Enclosure 3: Decommissioning Cost Analysis for the Callaway Energy Center - September 2023
ML25085A005
Person / Time
Site: Callaway Ameren icon.png
Issue date: 03/26/2025
From: Kaczmarek A, Martin J, Munz C
TLG Services
To:
Ameren Services Co, Office of Nuclear Reactor Regulation
Shared Package
ML25085A001 List:
References
ULNRC-06931 A22-1819-001, Rev 0
Download: ML25085A005 (1)


Text

ULNRC-06931 March 26, 2025 Decommissioning Cost Analysis for the Callaway Energy Center - September 2023 (154 pages follow this cover page)

Document 422-1819-007, Rev. 0 prepared for Ameren Services Company prepared by TLG Serviceso LLC Bridgewater, Connecticut September 2O23 DE COMMISSIONING COST ANALYSIS CALLAWAY ENERGY CENTER for the

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page ii of xxi TLG Services, LLC APPROVALS Project Manager Corey J. Munz Date Project Engineer Jeffrey J. Martin Date Technical Manager Adam M. Kaczmarek Date 9/1/2023 9/1/2023 9/1/2023

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page iii of xxi TABLE OF CONTENTS SECTION PAGE EXECUTIVE

SUMMARY

................................................................................. vii-xxi

1.

INTRODUCTION.................................................................................................... 1-1 1.1 Objectives of Study.......................................................................................... 1-1 1.2 Site Description............................................................................................... 1-2 1.3 Regulatory Guidance...................................................................................... 1-3 1.3.1 High-Level Radioactive Waste Management..................................... 1-5 1.3.2 Low-Level Radioactive Waste Disposal.............................................. 1-8 1.3.3 Radiological Criteria for License Termination................................... 1-9

2.

DECOMMISSIONING ALTERNATIVES............................................................. 2-1 2.1 DECON............................................................................................................ 2-2 2.1.1 Period 1 - Preparations........................................................................ 2-2 2.1.2 Period 2 - Decommissioning Operations............................................. 2-4 2.1.3 Period 3 - Site Restoration.................................................................. 2-7 2.2 SAFSTOR........................................................................................................ 2-8 2.2.1 Period 1 - Preparations........................................................................ 2-9 2.2.2 Period 2 - Dormancy.......................................................................... 2-10 2.2.3 Periods 3 and 4 - Delayed Decommissioning.................................... 2-11 2.2.4 Period 5 - Site Restoration................................................................ 2-12

3.

COST ESTIMATE................................................................................................... 3-1 3.1 Basis of Estimate............................................................................................ 3-1 3.2 Methodology.................................................................................................... 3-1 3.3 Financial Components of the Cost Model...................................................... 3-3 3.3.1 Contingency.......................................................................................... 3-3 3.3.2 Financial Risk...................................................................................... 3-5 3.4 Site-Specific Considerations........................................................................... 3-6 3.4.1 Spent Fuel Management..................................................................... 3-6 3.4.2 Reactor Vessel and Internal Components.......................................... 3-9 3.4.3 Primary System Components........................................................... 3-10 3.4.4 Retired Components.......................................................................... 3-11 3.4.5 Main Turbine and Condenser........................................................... 3-11 3.4.6 Transportation Methods.................................................................... 3-12 3.4.7 Low-Level Radioactive Waste Disposal............................................ 3-13 3.4.8 Site Conditions Following Decommissioning................................... 3-14

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page iv of xxi TABLE OF CONTENTS (continued)

SECTION PAGE TLG Services, LLC 3.5 Assumptions.................................................................................................. 3-15 3.5.1 Estimating Basis................................................................................ 3-15 3.5.2 Labor Costs......................................................................................... 3-15 3.5.3 Design Conditions.............................................................................. 3-16 3.5.4 General............................................................................................... 3-17 3.6 Cost Estimate Summary.............................................................................. 3-19

4.

SCHEDULE ESTIMATE........................................................................................ 4-1 4.1 Schedule Estimate Assumptions.................................................................... 4-1 4.2 Project Schedule.............................................................................................. 4-2

5. RADIOACTIVE WASTES...................................................................................... 5-1
6.

RESULTS................................................................................................................ 6-1

7.

REFERENCES........................................................................................................ 7-1 TABLES DECON Cost Summary, Decommissioning Cost Elements................................ xx SAFSTOR Cost Summary, Decommissioning Cost Elements........................... xxi 3.1 DECON Alternative, Total Annual Expenditures............................................ 3-21 3.1a DECON Alternative, License Termination Expenditures............................... 3-22 3.1b DECON Alternative, Spent fuel Management Expenditures.......................... 3-23 3.1c DECON Alternative, Site Restoration Expenditures....................................... 3-24 3.2 SAFSTOR Alternative, Total Annual Expenditures........................................ 3-25 3.2a SAFSTOR Alternative, License Termination Expenditures............................ 3-28 3.2b SAFSTOR Alternative, Spent Fuel Management Expenditures..................... 3-31 3.2c SAFTOR Alternative, Site Restoration Expenditures..................................... 3-32 5.1 DECON Alternative, Decommissioning Waste Summary................................. 5-5 5.2 SAFSTOR Alternative, Decommissioning Waste Summary............................. 5-6 6.1 DECON Alternative, Decommissioning Cost Elements..................................... 6-4 6.2 SAFSTOR Alternative, Decommissioning Cost Elements................................. 6-5

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page v of xxi TABLE OF CONTENTS (continued)

SECTION PAGE TLG Services, LLC FIGURES 3.1 Decommissioning Personnel Levels, DECON............................................... 3-33 3.2 Decommissioning Personnel Levels, SAFSTOR........................................... 3-34 4.1 Activity Schedule.............................................................................................. 4-3 4.2 Decommissioning Timeline, DECON.............................................................. 4-4 4.3.

Decommissioning Timeline, SAFSTOR.......................................................... 4-4 5.1 Radioactive Waste Disposition........................................................................ 5-3 5.2 Decommissioning Waste Destinations, Radiological...................................... 5-4 APPENDICES A.

Unit Cost Factor Development........................................................................... A-1 B.

Unit Cost Factor Listing.................................................................................... B-1 C.

DECON Decommissioning Cost Estimate with Low-Level Radioactive Waste Processing................................................................................................. C-1 D.

SAFSTOR Decommissioning Cost Estimate with Low-Level Radioactive Waste Processing................................................................................................. D-1 E.

DECON Decommissioning Cost Estimate with Direct Disposal of Low-Level Radioactive Waste......................................................................... E-1 F.

SAFSTOR Decommissioning Cost Estimate with Direct Disposal of Low-Level Radioactive Waste.......................................................................... F-1 G.

