiation dose exposures resulting from performance of torus inspections. The torus desludging process and the torus examinations typically accumulate 1 to 1.2 Rem total exposure to plant

U.S. Nuclear Regulatory Commission Supplement to Relief Request for Torus Examinations January 24, 2018 Page 2 personnel based on previous torus examinations performed. The requested extension would avoid unnecessary personnel radiological dose exposures resulting from the performance of the torus desludging and inspection in the OC1 R27 Refuel Outage, and is consistent with Oyster Creek ALARA goals and objectives.

As described in Reference 1, EGC established the technical evaluation basis for the requested extension of the torus inspection from 48 months to 64 months based on the detailed evaluation of previous torus inspection results. The technical evaluation provided in Reference 1 concluded that torus structural integrity will be adequately maintained, and the ECCS strainer acceptance criteria will continue to be satisfied, for the inspection interval extension from 48 months to 64 months. Therefore, it is concluded that no unacceptable structural degradation of the torus would occur as a result of continued plant operation during the 16-month extension duration.

Therefore, it is concluded that performance of the torus inspection in the OC1 R27 Refuel Outage (September 2018) as currently required by ASME Section XI results in hardship without a compensating increase in the level of quality and safety in accordance with 10 CFR 50.55a(z)(2).

This letter contains no new regulatory commitments. If you have any questions regarding this letter, please contact David Distel at 610-765-5517.

Respectfully submitted, James Barstow Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC cc: NRC Regional Administrator - Region I NRC Senior Resident Inspector- Oyster Creek Nuclear Generating Station NRC Project Manager, NRR - Oyster Creek Nuclear Generating Station Manager, Bureau of Nuclear Engineering- New Jersey Department of Environmental Protection Mayor of Lacey Township, Forked River, NJ