Letter Sequence Meeting |
|---|
EPID:L-2024-LRM-0009, Constellations Pre-Submittal Meeting Presentation About Peach Bottom ECCS Compensated Level System Replacement Project - July 22, 2024 (Open) |
Administration
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
|
MONTHYEARML24134A2032024-05-14014 May 2024 Lessons Learned for ECCS Digital I&C License Amendment - Rev 0 Project stage: Other ML24131A1282024-05-14014 May 2024 Lessons Learned for ECCS Digital I&C License Amendment Project stage: Other ML24121A1862024-05-14014 May 2024 Attachment 3: Peach Bottom ECCS Compensated Level System Replacement Project Presentation Material (Non-Proprietary Information) Project stage: Request PMNS20240898, Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32024-07-0808 July 2024 Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML24200A2312024-07-22022 July 2024 Constellations Pre-Submittal Meeting Presentation About Peach Bottom ECCS Compensated Level System Replacement Project - July 22, 2024 Project stage: Request ML24206A1782024-07-29029 July 2024 Summary of Public Meeting with Constellation Energy Generation, LLC Concerning Peach Bottom Units Nos. 2 and 3 Digital Upgrade of the ECCS Compensated Level System Project stage: Meeting ML24270A2612024-10-17017 October 2024 Summary of Public Meeting with Constellation Energy Generation, LLC Concerning Peach Bottom, Units Nos. 2 and 3 Digital Upgrade of the ECCS Compensated Level System Project stage: Meeting PMNS20241330, Meeting with Constellation Energy Generation, LLC to Discuss a Planned Licenseamendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32024-10-18018 October 2024 Meeting with Constellation Energy Generation, LLC to Discuss a Planned Licenseamendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML24302A2422024-10-29029 October 2024 ECCS Compensated Level System Replacement Project Pre-Submittal Meeting Slides Project stage: Meeting ML24305A0952024-10-29029 October 2024 Constellation Slides - ECCS Compensated Level System Replacement Project NRC Pre-submittal Meeting on October 29, 2024 Project stage: Request ML24325A5532024-11-21021 November 2024 Summary of October 29, 2024, Public Observation Meeting with Constellation Energy Generation, LLC Regarding Peach Bottom Atomic Power Station, Units 2 & 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System EPID L- Project stage: Meeting ML24325A5702024-11-22022 November 2024 ECCS Compensated Level System Replacement Project, Constellation Pre-submittal Meeting Slides November 22, 2024 (EPID L-2024-LRM-0009) Public Project stage: Meeting PMNS20241466, Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32024-12-11011 December 2024 Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML24366A0502024-12-12012 December 2024 Non-Proprietary Slides for 12/12/24 Meeting with Constellation - ECCS Compensated Level System Replacement Project Project stage: Meeting ML24344A2272024-12-12012 December 2024 Summary of Partially Closed Observation Meeting with Constellation Energy Generation, LLC Regarding Peach Bottom Atomic Power Station, Units 2 and 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System Project stage: Meeting ML25014A0552025-01-13013 January 2025 December 12, 2024, Summary of Closed Meeting with Constellation Energy Generation, LLC Regarding Peach Bottom, Units 2 & 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System (EPID L-2024-LRM-0009) Non-Proprietary Project stage: Meeting PMNS20250143, Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32025-01-31031 January 2025 Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML25051A2332025-02-16016 February 2025 Constellations Affidavit for Proprietary 2-21-25 Presubmittal Meeting Materials Project stage: Meeting ML25051A2292025-02-21021 February 2025 Constellations Non-Proprietary Slides for 2-21-25 Presubmittal Meeting Project stage: Meeting ML25083A0722025-04-0808 April 2025 Summary of February 21, 2025, Partially Closed Observation Meeting with Constellation Energy Generation, LLC Peach Bottom, Units 2 & 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System EPID L-2024-LRM-0009 Non-Pr Project stage: Meeting PMNS20250476, Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32025-04-28028 April 2025 Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML25118A0372025-05-0101 May 2025 NRC Public Meeting - Peach Bottom Atomic Power Station ECCS Compensated Level System Replacement Project Project stage: Meeting ML25118A0362025-05-0101 May 2025 NRC Slides Peach Bottom Pre-Application 5.1.25 Meeting - Radics Topical Report Safety Evaluation Conclusions on Internal Diversity Project stage: Approval ML25122A1722025-05-0505 May 2025 Summary of Public Observation Meeting with Constellation Energy Generation, LLC Regarding Peach Bottom Atomic Power Station, Units 2 and 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System Project stage: Meeting 2024-07-29
[Table View] |
Text
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION January 13, 2025 LICENSEE:
Constellation Energy Generation, LLC FACILITY:
Peach Bottom Atomic Power Station, Units 2 and 3
SUBJECT:
SUMMARY
OF DECEMBER 12, 2024, CLOSED MEETING WITH CONSTELLATION ENERGY GENERATION, LLC REGARDING PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 DIGITAL UPGRADE OF THE EMERGENCY CORE COOLING SYSTEM COMPENSATED LEVEL SYSTEM (EPID L-2024-LRM-0009)
On December 12, 2024, the U.S. Nuclear Regulatory Commission (NRC) staff held a closed meeting with Constellation Energy Generation, LLC (Constellation, the licensee) at NRC Headquarters in Rockville, Maryland. The purpose of the meeting was for Constellation and the NRC staff to discuss a proposed license amendment request (LAR) regarding a digital instrumentation and controls (DI&C) upgrade to the emergency core cooling system (ECCS) compensated level system for Peach Bottom Atomic Power Station, Units 2 and 3 (Peach Bottom). The meeting notice and agenda, dated November 26, 2024, are available in the NRCs Agencywide Documents Access and Management System (ADAMS) at Accession No. ML24346A329. The enclosure to this summary contains a list of attendees.
