MONTHYEARND-24-0019, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-02-0101 February 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0912, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-01-0202 January 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0881, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-12-0404 December 2023 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0817, (Vegp), Units 3 and 4 - Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a)2023-11-17017 November 2023 (Vegp), Units 3 and 4 - Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a) ND-23-0823, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-11-0303 November 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0723, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-10-0404 October 2023 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0697, (Vegp), Unit 4, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-09-0505 September 2023 (Vegp), Unit 4, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0669, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-08-0707 August 2023 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0205, (Vegp), Unit 3 - Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2023-07-28028 July 2023 (Vegp), Unit 3 - Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-23-0618, Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797)2023-07-20020 July 2023 Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797) ND-23-0609, Notification of Completion of All ITAAC2023-07-20020 July 2023 Notification of Completion of All ITAAC ND-23-0608, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) ND-23-0607, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) ND-22-0796, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813) ND-23-0459, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587) ND-23-0162, ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165) ND-23-0575, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588) ND-23-0439, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265) ND-23-0552, Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624)2023-07-18018 July 2023 Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624) ND-23-0483, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) ND-23-0586, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2023-07-17017 July 2023 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) ND-23-0610, ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603)2023-07-17017 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603) ND-23-0573, ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497) ND-23-0406, ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498) ND-22-0816, ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19)2023-07-15015 July 2023 ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19) ND-23-0603, ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831) ND-23-0446, ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250) ND-23-0594, ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629) ND-23-0601, ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719) ND-23-0606, ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557) ND-23-0476, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) ND-23-0499, ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700) ND-23-0588, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) ND-23-0121, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667) ND-23-0122, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668) ND-23-0597, ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530) ND-23-0002, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270) ND-23-0111, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) ND-22-0980, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75) ND-23-0587, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) ND-23-0461, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652) ND-23-0543, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622) ND-23-0394, ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703) ND-23-0592, ITAAC Closure Notification on Completion of 2.7.06.03.i (Index Number 726)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of 2.7.06.03.i (Index Number 726) ND-23-0589, ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601) ND-23-0581, ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220) ND-23-0486, ITAAC Closure Notification on Completion of ITAAC 2.2.01.11a.iv (Index Number 117)2023-07-11011 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.01.11a.iv (Index Number 117) ND-23-0559, CFR26.719(c)(1) 30-Day Report for a Blind Sample Analysis Error2023-07-11011 July 2023 CFR26.719(c)(1) 30-Day Report for a Blind Sample Analysis Error ND-23-0443, ITAAC Closure Notification on Completion of ITAAC 2.3.10.07a.ii (Index Number 444)2023-07-0808 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.10.07a.ii (Index Number 444) ND-23-0183, ITAAC Closure Notification on Completion of ITAAC Item 2.3.11.03b (Index Number 454)2023-07-0808 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.3.11.03b (Index Number 454) 2024-02-01
