- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance
|
MONTHYEARND-22-0830, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.1 0.ii (Index Number 816)2022-10-26026 October 2022 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.1 0.ii (Index Number 816) Project stage: Request ND-22-0689, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.i (Index Number 53)2022-11-0303 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.i (Index Number 53) Project stage: Request ND-22-0862, ITAAC Closure Notification on Completion of ITAAC Item C.2.5.04.04a (Index Number 561)2022-11-0808 November 2022 ITAAC Closure Notification on Completion of ITAAC Item C.2.5.04.04a (Index Number 561) Project stage: Request ND-22-0730, ITAAC Closure Notification on Completion of ITAAC 2.3.03.02 (Index Number 319)2022-11-10010 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.03.02 (Index Number 319) Project stage: Request ND-22-0657, ITAAC Closure Notification on Completion of ITAAC 2.3.14.04 (Index Number 480)2022-11-17017 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.14.04 (Index Number 480) Project stage: Request ND-22-0898, ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751)2022-11-18018 November 2022 ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751) Project stage: Request ND-22-0714, ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.iii (Index Number 4171)2022-11-22022 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.iii (Index Number 4171) Project stage: Request ND-22-0711, ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759)2022-11-23023 November 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759) Project stage: Request ML22332A5372022-11-28028 November 2022 Draft LAR 23-001 for 12-8-22 Public Meeting ND-22-0821, ITAAC Closure Notification on Completion of ITAAC 3.3.00.13 (Index Number 819)2022-11-29029 November 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.13 (Index Number 819) Project stage: Request ML22334A0752022-12-0101 December 2022 Update to Targeted Inspections, Tests, Analysis, and Acceptance Criteria for Vogtle Electric Generating Plant Unit 4 Project stage: Request ND-22-0920, ITAAC Closure Notification on Completion of ITAAC 2.7.01 .02a (Index Number 678)2022-12-0707 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.7.01 .02a (Index Number 678) Project stage: Request ND-22-0899, ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.i (Index Number 214)2022-12-15015 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.i (Index Number 214) Project stage: Request ND-22-0656, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03b.iii (Index Number 348)2022-12-15015 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03b.iii (Index Number 348) Project stage: Request ND-22-0600, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.i (Index Number 291)2022-12-16016 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.i (Index Number 291) Project stage: Request ND-22-0747, ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33)2022-12-21021 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33) Project stage: Request ND-22-0967, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.c (Index Number 802)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.c (Index Number 802) Project stage: Request ND-22-0964, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.a (Index Number 800)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.a (Index Number 800) Project stage: Request ND-22-0965, Resubmittal of Notice of Uncompleted IT Aac 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.b (Index Number 801)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted IT Aac 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.b (Index Number 801) Project stage: Request ND-22-0895, ITAAC Closure Notification on Completion of ITAAC 2.2.01.01 (Index Number 90)2022-12-28028 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.2.01.01 (Index Number 90) Project stage: Request ML22349A2142023-01-0303 January 2023 Summary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company Project stage: Request ND-23-1001, ITAAC Closure Notification on Completion of ITAAC 2.7.01.05.i (Index Number 684)2023-01-0505 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.05.i (Index Number 684) Project stage: Request ND-22-0848, ITAAC Closure Notification on Completion of ITAAC 2.3.02.14 (Index Number 317)2023-01-10010 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.02.14 (Index Number 317) Project stage: Request ND-22-0869, ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462)2023-01-12012 January 2023 ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462) Project stage: Request ND-23-0030, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763) Project stage: Request ND-23-0026, ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.iv (Index Number 216)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.iv (Index Number 216) Project stage: Request ND-23-0029, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.c (Index Number 762)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.c (Index Number 762) Project stage: Request ND-22-0649, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56) Project stage: Request ND-22-0893, ITAAC