MONTHYEARML22305A5502022-10-13013 October 2022 News Release-III-22-024: NRC Names New Inspector at Fermi Nuclear Power Plant Press Release-III-22-008, NRC to Hold Public Meeting to Discuss 2021 Performance of Fermi Nuclear Power Plant2022-05-0909 May 2022 Press Release-III-22-008: NRC to Hold Public Meeting to Discuss 2021 Performance of Fermi Nuclear Power Plant Press Release-III-21-011, NRC to Hold Virtual Meeting to Discuss 2020 Performance of Fermi Nuclear Power Plant2021-06-16016 June 2021 Press Release-III-21-011: NRC to Hold Virtual Meeting to Discuss 2020 Performance of Fermi Nuclear Power Plant Press Release-III-20-013, NRC to Hold Virtual Meeting to Discuss 2019 Performance of Fermi Nuclear Power Plant2020-08-20020 August 2020 Press Release-III-20-013: NRC to Hold Virtual Meeting to Discuss 2019 Performance of Fermi Nuclear Power Plant Press Release-III-19-021, NRC Issues Confirmatory Action Letter to Fermi Nuclear Power Plant2019-10-0808 October 2019 Press Release-III-19-021: NRC Issues Confirmatory Action Letter to Fermi Nuclear Power Plant Press Release-III-19-018, NRC Launches Special Inspection at Fermi Nuclear Power Plant2019-07-11011 July 2019 Press Release-III-19-018: NRC Launches Special Inspection at Fermi Nuclear Power Plant Press Release-III-19-007, NRC to Hold Open House to Discuss 2018 Performance of Fermi Nuclear Power Plant2019-04-23023 April 2019 Press Release-III-19-007: NRC to Hold Open House to Discuss 2018 Performance of Fermi Nuclear Power Plant Press Release-III-19-001, NRC Names New Resident Inspector at Fermi Nuclear Power Station2019-01-0808 January 2019 Press Release-III-19-001: NRC Names New Resident Inspector at Fermi Nuclear Power Station Press Release-III-18-019, NRC to Hold Open House to Discuss 2017 Performance of Fermi Nuclear Power Plant2018-05-24024 May 2018 Press Release-III-18-019: NRC to Hold Open House to Discuss 2017 Performance of Fermi Nuclear Power Plant Press Release-18-008, NRC Issues Annual Assessments for Nation'S Nuclear Plants2018-03-0505 March 2018 Press Release-18-008: NRC Issues Annual Assessments for Nation'S Nuclear Plants Press Release-III-17-025, NRC Names New Senior Resident Inspector at Fermi Nuclear Plant2017-10-17017 October 2017 Press Release-III-17-025: NRC Names New Senior Resident Inspector at Fermi Nuclear Plant Press Release-III-17-016, NRC to Conduct Open House to Discuss 2016 Performance of Fermi Nuclear Power Plant2017-06-28028 June 2017 Press Release-III-17-016: NRC to Conduct Open House to Discuss 2016 Performance of Fermi Nuclear Power Plant Press Release-16-073, NRC Renews Operating License of Fermi, Unit 2 Nuclear Plant, Michigan2016-12-16016 December 2016 Press Release-16-073: NRC Renews Operating License of Fermi, Unit 2 Nuclear Plant, Michigan Press Release-16-055, NRC Issues Final Environmental Review on License Renewal for Fermi 2 Nuclear Power Plant2016-09-16016 September 2016 Press Release-16-055: NRC Issues Final Environmental Review on License Renewal for Fermi 2 Nuclear Power Plant Press Release-III-16-011, NRC to Hold Open House to Discuss Agency'S Assessment of Fermi Nuclear Power Plant2016-05-26026 May 2016 Press Release-III-16-011: NRC to Hold Open House to Discuss Agency'S Assessment of Fermi Nuclear Power Plant Press Release-15-073, NRC Seeks Public Comment on Draft Environmental Study of Fermi 2 Nuclear Plant License Renewal2015-11-0909 November 2015 Press Release-15-073: NRC Seeks Public Comment on Draft Environmental Study of Fermi 2 Nuclear Plant License Renewal Press Release-III-15-017, NRC Schedules Open House June 18 to Discuss Performance of Fermi Power Plant2015-06-0909 June 2015 Press Release-III-15-017: NRC Schedules Open House June 18 to Discuss Performance of Fermi Power Plant Press