MONTHYEARND-24-0019, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-02-0101 February 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0912, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-01-0202 January 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0881, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-12-0404 December 2023 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0817, (Vegp), Units 3 and 4 - Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a)2023-11-17017 November 2023 (Vegp), Units 3 and 4 - Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a) ND-23-0823, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-11-0303 November 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0723, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-10-0404 October 2023 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0697, (Vegp), Unit 4, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-09-0505 September 2023 (Vegp), Unit 4, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0669, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-08-0707 August 2023 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0205, (Vegp), Unit 3 - Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2023-07-28028 July 2023 (Vegp), Unit 3 - Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-23-0618, Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797)2023-07-20020 July 2023 Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797) ND-23-0609, Notification of Completion of All ITAAC2023-07-20020 July 2023 Notification of Completion of All ITAAC ND-23-0608, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) ND-23-0607, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) ND-22-0796, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813) ND-23-0459, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587) ND-23-0162, ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165) ND-23-0575, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588) ND-23-0439, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265) ND-23-0552, Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624)2023-07-18018 July 2023 Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624) ND-23-0483, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) ND-23-0586, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2023-07-17017 July 2023 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) ND-23-0610, ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603)2023-07-17017 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603) ND-23-0573, ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497) ND-23-0406, ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498) ND-22-0816, ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19)2023-07-15015 July 2023 ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19) ND-23-0603, ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831) ND-23-0446, ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250) ND-23-0594, ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629) ND-23-0601, ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719) ND-23-0606, ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557) ND-23-0476, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) ND-23-0499, ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700) ND-23-0588, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) ND-23-0121, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667) ND-23-0122, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668) ND-23-0597, ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530) ND-23-0002, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270) ND-23-0111, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) ND-22-0980, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75) ND-23-0587, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) ND-23-0461, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652) ND-23-0543, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622) ND-23-0394, ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703) ND-23-0592, ITAAC Closure Notification on Completion of 2.7.06.03.i (Index Number 726)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of 2.7.06.03.i (Index Number 726) ND-23-0589, ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601) ND-23-0581, ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220) ND-23-0486, ITAAC Closure Notification on Completion of ITAAC 2.2.01.11a.iv (Index Number 117)2023-07-11011 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.01.11a.iv (Index Number 117) ND-23-0559, CFR26.719(c)(1) 30-Day Report for a Blind Sample Analysis Error2023-07-11011 July 2023 CFR26.719(c)(1) 30-Day Report for a Blind Sample Analysis Error ND-23-0443, ITAAC Closure Notification on Completion of ITAAC 2.3.10.07a.ii (Index Number 444)2023-07-0808 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.10.07a.ii (Index Number 444) ND-23-0183, ITAAC Closure Notification on Completion of ITAAC Item 2.3.11.03b (Index Number 454)2023-07-0808 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.3.11.03b (Index Number 454) 2024-02-01
[Table view] Category:License-Application for Combined License (COL) (Amend/Renewal) DKT 52
MONTHYEARNL-23-0346, License Amendment Request for Exception to Regulatory Guide 1.163 (LAR 23-007)2023-05-25025 May 2023 License Amendment Request for Exception to Regulatory Guide 1.163 (LAR 23-007) NL-23-0385, License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006R1)2023-05-17017 May 2023 License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006R1) ML23088A1382023-05-0404 May 2023 Enclosure 9 - Attachment to License Amendment No. 189 for COL No. NPF-91 ML23088A1372023-05-0404 May 2023 Enclosure 8 - Attachment to License Amendment No. 124 for COL No. NPF-92 ML23088A1362023-05-0404 May 2023 Enclosure 7 - Attachment to License Amendment No. 181 for COL No. NPF-92 ML23088A1352023-05-0404 May 2023 Enclosure 6 - Attachment to License Amendment No. 166 for COL No. NPF-92 ML23088A1342023-05-0404 May 2023 Enclosure 5 - Attachment to License Amendment No. 188 for COL No. NPF-91 ML23045A1802023-05-0404 May 2023 Enclosure 4 - Attachment to License Amendment No. 147 for COL No. NPF-92 ML23045A1792023-05-0404 May 2023 Enclosure 3 - Attachment to License Amendment No. 148 for COL No. NPF-91 ML23045A1782023-05-0404 May 2023 Enclosure 2 - Attachment to License Amendment No. 117 for COL No. NPF-92 ML23045A1772023-05-0404 May 2023 Enclosure 1 - Attachment to License Amendment No. 118 for COL No. NPF-91 NL-23-0135, License Amendment Request: Timing of Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005)2023-04-17017 April 2023 License Amendment Request: Timing of Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005) NL-23-0132, License Amendment Request: Remove Combined License Appendix C (LAR 23-001)2023-04-0404 April 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-001) NL-23-0193, Request for License Amendment: Relocation of TS 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003)2023-03-24024 March 2023 Request for License Amendment: Relocation of TS 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003) ML23039A1672023-02-0808 February 2023 Draft LAR to Remove Tier 1 and Tier 2 Star Requirements NL-23-0076, Exigent License Amendment Request: Technical Specification Exceptions for In-containment Refueling Water Storage Tank Operability Prior to Initial Criticality (LAR-23-004)2023-01-31031 January 2023 Exigent License Amendment Request: Technical Specification Exceptions for In-containment Refueling Water Storage Tank Operability Prior to Initial Criticality (LAR-23-004) NL-23-0020, Emergency License Amendment Request: Technical Specification Limiting Conditions for Operation 3.4.11, 3.4.12, and 3.4.13 Operability Requirements for Automatic Depressurization System Stage 4 Flow Paths Prior to Initial Criticality2023-01-12012 January 2023 Emergency License Amendment Request: Technical Specification Limiting Conditions for Operation 3.4.11, 3.4.12, and 3.4.13 Operability Requirements for Automatic Depressurization System Stage 4 Flow Paths Prior to Initial Criticality ND-22-0881, License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002)2023-01-0303 January 2023 License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002) ML22332A5372022-11-28028 November 2022 Draft LAR 23-001 for 12-8-22 Public Meeting ML22284A1312022-11-22022 November 2022 LAR-22-003 U4 Electrical ITAAC Consolidation Amendment No. 187 ML22307A0072022-11-0202 November 2022 Draft LAR for TS 3.8.3 Inverters Operating Completion Time Extension ND-22-0709, Request for License Amendment and Exemption Electrical Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Optimization (LAR-22-003)2022-09-0202 September 2022 Request for License Amendment and Exemption Electrical Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Optimization (LAR-22-003) ML22087A0682022-03-31031 