Closure Notification on Completion of ITAAC 2.1.02.01 (Index Number 12)2023-01-16016 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.01 (Index Number 12) Project stage: Request ND-22-0700, ITAAC Closure Notification on Completion of Item 2.2.04.12a.i (Index Number 248)2023-01-20020 January 2023 ITAAC Closure Notification on Completion of Item 2.2.04.12a.i (Index Number 248) Project stage: Request ND-22-0521, ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.i.03 (Index Number 179)2023-01-20020 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.i.03 (Index Number 179) Project stage: Request ND-22-0585, ITAAC Closure Notification on Completion of 2.2.02.11a.i (Index Number 154)2023-01-23023 January 2023 ITAAC Closure Notification on Completion of 2.2.02.11a.i (Index Number 154) Project stage: Request ND-23-0041, ITAAC Closure Notification on Completion of ITAAC 2.2.04.01 (Index Number 219)2023-01-26026 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.01 (Index Number 219) Project stage: Request ND-23-0078, ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133)2023-01-27027 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133) Project stage: Request ND-22-0739, ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.i (Index Number 415)2023-01-31031 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.i (Index Number 415) Project stage: Request ND-22-0876, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02h 9Index Number 776)2023-01-31031 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02h 9Index Number 776) Project stage: Request ND-23-0079, ITAAC Closure Notification on Completion of ITAAC 2.3.02.02a (Index Number 285)2023-02-0202 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.02.02a (Index Number 285) Project stage: Request ND-23-0039, ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.ii (Index Number 181)2023-02-0303 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.ii (Index Number 181) Project stage: Request ND-23-0043, ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.i (Index Number 32)2023-02-0303 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.i (Index Number 32) Project stage: Request ND-22-0670, ITAAC Closure Notification on Completion of 2.4.06.02 (Index Number 504)2023-02-0707 February 2023 ITAAC Closure Notification on Completion of 2.4.06.02 (Index Number 504) Project stage: Request ND-22-0733, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03c.ii (Index Number 350)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03c.ii (Index Number 350) Project stage: Request ND-23-0130, ITAAC Closure Notification on Completion of ITAAC 2.3.07.07c (Index Number 408)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.07.07c (Index Number 408) Project stage: Request ND-22-0737, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.ii (Index Number 352)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.ii (Index Number 352) Project stage: Request ND-23-0124, ITAAC Closure Notification on Completion of ITAAC Item 2.3.10.12 (Index Number 879)2023-02-13013 February 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.3.10.12 (Index Number 879) Project stage: Request ND-23-0153, ITAAC Closure Notification on Completion of ITAAC 2.3.09.02a (Index Number 421)2023-02-16016 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.09.02a (Index Number 421) Project stage: Request ND-23-0141, ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332)2023-02-16016 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332) Project stage: Request ND-23-0071, ITAAC Closure Notification on Completion of Item 2.2.05.05a.i (Index Number 259)2023-02-17017 February 2023 ITAAC Closure Notification on Completion of Item 2.2.05.05a.i (Index Number 259) Project stage: Request ND-23-0118, ITAAC Closure Notification on Completion of ITAAC 2.3.07.05.i (Index Number 396)2023-02-17017 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.07.05.i (Index Number 396) Project stage: Request ND-22-0919, ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.i (Index Number 799)2023-02-24024 February 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.i (Index Number 799) Project stage: Request ND-23-0159, ITAAC Closure Notification on Completion of ITAAC 2.6.03.05d.i (Index Number 613)2023-03-0101 March 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.05d.i (Index Number 613) Project stage: Request 2023-01-12
[Table View] |
Text
Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6926 tel July 12, 2023 Docket No.:
52-026 ND-23-0592 10 CFR 52.99(c)(1)
U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 ITAAC Closure Notification on Completion of 2.7.06.03.i [Index Number 726]
Ladies and Gentlemen:
In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 4 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) item 2.7.06.03.i [Index Number 726]
which verifies fan flow rates, nominal discharge line size, Main Control Room (MCR) controls, and MCR indications for the Containment Air Filtration System (VFS). The closure process for this ITAAC is based on the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215.
This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.
If there are any questions, please contact Kelli Roberts at 706-848-6991.