Release-15-030, NRC Concludes Hearing on Fermi New Reactor, Combined License to Be Issued2015-04-30030 April 2015 Press Release-15-030: NRC Concludes Hearing on Fermi New Reactor, Combined License to Be Issued Press Release-15-004, NRC to Hold Mandatory Hearing on Fermi New Reactor Application Feb. 4 in Rockville, MD2015-01-21021 January 2015 Press Release-15-004: NRC to Hold Mandatory Hearing on Fermi New Reactor Application Feb. 4 in Rockville, MD Press Release-14-082, NRC Completes Safety Review of Proposed New Reactor at Fermi Site in Michigan2014-11-19019 November 2014 Press Release-14-082: NRC Completes Safety Review of Proposed New Reactor at Fermi Site in Michigan Press Release-14-060, NRC Certifies GE-Hitachi New Reactor Design2014-09-16016 September 2014 Press Release-14-060: NRC Certifies GE-Hitachi New Reactor Design Press Release-14-058, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2014-09-0404 September 2014 Press Release-14-058: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-III-14-030, NRC Seeks Public Input on Fermi Nuclear Plant License Renewal Application2014-07-16016 July 2014 Press Release-III-14-030: NRC Seeks Public Input on Fermi Nuclear Plant License Renewal Application Press Release-14-036, NRC Announces Opportunity to Request a Hearing on Fermi 2 Nuclear Plant License Renewal Application2014-06-18018 June 2014 Press Release-14-036: NRC Announces Opportunity to Request a Hearing on Fermi 2 Nuclear Plant License Renewal Application Press Release-III-14-019, NRC Schedules Open House May 22 to Discuss Performance of Fermi Nuclear Power Plant2014-05-16016 May 2014 Press Release-III-14-019: NRC Schedules Open House May 22 to Discuss Performance of Fermi Nuclear Power Plant Press Release-14-031, NRC Announces Public Availability of Fermi 2 Nuclear Plant License Renewal Application2014-05-0707 May 2014 Press Release-14-031: NRC Announces Public Availability of Fermi 2 Nuclear Plant License Renewal Application Press Release-III-14-009, NRC Responded to an Alert at Fermi Nuclear Power Plant2014-03-21021 March 2014 Press Release-III-14-009: NRC Responded to an Alert at Fermi Nuclear Power Plant Press Release-14-006, NRC Approves Power Uprate for Fermi Nuclear Power Plant2014-02-10010 February 2014 Press Release-14-006: NRC Approves Power Uprate for Fermi Nuclear Power Plant Press Release-13-087, Atomic Safety and Licensing Board Going Forward with Hearing Oct. 30 on Proposed Fermi New Reactor2013-10-18018 October 2013 Press Release-13-087: Atomic Safety and Licensing Board Going Forward with Hearing Oct. 30 on Proposed Fermi New Reactor Press Release-13-073, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2013-09-0606 September 2013 Press Release-13-073: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-III-13-019, NRC Schedules Open House May 29 to Discuss Performance of Fermi Nuclear Power Plant2013-05-23023 May 2013 Press Release-III-13-019: NRC Schedules Open House May 29 to Discuss Performance of Fermi Nuclear Power Plant Press Release-13-037, Atomic Safety Licensing Board to Take Public Comment, Hold Hearing Oct. 30 on Proposed New Reactor in Michigan2013-05-16016 May 2013 Press Release-13-037: Atomic Safety Licensing Board to Take Public Comment, Hold Hearing Oct. 30 on Proposed New Reactor in Michigan Press Release-13-008, NRC, U.S. Army Corps of Engineers Issue Final Environmental Impact Statement for Proposed Fermi 3 Reactor2013-02-0707 February 2013 Press Release-13-008: NRC, U.S. Army Corps of Engineers Issue Final Environmental Impact Statement for Proposed Fermi 3 Reactor Press Release-12-099, NRC Issues Mid-Cycle Assessments for Nation? Nuclear Plants2012-09-0606 September 2012 Press Release-12-099: NRC Issues Mid-Cycle Assessments for Nation? Nuclear Plants