NL-03-2137, Unit 1 Cycle 21 Core Operating Limits Report (Colr), Revision 2

From kanterella
(Redirected from NL-03-2137)
Jump to navigation Jump to search
Unit 1 Cycle 21 Core Operating Limits Report (Colr), Revision 2
ML033000209
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 10/22/2003
From: Sumner H
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-03-2137
Download: ML033000209 (36)


Text

H.L Sumner, Jr. Southern Nuclear Vice President Operating Company, Inc.

Hatch Project Post Office Box 1295 Birmingham. Alabama 35201 Tel 205.992.7279 SOUTHERNAZ COMPANY October 22, 2003 Energy to ServeYour World' Docket No.: 50-32 i NL-03-2137 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant Unit I Cycle 21 Core Operating Limits Report (COLR), Revision 2 Ladies and Gentlemen:

In accordance with Technical Specification 5.6.5, Southern Nuclear Operating Company (SNC) hereby submits the Edwin I. Hatch Nuclear Plant Unit I Cycle 21 Core Operating Limits Report, Revision 2.

This revision is needed to reflect the fact that power distribution limits monitoring will be required at core thermal power levels greater than or equal to 24% of rated core thermal power when the 1.5% Thermal Power Optimization (TPO) uprate is implemented on Unit 1.

Also, due to recent changes in the Oscillation Power Range Monitor (OPRM) setpoints on Unit 1, Revision 2 of the Hatch-l Cycle 21 COLR is being updated to include additional Period Based Detection Algorithm (PBDA) amplitude setpoints in Section 4.0.

This letter contains no NRC commitments. If you have any questions, please advise.

Sincerely, H. L. Sumner, Jr.

HLS/whc/daj

-D (D i

U. S. Nuclear Regulatory Commission NL-03-2137 Page 2

Enclosure:

Unit I Cycle 21 Core Operating Limits Report, Revision 2 cc: Southern Nuclear Operating Companv Mr. J. D. Woodard, Executive Vice President Mr. G. R. Frederick, General Manager - Plant Hatch Document Services RTYPE: CHAO2.004 U. S. Nuclear Regulatory Commission Mr. L. A. Reyes, Regional Administrator Mr. S. D. Bloom, NRR Project Manager - Hatch Mr. D. S. Simpkins, Senior Resident Inspector - Hatch

SOUTHERN NUCLEAR OPERATING COMPANY EDWIN I. HATCH NUCLEAR PLANT Unit I Cycle 21 CORE OPERATING LIMITS REPORT Revision 2 Southern Nuclear Operating Company Post Office Box 1295 Birmingham, Alabama 35201

Edwin I. Hatch Nuclear Plant Unit 1 Cycle 21 Core Operating Limits Report TABLE OF CONTENTS Section Title Page 1.0 Introduction 1 2.0 APLHGR Limits 2 3.0 MCPR Operating Limits 14 4.0 PBDA Amplitude Setpoint 28 5.0 References 29 Revision 2

Plant Hatch Unit I Cycle 21 Core Operating Limits Report TABLES Table No. Title Page 2-1 APLHGR Operating Flexibility Options 3 3-1A MCPR Operating Flexibility Options for 16 Cycle Exposures BOC to EOC-2100 3-1 B MCPR Operating Flexibility Options for 17 Cycle Exposures EOC-2100 to EEOC ii Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report FIGURES Figure No. Title Paqe 2-1 Flow-Dependent APLHGR Multiplier 4 (MAPFACF) versus Core Flow .

2-2A Power-Dependent APLHGR Multiplier 5 (MAPFACp) versus Core Power (Bypass Valves Operable and Pressure Regulator Operable) 2-2B Power-Dependent APLHGR Multiplier 6 (MAPFACp) versus Core Power (Bypass Valves Inoperable and Pressure Regulator Operable) 2-2C Power-Dependent APLHGR Multiplier 7 (MAPFACp) versus Core Power (Pressure Regulator Inoperable) 2-3 APLHGR Limit versus Average Planar Exposure 8 (GE14-PIODNAB399-16GZ-IOOT-150-T-2517) 2-4 APLHGR Limit versus Average Planar Exposure 9 (GE13-P9HTB378-6G5.0/6G4.0/1G2.0-IOOT-146-T) 2-5 APLHGR Limit versus Average Planar Exposure 10 (GE13-P9HTB378-6G5.0/6G4.0-IOOT-146-T) 2-6 APLHGR Limit versus Average Planar Exposure 11 (GE14-PIODNAB398-15GZ-IOOT-150-T-2518) 2-7 APLHGR Limit versus Average Planar Exposure 12 (GE13-P9DTB378-6G5.0/6G4.0-IOOT-146-T-2411) 2-8 APLHGR Limit versus Average Planar Exposure 13 (GE13-P9DTB378-6G5.016G4.0/1G2.0-IOOT-146-T)