Respectfully submitted, Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4
Enclosure:
Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of 2.7.06.03.i [Index Number 726]
JMC/KIK/sfr
U.S. Nuclear Regulatory Commission ND-23-0592 Page 2 of 2 cc:
Regional Administrator, Region ll Director, Office of Nuclear Reactor Regulation (NRR)
Director, Vogtle Project Office NRR Senior Resident Inspector - Vogtle 3 & 4
U.S. Nuclear Regulatory Commission ND-23-0592 Enclosure Page 1 of 6 Southern Nuclear Operating Company ND-23-0592 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of ITAAC 2.7.06.03.i [Index Number 726]
U.S. Nuclear Regulatory Commission ND-23-0592 Enclosure Page 2 of 6 ITAAC Statement Design Commitment
- 3. The VFS provides the intermittent flow of outdoor air to purge the containment atmosphere during normal plant operation, and continuous flow during hot or cold plant shutdown conditions.
- 4. Controls exist in the MCR to cause the components identified in Table 2.7.6-1 to perform the listed function.
- 5. Displays of the parameters identified in Table 2.7.6-1 can be retrieved in the MCR.
Inspections/Tests/Analyses i) Testing will be performed to confirm that containment supply AHU fan A when operated with containment exhaust fan A provides a flow of outdoor air.
ii) Testing will be performed to confirm that containment supply AHU fan B when operated with containment exhaust fan B provides a flow of outdoor air.
iii) Inspection will be conducted of the containment purge discharge line (VFS-L204) penetrating the containment.
Testing will be performed on the components in Table 2.7.6-1 using controls in the MCR.
Inspection will be performed for retrievability of the parameters in the MCR Acceptance Criteria i) The flow rate measured at each fan is greater than or equal to 3,600 scfm.
ii) The flow rate measured at each fan is greater than or equal to 3,600 scfm.
iii) The nominal line size is 36 in.
Controls in the MCR operate to cause the components listed in Table 2.7.6-1 to perform the listed functions.
The displays identified in Table 2.7.6-1 can be retrieved in the MCR.
ITAAC Determination Basis Testing and inspections were performed in accordance with Unit 4 preoperational tests, component tests, and implementing work orders as listed in References 1, 2 and 3. The information summarized in References 1, 2, and 3 confirm the Containment Air Filtration System (VFS) provides the intermittent flow of outdoor air to purge the containment atmosphere during normal plant operation, and continuous flow during hot or cold plant shutdown conditions, that controls exist in the Main Control Room (MCR) to cause the components identified in Combined License (COL) Appendix C Table 2.7.6-1 to perform the listed function, and displays of the parameters identified in COL Appendix C Table 2.7.6-1 can be retrieved in the MCR.
U.S. Nuclear Regulatory Commission ND-23-0592 Enclosure Page 3 of 6 i) The flow rate measured at each fan is greater than or equal to 3,600 scfm Reference 2 documented testing performed in accordance with Unit 4 preoperational test procedure. The test was conducted by running containment supply fan A (VFS-MA-01A) and containment exhaust fan A (VFS-MA-02A) and measuring airflow for each fan. The measured airflow readings were corrected for instrument accuracy and for standard conditions. The corrected airflow was compared to the acceptance criteria and verified to exceed the minimum flow.
The Unit 4 A containment supply fan produced a minimum flow of 3896 scfm and the Unit 4 A containment exhaust fan produced a minimum flow of 4301 scfm during testing.
The Unit 4 test results in Reference 2 confirm that each VFS A containment supply fan and containment exhaust fan produced a flow rate measured at each fan that is greater than or equal to 3,600 scfm.
ii) The flow rate measured at each fan is greater than or equal to 3,600 scfm.
Reference 2 documented testing performed in accordance with Unit 4 preoperational test procedure. The test was conducted by running containment supply fan B (VFS-MA-01B) and containment exhaust fan B (VFS-MA-02B) and measuring airflow for each fan. The measured airflow readings were corrected for instrument accuracy and for standard conditions. The corrected airflow was compared to the acceptance criteria and verified to exceed the minimum flow.
The Unit 4 B containment supply fan produced a minimum flow of 3976 scfm and the Unit 4 B containment exhaust fan produced a minimum flow of 3916 scfm during testing.
The Unit 4 test results in Reference 2 confirm that each VFS B containment supply fan and containment exhaust fan produced a flow rate measured at each fan that is greater than or equal to 3,600 scfm.
iii) The nominal line size is 36 in.