March 2022 Draft LAR 22-001, Unit 4 Security ITAAC for 3-31-22 Public Meeting with SNC ND-21-0772, Request for License Amendment and Exemption: Clarification of ITAAC Regarding Invessel Components (LAR-21-001)2021-08-24024 August 2021 Request for License Amendment and Exemption: Clarification of ITAAC Regarding Invessel Components (LAR-21-001) ML21230A0162021-08-19019 August 2021 Invessel As-built ITAAC Draft LAR 21-001 for 210819 Psm ML20196L6762020-08-11011 August 2020 Amendment 183 - Vogtle Electric Generating Plant Unit 3 for LAR 20-002 ML20132A0522020-08-0303 August 2020 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 20-001) ND-20-0725, Plants Units 3 and 4, Revision to License Amendment Request: Technical Specification 3.3.13 for Main Control Room Emergency Habitability System (Ves) Instrumentation Applicability Change and Include Undervoltage Actuation2020-06-22022 June 2020 Plants Units 3 and 4, Revision to License Amendment Request: Technical Specification 3.3.13 for Main Control Room Emergency Habitability System (Ves) Instrumentation Applicability Change and Include Undervoltage Actuation ND-20-0668, Request for License Amendment for Vacuum Relief Valve Technical Specification Changes (LAR-20-005)2020-06-19019 June 2020 Request for License Amendment for Vacuum Relief Valve Technical Specification Changes (LAR-20-005) ND-20-0464, Request for License Amendment: Technical Specification 3.3.13 for Main Control Room Emergency Habitability System (Ves) Instrumentation Applicability Change and Include Undervoltage Actuation2020-05-0707 May 2020 Request for License Amendment: Technical Specification 3.3.13 for Main Control Room Emergency Habitability System (Ves) Instrumentation Applicability Change and Include Undervoltage Actuation ND-20-0504, Transmittal of Section 404 Permit Modification Request2020-05-0404 May 2020 Transmittal of Section 404 Permit Modification Request ND-20-0507, Request for License Amendment: Core Makeup Tank Boron Concentration Requirements (LAR-20-004)2020-04-30030 April 2020 Request for License Amendment: Core Makeup Tank Boron Concentration Requirements (LAR-20-004) ND-20-0289, Transmittal of NPDES Permit Renewal Application2020-03-31031 March 2020 Transmittal of NPDES Permit Renewal Application ND-20-0266, Revised Request for License Amendment: Reconciliation of Environmental Conditions Inputs to Civil Structural Design Licensing Basis (LAR-19-019R1)2020-03-20020 March 2020 Revised Request for License Amendment: Reconciliation of Environmental Conditions Inputs to Civil Structural Design Licensing Basis (LAR-19-019R1) ND-20-0122, Request for License Amendment: Main Control Room Emergency Habitability System (Ves) Pressure Regulating Valve and Source Range Neutron Flux Doubling Surveillance Changes, and Other Miscellaneous.2020-02-28028 February 2020 Request for License Amendment: Main Control Room Emergency Habitability System (Ves) Pressure Regulating Valve and Source Range Neutron Flux Doubling Surveillance Changes, and Other Miscellaneous. ND-20-0075, Request for License Amendment and Exemption: Unit 3 Auxiliary Building Wall 11 Seismic Gap Requirements (LAR-20-001)2020-02-0707 February 2020 Request for License Amendment and Exemption: Unit 3 Auxiliary Building Wall 11 Seismic Gap Requirements (LAR-20-001) ND-20-0092, Revision to Request for License Amendment: Removal of the Preoperational Passive Residual Heat Removal Heat Exchanger Natural Circulation Test (LAR-19-017R1)2020-01-31031 January 2020 Revision to Request for License Amendment: Removal of the Preoperational Passive Residual Heat Removal Heat Exchanger Natural Circulation Test (LAR-19-017R1) ND-19-1388, Preliminary Amendment Request (Par): Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (PAR-19-014)2019-11-13013 November 2019 Preliminary Amendment Request (Par): Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (PAR-19-014) ND-19-1292, Proposed Changes to the Licensing Basis Documents (LAR-19-018)2019-10-31031 October 2019 Proposed Changes to the Licensing Basis Documents (LAR-19-018) ND-19-1314, Second Preliminary Amendment Request (Par): Reinforcement Changes for Wall L (PAR-19-016-2)2019-10-25025 October 2019 Second Preliminary Amendment Request (Par): Reinforcement Changes for Wall L (PAR-19-016-2) ND-19-1313, Revision to Request for License Amendment: Reinforcement Changes for Wall L and Wall 7.3 (LAR-19-016R1)2019-10-25025 October 2019 Revision to Request for License