NL-17-0917, Response to Request for Additional Information Regarding Relief Requests RR-16, RR-17. RR-21 and RR-22

From kanterella
Jump to navigation Jump to search

Response to Request for Additional Information Regarding Relief Requests RR-16, RR-17. RR-21 and RR-22
ML17151A914
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 05/31/2017
From: Wheat J
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-17-0917
Download: ML17151A914 (11)


Text

~ Southern Nuclear Justin T. Wheat Nuclear Licensing Manager

-10 lmeme" Center PJJ~w.Jy Post Oflke Box 1295 Birm111gh.m1. AI. i52-12 205 992 5998 tel 205 992 76111 fax

)twhedt @;outhernco.com May31,2017 Docket Nos.: 50-321 NL-17-0917 50-366 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. H ~tch Nuclear Plant Response to Request for Additional Information Regarding Relief Requests RR-16, RR-17. RR-21 and RR-22 Ladies and Gentlemen:

By letter dated December 27, 2016 (Agencywide Documents Access and Management System Accession No. ML16362A273), Southern Nuclear Operating Company (SNC) submitted 11 Requests for Relief associated with the fourth 10-year Interval lnservice Inspection (lSI) Program for the Edwin I. Hatch Nuclear Plant (HNP), Units 1 and 2. The Nuclear Regulatory Commission (NRC) staff reviewed the information provided regarding relief requests RR-16, RR-17, RR-21, and RR-22, and determined that additional information is needed to complete its evaluation. The Enclosure provides the SNC response to the NRC request for additional information.

This letter contains no new NRC commitments. If you have any questions, please contact Ken McElroy at 205.992.7369.