Hii Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report FIGURES (Continued)

Figure No. Title Paqe 3-1A . Power-Dependent MCPR Limit (MCPRp) versus 18 Core Power from 24% to 28% of Rated Core Power (Bypass Valves Operable) 3-1 B Power-Dependent MCPR Limit (MCPRp) versus 19 Core Power from 24% to 28% of Rated Core Power (Bypass Valves Inoperable) 3-2 Flow-Dependent MCPR Limit (MCPRF) versus 20 Core Flow 3-3A Power-Dependent MCPR Multiplier (Kp) versus 21 Core Power (Pressure Regulator Operable) 3-38 Power-Dependent MCPR Multiplier (Kp) versus 22 Core Power (Pressure Regulator Inoperable) 34A MCPR Limits versus Average Scram Time 23 (BOC to EOC-2100 with EOC-RPT System Operable and Bypass Valves Operable) 3-4B MCPR Limits versus Average Scram Time 24 (BOC to EOC-2100 with EOC-RPT System Inoperable and Bypass Valves Operable) 3-4C MCPR Limits versus Average Scram Time 25 (BOC to EEOC with EOC-RPT System Operable and Bypass Valves Inoperable) 34D MCPR Limits versus Average Scram Time 26 (EOC-2100 to EEOC with EOC-RPT System Operable and Bypass Valves Operable) 3-4E MCPR Limits versus Average Scram Time 27 (EOC-2100 to EEOC with EOC-RPT System Inoperable and Bypass Valves Operable) iv Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report

1.0 INTRODUCTION

The Core Operating Limits Report (COLR) for Plant Hatch Unit 1 Cycle 21 is prepared in accordance with the requirements of Technical Specification 5.6.5.

The core operating limits presented herein were developed using NRC-approved methods (Reference 1). Results from the reload analyses for the fuel in Unit 1 Cycle 21 are documented in References 2, 3, and 4. These analyses are supplemented for the mid-cycle Thermal Power Optimization (TPO) uprate by References 8 and 9. Results from the most recent cycle independent analyses are documented in Reference 5. Revised APLHGR limits for GE1 3 fuel are documented in References 6 and 7.

The following core operating limits are included in this report:

a. Average Planar Linear Heat Generation Rate (APLHGR) - Technical Specification 3.2.1.
b. Minimum Critical Power Ratio (MCPR) - Technical Specification 3.2.2.
c. Maximum allowable scram setpoints for the Period Based Detection Algorithm (PBDA) in the Oscillation Power Range Monitor (OPRM) system.

From a fuel thermal limits perspective, the following limitations are placed on Unit 1 operation with equipment out of service.

Equipment/ Condition Limitation EOC-RPT Out of Service AND Not analyzed Turbine Bypass Valves Inoperable Simultaneously Single-Loop Operation (SLO)

  • s 2000 MWt
  • < 56% Core Flow Also included in this report are the maximum allowable scram setpoints for the Period Based Detection Algorithm (PBDA) in the Oscillation Power Range Monitor (OPRM).

1 Revision 2

Plant Hatch Unit 1Cycle 21 Core Operating Limits Report 2.0 APLHGR LIMITS (Technical Specification 3.2.1)

The APLHGR limit for each fuel assembly is the applicable rated-power, rated-flow APLHGR limit taken from Figures 2-3 through 2-8, multiplied by the smaller of either:

a. The flow-dependent multiplier, MAPFACF, from Figure 2-1, or
b. The power-dependent multiplier, MAPFACp, as determined by Table 2-1.