Amendment: Reinforcement Changes for Wall L and Wall 7.3 (LAR-19-016R1) ML19262F8572019-10-22022 October 2019 Attachment - Vogtle Electric Generating Plant, Unit 4 Amendment 163 (LAR-19-006) ML19262F8562019-10-22022 October 2019 License Amendment - Vogtle Electric Generating Plant, Unit 4 (LAR 19-006) ML19262F8552019-10-22022 October 2019 Attachment - Vogtle Electric Generating Plant, Unit 3 Amendment 165 (LAR-19-006) ND-19-1142, Request for License Amendment and Exemption: Automatic Depressurization System (ADS) and Core Makeup Tank (Cmt) Design Parameters (LAR-19-009)2019-09-30030 September 2019 Request for License Amendment and Exemption: Automatic Depressurization System (ADS) and Core Makeup Tank (Cmt) Design Parameters (LAR-19-009) ML19247C8572019-09-0909 September 2019 Notice of No Objection for Preliminary Amendment Request for LAR-19-016 ND-19-1032, Preliminary Amendment Request (Par): Reinforcement Changes for Wall L and Wall 7.3 (PAR-19-016)2019-08-23023 August 2019 Preliminary Amendment Request (Par): Reinforcement Changes for Wall L and Wall 7.3 (PAR-19-016) ND-19-1031, Request for License Amendment: Reinforcement Changes for Wall Land Wall 7.3 (LAR-19-016)2019-08-22022 August 2019 Request for License Amendment: Reinforcement Changes for Wall Land Wall 7.3 (LAR-19-016) ND-19-0855, Request for License Amendment: Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (LAR-19-014) - Without Proprietary Enclosure 32019-08-16016 August 2019 Request for License Amendment: Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (LAR-19-014) - Without Proprietary Enclosure 3 ND-19-0782, Request for License Amendment and Exemption: Onsite Standby Diesel Generator Loading Changes (LAR-19-015)2019-08-0909 August 2019 Request for License Amendment and Exemption: Onsite Standby Diesel Generator Loading Changes (LAR-19-015) 2023-05-04
[Table view] |
Text
B. H. Whitley Southern Nuclear Director Operating Company, Inc.
Regulatory Affairs 42 Inverness Center Parkway Birmingham, AL 35242 Tel 205.992.7079 Fax 205.992.5296 February 1, 2018 Docket Nos.: 52-025 52-026 ND-18-0121 10 CFR 50.90 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Units 3 and 4 Preliminary Amendment Request (PAR):
Changes to the Building Gap between the Nuclear Island and Adjacent Buildings (PAR-18-002)
Ladies and Gentlemen:
The U.S. Nuclear Regulatory Commission (NRC) issued the Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 combined licenses (COLs) (License Nos. NPF-91 and NPF-92, respectively) to Southern Nuclear Operating Company (SNC) on February 10, 2012.
SNC submitted a License Amendment Request (LAR)-18-002 on February 1, 2018 via SNC letter ND-18-0106 [ADAMS Accession Number ML18032A359]. The LAR proposes to amend the VEGP Units 3 and 4 Updated Final Safety Analysis Report (UFSAR) and corresponding COL Appendix C (and associated plant-specific Tier 1) information to relax the minimum gap requirement above grade between the nuclear island and the annex building/turbine building and remove the minimum gap requirement for the radwaste building from the Inspections, Tests, Analyses and Acceptance Criteria (ITAAC).
SNC is submitting this Preliminary Amendment Request (PAR), PAR-18-002, to minimize construction delays for VEGP Units 3 and 4 during the NRCs evaluation of the related LAR. The determination of whether the NRC has any objection to SNC proceeding with construction based on the proposed licensing basis changes identified in the LAR is requested on or before March 16, 2018. Delayed determination regarding this PAR could result in delay of the completion of the column line 11 wall and the column line I wall for VEGP Units 3 and 4.
A description of the proposed change and the reason for the change are contained in the Enclosure to this letter. This PAR has been developed in accordance with guidance provided in the most recent revision to the Interim Staff Guidance on Changes during Construction Under 10 CFR Part 52, COL-ISG-25 [ADAMS Accession Number ML15058A377], and corresponds accurately and technically with the above-mentioned LAR-18-002. The technical scope of this PAR is consistent with the subject LAR. Section 7 of the Enclosure further identifies and details the scope of the no objection finding sought in this PAR.
U.S. Nuclear Regulatory Commission ND-18-0121 Page 2 of 4 This letter does not contain any NRC commitments. This letter has been reviewed and confirmed to not contain security-related information.