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARNL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report2024-01-22022 January 2024 Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report NL-23-0827, Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.142023-11-17017 November 2023 Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.14 NL-23-0750, Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr2023-10-0404 October 2023 Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2) NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0670, Response to Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-144832023-08-11011 August 2023 Response to Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483 NL-23-0339, Response to Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters - Operating, Completion Time Extension (LAR-22-002S1)2023-06-13013 June 2023 Response to Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters - Operating, Completion Time Extension (LAR-22-002S1) NL-23-0467, Response to Request for Additional Information Regarding License Amendment Request: Timing of Unit 4 Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005S1)2023-06-0909 June 2023 Response to Request for Additional Information Regarding License Amendment Request: Timing of Unit 4 Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005S1) NL-23-0196, Response to Request for Additional Information Regarding License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-4902023-03-24024 March 2023 Response to Request for Additional Information Regarding License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-490 NL-23-0010, Response to Request for Additional Information Regarding License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-4902023-02-0606 February 2023 Response to Request for Additional Information Regarding License Amendment Request for Alternative Source Term, TSTF-51, TSTF-471, and TSTF-490 NL-23-0013, Response to Request for Additional Information Related to 10CFR 50.75 Decommissioning Funding Assurance Requirements2023-01-30030 January 2023 Response to Request for Additional Information Related to 10CFR 50.75 Decommissioning Funding Assurance Requirements NL-23-0068, Responses to NRC Request for Additional Information Related to the Refueling Outage 2R22 Steam Generator Tube Inspection Report2023-01-27027 January 2023 Responses to NRC Request for Additional Information Related to the Refueling Outage 2R22 Steam Generator Tube Inspection Report NL-23-0012, Post-Audit Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel2023-01-20020 January 2023 Post-Audit Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel NL-22-0609, Response to NRC Requests for Information License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel2022-09-13013 September 2022 Response to NRC Requests for Information License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel NL-22-0549, Responses to NRC Request for Additional Information for Refueling Outage 1R23 Steam Generator Tube Inspection Report2022-07-19019 July 2022 Responses to NRC Request for Additional Information for Refueling Outage 1R23 Steam Generator Tube Inspection Report ND-22-0328, Enclosuvogtle Electric Generating Plant, Units 3 & 4 - Fukushima Response NEI 12-01 On-Shift Staffing Analysis Phase 2 Report, Revision 3.0, Standard Emergency Plan Annex, Revision 6.02022-06-29029 June 2022 Enclosuvogtle Electric Generating Plant, Units 3 & 4 - Fukushima Response NEI 12-01 On-Shift Staffing Analysis Phase 2 Report, Revision 3.0, Standard Emergency Plan Annex, Revision 6.0 NL-22-0055, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System2022-02-28028 February 2022 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System NL-21-1015, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System2022-01-13013 January 2022 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System ND-21-0618, Response to Request for Additional Information Regarding Request for Alternative: Alternative Requirements for ASME Section Ill Remediation of Containment Vessel Unistrut Welding (VEGP 3-ALT-16)2021-07-0202 July 2021 Response to Request for Additional Information Regarding Request for Alternative: Alternative Requirements for ASME Section Ill Remediation of Containment Vessel Unistrut Welding (VEGP 3-ALT-16) NL-21-0208, Response to Request for Additional Information Related to Refueling Outage 1R22 Steam Generator Tube Inspection Report2021-03-0202 March 2021 Response to Request for Additional Information Related to Refueling Outage 1R22 Steam