Letter Sequence Supplement |
---|
|
|
MONTHYEARNL-09-0586, Unit 2, VEGP-ISI-RR-01, Version 1.0, Relief Request in Accordance with 10 CFR 50.55a(g)(5)(iii)2009-04-23023 April 2009 Unit 2, VEGP-ISI-RR-01, Version 1.0, Relief Request in Accordance with 10 CFR 50.55a(g)(5)(iii) Project stage: Request NL-09-1410, VEGP-ISI-RR-01, Version 1.0, Relief Request in Accordance with 10 CFR 50.55a(g)(5)(iii)2009-09-0909 September 2009 VEGP-ISI-RR-01, Version 1.0, Relief Request in Accordance with 10 CFR 50.55a(g)(5)(iii) Project stage: Request ML0928802332009-10-19019 October 2009 Supplemental Information Needed for Acceptance of Requested Licensing Action Relief Request VEGP-ISI-ALT-04 Project stage: Acceptance Review NL-09-1739, Supplemental Information Regarding VEGP-ISI-RR-01, Version 1.0 (Unit 2), Relief Request in Accordance with 10 CFR 50.55a(g)(5)(iii) and VEGP-ISI-ALT-04, Version 2, Alternative in Accordance with 10 CFR 50.55a(a)(3)(i)2009-10-26026 October 2009 Supplemental Information Regarding VEGP-ISI-RR-01, Version 1.0 (Unit 2), Relief Request in Accordance with 10 CFR 50.55a(g)(5)(iii) and VEGP-ISI-ALT-04, Version 2, Alternative in Accordance with 10 CFR 50.55a(a)(3)(i) Project stage: Supplement NL-10-0335, Request for Additional Information Regarding VEGP-ISI-ALT-04, Version 2, Alternative in Accordance with 10CFR50.55a(a)(3)(i)2010-02-25025 February 2010 Request for Additional Information Regarding VEGP-ISI-ALT-04, Version 2, Alternative in Accordance with 10CFR50.55a(a)(3)(i) Project stage: Request ML1009001292010-06-11011 June 2010 Relief Requests VEGP-ISI-ALT-04 (Units 1 and 2) and VEGP-ISI-RR-01 (Unit 2) Inservice Inspection Alternatives for Third and Subsequent Inservice Inspection Intervals (TAC Nos. ME2226, ME2227, and ME1134) Project stage: Other 2009-04-23
[Table View] |
|
---|
Category:Inservice/Preservice Inspection and Test Report
MONTHYEARNL-24-0031, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R232024-01-29029 January 2024 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 NL-23-0745, Refueling Outage 1R24 Steam Generator Tube Inspection Report2023-09-22022 September 2023 Refueling Outage 1R24 Steam Generator Tube Inspection Report NL-23-0584, Preservice Inspection Program Owner'S Activity Report2023-07-10010 July 2023 Preservice Inspection Program Owner'S Activity Report NL-23-0541, Inservice Inspection Program Owners Activity Report for Outage 1R242023-06-28028 June 2023 Inservice Inspection Program Owners Activity Report for Outage 1R24 NL-22-0778, Refueling Outage 2R22 Steam Generator Tube Inspection Report2022-09-30030 September 2022 Refueling Outage 2R22 Steam Generator Tube Inspection Report NL-22-0512, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R222022-07-0101 July 2022 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R22 ML22180A2612022-06-29029 June 2022 Proposed Inservice Testing Alterative ALT-VR-01 ND-22-0254, Submittal of Inservice Testing Program Plan - 1st Interval, Version 2.02022-04-0707 April 2022 Submittal of Inservice Testing Program Plan - 1st Interval, Version 2.0 ND-22-0253, Submittal of Preservice Test Plan - Version 4.02022-04-0707 April 2022 Submittal of Preservice Test Plan - Version 4.0 NL-22-0227, Refueling Outage 1R23 Steam Generator Tube Inspection Report2022-04-0101 April 2022 Refueling Outage 1R23 Steam Generator Tube Inspection Report NL-21-1130, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1 R232022-01-0303 January 2022 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1 R23 NL-21-0767, Proposed Alternative Requirements for the Repair of Reactor Vessel Head Penetrations for the 4th 10-Year Inservice Inspection Internal (VEGP-ISI-ALT-04-05, Version 1.0)2021-09-10010 September 2021 Proposed Alternative Requirements for the Repair of Reactor Vessel Head Penetrations for the 4th 10-Year Inservice Inspection Internal (VEGP-ISI-ALT-04-05, Version 1.0) NL-21-0381, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R212021-04-26026 April 2021 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R21 NL-20-1312, Response to Request for Additional Information Related to Proposed Inservice Inspection