Since every assembly in the core contains more than one enriched lattice, GESTAR-I1 (Reference 1) requires that the appropriate APLHGR limit from Figures 2-3 through Figures 2-8 be applied to every axial location in the fuel assembly, when APLHGR values are hand-calculated. The limits shown in those figures are the values for the most limiting enriched lattice in each fuel bundle as a function of average planar exposure.

When APLHGR values are determined by the process computer, the lattice type-dependent APLHGR limits are used. Under these conditions, some axial locations may have APLHGR Values exceeding the values shown in the figures.

2 Revision 2

Plant Hatch Unit I Cycle 21 Core Operating Limits Report Table 2-1 APLHGR Operating Flexibility Options Cycle - Bypass Pressure MAPFACp Exposure Valves Regulator  :,Curve BOC to Operable Operable Figure 2-2A EEOC BOC to Inoperable Operable Figure 2-2B EEOC Inoprabl BOC Operable to or Inoperable Figure 2-2C EEOC Inoperable _____ _____

3 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report W1 Core Flow (%of FRted)

MAPFACF = Minimum [1.0, (A+B*F), MAPMULT]

Maximum Core I Flow (% of Rated) A B 107.0 0.4574 0.006758 MAPMULT = 1.0 for F > 61.0 0.86 for F1s 61.0 F = Percent of Rated Core Flow FIGURE 2-1 Flow-Dependent APLHGR Multiplier (MAPFACF) versus Core Flow 4 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report CL 0.8

Il S 60% CORE FLOW (TLO 0Q7

> 60% CORE FLO o 0.5-OA4- . - l .

24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 Core Power (%of Rated)

MAPFACp = A - B (Po-P)

Operating Conditions Values of Variables P F FuelType SLO/TLO A B Po 24 S P < 28 F s 60 GE13/14 SLO/TLO 0.603 0 28 24 s P < 28 F> 60 GE13/14 SLOITLO 0.560 0 28 28 s P < 61.72 All GE13/14 SLOITLO 1.00 0.005224 100 61.72s5 P <71.28 All GE13 SLO/TLO 1.00 0.005224 100 61.72 S P < 71.28 All GE14 TLO 1.00 0.005224 100 71.28 s P All GE13114 TLO 1.00 0.005224 100 71.28 s P All GE13 SLO 0.85 0.000 100 61.72 s P All GE14 SLO 0.80 0.000 100 P = Percent of Rated Core Power F = Percent of Rated Core Flow FIGURE 2-2A Power-Dependent APLHGR Multiplier (MAPFACp) versus Core Power (Bypass Valves Operable and Pressure Regulator Operable) 5 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report to,

l S 6 0% CORE FLOW (TLOa r° 10 0.5 11 - -1 , 60% CORE FLO-I I I :I 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 Core Power (%of Rated)

MAPFACp A - B (PO-P)

Operating Conditions Values of Variables P F Fuel Type SLO/TLO A B Po 24s P<28 Fs 60 GE13/14 SLO/TLO 0.588 0.01167 28 24 s P < 28 F> 60 GE13/14 SLOITLO 0.450 0.00967 28 28 s P < 61.72 All GE13/14 SLO/TLO 1.00 0.005224 100 61.72 s P < 71.28 All GE13 SLOITLO 1.00 0.005224 100 61.72 s P < 71.28 All GE14 TLO 1.00 0.005224 100 71.28s P All GE13/14 TLO 1.00 0.005224 100 71.28 s P All GE13 SLO 0.85 0.000 100 61.72 s P All GE14 SLO 0.80 0.000 100 P = Percent of Rated Core Power F = Percent of Rated Core Flow FIGURE 2-2B Power-Dependent APLHGR Multiplier (MAPFACp) versus Core Power (Bypass Valves Inoperable and Pressure Regulator Operable) 6 Revision 2

Plant Hatch Unit I Cycle 21 Core Operating Limits Report 10*. _.

< 0.9 --

0. ---

CD2 0.7 - - - -

-j I-ci0.5 - - - -

0.4 I1 I I I 24 28 32 1

36 40 44 48 52 56 60 I

64 68 Core Power (%of Pated) 72 76 I.