An inspection was conducted of the containment purge discharge line (VFS-L204) penetrating the containment to verify the containment penetration nominal size is 36 in. The inspection was performed by verifying completion of the construction work packages for installation and inspecting the Quality Assurance Data Packages (QADP). ITAAC Technical Report (ITR)
(Reference 1) documents the inspection and the QADP review and documented the line size is 36 inches.
Reference 1 confirms the containment penetration nominal line size is 36 in.
U.S. Nuclear Regulatory Commission ND-23-0592 Enclosure Page 4 of 6 Controls in the MCR operate to cause the components listed in Table 2.7.6-1 to perform the listed functions.
Testing, as summarized in Reference 3, was performed to verify that controls in the MCR operate to cause the components listed in Table 2.7.6-1 (Attachment A) to perform the listed functions.
Testing was conducted at an operator workstation in Unit 4 MCR with the VFS train A and B verified to be in a standby alignment. The containment air handling unit (AHU) supply fan A and containment exhaust fan A were placed in service in accordance with the operating procedure and verified to start and then removed from service in accordance with the operating procedure.
This was repeated for the B AHU supply and exhaust fan.
This testing confirmed that controls in the Unit 4 MCR operate to cause the components listed in Table 2.7.6-1 to perform the listed functions.
The displays identified in Table 2.7.6-1 can be retrieved in the MCR.
The inspection, as summarized in Reference 3, was performed to verify that the displays identified in Table 2.7.6-1 (Attachment B) can be retrieved in the MCR.
The component test was conducted in the MCR at the PLS displays and verified the displays in Attachment B could be retrieved in the MCR. Each display in Attachment B was located on the PLS displays and verified to indicate properly.
This confirmed that all the displays identified in Table 2.7.6-1 can be retrieved in Unit 4 MCR.
References 1 through 3 are available for NRC inspection as part of ITAAC 2.7.06.03.i Unit 4 Completion Package (Reference 4).
ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 2.7.06.03.i (Reference 4) and is available for NRC review.
ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 2.7.06.03.i was performed for VEGP Unit 4 and that the prescribed acceptance criteria were met.
Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.
U.S. Nuclear Regulatory Commission ND-23-0592 Enclosure Page 5 of 6 References (available for NRC inspection)
- 1. SV4-VFS-ITR-800726, Rev 0, Unit 4 Containment Air Filtration System: ITAAC 2.7.06.03.i Item 3.iii
- 2. SV4-VFS-ITR-801726, Rev. 0, Unit 4 Containment Air Filtration System: ITAAC 2.7.06.03.i Items 3.i and 3.ii
- 3. SV4-VFS-ITR-802726, Rev. 0, Unit 4 Containment Air Filtration System: ITAAC 2.7.06.03.i Items 4 and 5
- 4. 2.7.06.03.i-U4-CP-Rev0, ITAAC Completion Package
U.S. Nuclear Regulatory Commission ND-23-0592 Enclosure Page 6 of 6 Attachment A
- Excerpt from COL Appendix C Table 2.7.6-1
- Control Function Containment Air Handling Units (AHU) Supply Fan A VFS-MA-01A Start Containment AHU Supply Fan B VFS-MA-01B Start Containment Exhaust Fan A VFS-MA-02A Start Containment Exhaust Fan B VFS-MA-02B Start Attachment B
- Excerpt from COL Appendix C Table 2.7.6-1
- Display Containment Air Handling Units (AHU) Supply Fan A VFS-MA-01A Yes (Run Status)
Containment AHU Supply Fan B VFS-MA-01B Yes (Run Status)
Containment AHU Supply Fan A Flow Sensor VFS-012A Yes Containment AHU Supply Fan B Flow Sensor VFS-012B Yes Containment Exhaust Fan A VFS-MA-02A Yes (Run Status)
Containment Exhaust Fan B VFS-MA-02B Yes (Run Status)
Containment Exhaust Fan A Flow Sensor VFS-011A Yes Containment Exhaust Fan B Flow Sensor VFS-011B Yes