Alternative VEGP-ISI-ALT-04-04 Version 2.02020-11-23023 November 2020 Response to Request for Additional Information Related to Proposed Inservice Inspection Alternative VEGP-ISI-ALT-04-04 Version 2.0 NL-20-1329, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1 R222020-11-23023 November 2020 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1 R22 NL-20-1086, Refueling Outage 1R22 Steam Generator Tube Inspection Report2020-09-17017 September 2020 Refueling Outage 1R22 Steam Generator Tube Inspection Report NL-20-1011, Proposed Inservice Inspection Alternative VEGP-ISI-ALT-04-04 Version 2.02020-09-0909 September 2020 Proposed Inservice Inspection Alternative VEGP-ISI-ALT-04-04 Version 2.0 ND-20-0645, Submittal of Preservice Test Plan - Version 3.02020-06-0303 June 2020 Submittal of Preservice Test Plan - Version 3.0 ND-20-0601, Submittal of Inservice Testing Program Plan - 1st Interval2020-05-21021 May 2020 Submittal of Inservice Testing Program Plan - 1st Interval ND-19-1416, Report of 10 CFR 50.59 Changes, Tests and Experiments and 10 CFR 52 Appendix D Departure Report2019-12-0909 December 2019 Report of 10 CFR 50.59 Changes, Tests and Experiments and 10 CFR 52 Appendix D Departure Report NL-19-1094, Refueling Outage 2R20 Steam Generator Tube Inspection Report2019-09-10010 September 2019 Refueling Outage 2R20 Steam Generator Tube Inspection Report ND-19-0747, Preservice Test Plan, Version 2.02019-07-24024 July 2019 Preservice Test Plan, Version 2.0 NL-19-0712, Submittal of Inservice Inspection Program Owner'S Activity Report for Outage 2R202019-06-26026 June 2019 Submittal of Inservice Inspection Program Owner'S Activity Report for Outage 2R20 NL-19-0204, R21 Steam Generator Tube Inspection Report2019-03-21021 March 2019 R21 Steam Generator Tube Inspection Report NL-18-1571, Proposed ISI Alternative VEGP-ISI-ALT-19-01 for Tendon Inservice Inspection Extension2019-02-18018 February 2019 Proposed ISI Alternative VEGP-ISI-ALT-19-01 for Tendon Inservice Inspection Extension NL-18-1565, Inservice Inspection Program Owner'S Activity Report for Outage 1R212019-01-0303 January 2019 Inservice Inspection Program Owner'S Activity Report for Outage 1R21 ND-18-1504, Report of 10 CFR 50.59 Changes, Tests and Experiments and 10 CFR 52 Appendix D Departure Report2018-12-0707 December 2018 Report of 10 CFR 50.59 Changes, Tests and Experiments and 10 CFR 52 Appendix D Departure Report ND-18-1401, Request for Alternative: Alternative Requirements for Preservice Testing of Explosively Actuated Valves (VEGP 3&4-PST-Alt-01)2018-11-29029 November 2018 Request for Alternative: Alternative Requirements for Preservice Testing of Explosively Actuated Valves (VEGP 3&4-PST-Alt-01) ND-18-1185, Request for Alternative: Preservice and Inservice Inspection Requirements for Specific Valve-to-Pipe Welds (VEGP 3&4-PSI/ISI-ALT-06)2018-10-19019 October 2018 Request for Alternative: Preservice and Inservice Inspection Requirements for Specific Valve-to-Pipe Welds (VEGP 3&4-PSI/ISI-ALT-06) ND-18-1014, Request for Alternative: Alternative Requirements for Preservice Examination Volumetric Surface Configuration Requirements (VEGP 3&4 - PSI/ISI-ALT-10)2018-07-26026 July 2018 Request for Alternative: Alternative Requirements for Preservice Examination Volumetric Surface Configuration Requirements (VEGP 3&4 - PSI/ISI-ALT-10) NL-17-2128, Inservice Inspection Program Owner'S Activity Report for Outage 2R192017-12-21021 December 2017 Inservice Inspection Program Owner'S Activity Report for Outage 2R19 NL-17-1197, Fourth Ten-Year Interval Lnservice Testing Program Update2017-10-23023 October 2017 Fourth Ten-Year Interval Lnservice Testing Program Update NL-17-1641, Submittal of 1R20 Steam Generator Tube Inspection Report2017-09-27027 September 2017 Submittal of 1R20 Steam Generator Tube Inspection Report NL-17-1157, Transmittal of 1R20 ISI Report Summary2017-06-30030 June 2017 Transmittal of 1R20 ISI Report Summary NL-17-0659, Response to Request for Additional Information Re VEGP-ISI-ALT-13 Category B-N-2 and B-N-3 Examination Extension from 10 to 20 Years2017-04-20020 April 2017 Response to Request for Additional