80 84 88 92 96 100 MAPFACp = A - B (Po-P) 0peratin Conditions Values of Variables P F I Fuel Type I SLOITLO A B lPo 245 P < 40 All I GE13114 SLO/TLO 0.49 0.0058 40 40 s P < 100 All I GE13/14 SLOrrLO 1.00 0.0085 100 P = Percent of Rated Core Power F = Percent of Rated Core Flow FIGURE 2-2C Power-Dependent APLHGR Multiplier (MAPFACp) versus Core Power (PressureRegulatorInoperable) 7 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report Average Planar APLHGR Exposure 0.00 0.20 1.00 Limit 9.59 9.66 9.78 no

~~ [ 77. I 2.00 9.94 UNACCEPTABLEl 3.00 10.06 OPERATION]

4.00 10.19 5.00 10.28 i 9.0 6.00 10.38 7.00 10.48 10.58 E 8.00 E3 8.0 9.00 10.68 ACCEPTABLE 10.00 10.78 OPERATION

-J 11.00 10.89 0. 7.0 12.00 10.91 13.00 10.93 6.0 14.00 10.95 15.00 10.97 17.00 10.94 5.0 20.00 10.80 25.00 10.44 30.00 10.05 4.0 35.00 9.59 0.0 5.0 10.0 1.0 20.0 25.0 30.0 35s 40.0 45.0 50.0 550o 60.0 65.0 40.00 9.07 Average Planar Exposure (GWd/ST) 45.00 8.54 50.00 7.99 55.00 6.16 NOTE: THIS IS THE APLHGR LIMIT FOR THE 57.45 4.92 MOST LIMlTING LATTICE AS A FUNCTION OF AVERAGE PLANAR EXPOSURE.

FIGURE 2-3 APLHGR Limit versus Average Planar Exposure (Bundle Type: GE14-PIODNAB399-16GZ-10OT-150-T-2517) 8 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report Aerage Planar APLHGR 14.0 Exposure Limit 0.00 10.51 1.0 0.20 10.57 ACCEPTABLEi~CE TA LE 1.00 10.73 2.0 2.00 10.97 3.00 11.24 4.00 11.48 no 5.00 11.73 6.00 7.00 11.92 12.06 V.0 OPERATIO[NERA 1O .

8.00 12.21 E

-j 9.00 12.36 0

10.00 12.47 -J 8D 12.50 a.

12.67 15.00 12.57 7.0 17.50 12.36 20.00 12.14 6.0 24.40 11.80 25.00 11.76 30.00 11.38 5.0 35.00 10.70 40.00 10.04 4.0 45.00 9.38 0.0 5.0 D.0 S.0 20.0 25.0 30.0 35.0 40.0 450 50.0 55fD 60.0 50.00 8.72 Average Planar Exposure (GWd/ST) 55.00 7.12 56.70 6.50 57.53 6.19 NOTE: THIS IS THE APLHGR LIMIT FOR THE MOST LIMmNG LAT11CE AS A FUNCTION OF AVERAGE PLANAR EXPOSURE.

FIGURE 2-4 APLHGR Limit versus Average Planar Exposure (Bundle Type: GE13-P9HTB378-6G5.016G4.0/1G2.0-IOOT-146-T) 9 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report Awerage Planar APLHGR 14.0 Exposure 0.00 0.20 Umit 10.64 10.70

__ I UNACCEPTABLE 1.00 10.85 OPERATION 2

12.0 -

2.00 11.06 I . . I , I I , .

3.00 11.30 4.00 11.51 to 1 4o 5.00 11.75 6.00 11.92 7.00 12.06 8.00 12.21 :E 9.0 9.00 12.35 l l l lACCEPTABLE ll l l l II__

v 10.00 12.49 j 8.0 OPERATION 12.50 15.00 17.50 12.69 12.59 12.38 7.0 ,,,, --

20.00 12.16 6.0 F24.40 11.82 25.00 11.78 30.00 11.40 5.0 32.66 11.04 35.00 10.72 4.0 40.00 10.06 0.0 5.0 S0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0 60.0 45.00 9.40 Average Planar BUposure (GWdIST) 50.00 8.74 55.00 7.14 56.70 6.52 NOTE: THIS IS THE APLHGR LIMIT FOR THE 57.54 6.21 MOST LIMmNG LATTICE AS A FUNCTION OF AVERAGE PLANAR EXPOSURE.