ISFSI Decommissioning and Demolition........................................................... G-1

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page vi of xxi TLG Services, LLC REVISION LOG No.

Date Item Revised Reason for Revision 0

09-01-2023 Original Issue

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page vii of xxi TLG Services, LLC EXECUTIVE

SUMMARY

This report presents estimates of the cost to decommission the Callaway Energy Center (Callaway) for the selected decommissioning alternatives and scenarios following the scheduled cessation of plant operations. The estimates are designed to provide Ameren Services with sufficient information to assess its financial obligations, as they pertain to the eventual decommissioning of the nuclear unit.

The analysis relies upon site-specific, technical information from an evaluation prepared in 2020,[1] updated to reflect current assumptions pertaining to the disposition of the nuclear unit and relevant industry experience in undertaking such projects. The costs are based on several key assumptions in areas of regulation, component characterization, high-level radioactive waste management, low-level radioactive waste disposal, performance uncertainties (contingency), and site restoration requirements.

The analysis is not a detailed engineering evaluation, but represents estimates prepared in advance of the detailed engineering required to carry out the decommissioning of the nuclear unit. It may also not reflect the actual plan to decommission Callaway; the plan may differ from the assumptions made in this analysis based on facts that exist at the time of decommissioning.

The 2020 plant inventory, the basis for the decontamination and dismantling requirements and cost, and the decommissioning waste streams, was reviewed for this analysis. There have been no substantive changes made to the plant inventory that would impact the estimated decommissioning costs.

The costs to decommission Callaway for the base scenarios (disposal with low-level radioactive waste processing) are presented at the end of this section. Costs are reported in 2023 dollars and include monies anticipated to be spent for radiological remediation and operating license termination, spent fuel management, and site restoration activities.

A complete discussion of the assumptions relied upon in this analysis is provided in Section 3, along with schedules of annual expenditures for the base scenarios. A sequence of significant project activities is provided in Section 4 with a timeline for each scenario. Detailed cost reports used to generate the summary tables contained 1

Decommissioning Cost Analysis for the Callaway Energy Center, Document A22-1782-001, Rev. 0, TLG Services, Inc., October 2020

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page viii of xxi TLG Services, LLC within this document are provided in the appendices along with the costs for the alternative scenario (direct low-level radioactive waste disposal).

Consistent with the 2020 analysis, the current cost estimates assume that the shutdown of the nuclear unit is a scheduled and pre-planned event (e.g., there is no delay in transitioning the plant and workforce from operations or in obtaining regulatory relief from operating requirements, etc.). The estimates include the continued operation of the fuel building as an interim wet fuel storage facility for approximately five and one-half years after operations cease. During this period, it is assumed that the spent fuel residing in the pool will be transferred to a Department of Energy (DOE) federal facility (e.g., a monitored retrievable storage facility). All spent fuel stored on site in the independent spent fuel storage installation (ISFSI) will also be removed by the DOE during this time.

Alternatives and Regulations The ultimate objective of the decommissioning process is to reduce the inventory of contaminated and activated material so that the license can be terminated. The Nuclear Regulatory Commission (NRC or Commission) provided initial decommissioning requirements in its rule adopted on June 27, 1988.[2] In this rule, the NRC set forth financial criteria for decommissioning licensed nuclear power facilities. The regulations addressed planning needs, timing, funding methods, and environmental review requirements for decommissioning. The rule also defined three decommissioning alternatives as being acceptable to the NRC: DECON, SAFSTOR, and ENTOMB.

DECON is defined as "the alternative in which the equipment, structures, and portions of a facility and site containing radioactive contaminants are removed or decontaminated to a level that permits the property to be released for unrestricted use shortly after cessation of operations."[3]

SAFSTOR is defined as "the alternative in which the nuclear facility is placed and maintained in a condition that allows the nuclear facility to be safely stored and subsequently decontaminated (deferred decontamination) to levels that permit release for unrestricted use."[4]

Decommissioning is to be completed within 60 years, although longer 2

U.S. Code of Federal Regulations, Title 10, Parts 30, 40, 50, 51, 70 and 72 "General Requirements for Decommissioning Nuclear Facilities," Nuclear Regulatory Commission, Federal Register Volume 53, Number 123 (p 24018 et seq.), June 27, 1988 3

Ibid. Page FR24022, Column 3 4

Ibid.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page ix of xxi TLG Services, LLC periods will be considered when necessary to protect public health and safety.

ENTOMB is defined as "the alternative in which radioactive contaminants are encased in a structurally long-lived material, such as concrete; the entombed structure is appropriately maintained and continued surveillance is carried out until the radioactive material decays to a level permitting unrestricted release of the property."[5] As with the SAFSTOR alternative, decommissioning is currently required to be completed within 60 years, although longer time periods will also be considered when necessary to protect public health and safety.

The 60-year restriction has limited the practicality for the ENTOMB alternative at commercial reactors that generate significant amounts of long-lived radioactive material. In 1997, the Commission directed its staff to re-evaluate this alternative and identify the technical requirements and regulatory actions that would be necessary for entombment to become a viable option.

The resulting evaluation provided several recommendations; however, rulemaking has been deferred pending the completion of additional research studies, for example, on engineered barriers. In a draft regulatory basis document published in March 2017 in support of rulemaking that would amend NRC regulations concerning nuclear plant decommissioning, the NRC staff proposes removing any discussion of the ENTOMB option from existing guidance documents since the method is not deemed practically feasible.

In 1996, the NRC published revisions to the general requirements for decommissioning nuclear power plants to clarify ambiguities and codify procedures and terminology as a means of enhancing efficiency and uniformity in the decommissioning process.[6] The amendments allow for greater public participation and better define the transition process from operations to decommissioning. Regulatory Guide 1.184, issued in July 2000, (as revised in October 2013), further described the methods and procedures that are acceptable to the NRC staff for implementing the requirements of the 1996 revised rule that relate to the initial activities and the major phases of the decommissioning process. The costs and schedules presented in this analysis follow the general guidance and sequence in the amended regulations. The format and content of 5

Ibid. Page FR24023, Column 2 6

U.S. Code of Federal Regulations, Title 10, Parts 2, 50, and 51, "Decommissioning of Nuclear Power Reactors," Nuclear Regulatory Commission, Federal Register Volume 61, (p 39278 et seq.), July 29, 1996

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page x of xxi TLG Services, LLC the estimates is also consistent with the recommendations of Regulatory Guide 1.202, issued in February 2005.[7]

In 2011, the NRC issued regulations to improve decommissioning planning and thereby reduce the likelihood that any current operating facility will become a legacy site.[8] The regulations require licensees to report additional details in their decommissioning cost estimate, including a decommissioning estimate for any on-site ISFSI. Since an ISFSI is required to support continued operation at Callaway, a representative decommissioning cost is included within the DECON and SAFSTOR estimates, and reported separately in Appendix G.