Should you have any questions, please contact Ms. Paige Ridgway at (205) 992-7516.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 1st of February 2018.
Respectfully submitted, Brian H. Whitley Director, Regulatory Affairs Southern Nuclear Operating Company
Enclosure:
Vogtle Electric Generating Plant (VEGP) Units 3 and 4- Preliminary Amendment Request: Changes to the Building Gap between the Nuclear Island and Adjacent Buildings (PAR-18-002)
U.S. Nuclear Regulatory Commission ND-18-0121 Page 3 of 4 cc:
Southern Nuclear Operating Company / Georgia Power Company Mr. S. E. Kuczynski (w/o enclosure)
Mr. M. D. Rauckhorst Mr. D. G. Bost (w/o enclosure)
Mr. M. D. Meier (w/o enclosure)
Mr. D. H. Jones (w/o enclosure)
Mr. D. L. McKinney (w/o enclosure)
Mr. T. W. Yelverton (w/o enclosure)
Mr. B. H. Whitley Mr. J. J. Hutto Mr. C. R. Pierce Ms. A. G. Aughtman Mr. D. L. Fulton Mr. M. J. Yox Mr. J. Tupik Mr. W. A. Sparkman Ms. A. C. Chamberlain Ms. A. L. Pugh Mr. J. D. Williams Mr. F. J. Redwanz Document Services RTYPE: VND.LI.L00 File AR.01.02.06 Nuclear Regulatory Commission Mr. W. Jones (w/o enclosure)
Ms. J. Dixon-Herrity Mr. C. Patel Ms. J. M. Heisserer Mr. B. Kemker Mr. G. Khouri Ms. S. Temple Mr. F. Brown Mr. T.E. Chandler Ms. P. Braxton Mr. T. Brimfield Mr. C. J. Even Mr. A. Lerch State of Georgia Mr. R. Dunn
U.S. Nuclear Regulatory Commission ND-18-0121 Page 4 of 4 Oglethorpe Power Corporation Mr. M. W. Price Mr. K. T. Haynes Ms. A. Whaley Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Mr. L. Oriani (w/o enclosure)
Mr. G. Koucheravy (w/o enclosure)
Mr. M. Corletti Mr. M. L. Clyde Ms. L. Iller Mr. D. Hawkins Mr. J. Coward Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. A. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Ms. S. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham Mr. R. Grumbir, APOG NDDocumentinBox@duke-energy.com, Duke Energy Mr. S. Franzone, Florida Power & Light
Southern Nuclear Operating Company ND-18-0121 Enclosure Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Preliminary Amendment Request:
Changes to the Building Gap between the Nuclear Island and Adjacent Buildings (PAR-18-002)
(This Enclosure consists of 5 pages, including this cover page.)
ND-18-0121 Enclosure PAR-18-002: Changes to the Building Gap between the Nuclear Island and Adjacent Buildings Pursuant to 10 CFR 52.98(c) and in accordance with 10 CFR 50.90, Southern Nuclear Operating Company (SNC) submitted a license amendment request (LAR) to change the Vogtle Electric Generating Plant (VEGP) Units 3 and 4 licensing basis documents associated with Combined License Nos. NPF-91 and NPF-92, respectively.
Accordingly, SNC requests the determination of whether the NRC has any objection to SNC proceeding with construction of VEGP Units 3 and 4 column line 11 wall (wall between the nuclear island and the turbine building) and the column line I wall (wall between the nuclear island and the annex building) subject to the changes proposed in LAR-18-002. Delayed determination regarding this PAR will result in delay in the construction completion of VEGP Units 3 and 4 structures, as identified in the Preliminary Amendment Request (PAR) provided below, to be provided by the date shown below.