FIGURE 2-5 APLHGR Limit versus Average Planar Exposure (Bundle Type: GE13-P9HTB378-6G5.0/6G4.0-10OT-146-T) 10 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report Average Planar APLHGR 120 Exposure Limit 0.00 9.72 0.20 9.79 Ito 1.00 9.89 2.00 10.01 D.0 3.00 10.13 4.00 10.22 5.00 10.31 r 9.0 6.00 10.41 57.00 10.50 :e E

8.00 10.60 80 9.00 10.70 10.00 10.80 - 7

0. 7.0 11.00 10.92 12.00 10.94 13.00 10.96 6.0 X X X -

14.00 10.98 15.00 10.99 17.00 10.96 5.0 1X 1 .:1- .1 '

20.00 10.81 25.00 10.44 30.00 10.05 4.0 -.- .1 1: :- -

0.0 5.0 D.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0 60.0 35.00 9.59 40.00 9.07 Average Planar Exposure (GWdI' ST) 45.00 8.54 50.00 7.99 55.00 6.17 NOTE: THIS IS THE APLHGR LIMIT FOR THE 57.47 MOST LIMmNG LATTICE AS A FUNCTION OF AVERAGE PLANAR EXPOSURE.

FIGURE 2-6 APLHGR Limit versus Average Planar Exposure (Bundle Type: GE14-PIODNAB398-15GZ-IOOT-150-T-2518) 11 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report Aerage Planar APLHGR 14.0 Exposure Limit 0.00 10.83 0.20 10.89 1.00 11.04

'2.0 2.00 11.25 3.00 11.48 4.00 11.73 1¶0 5.00 11.96 6.00 12.14 7.00 12.28 8.00 12.42 :3 9.0 9.00 12.57 10.00 12.71 -i 6.0 0.

12.50 12.69 15.00 12.50 7.0 -

17.50 12.31 20.00 12.13 6.0 -

24.40 11.81 25.00 11.77 30.00 .11.34 5.0 -

32.66 10.99 35.00 10.69 4.0 - I I 40.00 10.04 0.0 5.0 1D.0 5.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0 60.0 45.00 9.40 Average Planar Exposure (GWd/ST) 50.00 8.74 55.00 7.14 56.70 6.51 NOTE: THIS IS THE APLHGR LIMIT FOR THE 57.54 6.20 j MOST LIMING LAT11CE AS A FUNCTION OF AVERAGE PLANAR EXPOSURE.

FIGURE 2-7 APLHGR Limit versus Average Planar Exposure (Bundle Type: GE13-P9DTB378-6G5.0/6G4.0-10OT-146-T-2411) 12 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report Auerage Planar APLHGR 14.0 Exposure Limit 0.00 10.64 o.0 0.20 10.71 1.00 10.88

[UNACCEPTABLE 2.00 3.00 11.12 11.39 Ito 1:f:;E;1AS':.1.'.:1:~~~~~~~________

- __ -- OPERATION I ________

4.00 11.67 5.00 11.93 6.00 12.14 1D.0 7.00 8.00 9.00 12.28 12.42 12.58 E

-j 9.0 I117.9I f11 .1 ACCEPTABLE 171-1 10.00 12.71 0~ 8.0 OPERAllON 12.50 12.69 15.00 12.50 7.0 17.50 12.31 20.00 12.13 6.0 24.40 11.81 25.00 11.77 30.00 11.33 5.0 32.66 10.99 35.00 10.68 4.0 1-Y.

40.00 Dc I 5.0 1D.0 5.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0 60.0 10.04 45.00 9.40 Average Planar Eposure (GWdIST) 50.00 8.74 55.00 7.13 56.70 6.50 NOTE: THIS IS THE APLHGR LIMIT FOR THE 57.53 6.20 MOST LIM flNG LATliCE AS A FUNCTION OF AVERAGE PLANAR EXPOSURE.