Decommissioning Scenarios Two decommissioning alternatives were evaluated for the Callaway Energy Center.

The scenarios selected are representative of alternatives currently available to the owner and are defined as follows:

1. The first scenario assumes that the nuclear unit is promptly decommissioned (DECON alternative) upon the expiration of the current operating license in 2044. Following the permanent cessation of operations, and over the first five and one-half years, the spent fuel is transferred directly from the wet storage pool to the DOE (the fuel stored on the ISFSI is also removed from the site during this time period). Concurrently, the majority of the plant components, including the nuclear steam supply system components, are removed. Once the spent fuel stored in the fuel pool has been transferred off-site, the remaining portions of the power block are decommissioned and the surrounding site is remediated. Following the termination of the operating license, non-essential structures (not designated for reuse) are dismantled.
2. In the second scenario, the nuclear unit is placed into safe-storage (SAFSTOR alternative) upon the expiration of the current operating license in 2044. As with the first scenario, the spent fuel is removed from the site (transferred to the DOE) during the first five and one-half years following the permanent cessation of operations. The facility is then placed into safe-storage (with non-essential systems de-energized and 7

Standard Format and Content of Decommissioning Cost Estimates for Nuclear Power Reactors, Regulatory Guide 1.202, Nuclear Regulatory Commission, February 2005 8

U.S. Code of Federal Regulations, Title 10, Parts 20, 30, 40, 50, 70, and 72, "Decommissioning Planning," Nuclear Regulatory Commission, Federal Register Volume 76, (p 35512 et seq.), June 17, 2011

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page xi of xxi TLG Services, LLC buildings secured). The start of decontamination and dismantling activities is deferred to the maximum extent (approximately 50 years from the cessation of operations) such that the license is terminated within the required 60-year period post cessation of operations.

In addition to the two decommissioning alternatives, two low-level radioactive waste disposal options were assessed for each decommissioning alternative: one assuming the use of radioactive waste processing; the other assuming all radioactive waste is directly disposed of by burial. Off-site processing of a portion of the radioactive waste stream is presented as the base option. This option considers the off-site processing of the plant equipment and commodities with low levels of radiological contamination and/or material suspected to be contaminated for volume reduction, decontamination, or segmentation and removal of clean portions prior to disposal as radioactive waste.

The direct disposal option assumes that all contaminated and suspect material is packaged at the site for disposal at a regulated disposal facility. The scenarios are summarized as follows.

Alternative Low-Level Radioactive Waste Options Cost Summaries and/or Detailed Estimates DECON Recycling Sections 3, 6, Appendix C Direct Disposal Appendix E SAFSTOR Recycling Sections 3, 6, Appendix D Direct Disposal Appendix F Methodology The methodology used to develop the estimates described within this document follows the basic approach originally presented in the cost estimating guidelines[9] developed by the Atomic Industrial Forum (now Nuclear Energy Institute). This reference describes a unit factor method for determining decommissioning activity costs. The unit factors used in this analysis incorporate site-specific costs and the latest available information on worker productivity in decommissioning.

An activity duration critical path is used to determine the total decommissioning program schedule. The schedule is relied upon in calculating the carrying costs, which include program management, administration, field engineering, equipment rental, and support services, such as quality control and security.

9 T.S. LaGuardia et al., "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page xii of xxi TLG Services, LLC The estimates also reflect lessons learned from TLGs involvement in the Shippingport Station Decommissioning Project, completed in 1989, as well as the decommissioning of the Cintichem reactor, hot cells and associated facilities, completed in 1997. In addition, the planning and engineering for the Rancho Seco, Trojan, Yankee Rowe, Big Rock Point, Maine Yankee, Humboldt Bay-3, Oyster Creek, Connecticut Yankee, Crystal River, Vermont Yankee, Fort Calhoun, Pilgrim, and Indian Point nuclear units have provided additional insight into the process, the regulatory aspects, and the technical challenges of decommissioning commercial nuclear units.

Contingency Consistent with cost estimating practice, contingencies are applied to the decontamination and dismantling costs developed as "specific provision for unforeseeable elements of cost within the defined project scope, particularly important where previous experience relating estimates and actual costs has shown that unforeseeable events which will increase costs are likely to occur.[10] The cost elements in the estimates are based on ideal conditions; therefore, the types of unforeseeable events that are almost certain to occur in decommissioning, based on industry experience, are addressed through a percentage contingency applied on a line-item basis. This contingency factor is a nearly universal element in all large-scale construction and demolition projects. It should be noted that contingency, as used in this analysis, does not account for price escalation and inflation in the cost of decommissioning over the remaining operating life of the station.

Contingency funds are expected to be fully expended throughout the program. As such, inclusion of contingency is necessary to provide assurance that sufficient funding will be available to accomplish the intended tasks.

Low-Level Radioactive Waste Disposal The contaminated and activated material generated in the decontamination and dismantling of a commercial nuclear reactor is classified as low-level (radioactive) waste, although not all of the material is suitable for shallow-land disposal. With the passage of the Low-Level Radioactive Waste Policy Act in 1980,[11] and its Amendments of 1985,[12] the states became ultimately responsible for the disposition of low-level radioactive waste generated within their own borders.

10 Project and Cost Engineers Handbook, Second Edition, American Association of Cost Engineers, Marcel Dekker, Inc., New York, New York, p. 239 11 Low-Level Radioactive Waste Policy Act of 1980, Public Law 96-573, 1980 12 Low-Level Radioactive Waste Policy Amendments Act of 1985, Public Law 99-240, 1986

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page xiii of xxi TLG Services, LLC With the exception of Texas, no new compact facilities have been successfully sited, licensed, and constructed. The Texas Compact disposal facility is assumed operational and waste is being accepted from generators within the Compact by the operator, Waste Control Specialists (WCS). The facility, located in Andrews, Texas, is also assumed able to accept limited volumes of non-Compact waste.

Disposition of the various waste streams produced by the decommissioning process considered all options and services currently available to Ameren Services. The majority of the low-level radioactive waste designated for controlled disposal (Class A[13]) can be sent to EnergySolutions facility in Clive, Utah. Therefore, disposal costs for Class A waste were based upon Ameren Services agreement with EnergySolutions. This facility is not licensed to receive the higher activity portion (Classes B and C) of the decommissioning waste stream.

The WCS facility is able to receive the Class B and C waste. As such, for this analysis, Class B and C waste was assumed to be shipped to the WCS facility for disposal.

Disposal costs were based upon Ameren Services current agreement with WCS.