PAR Request Number: Station Name: Unit Number(s): PAR Request Date:
SNC PAR-18-002 VEGP 3 4 February 1, 2018
- 1. NRC PAR Notification Requested Date (see Block 7 for basis): March 16, 2018
- 2. License Amendment Request References (as applicable):
LAR submittal date and SNC Correspondence Number: LAR-18-002 - February 1, 2018 /
ND-18-0106 Expected LAR submittal date:
- 3. Brief Description of Proposed Change:
The structures adjacent to the nuclear island are the annex building, the radwaste building, and the turbine building. As described in the Combined License (COL) Appendix C (and associated plant-specific Tier 1) Table 3.3-6 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) No.
3.3.00.13, Updated Final Safety Analysis Report (UFSAR) Appendix 2.5E Section 5.2 and UFSAR Subsections 3.7.2.8.1, 3.7.2.8.2 and 3.8.5.1, there is a 4 inch minimum gap above grade (grade is defined as Elevation 100-0" in the licensing basis) between the nuclear island and adjoining buildings.
The purpose of the gap is to avoid contact between the nuclear island and seismic Category II structures (annex building/turbine building) when the buildings deflect during a safe shutdown earthquake (SSE) event. The non-seismic radwaste building is assumed to not impair the integrity of the nuclear island if it were to impact the nuclear island or collapse during an SSE event, as discussed in UFSAR Subsection 3.7.2.8.2.
In order to facilitate the construction of the nuclear island and adjacent buildings and to maintain the seismic gap in compliance with the licensing basis, it is proposed to modify the seismic gap requirement above grade between the nuclear island and adjacent buildings in the licensing basis to accommodate construction tolerances. The proposed changes relax the minimum gap requirement above grade between the nuclear island and the annex building/turbine building from a 4 inch gap to a 3 inch gap and delete the gap requirement for the radwaste building from COL Appendix C ITAAC No.
3.3.00.13. The proposed changes delete minimum from the gap requirement for the radwaste building in UFSAR Subsection 3.7.2.8.2 to allow the gap between the radwaste building and the nuclear island to be considered a nominal gap.
These changes impact COL Appendix C (and associated plant-specific Tier 1) Subsection 3.3 and Table 3.3-6 and UFSAR Appendix 2.5E and Subsections 3.7.2.8 and 3.8.5.1.
Page 2 of 5
ND-18-0121 Enclosure PAR-18-002: Changes to the Building Gap between the Nuclear Island and Adjacent Buildings
- 4. Reason for License Amendment Request:
The purpose of the change is to facilitate the construction of the nuclear island and adjacent buildings by aligning the licensing basis with the underlying design documents and construction tolerances for the seismic gap.
The proposed change reduces the minimum gap requirement between the nuclear island and the annex building/turbine building to 3 inches, which leaves at least a 1 inch gap between the nuclear island and the annex building/turbine building during a seismic event. The Soil-Structure Interaction (SASSI) analyses and the settlement evaluation results support the requirement that the maximum relative seismic displacement between the roof of the nuclear island and any adjoining buildings is less than 2 inches. Therefore, the proposed change to the gap requirement between the nuclear island and the annex building/turbine building does not reduce the 1 inch gap margin during a seismic event, as specified in UFSAR Subsection 3.8.5.1. The seismic gap requirement between the nuclear island and the annex building/turbine building in the underlying design documents is described as a nominal 4 inch gap above grade. The proposed change to the minimum seismic gap between the nuclear island and the annex building/turbine building are only to the minimum seismic gap requirement in the licensing basis and does not affect the 4 inch nominal design gap above grade presented in the underlying design documents. The proposed change does not affect the gap below grade between the nuclear island and the annex building/turbine building, as defined in the licensing basis and in the underlying design documents.
