Letter Sequence Meeting |
|---|
EPID:L-2024-LRM-0009, Constellations Pre-Submittal Meeting Presentation About Peach Bottom ECCS Compensated Level System Replacement Project - July 22, 2024 (Open) |
Administration
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
|
MONTHYEARML24134A2032024-05-14014 May 2024 Lessons Learned for ECCS Digital I&C License Amendment - Rev 0 Project stage: Other ML24131A1282024-05-14014 May 2024 Lessons Learned for ECCS Digital I&C License Amendment Project stage: Other ML24121A1862024-05-14014 May 2024 Attachment 3: Peach Bottom ECCS Compensated Level System Replacement Project Presentation Material (Non-Proprietary Information) Project stage: Request PMNS20240898, Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32024-07-0808 July 2024 Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML24200A2312024-07-22022 July 2024 Constellations Pre-Submittal Meeting Presentation About Peach Bottom ECCS Compensated Level System Replacement Project - July 22, 2024 Project stage: Request ML24206A1782024-07-29029 July 2024 Summary of Public Meeting with Constellation Energy Generation, LLC Concerning Peach Bottom Units Nos. 2 and 3 Digital Upgrade of the ECCS Compensated Level System Project stage: Meeting ML24270A2612024-10-17017 October 2024 Summary of Public Meeting with Constellation Energy Generation, LLC Concerning Peach Bottom, Units Nos. 2 and 3 Digital Upgrade of the ECCS Compensated Level System Project stage: Meeting PMNS20241330, Meeting with Constellation Energy Generation, LLC to Discuss a Planned Licenseamendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32024-10-18018 October 2024 Meeting with Constellation Energy Generation, LLC to Discuss a Planned Licenseamendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML24305A0952024-10-29029 October 2024 Constellation Slides - ECCS Compensated Level System Replacement Project NRC Pre-submittal Meeting on October 29, 2024 Project stage: Request ML24302A2422024-10-29029 October 2024 ECCS Compensated Level System Replacement Project Pre-Submittal Meeting Slides Project stage: Meeting ML24325A5532024-11-21021 November 2024 Summary of October 29, 2024, Public Observation Meeting with Constellation Energy Generation, LLC Regarding Peach Bottom Atomic Power Station, Units 2 & 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System EPID L- Project stage: Meeting ML24325A5702024-11-22022 November 2024 ECCS Compensated Level System Replacement Project, Constellation Pre-submittal Meeting Slides November 22, 2024 (EPID L-2024-LRM-0009) Public Project stage: Meeting PMNS20241466, Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32024-12-11011 December 2024 Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML24344A2272024-12-12012 December 2024 Summary of Partially Closed Observation Meeting with Constellation Energy Generation, LLC Regarding Peach Bottom Atomic Power Station, Units 2 and 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System Project stage: Meeting ML24366A0502024-12-12012 December 2024 Non-Proprietary Slides for 12/12/24 Meeting with Constellation - ECCS Compensated Level System Replacement Project Project stage: Meeting ML25014A0552025-01-13013 January 2025 December 12, 2024, Summary of Closed Meeting with Constellation Energy Generation, LLC Regarding Peach Bottom, Units 2 & 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System (EPID L-2024-LRM-0009) Non-Proprietary Project stage: Meeting ML25051A2332025-02-16016 February 2025 Constellations Affidavit for Proprietary 2-21-25 Presubmittal Meeting Materials Project stage: Meeting ML25051A2292025-02-21021 February 2025 Constellations Non-Proprietary Slides for 2-21-25 Presubmittal Meeting Project stage: Meeting ML25083A0722025-04-0808 April 2025 Summary of February 21, 2025, Partially Closed Observation Meeting with Constellation Energy Generation, LLC Peach Bottom, Units 2 & 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System EPID L-2024-LRM-0009 Non-Pr Project stage: Meeting ML25118A0372025-05-0101 May 2025 NRC Public Meeting - Peach Bottom Atomic Power Station ECCS Compensated Level System Replacement Project Project stage: Meeting ML25118A0362025-05-0101 May 2025 NRC Slides Peach Bottom Pre-Application 5.1.25 Meeting - Radics Topical Report Safety Evaluation Conclusions on Internal Diversity Project stage: Approval ML25122A1722025-05-0505 May 2025 Summary of Public Observation Meeting with Constellation Energy Generation, LLC Regarding Peach Bottom Atomic Power Station, Units 2 and 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System Project stage: Meeting 2024-07-22