The dismantling of the components residing closest to the reactor core generates radioactive waste that may be considered unsuitable for shallow-land disposal (i.e., low-level radioactive waste with concentrations of radionuclides that exceed the limits established by the NRC for Class C radioactive waste, Greater than Class C waste (GTCC)). The Low-Level Radioactive Waste Policy Amendments Act of 1985 assigned the federal government the responsibility for the disposal of this material. The Act also stated that the beneficiaries of the activities resulting in the generation of such radioactive waste bear all reasonable costs of disposing of such waste.

The DOE issued its Final Environmental Impact Statement for the disposal of GTCC on January 2016. [14]The study evaluated the potential environmental impacts associated with constructing and operating a new facility or using an existing facility, disposal methods, and locations. DOE is awaiting Congressional action on the report and its recommendations. At this time, the federal government has not identified a specific cost for disposing of GTCC or a schedule for acceptance.

For purposes of this analysis only, the GTCC radioactive waste is assumed to be packaged and disposed of in a similar manner as high-level waste and at a cost equivalent to that envisioned for the spent fuel. The GTCC is packaged in canisters compatible with the spent fuel dry storage system and either stored on site or shipped directly to a federal facility as it is generated (depending upon the timing of the decommissioning and whether the spent fuel has been removed from the site prior to 13 Waste is classified in accordance with U.S. Code of Federal Regulations, Title 10, Part 61.55 14 Final Environmental Impact Statement for the Disposal of Greater-Than-Class C (GTCC) Low-Level Radioactive Waste and GTCC-Like Waste (DOE/EIS-0375), January 2016

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page xiv of xxi TLG Services, LLC the start of decommissioning).

A significant portion of the waste material generated during decommissioning may only be potentially contaminated by radioactive materials. This material can be analyzed on site or shipped off site to licensed facilities for further analysis, for processing and/or for conditioning/recovery. Reduction in the volume of low-level radioactive waste requiring direct disposal in a licensed low-level radioactive waste disposal facility can be accomplished through a variety of methods, including analyses and surveys or decontamination to eliminate the portion of waste that does not require disposal as radioactive waste, compaction, incineration or metal melt. The estimates for the base case scenarios reflect the savings from waste recovery/volume reduction.

High-Level Radioactive Waste Management Congress passed the Nuclear Waste Policy Act[15] (NWPA) in 1982, assigning the federal governments long-standing responsibility for disposal of the spent nuclear fuel created by the commercial nuclear generating plants to the DOE. The DOE was to begin accepting spent fuel by January 31, 1998; however, to date no progress in the removal of spent fuel from commercial generating sites has been made.

Today, the country is at an impasse on high-level waste disposal, despite DOEs submittal of its License Application for a geologic repository to the NRC in 2008. The Obama administration eliminated the budget for the repository program while promising to conduct a comprehensive review of policies for managing the back end of the nuclear fuel cycle and make recommendations for a new plan.[16] Towards this goal, the Obama administration appointed a Blue Ribbon Commission on Americas Nuclear Future (Blue Ribbon Commission) to make recommendations for a new plan for nuclear waste disposal. The Blue Ribbon Commissions charter included a requirement that it consider [o]ptions for safe storage of used nuclear fuel while final disposition pathways are selected and deployed.[17]

On January 26, 2012, the Blue Ribbon Commission issued its Report to the Secretary of Energy containing a number of recommendations on nuclear waste disposal. Two of the recommendations that may impact decommissioning planning are:

15 Nuclear Waste Policy Act of 1982 and Amendments, DOEs Office of Civilian Radioactive Management, 1982 16 Advisory Committee Charter, Blue Ribbon Commission on Americas Nuclear Future, Appendix A, January 2012 17 Ibid.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page xv of xxi TLG Services, LLC

[T]he United States [should] establish a program that leads to the timely development of one or more consolidated storage facilities[18]

[T]he United States should undertake an integrated nuclear waste management program that leads to the timely development of one or more permanent deep geological facilities for the safe disposal of spent fuel and high-level nuclear waste.[19]

In January 2013, the DOE issued the Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste, in response to the recommendations made by the Blue Ribbon Commission and as a framework for moving toward a sustainable program to deploy an integrated system capable of transporting, storing, and disposing of used nuclear fuel...[20] This document states:

With the appropriate authorizations from Congress, the Administration currently plans to implement a program over the next 10 years that:

Sites, designs and licenses, constructs and begins operations of a pilot interim storage facility by 2021 with an initial focus on accepting used nuclear fuel from shut-down reactor sites; Advances toward the siting and licensing of a larger interim storage facility to be available by 2025 that will have sufficient capacity to provide flexibility in the waste management system and allows for acceptance of enough used nuclear fuel to reduce expected government liabilities; and Makes demonstrable progress on the siting and characterization of repository sites to facilitate the availability of a geologic repository by 2048.[21]

The NRCs review of DOEs license application to construct a geologic repository at Yucca Mountain was suspended in 2011 when the Obama administration significantly reduced the budget for completing that work. However, the US Court of Appeals for the District of Columbia Circuit issued a writ of mandamus (in August 2013)[22] ordering NRC to comply with federal law and resume its review of DOE's Yucca Mountain repository license application, to the extent allowed by previously 18 Blue Ribbon Commission on Americas Nuclear Future, Report to the Secretary of Energy, http://www.brc.gov/sites/default/files/documents/brc_finalreport_jan2012.pdf, p. 32, January 2012 32, January 2012 19 Ibid., p.27 20 Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste, U.S. DOE, January 11, 2013 21 Ibid., p.2 22 U.S. Court of Appeals for the District Of Columbia Circuit, In Re: Aiken County, et al, Aug. 2013

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page xvi of xxi TLG Services, LLC appropriated funding for the review. That review was completed with the publication of the five-volume safety evaluation report. A supplement to DOEs environmental impact statement and adjudicatory hearing on the contentions filed by interested parties must be completed before a licensing decision can be made. Although the DOE proposed it would start fuel acceptance in 2025, no progress has been made in the repository program since DOEs 2013 strategy was issued except for the completion of the Yucca Mountain safety evaluation report.

Holtec International submitted a license application to the NRC on March 30, 2017 for a consolidated interim spent fuel storage facility in southeast New Mexico called HI-STORE CISF (Consolidated Interim Storage Facility) under the provisions of 10 CFR Part 72. In May 2023, the NRC issued a license to Holtec to construct and operate a facility to receive, possess, store, and transfer spent nuclear fuel at the HI-STORE CISF.