Information Re VEGP-ISI-ALT-13 Category B-N-2 and B-N-3 Examination Extension from 10 to 20 Years NL-17-0101, Proposed Alternative VEGP-ISI-AL T-13 in Accordance with 10 CFR 50.55a(z)(2) to Extend B-N-2 and B-N-3 Inservice Inspection Examinations Schedule2017-01-26026 January 2017 Proposed Alternative VEGP-ISI-AL T-13 in Accordance with 10 CFR 50.55a(z)(2) to Extend B-N-2 and B-N-3 Inservice Inspection Examinations Schedule NL-16-1609, Refueling Outage 2R18 Steam Generator Tube Inspection Report2016-09-13013 September 2016 Refueling Outage 2R18 Steam Generator Tube Inspection Report NL-16-1329, Proposed Inservice Inspection Alternative VEGP-ISI-ALT-11, Version 2.0 and Proposed Inservice Inspection Alternative FNP-ISI-ALT-19, Version 2.02016-08-0404 August 2016 Proposed Inservice Inspection Alternative VEGP-ISI-ALT-11, Version 2.0 and Proposed Inservice Inspection Alternative FNP-ISI-ALT-19, Version 2.0 NL-16-1242, Submittal of the Inservice Testing Program Relief Request and Alternatives for Pumps and Valves - Fourth Ten-Year Interval2016-07-28028 July 2016 Submittal of the Inservice Testing Program Relief Request and Alternatives for Pumps and Valves - Fourth Ten-Year Interval NL-16-0927, 2R18 Lnservice Inspection Report Summary2016-06-27027 June 2016 2R18 Lnservice Inspection Report Summary NL-16-0081, Submittal of 1R19 Inservice Inspection Report Summary2016-01-20020 January 2016 Submittal of 1R19 Inservice Inspection Report Summary NL-15-0058, 2R17 Inservice Inspection Report Summary2015-01-12012 January 2015 2R17 Inservice Inspection Report Summary NL-14-1276, Snubber Inspection Plan Submittal in Accordance with ASME OM Code2014-10-31031 October 2014 Snubber Inspection Plan Submittal in Accordance with ASME OM Code NL-14-1081, R18 Inservice Inspection Report Summary2014-07-11011 July 2014 R18 Inservice Inspection Report Summary NL-13-2036, Sixteenth Maintenance / Refueling Outage Steam Generator Tube Inspection Report2013-09-26026 September 2013 Sixteenth Maintenance / Refueling Outage Steam Generator Tube Inspection Report ML13184A2692013-07-0202 July 2013 R16 Inservice Inspection Report Summary NL-13-0090, 1R17 Inservice Inspection Report Summary2013-01-16016 January 2013 1R17 Inservice Inspection Report Summary ML12314A4192012-11-15015 November 2012 Review of the 2011 Steam Generator Tube Inservice Inspection Report ML12249A1932012-09-11011 September 2012 Review of the 2011 Refueling Outage Steam Generators Tube Inservice Inspection Report NL-12-0067, Unit 2 - 2R15 Inservice Inspection Report Summary2012-01-10010 January 2012 Unit 2 - 2R15 Inservice Inspection Report Summary 2024-01-29
[Table view] Category:Letter type:NL
MONTHYEARNL-24-0031, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R232024-01-29029 January 2024 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 NL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report2024-01-22022 January 2024 Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report NL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0827, Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.142023-11-17017 November 2023 Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.14 NL-23-0750, Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr2023-10-0404 October 2023 Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr NL-23-0745, Refueling Outage 1R24 Steam Generator Tube Inspection Report2023-09-22022 September 2023 Refueling Outage 1R24 Steam Generator Tube Inspection Report NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2) NL-23-0666, License Amendment Request: Remove Combined License Appendix C (LAR 23-008)2023-08-28028 August 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-008) NL-23-0670, Response to Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-144832023-08-11011 August 2023 Response to Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483 NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0672, Licensee Guarantees of Payment of Deferred Premiums2023-08-10010 August 2023 Licensee Guarantees of Payment of Deferred Premiums NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-23-0611, Core