The non-seismic radwaste building is evaluated based on the assumption that it impacts the nuclear island or collapses during an SSE event. The minimum gap between the nuclear island and the radwaste building is not used to prevent interactions between the two, and is not used as an input to the analysis. Therefore, the size of the gap above grade between the nuclear island and the radwaste building does not affect the licensing requirement that the radwaste building will not impair the structural integrity of the nuclear island if it impacts the nuclear island. Since the minimum gap between the radwaste building and the nuclear island above grade is not used as an input to the radwaste building analysis, it is not meaningful to perform the ITAAC inspection on this gap for Vogtle Units 3&4. The minimum gap requirement for the radwaste building is proposed to be deleted from Subsection 3.3, item 13 and COL Appendix C ITAAC No. 3.3.00.13. It is proposed to delete minimum and modify clearance to gap in the first paragraph of UFSAR Subsection 3.7.2.8.2 to define a nominal gap requirement for the radwaste building which allows accounting for the construction tolerances defined in American Concrete Institute (ACI) 117 and American Institute of Steel Construction (AISC) 303. The proposed change does not affect the gap below grade between the nuclear island and the radwaste building, as defined in the licensing basis and in the underlying design documents.
Additional details are provided in the referenced LAR (LAR-18-002).
- 5. Is Exemption Request Required? Yes No If Yes, Briefly Describe the Reason for the Exemption.
An exemption is requested to depart from AP1000 generic Tier 1 material related to changing the gap requirements between the nuclear island and the annex building/turbine building and removing the minimum gap requirement between the nuclear island and radwaste building from the ITAAC.
An exemption is requested because LAR-18-002 requests a departure from generic DCD Tier 1 information incorporated by reference into plant-specific Tier 1 Subsection 3.3 and Table 3.3-6.
Specifically, the plant-specific departure would reduce the minimum gap requirement between the nuclear island and the annex building/turbine building from a 4 inch gap to a 3 inch gap and remove the minimum gap requirement between the nuclear island and the radwaste building from the ITAAC.
Page 3 of 5
ND-18-0121 Enclosure PAR-18-002: Changes to the Building Gap between the Nuclear Island and Adjacent Buildings
- 6. Identify Applicable Precedents:
No precedent identified.
- 7. Impact of Change on Installation and Testing Schedules:
A delayed determination regarding this PAR will result in delay of the concrete pours for the associated column line 11 and I walls, described below.
As such, this PAR requests a no objection finding related to the changes described in LAR-18-002 by the date identified in Block 1 above (or sooner if reasonably achievable) to allow for appropriate notifications and release of further activities dependent on construction of the walls, specifically as noted in the locations below.
Vogtle Unit 3:
o Elevation 117'-6":
Place concrete at column line I (from column lines 1 to 4)
Place concrete at column line I (from column lines 4 to 7)
Place concrete at column line I (from column lines 10 to 11) and column line 11 (from column lines I to L)
Place concrete at column line 11 (from column lines L to Q)
Vogtle Unit 4:
o Elevation 100'-0":
Place concrete at column line I (from column lines 1 to 4)
Place concrete at column line I (from column lines 4 to 7)
Place concrete at column line I (from column lines 7 to 10)
Place concrete at column line 11 (from column lines L to Q)
Place concrete at column line I (from column lines 10 to 11) and column line 11 (from column lines I to L) o Elevation 107'-2":
Place concrete at column line I (from column lines 4 to 7)
A no objection finding for the above activities would allow for VEGP Units 3 and 4 construction activities to proceed.
- 8. Impact of Change on ITAAC:
The proposed changes in LAR 18-002 would relax the minimum gap requirement above grade between the nuclear island and the annex building/turbine building and remove the minimum gap requirement for the radwaste building from the Inspections, Tests, Analyses and Acceptance Criteria (ITAAC). The change to the minimum gap requirement above grade between the nuclear island and the annex building/turbine building from 4 inch to 3 inch is made to accommodate construction tolerances. Since the minimum gap between the radwaste building and the nuclear island above grade is not used as an input to the radwaste building analysis, it is not meaningful to perform the ITAAC inspection on this gap for Vogtle Units 3&4. Therefore, COL Appendix C Table 3.3-6, Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) No. 3.3.00.13 is revised.
Page 4 of 5
ND-18-0121 Enclosure PAR-18-002: Changes to the Building Gap between the Nuclear Island and Adjacent Buildings
- 9. Additional Information:
None Page 5 of 5