Waste Control Specialists submitted an application to the NRC on April 28, 2016, to construct and operate a Consolidated Interim Storage Facility (CISF) at its West Texas facility. On April 18, 2017, WCS requested that the NRC temporarily suspend all safety and environmental review activities, as well as public participation activities associated with WCSs license application. In March 2018, WCS and Orano USA, announced their intent to form a joint venture to license the facility. The joint venture, named Interim Storage Partners (ISP), requested that the NRC resume its review of the original CISF license application. Subsequently, in September, 2021, NRC issued a license to ISP for its WCS CISF to construct and operate the facility for spent nuclear fuel and GTCC storage. However, the facility is not yet operational.

Completion of the decommissioning process is dependent upon the DOEs ability to remove spent fuel from the site in a timely manner. In June 2011, Ameren Services and the DOE reached an agreement on a settlement. The terms include payment to Ameren Services for spent fuel storage and related costs through 2010, and thereafter, annual payment of such costs after they are incurred.

It is generally necessary that spent fuel be cooled and stored for a minimum period at the generating site prior to transfer. As such, the NRC requires that licensees establish a program to manage and provide funding for the management of all irradiated fuel at the reactor site until title of the fuel is transferred to the DOE, pursuant to 10 CFR Part 50.54(bb).[23] The post-shutdown costs incurred to satisfy this requirement include the isolation and continued operation of the spent fuel pool and the ISFSI during the five and one-half years following the cessation of plant operations.

23 U.S. Code of Federal Regulations, Title 10, Part 50, Domestic Licensing of Production and Utilization Facilities, Subpart 54 (bb), Conditions of Licenses

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page xvii of xxi TLG Services, LLC At shutdown, the spent fuel pool is expected to contain freshly discharged assemblies (from the most recent refueling cycles) as well as the final reactor core. Over the following five and one-half years all the assemblies are packaged into canisters for transfer to the DOE. It is assumed that this period provides the necessary cooling for the final core to meet the transportation system requirements for decay heat.

Costs are included within the decommissioning estimates for offloading the pool. These costs include the loading of DOE-provided Transport/Aging/Disposal Canister (TADs) and the associated campaign costs to load the canisters into the DOE-provided transport vehicle.

Removal of the fuel from the ISFSI is expected to be fully reimbursable and therefore not addressed in this study. However, the eventual decommissioning of the ISFSI is included.

The estimates described in this analysis were developed with the assumption that the DOE would give priority to removing spent fuel from shutdown sites. The estimates further assume that the spent fuel would be removed from the Callaway site within five and one-half years of the cessation of plant operations (i.e., five and one-half years would provide sufficient cooling time for the spent fuel to meet DOE transportation requirements).

Site Restoration The efficient removal of the contaminated materials at the site may result in damage to many of the site structures. Blasting, coring, drilling, and the other decontamination activities can substantially damage power block structures, potentially weakening the footings and structural supports. It is unreasonable to anticipate that these structures would be repaired and preserved after the radiological contamination is removed. The cost to dismantle site structures with a work force already mobilized is more efficient and less costly than if the process is deferred.

Consequently, this study assumes that non-essential site structures addressed by this analysis are removed, once remediation is complete, to a nominal depth of three feet below the local grade level, wherever possible. The site is then graded and stabilized.

Summary The estimates to decommission Callaway assume the removal of all contaminated and activated plant components and structural materials such that the owner may then have unrestricted use of the site with no further requirements for an operating license.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page xviii of xxi TLG Services, LLC Low-level radioactive waste, other than GTCC waste, is sent to a commercial processor for treatment/conditioning or directly to a controlled disposal facility.

Decommissioning is accomplished within the 60-year period following permanent cessation of operations required by current NRC regulations. Regardless of the timing of the decommissioning activities, the estimates assume the eventual removal of all the contaminated and activated plant components and structural materials, such that the facility operator may then have unrestricted use of the site with no further requirement for an operating license.

The decommissioning scenarios are described in Section 2. The assumptions are presented in Section 3, along with schedules of annual expenditures for the base case scenario. The major cost contributors are identified in Section 6, with detailed activity costs, waste volumes, and associated workforce requirements delineated in the appendices to this report. The major cost components are also identified in the cost summary provided at the end of this section.

The cost elements in the estimates for the DECON and SAFSTOR alternatives are assigned to one of three subcategories: NRC License Termination (radiological remediation), Spent Fuel Management, and Site Restoration. The subcategory NRC License Termination is used to accumulate costs that are consistent with decommissioning as defined by the NRC in its financial assurance regulations (i.e., 10 CFR Part 50.75). The cost reported for this subcategory is generally sufficient to terminate the units operating license, recognizing that there may be some additional cost impact from spent fuel management. The License Termination cost subcategory also includes costs to decommission the ISFSI (as required by 10 CFR §72.30). Section 3.4.1 provides the basis for the ISFSI decommissioning cost.

The Spent Fuel Management subcategory is used to accumulate costs associated with operation of the fuel storage pool and the management of the ISFSI until such time that the transfer is complete. It does not include any spent fuel management expenses incurred prior to the cessation of plant operations, nor does it include any costs related to the final disposal of the spent fuel.

Site Restoration is used to capture costs associated with the dismantling and demolition of buildings and facilities demonstrated to be free from contamination. This includes structures never exposed to radioactive materials, as well as those facilities that have been decontaminated to appropriate levels. Structures are removed to a depth of three feet below grade and backfilled to conform to local grade.

It should be noted that the costs assigned to these subcategories are allocations.

Delegation of cost elements is for the purposes of comparison (e.g., with NRC financial guidelines) or to permit specific financial treatment (e.g., Asset Retirement Obligation

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page xix of xxi TLG Services, LLC determinations). In reality, there can be considerable interaction between the activities in the three subcategories. For example, an owner may decide to remove non-contaminated structures early in the project to improve access to highly contaminated facilities or plant components. In these instances, the non-contaminated removal costs could be reassigned from Site Restoration to an NRC License Termination support activity. However, in general, the allocations represent a reasonable accounting of those costs that can be expected to be incurred for the specific subcomponents of the total estimated program cost, if executed as described.

As noted within this document, the estimates were developed and costs are presented in 2023 dollars. As such, the estimates do not reflect the escalation of costs (due to inflationary and market forces) over the remaining operating life of the reactor or during the decommissioning period.

For the purposes of this analysis, the costs presented in the following tables reflect the use of off-site low-level radioactive waste processing to minimize the volume designated for controlled disposal. Costs for the direct disposal of the low-level radioactive waste (without processing) are presented in the appendices (E and F).