Press Release-12-089, NRC Completes Reintegration of Security Into Reactor Oversight Process Assessments2012-08-0101 August 2012 Press Release-12-089: NRC Completes Reintegration of Security Into Reactor Oversight Process Assessments Press Release-III-12-021, NRC Schedules June 20 Open House to Discuss Fermi Nuclear Power Station Performance and NRC Oversight2012-06-13013 June 2012 Press Release-III-12-021: NRC Schedules June 20 Open House to Discuss Fermi Nuclear Power Station Performance and NRC Oversight Press Release-11-205, NRC Seeks Public Input on Draft Environmental Impact Statement for Fermi New Reactor; Meetings Scheduled Dec. 152011-10-28028 October 2011 Press Release-11-205: NRC Seeks Public Input on Draft Environmental Impact Statement for Fermi New Reactor; Meetings Scheduled Dec. 15 Press Release-III-11-017, NRC Schedules Open House for May 23 to Discuss Fermi Nuclear Power Plant Performance and NRC Oversight2011-05-11011 May 2011 Press Release-III-11-017: NRC Schedules Open House for May 23 to Discuss Fermi Nuclear Power Plant Performance and NRC Oversight Press Release-III-10-023, NRC Activates Region III Incident Response Center Due to Alert at Fermi Nuclear Plant2010-06-0606 June 2010 Press Release-III-10-023: NRC Activates Region III Incident Response Center Due to Alert at Fermi Nuclear Plant ML1011900362010-04-29029 April 2010 Press Release-III-10-013: NRC to Discuss 2009 Performance Assessment for Fermi Nuclear Power Plant May 5 Press Release-III-09-034, NRC Names New Resident Inspector at Fermi Nuclear Power Plant2009-11-24024 November 2009 Press Release-III-09-034: NRC Names New Resident Inspector at Fermi Nuclear Power Plant Press Release-09-113, NRC to Discuss Decommissioning Plan for Fermi Nuclear Plant Unit 1 at Public Meeting June 30 in Monroe, Mich2009-06-19019 June 2009 Press Release-09-113: NRC to Discuss Decommissioning Plan for Fermi Nuclear Plant Unit 1 at Public Meeting June 30 in Monroe, Mich Press Release-III-09-018, NRC to Discuss 2008 Performance Assessment for Fermi Nuclear Power Plant May 272009-05-20020 May 2009 Press Release-III-09-018: NRC to Discuss 2008 Performance Assessment for Fermi Nuclear Power Plant May 27 Press Release-09-003, NRC Announces Opportunity to Participate in Hearing on New Nuclear Reactor Application for Fermi Site2009-01-0808 January 2009 Press Release-09-003: NRC Announces Opportunity to Participate in Hearing on New Nuclear Reactor Application for Fermi Site Press Release-08-216, NRC Accepts Application for New Reactor at Fermi Site2008-11-25025 November 2008 Press Release-08-216: NRC Accepts Application for New Reactor at Fermi Site Press Release-III-08-011, NRC to Discuss 2007 Performance Assessment for Fermi Nuclear Power Plant Unit 22008-04-0303 April 2008 Press Release-III-08-011: NRC to Discuss 2007 Performance Assessment for Fermi Nuclear Power Plant Unit 2 Press Release-III-07-023, NRC Conducts Special Inspection at Fermi Plant Due to Pipe Damage2007-10-16016 October 2007 Press Release-III-07-023: NRC Conducts Special Inspection at Fermi Plant Due to Pipe Damage Press Release-III-07-011, - NRC to Discuss 2006 Performance Assessment for Fermi Nuclear Power Plant2007-03-29029 March 2007 Press Release-III-07-011 - NRC to Discuss 2006 Performance Assessment for Fermi Nuclear Power Plant Press Release-III-06-010, NRC to Discuss 2005 Performance Assessment for Fermi Nuclear Power Plant2006-03-16016 March 2006 Press Release-III-06-010: NRC to Discuss 2005 Performance Assessment for Fermi Nuclear Power Plant Press Release-III-05-027, NRC to Discuss 2004 Performance Assessment for Fermi Nuclear Power Plant2005-05-19019 May 2005 Press Release-III-05-027: NRC to Discuss 2004 Performance Assessment for Fermi Nuclear Power Plant 2022-05-09