Generator Tube Inspection Report NL-20-1417, Vogltle, Units 1 and 2, Response to Request for Additional Information Regarding Risk-Informed Resolution to GSI-1912020-12-17017 December 2020 Vogltle, Units 1 and 2, Response to Request for Additional Information Regarding Risk-Informed Resolution to GSI-191 NL-20-1312, Response to Request for Additional Information Related to Proposed Inservice Inspection Alternative VEGP-ISI-ALT-04-04 Version 2.02020-11-23023 November 2020 Response to Request for Additional Information Related to Proposed Inservice Inspection Alternative VEGP-ISI-ALT-04-04 Version 2.0 NL-20-1273, Response to NRC Requests for Information License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for2020-11-20020 November 2020 Response to NRC Requests for Information License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for ND-20-1005, Supplement to Request for License Amendment: Vacuum Relief Valve Technical Specification Changes (LAR-20-005S1)2020-09-18018 September 2020 Supplement to Request for License Amendment: Vacuum Relief Valve Technical Specification Changes (LAR-20-005S1) NL-20-0640, Response to Request for Additional Information for Exemption Request2020-05-27027 May 2020 Response to Request for Additional Information for Exemption Request ND-19-1097, Response to Request for Additional Information - LAR-19-013R12019-11-0101 November 2019 Response to Request for Additional Information - LAR-19-013R1 NL-19-1183, Response to Request for Additional Information Regarding End State Revision from Hot Shutdown to Cold Shutdown2019-10-17017 October 2019 Response to Request for Additional Information Regarding End State Revision from Hot Shutdown to Cold Shutdown ND-19-1023, Enclosure 7 - Response to Draft Request for Additional Information (LAR-19-005R1)2019-10-10010 October 2019 Enclosure 7 - Response to Draft Request for Additional Information (LAR-19-005R1) ND-19-1129, Supplement to the Request for License Amendment Regarding Protection and Safety Monitoring System Surveillance Requirement Reduction Technical Specification ...2019-10-0707 October 2019 Supplement to the Request for License Amendment Regarding Protection and Safety Monitoring System Surveillance Requirement Reduction Technical Specification ... ND-19-1177, Supplement to Request for License Amendment and Exemption: Addition of In-Containment Refueling Water Storage Tank to Radiation Analyses (LAR-19-003S1)2019-10-0303 October 2019 Supplement to Request for License Amendment and Exemption: Addition of In-Containment Refueling Water Storage Tank to Radiation Analyses (LAR-19-003S1) NL-19-0709, Core Operating Limits Report, Cycle 21, Version 1, SNC Response to NRC Request for Additional Information2019-06-17017 June 2019 Core Operating Limits Report, Cycle 21, Version 1, SNC Response to NRC Request for Additional Information NL-19-0498, License Amendment Request for Technical Specification Improvement to Revise Actions for One Steam Supply to Turbine Driven Auxiliary Feedwater Pump Inoperable SNC Response to NRC Request for ...2019-04-30030 April 2019 License Amendment Request for Technical Specification Improvement to Revise Actions for One Steam Supply to Turbine Driven Auxiliary Feedwater Pump Inoperable SNC Response to NRC Request for ... ND-19-0289, Enclosure 1 - Revised Response to Request for Additional Information Question 1b Related to Request for Exemption from Operator Written Examination and Operating Test2019-04-16016 April 2019 Enclosure 1 - Revised Response to Request for Additional Information Question 1b Related to Request for Exemption from Operator Written Examination and Operating Test ND-19-0178, Supplement to Request for Exemption: 10 CFR Part 26 Visitor Access Requirements (Supplement 1)2019-03-0808 March 2019 Supplement to Request for Exemption: 10 CFR Part 26 Visitor Access Requirements (Supplement 1) ND-19-0216, Response to Request for Additional Information Related to Request for Exemption from Operator Written Examination and Operating Test2019-03-0404 March 2019 Response to Request for Additional Information Related to Request for Exemption from Operator Written Examination and Operating Test NL-18-1514, Response to Request for Information Regarding License Amendment Request to Revise Technical Specification 5.2.2.g and Update Emergency Plan Minimum On-Shift.2019-01-31031 January 2019 Response to Request for Information Regarding License Amendment Request to Revise Technical Specification 5.2.2.g and Update Emergency Plan Minimum On-Shift. ND-19-0007, Supplement to Request for Alternative: Preservice and Inservice Inspection Requirements for Specific Valve-to-Pipe Welds (VEGP 3&4-PSI/ISI-ALT-06S1)2019-01-28028 January 2019 Supplement to Request for Alternative: Preservice and Inservice Inspection Requirements for Specific Valve-to-Pipe Welds (VEGP 