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page xx of xxi TLG Services, LLC DECON COST

SUMMARY

DECOMMISSIONING COST ELEMENTS [1]

(thousands of 2023 dollars) 1DECON Cost Summary, Decommissioning Cost Elements Cost Element Cost Decontamination 24,795 Removal 206,170 Packaging 35,292 Transportation 25,123 Waste Disposal 130,929 Off-site Waste Processing [1]

37,057 Program Management [2]

359,753 Security 100,102 Corporate Allocations 9,270 Spent Fuel Pool Isolation 16,480 Spent Fuel Management [3]

78,615 Insurance and Regulatory Fees 18,310 Energy 13,975 Characterization and Licensing Surveys 32,090 Property Taxes 1,112 Miscellaneous Equipment 8,875 Total [4]

1,097,947 Cost Element Cost License Termination (excluding ISFSI) 891,881 ISFSI Decommissioning (License Termination) 10,556 Spent Fuel Management [3]

78,615 Site Restoration (excluding ISFSI) 115,155 ISFSI Demolition (Site Restoration) 1,740 Total [4]

1,097,947

[1]

Assumes low-level radioactive waste processing for volume reduction

[2]

Includes engineering costs

[3] Direct costs only. Excludes program management costs (staffing) but includes costs for spent fuel loading/spent fuel pool O&M and Emergency Planning fees

[4] Columns may not add due to rounding

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Page xxi of xxi TLG Services, LLC SAFSTOR COST

SUMMARY

DECOMMISSIONING COST ELEMENTS [1]

(thousands of 2023 dollars) 2SAFSTOR Cost Summary, Decommissioning Cost Elements Cost Element Cost Decontamination 22,031 Removal 210,552 Packaging 29,078 Transportation 20,724 Waste Disposal 99,601 Off-site Waste Processing [1]

40,909 Program Management [2]

471,962 Security 279,243 Corporate Allocations 14,255 Spent Fuel Pool Isolation 16,480 Spent Fuel Management [3]

78,615 Insurance and Regulatory Fees 58,283 Energy 28,359 Characterization and Licensing Surveys 32,222 Property Taxes 8,114 Miscellaneous Equipment 24,989 Total [4]

1,435,417 Cost Element Cost License Termination (excluding ISFSI) 1,212,752 ISFSI Decommissioning (License Termination) 10,556 Spent Fuel Management [5]

96,323 Site Restoration (excluding ISFSI) 114,046 ISFSI Demolition (Site Restoration) 1,740 Total [4]

1,435,417

[1]

Assumes low-level radioactive waste processing for volume reduction

[2]

Includes engineering costs

[3]

Direct costs only. Excludes program management costs (staffing) but includes costs for spent fuel loading/spent fuel pool O&M and Emergency Planning fees

[4]

Columns may not add due to rounding

[5]

Includes percentage of Period 2a (dormancy) plant operating costs until spent fuel pool is emptied, in addition to the direct costs.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section1, Page 1 of 10 TLG Services, LLC

1. INTRODUCTION This report presents estimates of the costs to decommission the Callaway Energy Center (Callaway) for the selected decommissioning alternatives and scenarios following the scheduled cessation of plant operations. The estimates are designed to provide Ameren Services with sufficient information to assess its financial obligations, as they pertain to the eventual decommissioning of the nuclear unit.

The analysis relies upon site-specific, technical information from an earlier evaluation prepared in 2020,[1]* updated to reflect current assumptions pertaining to the disposition of the nuclear station and relevant industry experience in undertaking such projects. The costs are based on several key assumptions in areas of regulation, component characterization, high-level radioactive waste management, low-level radioactive waste disposal, performance uncertainties (contingency), and site restoration requirements.

The analysis is not a detailed engineering evaluation, but rather estimates prepared in advance of the detailed engineering required to carry out the decommissioning of the nuclear unit. It may also not reflect the actual plan to decommission Callaway; the plan may differ from the assumptions made in this analysis based on facts that exist at the time of decommissioning.

The 2020 plant inventory, the basis for the decontamination and dismantling requirements and cost, and the decommissioning waste streams, were reviewed for this analysis. There were no substantive changes made to the plant inventory (that would impact decommissioning).

1.1 OBJECTIVES OF STUDY The objectives of this study were to prepare comprehensive estimates of the costs to decommission Callaway, to provide a sequence or schedule for the associated activities, and to develop waste stream projections from the decontamination and dismantling activities.

An operating license was issued for Callaway in 1984 for a 40 year operating period. On December 19, 2011, Ameren Services submitted a request for renewal of the operating license for an additional period of 20 years. On March 6, 2015, the Nuclear Regulatory Commission (NRC) renewed the operating license through October 18, 2044.

  • References provided in Section 7 of the document

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section1, Page 2 of 10 TLG Services, LLC For the purpose of this analysis, the base estimates reflect plant decommissioning at the expiration of its current operating license (2044) and the use of off-site low-level radioactive waste processing to minimize the volume designated for controlled disposal.

1.2 SITE DESCRIPTION The nuclear unit is located in Callaway County, Missouri, approximately 80 miles west of the St. Louis metropolitan area. The nearest population center is Jefferson City, 25 miles west-southwest of the plant site. The station is a 1,171 MWe (net design electrical rating) pressurized water reactor with supporting facilities.

Westinghouse Electric Company designed the nuclear steam supply system (NSSS). The NSSS consists of a pressurized water reactor with four independent primary coolant loops, each of which contains a reactor coolant pump and a steam generator. An electrically heated pressurizer and connecting piping complete the system. The NSSS is rated at a thermal power level of 3,579 MWt (3,565 MWt reactor core plus 14 MWt for reactor coolant pumps), with a corresponding turbine-generator gross output of 1,284 MWe. The system is housed within a containment structure, a pre-stressed, post-tensioned concrete structure with cylindrical wall, a hemispherical dome, and a flat foundation slab.

The wall and dome form a pre-stressed post-tensioned system. The inside surface of the structure is covered with a carbon steel liner, providing a leak tight membrane.

A power conversion system converts heat produced in the reactor to electrical energy. This system converts the thermal energy of the steam into mechanical shaft power and then into electrical energy. The turbine-generator is a tandem compound, six-flow, four element, 1800-rpm unit. The unit consists of one high pressure and three low-pressure turbine elements driving a directly coupled generator. The turbine is operated in a closed feedwater cycle that condenses the steam; the feedwater is returned to the steam generators. Heat rejected in the main condensers is removed by the circulating water system.

The circulating water system supplies cooling water to the main condenser, condensing the steam exhausted from the turbine. Cooling for the condenser circulating water system is supplied by a large natural draft cooling tower.

Makeup water for the cooling tower is drawn from the Missouri River.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section1, Page 3 of 10 TLG Services, LLC 1.3 REGULATORY GUIDANCE The Nuclear Regulatory Commission (NRC or Commission) provided initial decommissioning requirements in its rule "General Requirements for Decommissioning Nuclear Facilities," issued in June 1988.[2] This rule set forth financial criteria for decommissioning licensed nuclear power facilities. The regulation addressed decommissioning planning needs, timing, funding methods, and environmental review requirements. The intent of the rule was to ensure that decommissioning would be accomplished in a safe and timely manner and that adequate funds would be available for this purpose.