Operating Limits Report, Cycle 11 Version 12023-07-19019 July 2023 Core Operating Limits Report, Cycle 11 Version 1 NL-23-0584, Preservice Inspection Program Owner'S Activity Report2023-07-10010 July 2023 Preservice Inspection Program Owner'S Activity Report NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement NL-23-0506, to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications2023-07-0505 July 2023 to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications NL-23-0541, Inservice Inspection Program Owners Activity Report for Outage 1R242023-06-28028 June 2023 Inservice Inspection Program Owners Activity Report for Outage 1R24 NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal NL-23-0339, Response to Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters - Operating, Completion Time Extension (LAR-22-002S1)2023-06-13013 June 2023 Response to Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters - Operating, Completion Time Extension (LAR-22-002S1) NL-23-0455, Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report2023-06-12012 June 2023 Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report NL-23-0467, Response to Request for Additional Information Regarding License Amendment Request: Timing of Unit 4 Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005S1)2023-06-0909 June 2023 Response to Request for Additional Information Regarding License Amendment Request: Timing of Unit 4 Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005S1) NL-23-0346, License Amendment Request for Exception to Regulatory Guide 1.163 (LAR 23-007)2023-05-25025 May 2023 License Amendment Request for Exception to Regulatory Guide 1.163 (LAR 23-007) NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. NL-23-0385, License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006R1)2023-05-17017 May 2023 License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006R1) NL-23-0398, Withdrawal of Request of License Amendment Request Regarding More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006)2023-05-16016 May 2023 Withdrawal of Request of License Amendment Request Regarding More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006) NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 NL-23-0360, Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel2023-05-0505 May 2023 Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel NL-23-0326, Response to Apparent Violation in NRC Inspection Report 05000424, 425/2023090; EA-22-1082023-05-0101 May 2023 Response to Apparent Violation in NRC Inspection Report 05000424, 425/2023090; EA-22-108 NL-23-0217, License Amendment Request to Revise Technical Specification Surveillance Requirement 3.4.14.1 and Proposed Inservice Testing Alternative ALT-VR-022023-05-0101 May 2023 License Amendment Request to Revise Technical Specification Surveillance Requirement 3.4.14.1 and Proposed Inservice Testing Alternative ALT-VR-02 NL-23-0330, Core Operating Limits Report, Cycle 25, Version 12023-04-26026 April 2023 Core Operating Limits Report, Cycle 25, Version 1 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 NL-23-0135, License Amendment Request: Timing of Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005)2023-04-17017 April 2023 License Amendment Request: Timing of Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005) NL-23-0019, GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2023-04-12012 April 2023 GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI NL-23-0152, License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-144832023-04-11011 April 2023 License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483 NL-23-0263, Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report2023-04-0505 April 2023 Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report NL-23-0136, License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006)2023-04-0505 April 2023 License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006) NL-23-0132, License Amendment Request: Remove Combined License Appendix C (LAR 23-001)2023-04-0404 April 