Respectfully submitted,

~~~

Nuclear Licensing Manager JJH/RMJ/cg

Enclosure:

SNC Response to NRC RAI

Attachment:

Coverage Plots 2C-1 Vessel to Flange Weld cc: Regional Administrator, Region II NRR Project Manager- Hatch Senior Resident Inspector- Hatch RType: CHA02.004

Edwin I. Hatch Nuclear Plant Response to Request for Additional Information Regarding Relief Requests RR-16, RR-17, RR-21 and RR-22 Enclosure SNC Response to NRC RAI

Enclosure to NL-17-0917 SNC Response to NRC RAI RR-16

1. Please provide any plant-specific and industry-wide operating experience of detected flaws in the nozzle-to-vessel welds subject to relief request RR-16, since some of the welds had limited coverage (e.g., approximately 32% coverage was obtained for weld number 1B 11\1 N4C). Were any flaws or degradation identified in past examinations of the welds subject to relief request RR-16, and if so, how were the flaws dispositioned?

SNC Response No relevant industry experience was found. Below is a list of 4th interval B-D inspections with indications and dispositions. All the inspections were compared against the previous interval examinations with no changes in data.

1B11\1N2H(N-SH) 3 relevant indications were found. These indications were sub-surface. They did not have a measurable through wall to make them ID connected. The !indications were not service induced nor surface connected. The indications were from fabrication issues and were found to be acceptable per IWB-3512.

1B 11\1 N2K{N-SH) 2 relevant indications were found . These indications were sub-surface. They did not have a measurable through wall to make them ID connected. The indications were not service induced nor surface connected. The indications were from fabrication issues and were found to be acceptable per IWB-3512.

1B11\1 N3A(SH-N) 2 indications were found. Previous inspections found acceptable indications per IWB-3512. However, due to more reliable PDI exams, the flaws did not pass the acceptance criteria of IWB-3512 in the 4th Interval examination. The indications were evaluated per IWB-361 0 and were found to be acceptable. The evaluation was sent to the NRC (ML060610658).

1B11\1N3B(SH-N) 6 indications were found. These indications were sub-surface. They did not have a measurable through wall to make them ID connected. The indications were not service induced nor surface connected. The indications were from fabrication issues and were found to be acceptable per IWB-3512.

1B11\1 N4C(N-SH) 1 indication was found. This indication was sub-surface. It did not have a measurable through wall to make it ID connected. The indication was not service induced nor surface connected. The indication was from fabrication issues and was found to be acceptable per IWB-3512.

1B 11\1 N4D(N-SH) 2 indications were found. These indications were sub-surface. They did not have a measurable through wall to make them ID connected. The indications were not service induced nor surface connected. The indications were from fabrication issues and were found to be acceptable per IWB-3512.

E-1

Enclosure to NL-17-0917 SNC Response to NRC RAI 2B11\2N1A(SH-N) 4 indications were found. These indications were sub-surface. They did not have a measurable through wall to make them ID connected. The indications were not service induced nor surface connected. The indications were from fabrication issues and were found to be acceptable per IWB-3512.

2B11\2N2C(N-SH) 4 indications were found. These indications were sub-surface. They did not have a measurable through wall to make them ID connected. The indications were not service induced nor surface connected. The indications were from fabrication issues and were found to be acceptable per IWB-3512.

2B11\2N2E(N-SH) 1 indication was found . This indication was sub-surface. It did not have a measurable through wall to make it ID connected. The indication was not service induced nor surface connected. The indication was from fabrication issues and was found to \be acceptable per IWB-3512.

2B11\2N2H(N-SH) 5 indications were found. These indications were sub-surface. They did not have a measurable through wall to make them ID connected. The indications were not service induced nor surface connected . The indications were from fabrication issues and were found to be acceptable per IWB-3512.

2B11\2N4C(N-SH) 2 indications were found. These indications were sub-surface. They did not have a measurable through wall to make them ID connected. The indications were not service induced nor surface connected. The indications were from fabrication issues and were found to be acceptable per IWB-3512.

RR-17

2. Were any flaws or degradation identified in the past examination of the welds subject to relief request RR-17, and if so, how were the flaws dispositioned?

SNC Response Below is a list of 41h interval B-A inspections with indications and dispositions. All the inspections were compared against the previous interval examinations with no changes in data.

2B11\2C-1 3 relevant indications found. These indications were sub-surface. They did not have a measurable through wall to make them ID connected. The indications were not service induced nor surface connected. The data was evaluated per the requirements of IWB-351 0 and found to be acceptable.

3. It is not clear how the three thermocouple pads are positioned around the shell circumference and obstructing the examinations. Please provide a diagram that E-2

Enclosure to NL-17-0917 SNC Response to NRC RAI illustrates the position and size of the thermocouple pads on the shell side of the weld around the circumference.