Subsequent to the rule, the NRC issued Regulatory Guide 1.159, Assuring the Availability of Funds for Decommissioning Nuclear Reactors,[3] which provided additional guidance to the licensees of nuclear facilities on the financial methods acceptable to the NRC staff for complying with the requirements of the rule. The regulatory guide addressed the funding requirements and provided guidance on the content and form of the financial assurance mechanisms indicated in the rule.

The rule defined three decommissioning alternatives as being acceptable to the NRC: DECON, SAFSTOR, and ENTOMB. The DECON alternative assumes that any contaminated or activated portion of the plants systems, structures and facilities are removed or decontaminated to levels that permit the site to be released for unrestricted use shortly after the cessation of plant operations. The rule also placed limits on the time allowed to complete the decommissioning process. For SAFSTOR, the process is restricted in overall duration to 60 years, unless it can be shown that a longer duration is necessary to protect public health and safety. The guidelines for ENTOMB are similar, providing the NRC with both sufficient leverage and flexibility to ensure that these deferred options are only used in situations where it is reasonable and consistent with the definition of decommissioning. At the conclusion of a 60-year dormancy period (or longer for ENTOMB if the NRC approves such a case), the site would still require significant remediation to meet the unrestricted release limits for license termination.

The ENTOMB alternative has not been viewed as a viable option for power reactors due to the significant time required to isolate the long-lived radionuclides for decay to permissible levels. However, with rulemaking permitting the controlled release of a site,[4] the NRC has re-evaluated this alternative. The resulting feasibility study, based upon an assessment by Pacific Northwest National Laboratory, concluded that the method did have conditional merit for some, if not most reactors. However, the staff also found that additional rulemaking would be needed before this option could be treated as a generic alternative. The NRC had considered rulemaking to alter the 60-year time for

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section1, Page 4 of 10 TLG Services, LLC completing decommissioning and to clarify the use of engineered barriers for reactor entombments.[5]

The NRCs staff has recommended that rulemaking be deferred, based upon several factors, e.g., no licensee has committed to pursuing the entombment option, and the NRCs current priorities, at least until after the additional research studies are complete. The NRC concurred with the staffs recommendation. In a draft regulatory basis document published in March 2017 in support of rulemaking that would amend NRC regulations concerning nuclear plant decommissioning, the NRC staff proposes removing any discussion of the ENTOMB option from existing guidance documents since the method is not deemed practically feasible.

In 1996, the NRC published revisions to the general requirements for decommissioning nuclear power plants.[6] When the decommissioning regulations were adopted in 1988, it was assumed that the majority of licensees would decommission at the end of the facilitys operating licensed life. Since that time, several licensees permanently and prematurely ceased operations.

Exemptions from certain operating requirements were required once the reactor was defueled to facilitate the decommissioning. Each case was handled individually, without clearly defined generic requirements. The NRC amended the decommissioning regulations in 1996 to clarify ambiguities and codify procedures and terminology as a means of enhancing efficiency and uniformity in the decommissioning process. The amendments allow for greater public participation and better define the transition process from operations to decommissioning.

Under the revised regulations, licensees will submit written certification to the NRC within 30 days after the decision to cease operations. Certification will also be required once the fuel is permanently removed from the reactor vessel.

Submittal of these notices will entitle the licensee to a fee reduction and eliminate the obligation to follow certain requirements needed only during operation of the reactor. Within two years of submitting notice of permanent cessation of operations, the licensee is required to submit a Post-Shutdown Decommissioning Activities Report (PSDAR) to the NRC. The PSDAR describes the planned decommissioning activities, the associated sequence and schedule, and an estimate of expected costs. Prior to completing decommissioning, the licensee is required to submit an application to the NRC to terminate the license, which will include a license termination plan (LTP).

In 2011, the NRC issued regulations to improve decommissioning planning and thereby reduce the likelihood that any current operating facility will become a legacy site.[7] The regulations require licensees to report additional details in

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section1, Page 5 of 10 TLG Services, LLC their decommissioning cost estimate including a decommissioning estimate for the ISFSI. This estimate is provided in Appendix G.

1.3.1 High-Level Radioactive Waste Management Congress passed the Nuclear Waste Policy Act[8] (NWPA) in 1982, assigning the federal governments long-standing responsibility for disposal of the spent nuclear fuel created by the commercial nuclear generating plants to the U.S. Department of Energy (DOE). The DOE was to begin accepting spent fuel by January 31, 1998; however, to date no progress in the removal of spent fuel from commercial generating sites has been made.

Today, the country is at an impasse on high-level waste disposal, even with the License Application for a geologic repository submitted by the DOE to the NRC in 2008. The Obama administration has cut the budget for the repository program while promising to conduct a comprehensive review of policies for managing the back end of the nuclear fuel cycle and make recommendations for a new plan. Towards this goal, the Obama administration appointed a Blue Ribbon Commission on Americas Nuclear Future (Blue Ribbon Commission) to make recommendations for a new plan for nuclear waste disposal. The Blue Ribbon Commissions charter includes a requirement that it consider

[o]ptions for safe storage of used nuclear fuel while final disposition pathways are selected and deployed.[9]

On January 26, 2012, the Blue Ribbon Commission issued its Report to the Secretary of Energy containing a number of recommendations on nuclear waste disposal. Two of the recommendations that may impact decommissioning planning are:

[T]he United States [should] establish a program that leads to the timely development of one or more consolidated storage facilities

[T]he United States should undertake an integrated nuclear waste management program that leads to the timely development of one or more permanent deep geological facilities for the safe disposal of spent fuel and high-level nuclear waste.[10]

In January 2013, the DOE issued the Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste, in response to the recommendations made by the Blue Ribbon Commission

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section1, Page 6 of 10 TLG Services, LLC and as a framework for moving toward a sustainable program to deploy an integrated system capable of transporting, storing, and disposing of used nuclear fuel...[11]

With the appropriate authorizations from Congress, the Administration currently plans to implement a program over the next 10 years that:

Sites, designs and licenses, constructs and begins operations of a pilot interim storage facility by 2021 with an initial focus on accepting used nuclear fuel from shut-down reactor sites; Advances toward the siting and licensing of a larger interim storage facility to be available by 2025 that will have sufficient capacity to provide flexibility in the waste management system and allows for acceptance of enough used nuclear fuel to reduce expected government liabilities; and Makes demonstrable progress on the siting and characterization of repository sites to facilitate the availability of a geologic repository by 2048.

The NRCs review of DOEs license application to construct a geologic repository at Yucca Mountain was suspended in 2011 when the Obama administration significantly reduced the budget for completing that work.