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-001) NL-23-0014, Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding2023-03-29029 March 2023 Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding NL-23-0208, Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update2023-03-29029 March 2023 Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update NL-23-0193, Request for License Amendment: Relocation of TS 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003)2023-03-24024 March 2023 Request for License Amendment: Relocation of TS 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003) NL-23-0196, Response to Request for Additional Information Regarding License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-4902023-03-24024 March 2023 Response to Request for Additional Information Regarding License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-490 NL-23-0228, Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21)2023-03-20020 March 2023 Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21) NL-22-0977, License Amendment Request to Modify Technical Specification 5.5.11.c Acceptance Criteria for Charcoal Filter Testing2023-02-0909 February 2023 License Amendment Request to Modify Technical Specification 5.5.11.c Acceptance Criteria for Charcoal Filter Testing NL-23-0010, Response to Request for Additional Information Regarding License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-4902023-02-0606 February 2023 Response to Request for Additional Information Regarding License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-490 NL-23-0076, Exigent License Amendment Request: Technical Specification Exceptions for In-containment Refueling Water Storage Tank Operability Prior to Initial Criticality (LAR-23-004)2023-01-31031 January 2023 Exigent License Amendment Request: Technical Specification Exceptions for In-containment Refueling Water Storage Tank Operability Prior to Initial Criticality (LAR-23-004) NL-23-0013, Response to Request for Additional Information Related to 10CFR 50.75 Decommissioning Funding Assurance Requirements2023-01-30030 January 2023 Response to Request for Additional Information Related to 10CFR 50.75 Decommissioning Funding Assurance Requirements NL-23-0068, Responses to NRC Request for Additional Information Related to the Refueling Outage 2R22 Steam Generator Tube Inspection Report2023-01-27027 January 2023 Responses to NRC Request for Additional Information Related to the Refueling Outage 2R22 Steam Generator Tube Inspection Report NL-23-0012, Post-Audit Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel2023-01-20020 January 2023 Post-Audit Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel 2024-01-29
[Table view] |
Text
Southern NI!clea7 Operrlljll~ Company. illc SOUTHERN'\
October 26, 2009 COMPANY Docket Nos.: 50-424 NL-09-1739 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Vogtle Electric Generating Plant - Unit 1 & 2 Supplemental Information Regarding VEGP-ISI-RR-01, Version 1.0 (Unit 2),
Relief Request in Accordance With 10 CFR 50.55a(g)(5)(iii) and VEGP-ISI-ALT 04, Version 2, Alternative in Accordance With 10 CFR 50.55a(a)(3)(i)
Ladies and Gentlemen:
On April 23, 2009, Southern Nuclear Company (SNC) submitted relief request VEGP-ISI-RR-01 which requests relief from performing strand testing on Vogtle Unit 2 containment tendons, applicable for the 3 rd inservice inspection interval.
Per teleconference on July 24,2009, the NRC staff acknowledged RR-L-2 submitted by SNC on April 5, 1999 and approved by the NRC on June 16, 2000 which approved SNC request to align containment tendon schedules for Unit 1 and Unit 2 for the second inspection interval. The staff requested SNC submit a similar request for the 3rd inspection interval.
On July 29, 2009, SNC received a request for additional information (RAI) letter, which contained three (3) questions.
On September 9, 2009, SNC submitted responses to July 29, 2009 RAI letter.
This response contained VEGP-ISI-ALT-04, Version 1, which proposed an administrative Structural Integrity Test (SIT) date to allow SNC to align the testing schedules for IWL-2500 examinations required by IWL-2410(a) and IWL-2420(a).