FIGURE 2-8 ALPHGR Limit versus Average Planar Exposure (Bundle Type: GE13-P9DTB378-6G5.0/6G4.0/1G2.0-IOOT-146-T) 13 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 3.0 MCPR OPERATING LIMITS (Technical Specification 3.2.2)

The MCPR operating limit (OLMCPR) for each fuel type is a function of core power, core flow, average scram time, number of operating recirculation loops, operability of the EOC-RPT system, operability of the turbine bypass valve system, and whether both pressure regulators are operable.

With both recirculation pumps in operation (TLO), the OLMCPR for each fuel type is determined as follows:

a. For 24% _ power < 28%, the power-dependent MCPR limit, MCPRp, as determined by Table 3-1A or 3-1 B.
b. For power 2 28%, the OLMCPR is the greater of either:
1) The flow-dependent MCPR limit, MCPRF, from Figure 3-2, or
2) The product of the power-dependent multiplier, Kp, and the rated-power, rated-flow MCPR limit as determined by Table 3-1A or 3-1 B.

With only one recirculation pump in operation (SLO), the OLMCPR for each fuel type is the TLO OLMCPR plus 0.02.

These limits apply to all modes of operation with intermittent feedwater temperature reduction, as well as operation with normal feedwater temperatures.

In figures 34A through 3-4E, Option A scram time MCPR limits correspond to X=

1.0, where r is determined from scram time measurements performed in accordance with Technical Specifications Surveillance Requirements 3.1.4.1 and 3.1.4.2. Option B values correspond to r = 0.0. For scram times between Option A and Option B, the MCPR limit for each fuel corresponds to x. If Xrhas not been determined, Option A limits are to be used. Refer to Table 3-1A or 3-1 B to determine the applicable set of fuel-type dependent curves.

14 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report The average scram time of the control rods, r, is defined as:

'ave - TB T = 0, or , whichever is greater.

TA - TB where: TA = 1.08 sec (Technical Specification 3.1.4, Table 3.1.4-1, scram time limit to notch 36).

TB [l + 1.65

  • a
  • Ni EN, where: = 0.822 sec (mean scram time used in the transient analysis).

f = 0.018 sec (standard deviation of l).

n j:NiT, Tave = n Z:Ni i=1 where: n = number of surveillance tests performed to date in the cycle.

N, = number of active control rods measured in the ith surveillance test.

Tj = average scram time to notch 36 of all rods in the ith surveillance test.

N, = total number of active rods measured in Technical Specifications Surveillance Requirement 3.1.4.1.

15 Revision 2

Plant Hatch Unit 1Cycle 21 Core Operating Limits Report TABLE 3-1A MCPR Operating Flexibility Options for Cycle Exposures BOC to EOC-2100 Turbine Pressure Rated-Power, EOC-RPT Bypass Valve Regulator MCPRp. Rated-Flow System System System :Curve Kp Curve MCPR Limits Operable Operable Operable Figure 3-1A Figure 3-3A Figure 3-4A Operable Operable Inoperable Figure 3-1A Figure 3-38 Figure 34A Inoperable Operable Operable Figure 3-1A Figure 3-3A Figure 344B Inoperable Operable Inoperable Figure 3-1A Figure 3-3B Figure 348 Operable Inoperable Operable Figure 3-1B Figure 3-3A Figure 34C Operable Inoperable Inoperable Figure 3-1 B Figure 3-38 Figure 34C BOC = Beginning of Cycle EOC = End of Cycle EEOC = Extended End of Cycle 16 Revision 2

Plant Hatch Unit 1Cycle 21 Core Operating Limits Report TABLE 3-1 B MCPR Operating Flexibility Options for Cycle Exposures EOC-2100 to EEOC Turbine Pressure- Rated-Power, EOC-RPT Bypass Valve Regulator MCPRp Rated-Flow System- System :System, Curve Kp Curve MCPR Limits Operable Operable Operable Figure 3-1A Figure 3-3A Figure 34D Operable Operable Inoperable Figure 3-1A Figure 3-3B Figure 3-4D Inoperable Operable Operable Figure 3-1A Figure 3-3A Figure 34E Inoperable Operable Inoperable Figure 3-1A Figure 3-3B Figure 3-4E Operable Inoperable Operable Figure 3-1 B Figure 3-3A Figure 34C Operable Inoperable Inoperable Figure 3-1 B Figure 3-3B Figure 34C BOC = Beginning of Cycle EOC = End of Cycle EEOC = Extended End of Cycle 17 Revision 2

I Cycle Plant 21- Unit Hatch Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 9W2.8 IL 0. ..

