Constellation Slides - ECCS Compensated Level System Replacement Project NRC Pre-submittal Meeting on October 29, 2024
ML24305A095
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 10/29/2024
From:
Constellation Energy Generation
To: Robert Davis, Marshall M
NRC/NRR/DORL/LPL1
Klett, AL
Shared Package
ML24305A107 List:
References
Download: ML24305A095 (1)


Text

Peach Bottom Atomic Power Station ECCS Compensated Level System Replacement Project NRC Pre-submittal Meeting October 29, 2024

Meeting Purpose

  • Gain alignment on the basis of the additional NRC requested documents from DI&C-ISG-06 Rev 2 Enclosure B.

Agenda

  • Introductions - Project Team
  • Requested DI&C-ISG-06 Rev 2 Enclosure B documents
  • NRC to provide regulatory basis for the requested documents Purpose and Agenda l

1

Constellation Energy

  • Pablo Guardado, Principal PM, PEA Project Management
  • Steve Flickinger, Prin. Reg. Specialist, Corporate Licensing Sargent & Lundy
  • Pareez Golub - Project Director, Digital Licensing SME Introductions - Project Team l

2

Items submitted as part of the ARP

  • 1.3 Approved Topical Report Safety Evaluation
  • 1.4 System Description
  • 1.5 System Architecture
  • 1.6 (Summary of) Hardware Equipment Qualification
  • 1.7 (Unified Compliance/Conformance Matrix for) IEEE

[Institute of Electrical and Electronics Engineers] Stds 603-1991 and 7-4.3.2-2003

  • 1.8 (Changes to) Technical Specifications
  • 1.9 Setpoint Methodology and Calculations
  • 1.10 Secure Development and Operational Environment NRC Requested ISG-06 Enclosure B documents l

3 Additional documents requested by the NRC

  • 1.11 Software Requirements Specification
  • 1.12 Software Design Specification
  • 1.13 Design Analysis Reports for Platform Changes
  • 1.14 System Response Time Analysis Report
  • 1.17 Quality Assurance Plan for Hardware
  • 1.18 (Summary of) Hardware Development Process
  • 2.2 As-Manufactured, System Configuration Documentation
  • 2.3 Summary Test Reports
  • 2.6 System-Level Failure Modes and Effects Analysis
  • 2.9 (Summary of) Electromagnetic Interface, Temperature, Humidity, and Seismic Testing Results
  • The project team needs to understand the basis of the additional NRC requests to ensure that what we provide in the submittal meets the necessary basis.

Basis for the requested additional documents l

4