Per teleconference on October 9, 2009 and confirmed by October 19, 2009 letter, NRC staff has requested SNC provide supplemental information in accordance with the L1C-109 process. The October 19, 2009 letter requested the information by October 26,2009, however in accordance with the LlC-109 process, 13 working days from October 9, 2009 would be October 28, 2009. This was confirmed by NRC staff via telecom on October 20, 2009. contains the SNC responses to the request for supplemental information.
U. S. Nuclear Regulatory Commission NL-09-1739 Page 2 contains VEGP-ISI-ALT-04, Version 2, proposed alternative in accordance with 10 CFR 50.55a(a)(3)(i). VEGP-ISI-ALT-04 requests approval to align Unit 1 and 2 Class CC testing schedules. The proposed alternative contained in VEGP-ISI-ALT -04 would apply to the 3 fd inservice inspection interval and all subsequent inspection intervals for the remainder of plant operating life.
SNC requests approval by May 1, 2010 to support testing scheduled for summer 2010.
This letter contains no NRC commitments. If you have any questions, please advise.
Sincerely,
~~~
M. J. Ajluni Nuclear Licensing Manager MJAlTAH/lc
Enclosures:
- 1. Supplemental Information
- 2. VEGP-ISI-ALT-04, Version 2 cc: Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. T. Tynan, Vice President - Vogtle Ms. P. M. Marino, Vice President - Engineering RType: CVC7000 U. S. Nuclear Regulatory Commission Mr. L. A. Reyes, Regional Administrator Ms. D. N. Wright, NRR Project Manager - Vogtle Mr. M. Cain, Senior Resident Inspector - Vogtle
Vogtle Electric Gen~rating Plant - Unit 1 & 2 Supplemental Information regarding VEGP-ISI-RR-01, Version 1.0 (Unit 2),
Relief Request in Accordance With 10 CFR SO.SSa(g)(S)(iii) and VEGP-ISI ALT -04, Version 2, Alternative in Accordance With 10 CFR SO.SSa(a)(3)(i)
Enclosure 1 Supplemental Information
Vogtle Electric Generating Plant - Unit 1 & 2 Supplemental Information regarding VEGP-ISI-RR-01, Version 1.0 (Unit 2), Relief Request in Accordance With 10 CFR 50.55a(g)(5)(iii) and VEGP-ISI-AL T-04, Version 2, Alternative in Accordance With 10 CFR 50.55a(a)(3)(i)
Enclosure 1 NRC staff has requested SNC provide supplemental information regarding:
- 1. The applicable codes for which the alternative is proposed.
SNC response:
Per VEGP-ISI-ALT -04, Version 1, SNC proposed an alternative to the IWL-2410(b) Concrete inspection schedule and IWL-2420(b) testing schedule for the Unbonded Post-Tensioning Systems. After further review, IWL-2420(b) provides the testing schedule for single unit sites. As indicated in VEGP-ISI-ALT-04, Version 2, the proposed alternative is applicable to IWL-2410(b) Concrete inspection schedule and IWL-2421(b)
Unbonded Post-Tensioning Systems testing schedule for 2 unit sites.
- 2. Clarification of the proposed alternative testing schedule.
SNC response:
Table 1 of VEGP-ISI-ALT-04, Version 2 provides the schedule and scope of all required IWL-2500-1 examinations for Units 1 and 2 through 2030.
- 3. Additional technical information as to why the proposed alternative concrete inspection schedule provides an acceptable level of quality and safety.
SNC response:
Based on the language contained in IWL-2421 (b) and NRC approval of Farley RR-57 and 58 provided in March 28, 2006, the testing schedule contained in VEGP-ISI-AL T-04, Version 1 indicated VogUe would perform IWL-2500-1 Category L-A Concrete inspections on a ten year frequency.
After further review of industry standards, SNC will perform the IWL-2500 1 Category L-A Concrete inspections on a five year frequency as required by IWL-2410(b).