26 C I-'.,'-

MC22- = A ' : '. 8

E IL .

za-2.0 ., . ..

o24 MC= A. ., (8P 25 26 27 28 Core Power (%of Rated)

F A B I 60%

> 60%

2.15 2.5 0

0.03 P = Percent of Rated Core Thermal Power F = Percent of Rated Core Flow FIGURE 3-1A Power-Dependent MCPR Limit (MCPRp) versus Core Power From 24% to 28% of Rated Core Power (Bypass Valves Operable) 18 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 4.0.

40 ..

3.6~~~.

3.8 -_ -.

3.6

-E 3A 3.4 -

Q: 32 -:

3.0 .

c2.8 32.6 2.A - ..

22 -..

24 25 26 27 28 Core Power (% of Mated)

MCPRp = A + B (28-P)

I F

60%

60%

4: A 2.40 3.32 B

0.070 0.1167 I P = Percent of Rated Core Thermal Power F = Percent of Rated Core Flow FIGURE 3-1B Power-Dependent MCPR Limit (MCPRp) versus Core Power From 24% to 28% of Rated Core Power (Bypass Valves Inoperable) 19 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 16 t5 0

E14 0~

U I

'V 13 CL a-0

.2 LL t2 11 30 40 50 60 70 80 90 Core Flow (% of Rated)

MCPRF = Maximum [1.20, (A

  • F + B)]

Maximum Core Flow (% of Rated) A 16B 107.0 -0.00586 1 1.697 F = Percent of Rated Core Flow FIGURE 3-2 Flow-Dependent MCPR Limit (MCPRF) versus Core Flow 20 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report

__ 7 - _

18 - - - -

0.1 EL 14 - - -

Coo to I .

28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 I10 Core Power (%of Rated)

Kp = A + B*(Po-P)

P A B Po 28 s P <45 1.28 0.01340 l 45 45s P<60 l 1.15 I 0.00867 I 60 7 60 P 1.00 0.00375 100 P = Percent of Rated Core Power FIGURE 3-3A Power-Dependent MCPR Multiplier (Kp) versus Core Power (Pressure Regulator Operable) 21 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report

  • 19 - - - -

18 - -

17 - - - -

.9.

16 7 -

15.

14 -  : -l-CL 13- -

0L to 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 10o Core Power (%of Rated)

Kp = A + B*(Po-P) l P I A I B I Po 28< P<100 I 1.00 I 0.010 I 100 l P = Percent of Rated Core Power

- FIGURE 3-3B Power-Dependent MCPR Multiplier (Kp) versus Core Power (Pressure Regulator Inoperable) 22 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 140 138 t36 a 34 E

-i W.

E 132 130 128 n6 0.0 0.1 0.2 0.3 0.4 0.5 0.6 07 0.8 0.9 to Tau Tau GE14 GE1 3 1.37 1.33 1.34 1.28

. . . .~~~~~~~~~~~~~~~~~~~~~~~~~~

FIGURE 3-4A MCPR Limits versus Average Scram Time (BOC to EOC-2100 with EOC-RPT System Operable and Bypass Valves Operable) 23 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report SO en 142 WE

-J 140 C.)

138 0.0 0.1 0.2 0.3 0A 0.5 0.6 0.7 0.8 0.9 to Tau Tau I GE14 I GE13 I 1.0 1.49 1.37 0.0 1.38 1.32 FIGURE 3-4B MCPR Limits versus Average Scram Time (BOC to EOC-2100 with EOC-RPT Sysfem Inoperable and Bypass Valves Operable) 24 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 148 146 144 142 j

.. 140 0:

1138 134 132 0.0 0.1 02 0.3 OA 0.5 0.6 0.7 0.8 0.9 t0 Tau Tau GE14 I GE13 I 1.0 1.46 1.37 0.0 1.43 1 1.34 FIGURE 3-4C MCPR Limits versus Average Scram Time (BOC to EEOC with EOC-RPT System Operable and Bypass Valves Inoperable) 25 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 144 142 t40 El 4 138