3&4-PSI/ISI-ALT-06S1) ND-18-1439, Revised Request for License Amendment: Technical Specification Changes for Spent Fuel Pool Level - Low 2 and In-containment Refueling Water Storage Tank (IRWST) Wide Range Level - Low Operability (LAR-18-017R1)2018-12-0303 December 2018 Revised Request for License Amendment: Technical Specification Changes for Spent Fuel Pool Level - Low 2 and In-containment Refueling Water Storage Tank (IRWST) Wide Range Level - Low Operability (LAR-18-017R1) NL-18-1181, Relief Requests VEGP-ISI-RR-05 and VEGP-ISI-RR-06, SNC Response to NRC Request for Additional Information2018-10-17017 October 2018 Relief Requests VEGP-ISI-RR-05 and VEGP-ISI-RR-06, SNC Response to NRC Request for Additional Information ND-18-1058, Supplement to Request for License Amendment and Exemption: Containment Pressure Analysis (LAR-17-043S1)2018-09-28028 September 2018 Supplement to Request for License Amendment and Exemption: Containment Pressure Analysis (LAR-17-043S1) NL-18-1130, Units 1 and 2 - Relief Request VEGP-ISI-RR-03: SNC Response to NRC Request for Additional Information2018-09-26026 September 2018 Units 1 and 2 - Relief Request VEGP-ISI-RR-03: SNC Response to NRC Request for Additional Information NL-18-1179, Response to NRC Request for Additional Information Tornado Missile Risk Evaluator SNC Supplemental2018-09-14014 September 2018 Response to NRC Request for Additional Information Tornado Missile Risk Evaluator SNC Supplemental ND-18-0635, Response to Request for Additional Information Regarding Application of VT-1 Visual Examination Methodology for Preservice Inspection of the Reactor Vessel Nozzle Inner Radius Sections (VEGP 3&4-PSI-ALT-07S3)2018-08-31031 August 2018 Response to Request for Additional Information Regarding Application of VT-1 Visual Examination Methodology for Preservice Inspection of the Reactor Vessel Nozzle Inner Radius Sections (VEGP 3&4-PSI-ALT-07S3) ND-18-1040, Supplement to the Request for License Amendment: Technical Specification Changes to Support Operability During Mode 5 Vacuum Fill Operations (LAR-18-009S1)2018-08-10010 August 2018 Supplement to the Request for License Amendment: Technical Specification Changes to Support Operability During Mode 5 Vacuum Fill Operations (LAR-18-009S1) ND-18-1049, Supplement to Request for License Amendment: Technical Specification Updates for Reactivity Controls and Other Miscellaneous Changes (LAR-17-024S4)2018-08-0909 August 2018 Supplement to Request for License Amendment: Technical Specification Updates for Reactivity Controls and Other Miscellaneous Changes (LAR-17-024S4) NL-18-0815, Tornado Missile Risk Evaluator: SNC Response to NRC Request for Additional Information2018-07-26026 July 2018 Tornado Missile Risk Evaluator: SNC Response to NRC Request for Additional Information NL-18-0915, Enclosures 1, 3, 4 & 5 - Introduction and Overall Summary, Risk Quantification, Defense-in-Depth & Safety Margin and Supplemental Response to NRC Generic Letter 2004-022018-07-10010 July 2018 Enclosures 1, 3, 4 & 5 - Introduction and Overall Summary, Risk Quantification, Defense-in-Depth & Safety Margin and Supplemental Response to NRC Generic Letter 2004-02 ND-18-0646, Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S3)2018-06-18018 June 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S3) L-16-016, Response to NRC Rais Regarding Generic Letter 2016-012018-05-31031 May 2018 Response to NRC Rais Regarding Generic Letter 2016-01 ND-18-0643, Supplement to Request for License Amendment and Exemption Regarding Ventilation System Changes (LAR-16-030R1S2)2018-05-18018 May 2018 Supplement to Request for License Amendment and Exemption Regarding Ventilation System Changes (LAR-16-030R1S2) 2024-01-22
[Table view] |
Text
Brian H. Whitley Southern Nuclear Director Operating Company, Inc.
Regulatory Affairs 42 Inverness Center Parkway Birmingham, AL 35242 Tel 205.992.7079 Fax 205.992.5296 February 28, 2018 Docket Nos.: 52-025 ND-18-0111 52-026 10 CFR 50.90 10 CFR 52.98(c)
U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Units 3 and 4 Supplement to Request for License Amendment Regarding:
Passive Residual Heat Removal Heat Transfer and In-containment Refueling Water Storage Tank Heat Up Test Acceptance Criteria Change (LAR-17-033S1)
Ladies and Gentlemen:
Pursuant to 10 CFR 52.98(c) and in accordance with 10 CFR 50.90, Southern Nuclear Operating Company (SNC) requested an amendment to the combined licenses (COLs) for Vogtle Electric Generating Plant (VEGP) Units 3 and 4 (License Numbers NPF-91 and NPF-92, respectively), by SNC letter ND-17-1428, dated October 6, 2017 [ADAMS Accession Number ML17279B017]. The requested amendment proposes to depart from the incorporated plant-specific Design Control Document (DCD) Tier 2 information and a COL License Condition which references a UFSAR Section impacted by one of the proposed changes.