Vogtle Electric Generating Plant - Unit 1 & 2 Supplemental Information regarding VEGP-ISI-RR-01, Version 1.0 (Unit 2),
Relief Request in Accordance With 10 CFR SO.SSa(g)(S)(iii) and VEGP-ISI ALT-04, Version 2, Alternative in Accordance With 10 CFR SO.SSa(a)(3)(i)
Enclosure 2 VEGP-ISI-ALT-04, Version 2
Enclosure 2 SOUTHERN NUCLEAR OPERATING COMPANY VEGP-ISI-ALT-04, VERSION 2.0 PROPOSED ALTERNATIVE IN ACCORDANCE WITH 10 CFRSO.SSa(a)(3)(i) i Plant Site Vogtle Electric Generating Plant -Units 1 and 2 Unit:
Interval-Interval 3rd lSI Interval, May 31, 2007 through May 30, 2017 Dates:
Requested Date for Approval is requested by May 1, 2010 Approval and Basis:
. .- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1 ASMECode The exterior portion of the VEGP-1 and 2 Containment Buildings.
Components fabricated from concrete and their post-tensioning systems (ASME Section I:
Affected: XI, Table IWL-2500-1, Category L-A and L-B).
Applicable Code ASME Section XI, 2001 Edition through the 2003 Addenda Edition and Addenda:
IWL-2410(a) states: "Concrete shall be examined in accordance with IWL-2510 at 1,3, and 5 years following the completion of the containment Structural Integrity Test CC-6000 and every 5 years thereafter."
IWL-2421 (b) states: "When the conditions of IWL-2421 (a) are met, the inspection dates and examination requirements may be as follows.
Applicable (1) For the containment with the first Structural Integrity Test, all examinations required by IWL-2500 shall be performed at 1, 3, and 10 Code years and every 10 years thereafter. Only the examinations required by Requirements: IWL-2524 and IWL-2525 need be performed at 5 and 15 years and every 10 years thereafter.
(2) For each subsequent containment constructed at the site, all examinations required by IWL-2500 shall be performed at 1, 5, and 15 years and every 10 years thereafter. Only the examinations required by IWL-2524 and IWL-2525 need be performed at 3 and 10 years and every 10 years thereafter."
The Unit 1 Structural Integrity Test (SIT) was completed on August 23, 1986 and the Unit 2 SIT was completed on November 14, 1988. Based on these dates, IWL-2421 (b)(1) and (2) would require all IWL-2500 exams for Unit 1 in 2016 (SIT + 30-years) and Unit 2 in 2013 (SIT + 25 years). Therefore, this alternative is being proposed to allow VEGP to Reason for align the schedule for IWL-2510 and IWL-2520 examinations for both Request: units.
10CFR50.55a was revised in 1996 requiring containment examinations in accordance with ASME Section XI, Subsection IWE and IWL. With this rule change, the VEGP Technical Specifications were amended to I reference containment examinations in accordance with IWE and IWL.
E2-1
Enclosure 2 SOUTHERN NUCLEAR OPERATING COMPANY VEGP-ISI-ALT-04, VERSION 2.0 PROPOSED ALTERNATIVE IN ACCORDANCE WITH 10 CFR 50.55a(a)(3)(i)
Since IWL-2420 requires examinations based upon SIT date, SNC proposes an alternative equivalent to that of previous Technical Specification amendments which have been superseded by the ASME Section XI Code.
The last complete IWL-2500 examinations were performed in 2000 for Unit 1 and 2005 for Unit 2 and only the IWL-2524 and IWL-2525 examinations were performed in 2000 for Unit 2 and 2005 for Unit 1.
Therefore, SNC proposes an examination frequency equivalent to the requirements of the referenced ASME Section XI Code on a slightly altered schedule by "re-baselining" the IWL-2500 examinations in 2010 for both VEGP units. "Re-baselining" results in the examination schedule shown in the table on page 3 below.
VEGP Unit 1 and Unit 2 containments utilize the same pre-stressing system, are essentially identical in design (except Unit 2 tendons were not designed to allow detensioning) and are similarly exposed to the same environmental conditions. The post tensioning operations for VEGP-1 were completed on April 26, 1986 and VEGP-2 on December 31, 1986. Therefore, the VEGP units meet the criteria of IWL-2421 (a) allowing for examinations per IWL-2421 (b).