During the meeting, Constellation discussed the planned approach for addressing the information that needs to be submitted to the NRC with the proposed LAR. The NRC staff stated that the Licensing Technical Report to be submitted with the LAR, or the LAR itself, should describe the application system development areas not covered by the RadICS topical report safety evaluation (SE). The NRC also stated that summaries or descriptions of application software planning documents specific to the Peach Bottom ECCS compensated level system digital upgrade project should be submitted to the NRC for review rather than submitting the entire report or output document. Representatives from Curtiss-Wright asked the NRC to explain the difference between referencing and submitting various documents as part of the LAR. The NRC staff responded by referencing the DI&C interim staff guidance (ISG)
DI&C-ISG-06, Licensing Process, which indicates which documents can be summarized in the LAR, which can be referenced, and which need to be submitted in whole. The NRC staff further explained that the description of how the LAR meets regulatory requirements is needed in writing within the LAR submittal along with how the plant specific action items are addressed.
The NRC staff and Constellation further walked through the RadICS topical report SE and clarified what is needed for Constellation to submit as part of the LAR for application software development and what is credited in the topical report for platform development.
to this summary contains proprietary information.
When separated from Enclosure 1, this document is DECONTROLLED.
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION The NRC staff did not make any regulatory decisions at the meeting. Members of the public were not in attendance. Public Meeting Feedback forms were not received.
Please direct any inquiries to me at (301) 415-0805, or Rachael.Davis@nrc.gov.
/RA/
Rachael Davis, Project Manager Licensing Data Analytics, Tools, and Assessments Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-277 and 50-278
Enclosures:
- 1. Proprietary Information
- 2. Non-Proprietary Information
- 3. List of Attendees
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION (NON-PROPRIETARY INFORMATION)
This document contains proprietary information pursuant to Title 10 of Code of Federal Regulations Section 2.390.
Proprietary information is identified by bold text enclosed within double brackets, as shown here: (( example proprietary text )).
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION
SUMMARY
OF DECEMBER 12, 2024, CLOSED MEETING WITH CONSTELLAITION
[PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3]
The licensee discussed the organization of Curtiss-Wrights quality assurance programs and documents. The NRC staff asked if there is a difference between the roles and responsibilities in the Scientech quality assurance manual (QAM)/quality assurance procedures (QAP) and the Digital Safety Systems (DSS) quality assurance program description (QAPD). ((
)).
LIST OF ATTENDEES DECEMBER 12, 2024, MEETING WITH CONSTELLATION ENERGY GENERATION, LLC PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 Name Organization Aaron Armstrong U.S Nuclear Regulatory Commission (NRC)
Andrew Golio NRC Deanna Zhang NRC Eric Benner NRC Eric Nour NRC Jack Zhao NRC Michael Marshall NRC Ming Li NRC Rachael Davis NRC Samir Darbali NRC Pablo Guardado Constellation Energy Generation, LLC (Constellation)
Steve Dragovich Constellation Stephen Flickinger Constellation Richard Paese Sargent Lundy Rylee Runyon Sargent Lundy Blake Papet Curtiss-Wright Dan Hunt Curtiss-Wright Marty Murphy Curtiss-Wright Michael Kosman Curtiss-Wright Robert Ammon Curtiss-Wright
Package: ML24366A054 Meeting Notice: ML24346A329 Proprietary: ML24366A094 Non-Proprietary: ML25014A055 NRC-001 OFFICE NRR/DORL/LDATA/PM NRR/DORL/LPL1/LA NRR/DORL/LPL1/BC NRR/DORL/LDATA/PM NAME RDavis KEntz HGonzález RDavis DATE 12/31/2025 01/6/2025 01/10/2025 01/13/2025