The proposed changes would revise the licensing basis documents to change the methodology and acceptance criteria for the in-containment refueling water storage tank (IRWST) heatup preoperational test described in UFSAR Subsection 14.2.9.1.3, Item (h) and the passive residual heat removal (PRHR) heat exchanger preoperational test described in UFSAR Subsection 14.2.9.1.3, Item (g). These changes involve material which is specifically referenced in Section 2.D.(2) of the COLs for VEGP Units 3 and 4. to this letter supplements LAR-17-033 to address a Request for Additional Information (RAI) from the NRC Staff, which was transmitted by electronic mail (email) on January 30, 2018 [ADAMS Accession Number ML18030A734], to support review of LAR 033. This supplement does not impact the scope, document markups, technical content, or conclusions of the Technical Evaluation, Significant Hazards Consideration Determination, or Environmental Considerations of the original License Amendment Request (LAR) provided in Enclosures 1 and 2 of SNC letter ND-17-1428.
This letter contains no regulatory commitments. This letter has been reviewed and determined not to contain security related information.
U.S Nuclear Regulatory Commission ND-18-0111 Page 2 of 4 In accordance with 10 CFR 50.91, SNC is notifying the State of Georgia by transmitting a copy of this letter and its enclosure to the designated State Official.
SNC requests staff approval of this LAR by August 21, 2018 to support planning and execution of IRWST heatup testing . This approval date has been revised since the original submittal of LAR-17 -033 because SNC is developing other licensing actions that are dependent on the approval of this LAR. SNC expects to implement the proposed amendment through incorporation into the licensing basis documents; e.g., the UFSAR, within 30 days of approval of the requested changes.
Should you have any questions, please contact Ms. Stephanie Agee at (205) 992-7556.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 281h of February 2018.
Respectfully submitted, Brian H. Whitley Director, Regulatory Affairs Southern Nuclear Operating Company
Enclosures:
1 - 2) (Previously submitted with the original LAR, LAR-17-033, in SNC letter ND-17-1428)
- 3) Vogtle Electric Generating Plant (VEGP) Units 3 and 4 - Response to NRC Request for Additional Information (RAI) Regarding LAR 17-033 (LAR 033S1)
U.S Nuclear Regulatory Commission ND-18-0111 Page 3 of 4 cc:
Southern Nuclear Operating Company / Georgia Power Company Mr. S. E. Kuczynski (w/o enclosure)
Mr. M. D. Rauckhorst Mr. D. G. Bost (w/o enclosure)
Mr. M. D. Meier (w/o enclosure)
Mr. D. H. Jones (w/o enclosure)
Mr. D. L. McKinney (w/o enclosure)
Mr. T. W. Yelverton (w/o enclosure)
Mr. B. H. Whitley Mr. J. J. Hutto Mr. C. R. Pierce Ms. A. G. Aughtman Mr. D. L. Fulton Mr. M. J. Yox Mr. J. Tupik Mr. W. A. Sparkman Ms. A. C. Chamberlain Ms. A. L. Pugh Mr. J. D. Williams Mr. F. J. Redwanz Document Services RTYPE: VND.LI.L00 File AR.01.02.06 Nuclear Regulatory Commission Mr. W. Jones (w/o enclosure)
Ms. J. Dixon-Herrity Mr. C. Patel Ms. J. M. Heisserer Mr. B. Kemker Mr. G. Khouri Ms. S. Temple Mr. F. Brown Mr. T.E. Chandler Ms. P. Braxton Mr. T. Brimfield Mr. C. J. Even Mr. A. Lerch State of Georgia Mr. R. Dunn
U.S Nuclear Regulatory Commission ND-18-0111 Page 4 of 4 Oglethorpe Power Corporation Mr. M. W. Price Mr. K. T. Haynes Ms. A. Whaley Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Mr. L. Oriani (w/o enclosure)
Mr. G. Koucheravy (w/o enclosure)
Mr. M. Corletti Mr. M. L. Clyde Ms. L. Iller Mr. D. Hawkins Mr. J. Coward Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. A. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Ms. S. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham Mr. R. Grumbir, APOG NDDocumentinBox@duke-energy.com, Duke Energy Mr. S. Franzone, Florida Power & Light
Southern Nuclear Operating Company ND-18-0111 Enclosure 3 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Response to NRC Request for Additional Information (RAI)
Regarding LAR 17-033 (LAR-17-033S1)
(This Enclosure consists of 3 pages, including this cover page)
ND-18-0111 Response to NRC Request for Additional Information (RAI) Regarding LAR 17-033 (LAR-17-033S1)
The following request for additional information (RAI) [ADAMS Accession Number ML18030A734]
regarding the review of Southern Nuclear Operating Company (SNC) License Amendment Request (LAR)17-033, submitted by SNC letter ND-17-1428, was provided by the NRC Staff on January 30, 2018.