SNC is proposing to establish a "re-baselining" date for scheduling the 3rd Proposed lSI Interval and subsequent lSI Interval Subsection IWL examinations.
This "re-baselining" date has no impact on the code required examination Alternative frequencies for either unit but will allow VEGP to schedule both unit's and Basis for tendon and strand testing during the same time period. Being able to Use: perform tendon and strand testing on both units during the same time period decreases the cost for mobilization of contractor personnel, increases the efficiency of equipment and personnel resources, allows for more standardization and application of lessons learned between units and still provides and acceptable level of quality and safety for the containment structures.
Table 1 indicates that: 1) Subsection IWL, Table IWL-2500-1, Category L A, Item L 1.11 will be performed on a 5 year frequency, 2) Subsection IWL, Table IWL-2500-1, Category L-B Items will be performed on a 10 year frequency, and 3) Subsection IWL, Table IWL-2500-1, Category L-B, Items L2.30, L2.40 and L2.50 will be performed on a 5 year frequency as required by the code.
Based on the tendon lift off schedule being approved by a previous Technical Specification amendment and the proposed examination frequency being equivalent to that required by the code, this alternative should be granted under 10 CFR 50.55a(a)(3)(i) because the proposed alternative continues to provide an acceptable level of quality and safety.
Alternative 3rd lSI Interval, beginning May 31, 2007 and all subsequent lSI intervals.
Duration:
Precedents: Farley Alternative RR-58 approved via NRC SER dated March 28, 2006.
E2-2
Enclosure 2 SOUTHERN NUCLEAR OPERATING COMPANY VEGP-ISI-ALT-04, VERSION 2.0 PROPOSED ALTERNATIVE IN ACCORDANCE WITH 10 CFR 50.55a(a)(3)(i)
VEGP Technical Specifications SR 3.6.1.2 and 5.5.6 (prior to
References:
Amendments 147 (Unit 1) and 127 (Unit 2), dated 12/12/06) previously implemented the alternative examination schedule for lift off testing.
Status: Awaiting NRC approval.
E2-3
Enclosure 2 SOUTHERN NUCLEAR OPERATING COMPANY VEGP-ISI-ALT-04, VERSION 2.0 PROPOSED ALTERNATIVE IN ACCORDANCE WITH 10 CFR SO.SSa(a)(3)(i)
Table 1 - Proposed IWL Examination Schedule Re-Baselil1~ng Date of 0810 1/20 I 0 for Appl ication of FutureI~§xa.minations (L)
Unit 1 All Table IWL- Only Table IWL- All Table IWL- Only Table IWL- All Table IWL-
- 2500-1, Cat. L-A & 2500-1, Cat. L-A, 2500-1, Cat. L-A & 2500-1, Cat. L-A, 2500-1, Cat. L-A &
L-B Item L 1.11 + Cat L L-B Item L 1.I I + Cat. L-B B, Item L2.30, L2.40 L-B, Item L2.30, and L2.50 L2.40 and L2.50 08/01110 (I) 08/01liS (1) 08/0 lI20 (I) 08/01l2S (I) 08/0 1I30 (l)
Unit 2 All Table IWL- Only Table IWL- All Table IWL- Only Table IWL- All Table IWL-2500-1, Cat. L-A & 2500-1, Cat. L-A, 2500-1, Cat. L-A & 2500-1, Cat. L-A, 2500-1, Cat. L-A &
L-B as modified by Item L 1. I 1 + Cat. L-B as modified by Item L 1.11 + Cat. L-B as modified by VEGP-ISI-RR-O I L-B, Item L2.30, VEGP-ISI-RR-Ol L-B, Item L2.30, VEGP-ISI-RR-OI L2.40 and L2.50 L2.40 and L2.50 08/01/10 (ll 08/0IIIS (I) 08/0 1I20 (I) 08/0 1I2S (I) 08/0 1I30 (I)
Foot notes:
(1) +/- 1 year means that examinations shall commence no earlier than 1 year prior to the specified date and shall be completed no more than 1 year after specified date (as allowed by IWL-241 O(c) and IWL-2420(c)).