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Region III 2443 Warrenville Road Lisle IL 60532 No. III-08-011 April 3, 2008 Contacts: E-Mail: opa3@nrc.gov Viktoria Mitlyng 630-829-9662 Web site: www.nrc.gov Prema Chandrathil 630-829-9663 NRC TO DISCUSS 2007 PERFORMANCE ASSESSMENT FOR FERMI NUCLEAR POWER PLANT UNIT 2 The Nuclear Regulatory Commission staff will meet with representatives of Detroit Edison Co. Wednesday, April 9, to discuss the agencys assessment of safety performance for last year at the Fermi Nuclear Power Plant. The plant is located in Newport, Mich.
The meeting, which will be open to the public, is scheduled to begin at 6 p.m. EDT at Monroe County Board of Commissioners Chambers, County Courthouse, 125 E. Second St.,
Monroe. The NRC staff will present the results of the assessment, talk about the NRC and its range of activities, and be available to respond to questions or comments from the public before the close of the meeting.
The NRC continually reviews the performance of the Fermi plant and the nations other commercial nuclear power facilities, NRC Region III Administrator James Caldwell said. This meeting allows us to discuss our annual assessment of safety performance with the company and with local officials and area residents. Our goal is to explain how the NRC works and make sure as much information as possible is available on our regulation of these facilities.
A letter sent from the NRC Region III Office to plant officials addresses the performance of the plant during the period and will serve as the basis for the meeting discussion. It is available on the NRC web site at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/ferm_2007q4.pdf The NRCs assessment concluded that the Fermi plant operated safely during the period.
The NRC uses color-coded inspection findings and performance indicators to assess nuclear plant performance. The colors start with green and then increase to white, yellow or red, commensurate with the safety significance of the issues involved.
All of the inspection findings and performance indicators for Fermi during 2007 were determined to be green. As a result of this performance, the NRC will conduct the normal, baseline level of inspections during the upcoming year.
The NRC letter to the utility identified a substantive cross-cutting issue in the area of human performance. The issue is referred to as cross-cutting because it affects multiple areas of plant performance. The letter discussed 14 inspection findings whose root causes were associated with the cross-cutting issue of human performance.
Five of these findings were associated with deficiencies in plant procedures. Five additional findings were associated with the plant employees failures to adhere to existing plant procedures.
The NRCs letter to the utility expressed concern with the plants ability to follow work instructions and follow established procedures.
The letter also recognized the plants recent corrective actions to address the cross cutting issue in the area of human performance. However more time is required to evaluate the effectiveness of the plants efforts. The NRC will continue to monitor the plants implementation of the proposed corrective actions.
Routine inspections are performed by two NRC Resident Inspectors assigned to the plant and by inspection specialists from the Region III Office in Lisle, Ill., and the agencys headquarters in Rockville, Md. Among the areas of plant operations to be inspected this year by NRC specialists are emergency preparedness, radiation protection, and reactor system operations.
Current performance information for Fermi is available on the NRCs web site at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/FERM2/ferm2_chart.html.