SNC Response The thermocouple pads are 2.0 inches in diameter, 4.0 inches in separation (center to center) at oo, 135° and 270° on the shell side of the weld. The Attachment to this letter shows an excerpt from the General Electric Hitachi (GEH) nondestructive examination (NDE) report showing approximate placement within the examination area.

RR-21

4. Were any flaws or degradation identified in the past examination of the welds subject to relief request RR-21, and if so, how were the flaws dispositioned?

SNC Response No recordable indications were found during the 41h interval C-A inspections. All the inspections were compared against the previous interval examinations with no changes in data.

5. The staff reviewed the October 17, 1995 submittal identified under Section 8 (Precedents) of RR-21. In this submittal (which corresponds to a similar relief request for the third interval for weld 2E11-2HX-A-1 ), it is stated that 72% of the required volume was inspected. Please discuss the rationale and basis for the decrease in coverage to 40% during the fourth interval from 72% during the third interval.

SNC Response Upon review of the initial submittal of RR-5 and the data sheets from the examination, the 72% percent coverage contained in the submittal for 2E11-2HX-A-1 was actually 72" of coverage out of 180" of total weld length, or 40% (72"/180"). The volume calculation has been consistent when comparing examination results. The figure on the next page shows the configuration documented in the data sheets. This error has since been documented in the SNC Corrective Action Program (CAP).

E-3

Enclosure to NL-17-0917 SNC Response to NRC RAI N

I 2r TOTAL EXAM TOTAL CIRCUMFERENCE= 180 "

TOTAL INCHES UNOBSTRUCTED= 72" 72/180 = 40% OF EXAM VOLUME 2E11-2HX-A-1 TOP VIEW 2E11-2HX-A-1 Configuration E-4

Enclosure to NL-17-0917 SNC Response to NRC RAI RR-22

6. Were any flaws or degradation identified in the past examination of the welds subject to relief request RR-22, and if so, how were the flaws dispositioned?

SNC Response Below is a list of 41h interval C-8 inspections with indications and dispositions. All the inspections were compared against the previous interval examinations with no changes in data unless noted below.

2E11-2HX-A-O 2 flaw type indications were found. 1st flaw was characterized as porosity and validated by original RT film.

2nd flaw was characterized as slag and validated by original RT film. The indications were from fabrication issues and were found to be acceptable per IWC-3511. None of the flaws had degradation. I 1E11-2HX-A-I 2 flaw type indications were found. The indications were evaluated per IWB-3600 using an analytical evaluation and found acceptable. The evaluation was submitted to the NRC (ML081280092). These surface planar flaws were not previously noted.

7. It is stated that "two UT indications were recorded on weld 1E11-2HX-A-I" and a fracture mechanics and fatigue crack growth evaluation was performed. It is then stated that "the flaw is acceptable" based on the evaluation. Please confirm that the indications were first evaluated to the requirements of ASME Section XI, IWB-3500 and that the analyses performed by Structural Integrity Associates were evaluated to the requirements of IWB-3600. Please also confirm that the flaw size assumed in the flaw evaluation bounds the size of the two UT indications.

SNC Response As referenced in the original submittal to the NRC for the flaw evaluation (ML081280092), the indications were evaluated against the acceptance standards of Table IWC-3410-1 and IWC-3511 of ASME Section XI, 2001 Edition with Addenda through 2003. The analytical evaluation of the flaws was performed per the requirements of IWC-361 0 which references IWB-361 0 for the acceptance criteria.

I . .IS boun d.mg.

Th e fl aw s1ze use d.In th e analYSIS Flaws Depth Length Depth/Length (in) (in)

Flaw #1 0.12 0.75 0.16 Flaw#2 0.18 0.80 0.225 Flaw #3, Assumed 0.18 0.90 0.20 Flaw Since Flaw #2 is larger than Flaw #1 , both in the depth and the length directions, only Flaw #2 needs to be considered. Assuming the all for Flaw #2 to be 0.2 makes the flaw longer and thus more conservative.

E-5

Enclosure to NL-17-0917 SNC Response to NRC RAI The fatigue crack growth (Section 6.2.4) was performed using an initial crack of depth=

=

0.18 inch and length 0.9 inch (all 0.2). =

For further clarification, ignore a/1, and only compare the depths and the lengths of the flaws. The flaw assumed for further analysis (Flaw #3) is larger than the observed flaws as shown in the sketch below.

Crack size Flaw3 considered in the analysis Flaw2 Flaw 1 E-6

Edwin I. Hatch Nuclear Plant Response to Request for Additional Information Regarding Relief Requests RR-16, RR-17, RR-21 and RR-22 Attachment 1 Coverage Plots 2C-1 Vessel to Flange Weld

Attachment to NL-17-0917 Coverage Plots 2C-1 Vessel to Flange Weld 8 HITACHI Coverage Plot 2C-1 Vessel to Flange Weld 400" 200" 100" 0" Range 8

Thermocouples Flange Weld The Thermocouple pads are 2.0 inches i n diameter , 4 . 0 inches separation center to center at 0 , 135 and 27 0 degrees .

2N12A They are a few inches from the weld on the shell side .

Automated UT and Manual UT examination patches In the graphic above, the red boxes with numbered circles indicate automated scan areas. The blue boxes indicate where manual scans were performed in the location of the thermocouples to achieve greater coverage.

A-1

e Attachment to NL-17-0917 Coverage Plots 2C-1 Vessel to Flange Weld HITACHI Coverage Plot 2C-1 Vessel to Flange Weld 700" 600" 500" 400" Flange 2C-1 J/

730.50" (i) @

Thermocoupk!s Range Weld 2N12B uI

.-1 I

~

Automated Ul and Manual UT examination patches In the graphic above, the red boxes with numbered circles indicate automated scan areas. The blue boxes indicate where manual scans were performed in the location of the thermocouples to achieve greater coverage.

A-2