-j 136 a-C.,

134 El 3 132 130 t28 0.0 0.1 02 0.3 0.4 0.5 0.6 0.7 0.8 0.9 t0 Tau Tau GE14 GE13 1.0 1.42 1.33 0.0 1.39 1.30 FIGURE 3-4D MCPR Limits versus Average Scram Time (EOC-2100 to EEOC with EOC-RPT System Operable and Bypass Valves Operable) 26 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 164 162 160 158 156 154 152 150 0~

148 C., 146 144 142 140 138 t36 t34 132 0.5 to Tau

[au i1 GE14 GE13 1.62 1.42 1.45 1.34 FIGURE 3-4E MCPR Limits versus Average Scram Time (EOC-2100 to EEOC with EOC-RPT System Inoperable and Bypass Valves Operable) 27 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 4.0 PBDA AMPLITUDE SETPOINT The amplitude trip setpoint in the Period Based Detection Algorithm in the OPRM system shall not exceed the values reported in the Table below. This applies to instruments 1C51 K615 A, B, C, and D. These are the nominal trip setpoint values, not the allowable values. Projected Figure of Merit (FOM) value(s) throughout the cycle will be supplied by the Hatch Core Analysis Group.

OLMCPR 0.0 1FOM S92.1 92.1 <FOM *96.9 96.9 < FOM *102.4 102.4 < FOM *108.0 1.28 1.11 1.10 1.08 1.07 1.29 1.12 1.10 1.08 1.08 1.30 1.12 1.10 1.09 1.08 1.31 1.12 1.10 1.09 1.08 1.32 1.13 1.11 1.09 1.08 1.33 1.13 1.11 1.09 1.09 1.34 1.13 1.11 1.10 1.09 1.35 1.14 1.12 1.10 1.09 1.36 1.14 1.12 1.10 1.09 1.37 1.14 1.12 1.10 1.09 1.38 1.15 1.13 1.11 1.10 1.39 1.15 1.13 1.11 1.10 1.40 1.15 1.13 1.11 1.10 1.41 1.15 1.13 1.11 1.10 1.42 1.15 1.14 1.12 1.11 1.43 1.15 1.14 1.12 1.11 1.44 1.15 1.14 1.12 1.11 1.45 1.15 1.14 1.12 1.11 28 Revision 2

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report

5.0 REFERENCES

1. GE/GNF Report "General Electric Standard Application for Reactor Fuel,"

NEDE-24011-P-A-14, June 2000, and the US Supplement, NEDE-24011-P-A-14-US, June 2000.

2. GNF Report 0000-0002-7058-SRLR, Revision 0, "Supplemental Reload Licensing Report for Edwin I. Hatch Nuclear Power Plant Unit 1, Reload 20 Cycle 21," March 2002.
3. SNC Letter CAH-NF-2370, 'Hatch-1 Cycle 21 Pressure Regulator Out-of-Service ARTS Limits," E. B. Gibson to K. S. Folk, April 8, 2002.
4. SNC Letter CAH-NF-2371, 'GE14 Low Power ARTS Below PBYP With Bypass Valves Inoperable," W. R. Mertz to K. S. Folk, April 8, 2002.
5. GE Report GE-NE-0000-0001-3737-01P, "GE14 Fuel Design Cycle-Independent Analyses for Hatch Units 1 and 2," March 2002.
6. GNF LetterVRU-03-005, "Hatch 1 and 2 Improved MPLHGR Limits," V.

Ruiz-Ugalde to E. B. Gibson, June 26, 2003.

7. GNF Letter EWG-S-03-01 1, "Hatch-1 Bundle 2255 Improved MAPLHGRs," E. W. Gibbs to E. B. Gibson, July 17, 2003.
8. SNC Letter CAH-NF-2435, "Addendum to Hatch-1 Cycle 21 SRLR for TPO Uprate," W. R. Mertz to G. K. McElroy, September 12, 2003.
9. SNC Letter CAH-NF-2436, "H1 C21 TPO Low Power ARTS Multipliers,"

W. R. Mertz to K. S. Folk, September 12, 2003.

29 Revision 2