Request for Additional Information (RAI):
10 CFR Part 50, Appendix A, General Design Criterion 37, Testing of emergency core cooling system, requires in part that the emergency core cooling system shall be designed to permit appropriate periodic pressure and functional testing to assure the operability of the system as a whole and, under conditions as close to design as practical, the performance of the full operational sequence that brings the system into operation. The IRWST and PRHR heat exchanger make up part of the emergency core cooling system for this design.
One of the proposed changes in the LAR changes the acceptance criterion in UFSAR Subsection 14.2.9.1.3 from supporting the safe shutdown temperature criteria in Chapter 19 to demonstrating that the average IRWST heatup is consistent with the PRHR heat transfer modeling in Chapter
- 15. It is not clear to the staff how this acceptance criteria will be satisfied - unlike the previous acceptance criteria, which had a clear numerical basis (420F in 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />), the revised acceptance criteria cites consistency with a modeling approach. The technical evaluation section of the LAR states that data from the test will still be used to support the overall PPRHR heat transfer assumptions, and that the use of LOFTRAN allows for a one-to-one comparison between the as-built plant and the safety analysis presented in Chapter 15. Staff recognizes that testing at conditions akin to those in Chapter 15 and/or Chapter 19 may not be practical. However, the staff needs additional description of how the proposed test will demonstrate system performance under the expected conditions. Accordingly, staff requests that the applicant provide additional detail regarding the new acceptance criteria for a satisfactory test, and how the test data will be used to demonstrate consistency with the analysis documented in Chapter 15.
SNC Response to RAI:
The proposed changes to the acceptance criterion in Updated Final Safety Analysis Report (UFSAR) Subsection 14.2.9.1.3 Item (h) are intended to be coupled to the acceptance of the tests described in UFSAR Subsection 14.2.9.1.3 Items (f) and (g) to demonstrate that the Passive Residual Heat Removal Heat Exchanger (PRHR HX) heat transfer rate (e.g., as listed in Item (f) as 1.78 E+08 Btu/hr based on a 520°F hot leg temperature) is conservatively predicted in the Chapter 15 analyses. The purpose of the In-Containment Refueling Water Storage Tank (IRWST)
Heatup Test is to gather data that would be used in conjunction with the other data obtained during the PRHR HX tests described in Items (f) and (g) (e.g., natural circulation flow rate and the heat exchanger inlet and outlet temperatures) to determine the as-built PRHR HXs heat transfer performance. The heat transfer rates calculated from the test data are to be adjusted to account for differences in the IRWST temperatures among other parameters as stated in Items (f) and (g).
This adjustment is necessary to normalize the test results to compare to the heat transfer rates predicted for the test using the Chapter 15 LOFTRAN code (which is calculated with the specified conditions described in Items (f) and proposed Item (g) of the inlet temperature of 250°F, the initial IRWST temperature of 80°F and the design basis number of tubes plugged). The normalized test results will be reviewed to confirm that the PRHR HX performs as predicted (or better than predicted) by the analysis model. Since the analysis model used for the tests is the same analysis model used for the Chapter 15 analysis, with differences in input parameters due to the differences in the test conditions from the postulated accident conditions, the test results Page 2 of 3
ND-18-0111 Response to NRC Request for Additional Information (RAI) Regarding LAR 17-033 (LAR-17-033S1) demonstrate that the Chapter 15 model and methodology are sufficient to conservatively predict PRHR HX performance documented in the safety analyses. Therefore, the acceptance criteria for the IRWST Heatup Test is considered satisfied if the measured IRWST temperatures demonstrate that the average IRWST heatup during the test supports a normalized PRHR HX heat transfer rate that is greater than or equal to the LOFTRAN predicted heat transfer rate for the specific conditions described for the acceptance criteria of the PRHR HX Heat Transfer Tests.
Page 3 of 3