[Table View] |
Text
May 5, 2025 LICENSEE:
Constellation Energy Generation, LLC FACILITY:
Peach Bottom Atomic Power Station, Units 2 and 3
SUBJECT:
SUMMARY
OF MAY 1, 2025, PUBLIC OBSERVATION MEETING WITH CONSTELLATION ENERGY GENERATION, LLC REGARDING PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3, DIGITAL UPGRADE OF THE EMERGENCY CORE COOLING SYSTEM COMPENSATED LEVEL SYSTEM (EPID L-2024-LRM-0009)
On May 1, 2025, the U.S. Nuclear Regulatory Commission (NRC) staff held a virtual, public observation meeting with Constellation Energy Generation, LLC (the licensee). The purpose of the meeting was to discuss a proposed license amendment request (LAR) to support an emergency core cooling system (ECCS) digital instrumentation and controls (DI&C) upgrade for Peach Bottom Atomic Power Station, Units 2 and 3 (Peach Bottom). The meeting notice and agenda, dated April 11, 2025, are available in the NRCs Agencywide Documents Access and Management System (ADAMS) at Accession No. ML25118A231. The enclosure to this summary contains a list of attendees. The licensees presentation slides are available in ADAMS at ML25118A037. The NRCs presentation slides are available in ADAMS at ML25118A036.
During the meeting, the licensee discussed the internal diversity of the RadICS platform described in the referenced NRC topical report safety evaluation (SE) (ML19233A177). The licensee asked the NRC staff to confirm the staffs position regarding what the NRC credits from the RadICS topical report to eliminate the potential for common cause failure (CCF) of the RadICS platform. The NRC staff discussed specific language in the topical report using examples in the presentation to demonstrate that the NRC staff does not conclude in the topical report SE that the RadICS platforms diverse design features alone result in the platform not being susceptible to CCF. The licensee stated that they do not intend to submit a LAR for the ECCS DI&C upgrade to Peach Bottom at this time. Instead, the licensee plans to complete the modification under Section 50.59 of Title 10 of the Code of Federal Regulations (10 CFR). The licensee asked if the RadICS topical report SE could be used in the 10 CFR 50.59 evaluation, and the NRC staff responded that the topical report and topical report SE is intended to be used to support a licensing action not the 10 CFR 50.59 process.
The NRC staff did not make any regulatory decisions at the meeting. Members of the public were in attendance. Public Meeting Feedback forms were not received.
Please direct any inquiries to me at (301) 415-0805, or Rachael.Davis@nrc.gov.
/RA/
Rachael Davis, Project Manager Licensing Data Analysis, Tools, and Assessments Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-277 and 50-278
Enclosure:
List of Attendees cc: Listserv
Enclosure LIST OF ATTENDEES MAY 1, 2025, MEETING WITH CONSTELLATION ENERGY GENERATION, LLC PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 Name Organization Aaron Armstrong U.S Nuclear Regulatory Commission (NRC)
Andrew Golio NRC Brittany Ford NRC Christina Antonescu NRC Deanna Zhang NRC En De Chen NRC Fanta Sacko NRC Jack Zhao NRC Michael Marshall NRC Ming Li NRC Rachael Davis NRC Samir Darbali NRC William Roggenbrodt NRC Amy Huber Constellation Energy Generation, LLC (Constellation)
Brian Woodard Constellation Pablo Guardado Constellation John Hopson Constellation Steve Dragovich Constellation Stephen Flickinger Constellation Wendi Para Constellation Zachariah Shukur Constellation Wendi Para Constellation Pareez Golub Sargent Lundy Richard Paese Sargent Lundy Jana Bergman Curtiss-Wright Michael Kosman Curtiss-Wright Abdelnaeem Taha Framatome Hugh Casper Dominion Energy Jodi Marsico Joseph Neild Mary Miller Dominion Energy Melissa Pelletier Dominion Energy Nicholas Maynard Dominion Energy Robert Atkinson Dominion Energy Robert Chenkovich Dominion Energy Ronald Jones Dominion Energy Tyler Elford Dominion Energy
ML25122A172 OFFICE NRR/DORL/LDATA/PM NRR/DORL/LPL1/LA NRR/DORL/LPL1/BC NRR/DORL/LDATA/PM NAME RDavis KEntz HGonzález (MMarshall for) RDavis DATE 5/2/2025 5/5/2025 5/5/2025 5/5/2025