Letter Sequence Withholding Request Acceptance |
|---|
EPID:L-2022-NFW-0002, Abilene Christian University Construction Permit Application Preliminary Safety Analysis Report Revision 1 (Approved, Closed) |
Results
Other: ML22341A615, ML23013A089, ML23052A087, ML23061A132, ML23065A048, ML23065A051, ML23065A052, ML23065A055, ML23065A056, ML23249A095, ML24024A009, ML24096B783, ML24162A093, ML24213A286, ML24229A195
|
MONTHYEARML22227A2022022-08-12012 August 2022 Abilene Christian University, Submittal of Construction Permit Application for the Molten Salt Research Reactor Project stage: Request ML22313A0972022-11-18018 November 2022 Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Construction Permit Application Acceptance Letter Project stage: Acceptance Review PMNS20221202, Public Meeting with Abilene Christian University (Acu)2022-11-21021 November 2022 Public Meeting with Abilene Christian University (Acu) Project stage: Request ML22341A6152022-12-16016 December 2022 Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Construction Permit Application Review Schedule Letter Project stage: Other ML23013A0892023-01-13013 January 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Technical Topics Project stage: Other ML23065A0562023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 9.2 and 13 Project stage: Other ML23065A0522023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 1, 5, 8, 9 (Except 9.2 and 9.6), 10, 11, 12, 14-18, and General Topics Project stage: Other ML23065A0512023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapter 7 Project stage: Other ML23065A0482023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 2 & 3 Project stage: Other ML23065A0552023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 4, 6, and 9.6 Project stage: Other ML23052A0872023-03-0909 March 2023 Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Technical Topics Project stage: Other ML23061A1322023-03-0909 March 2023 Acu Lu, Vr, WR, Rh, Wm, TR, AC, Fc Info Needs Items Q2FY2023 Project stage: Other ML23065A3342023-05-0101 May 2023 Abilene Christian University - December 9, 2022, Public Meeting Summary Regarding Discussion on Technical Focus Areas Project stage: Meeting ML23249A0952023-09-14014 September 2023 Abilene Christian University - Update to Construction Permit Application Technical Review Schedule Project stage: Other ML23319A0942023-11-14014 November 2023, 30 November 2023 Abilene Christian University Construction Permit Application Preliminary Safety Analysis Report Revision 1 Project stage: Request ML23348A1962023-12-21021 December 2023 Abilene Christian University (Acu) - Transmittal of Requests for Additional Information Project stage: RAI ML24024A0092024-01-23023 January 2024 Abilene Christian University Construction Permit Application Partial Response to Audit Questions 3.5-4, 4.2-9, and 4.3-3 Project stage: Other ML24030A8702024-02-0606 February 2024 NRC Response to Request for Withholding Information from Public Disclosure for Abilene Christian University (Acu) Project stage: Withholding Request Acceptance ML24094A3322024-03-28028 March 2024 Abilene Christian University, Construction Permit Application - Response to Request for Additional Information 1 Project stage: Response to RAI ML24096B7832024-04-0505 April 2024 NRR E-mail Capture - Requests for Confirmation of Information Related to the Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Construction Permit Application Project stage: Other ML24109A2032024-04-18018 April 2024 Next, Abilene Christian University Construction Permit Application Response to Request for Confirmatory Information Project stage: Request ML24121A2722024-04-30030 April 2024 Abilene Christian University Construction Permit Application Response to Request for Additional Information 2 Project stage: Response to RAI ML24162A0932024-06-12012 June 2024 Abilene Christian University - Molten Salt Research Reactor Construction Permit Application Revised Review Schedule Letter Project stage: Other ML24164A2362024-06-12012 June 2024 Abilene Christian University Construction Permit Application Response to Request for Confirmatory Information Project stage: Request ML24213A2862024-07-30030 July 2024 Submittal of Abilene Christian University Construction Permit Application Preliminary Safety Analysis Report Revision 2 Project stage: Other ML24219A2592024-07-30030 July 2024 Enclosure 2, Mssr Codes and Service Conditions Redacted Project stage: Request ML24219A2622024-07-30030 July 2024 Enclosure 3, Safety Related Valve Requirements Redacted Project stage: Request ML24229A1952024-09-0303 September 2024 Notice of Significant Licensing Action - Abilene Christian University (Acu) Construction Permit Issuance Project stage: Other ML24243A0422024-09-16016 September 2024 Abilene Christian University, Safety Evaluation for Issuance of Construction Permit for the Molten Salt Research Reactor Project stage: Request ML24243A0412024-09-16016 September 2024 Abilene Christian University, Transmittal Letter for Issuance of Construction Permit for the Molten Salt Research Reactor Project stage: Approval ML24249A0302024-09-27027 September 2024 Abilene Christian University, Response to Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML24341A1332024-12-0505 December 2024 Abilene Christian University, Nuclear Energy Experimental Testing Lab., Msrr Degradation Management Program Project stage: Request ML25129A1262025-05-13013 May 2025 Request for Withholding Information from Public Disclosure for Abilene Christian University (Acu) Project stage: Withholding Request Acceptance 2024-01-23
[Table View] |
Text
May 13, 2025 Dr. Rusty Towell Director of NEXT Lab Abilene Christian University ACU Box 27963 Abilene, TX 79699
SUBJECT:
REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR ABILENE CHRISTIAN UNIVERSITY (EPID: L-2022-NFW-0002)
Dear Dr. Towell:
By letter dated December 5, 2024 (Agencywide Documents Access and Management System Accession No. ML24341A133), you submitted an affidavit dated December 5, 2024, executed by Jordan Robison of Natura Resources (Enclosure 3 to the letter) requesting that the information contained in the following documents be withheld from public disclosure pursuant to Section 2.390, Public inspections, exemptions, requests for withholding, of Title 10 of the Code of Federal Regulations (10 CFR):
- Degradation Management Program The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
- a. The information sought to be withheld is owned and has been held in confidence by ACU [Abilene Christian University], the Other Universities and Natura as confidential and proprietary, trade secret information.
- b. The information is of a type that is customarily held in confidence by ACU, the Other Universities, and Natura based on the rationale described in this affidavit.
- c. The information is being transmitted to and, pursuant to 10 CFR 2.390, received by the NRC [U.S. Nuclear Regulatory Commission] in confidence.
- d. No public disclosure of the information has been made, and it is not available in public sources. All disclosures to third parties, including any required transmittals to NRC, have been made, or must be made, pursuant to regulatory provisions or contractual agreements that provide for maintenance of the information in confidence.
- e. The information requested to be withheld reveals specific distinguishing design aspects. The information consists of supporting data relative to a process,
component, structure, tool, method, etc., and the application of the data secures a competitive advantage as described in paragraph 5.
- f. Use by a competitor of the information requested to be withheld would reduce the competitors expenditure of resources, or improve its competitive position, in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390, and the basis of the statements in the affidavit, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the documents listed above in this letter, marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
R. Towell If you have any questions, please contact me at (301) 287-9096, or via email at jorge.hernandez@nrc.gov.
Sincerely, Jorge Hernandez, Project Manager Advanced Reactor Licensing Branch 2 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation Docket No.: 50-610 cc: Abilene Christian University MSRR via GovDelivery
ML25129A126 NRR-106 OFFICE NRR/DANU/UAL2:PM NRR/DANU/UAL2:BC NRR/DANU/UAL2:PM NAME JHernandez SPhilpott JHernandez DATE 05/09/2025 05/12/2025 05/13/2025