However, the US Court of Appeals for the District of Columbia Circuit issued a writ of mandamus (in August 2013)[12] ordering NRC to comply with federal law and resume its review of DOE's Yucca Mountain repository license application, to the extent allowed by previously appropriated funding for the review. That review is now complete with the publication of the five-volume safety evaluation report. A supplement to DOEs environmental impact statement and adjudicatory hearing on the contentions filed by interested parties must be completed before a licensing decision can be made. Although the DOE proposed it would start fuel acceptance in 2025, no progress has been made in the repository program since DOEs 2013 strategy was issued except for the completion of the Yucca Mountain safety evaluation report.

Holtec International submitted a license application to the NRC on March 30, 2017 for a consolidated interim spent fuel storage facility in southeast New Mexico called HI-STORE CISF (Consolidated Interim Storage Facility) under the provisions of 10 CFR Part 72. In May 2023, the NRC issued a license to Holtec to construct and operate a facility to receive, possess, store, and transfer spent nuclear fuel at the HI-STORE CISF.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section1, Page 7 of 10 TLG Services, LLC Waste Control Specialists (WCS) submitted an application to the NRC on April 28, 2016, to construct and operate a Consolidated Interim Storage Facility (CISF) at its West Texas facility. On April 18, 2017, WCS requested that the NRC temporarily suspend all safety and environmental review activities, as well as public participation activities associated with WCSs license application. In March 2018, WCS and Orano USA, announced their intent to form a joint venture to license the facility. The joint venture, named Interim Storage Partners (ISP),

requested that the NRC resume its review of the original CISF license application. Subsequently, in September, 2021, NRC issued a license to ISP for its WCS CISF to construct and operate the facility for spent nuclear fuel and Greater than Class C waste (GTCC) storage. However, the facility is not yet operational.

Completion of the decommissioning process is dependent upon the DOEs ability to remove spent fuel from the site in a timely manner. In June 2011, Ameren Services and the DOE reached an agreement on a settlement. The terms include payment to Ameren Services for spent fuel storage and related costs through 2010, and thereafter, annual payment of such costs after they are incurred.

It is generally necessary that spent fuel be cooled and stored for a minimum period at the generating site prior to transfer. As such, the NRC requires that licensees establish a program to manage and provide funding for the management of all irradiated fuel at the reactor site until title of the fuel is transferred to the DOE, pursuant to 10 CFR Part 50.54(bb).[13] The post-shutdown costs incurred to satisfy this requirement include the isolation and continued operation of the spent fuel pool and the ISFSI during the five and one-half years following the cessation of plant operations.

At shutdown, the spent fuel pool is expected to contain freshly discharged assemblies (from the most recent refueling cycles) as well as the final reactor core. During the next five and one-half years, the assemblies are packaged into Transportation, Aging, and Disposal canisters (TADs) for transfer to the DOE. It is assumed that this period provides the necessary cooling for the final core to meet the transportation system requirements for decay heat.

Costs are included within the decommissioning estimates for offloading the pool. These costs include the loading of DOE-provided TADs and the associated campaign costs to load the canisters into the DOE-provided transport vehicle.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section1, Page 8 of 10 TLG Services, LLC Removal of the fuel from the ISFSI is expected to be fully reimbursable and therefore not addressed in this study. However, the eventual decommissioning of the ISFSI is included.

The estimates described in this analysis were developed with the assumption that the DOE would give priority to removing spent fuel from shutdown sites. The estimates further assume that the spent fuel would be removed from the Callaway site within five and one-half years of the cessation of plant operations (i.e., five and one-half years would provide sufficient cooling time for the spent fuel to meet DOE transportation requirements).

1.3.2 Low-Level Radioactive Waste Disposal The contaminated and activated material generated in the decontamination and dismantling of a commercial nuclear reactor is classified as low-level (radioactive) waste, although not all of the material is suitable for shallow-land disposal. With the passage of the Low-Level Radioactive Waste Policy Act in 1980,[14] and its Amendments of 1985,[15]

the states became ultimately responsible for the disposition of low-level radioactive waste generated within their own borders.

With the exception of Texas, no new compact facilities have been successfully sited, licensed, and constructed. The Texas Compact disposal facility is assumed operational and waste is being accepted from generators within the Compact by the operator, Waste Control Specialists (WCS). The facility, located in Andrews, Texas, is also assumed able to accept limited quantities of non-Compact waste.

Disposition of the various waste streams produced by the decommissioning process considered all options and services currently available to Ameren Services. The majority of the low-level radioactive waste designated for controlled disposal (Class A[16] ) can be sent to EnergySolutions facility in Clive, Utah. Therefore, disposal costs for Class A waste were based upon Ameren Services agreement with EnergySolutions. This facility is not licensed to receive the higher activity portion (Classes B and C) of the decommissioning waste stream.

The WCS facility is able to receive the Class B and C waste. As such, for this analysis, Class B and C waste was assumed to be shipped to the WCS facility for disposal. Disposal costs were based upon Ameren Services current agreement with WCS.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section1, Page 9 of 10 TLG Services, LLC The dismantling of the components residing closest to the reactor core generates radioactive waste that may be considered unsuitable for shallow-land disposal (i.e., low-level radioactive waste with concentrations of radionuclides that exceed the limits established by the NRC for Class C radioactive waste (GTCC)). The Low-Level Radioactive Waste Policy Amendments Act of 1985 assigned the federal government the responsibility for the disposal of this material. The Act also stated that the beneficiaries of the activities resulting in the generation of such radioactive waste bear all reasonable costs of disposing of such waste.

The DOE issued its Final Environmental Impact Statement for the disposal of GTCC on January 2016.[17] The study evaluated the potential environmental impacts associated with constructing and operating a new facility or using an existing facility, disposal methods, and locations. DOE is awaiting congressional action on the report and its recommendations.

At this time, the federal government has not identified a specific cost for disposing of GTCC or a schedule for acceptance.

For purposes of this analysis only, the GTCC radioactive waste is assumed to be packaged and disposed of in a similar manner as high-level waste and at a cost equivalent to that envisioned for the spent fuel. The GTCC is packaged in the same canisters used for spent fuel and shipped to a DOE facility.

A significant portion of the waste material generated during decommissioning may only be potentially contaminated by radioactive materials. This material can be analyzed on site or shipped off site to licensed facilities for further analysis, for processing and/or for conditioning/recovery. Reduction in the volume of low-level radioactive waste requiring disposal in a licensed low-level radioactive waste disposal facility can be accomplished through a variety of methods, including analyses and surveys or decontamination to eliminate the portion of waste that does not require disposal as radioactive waste, compaction, incineration or metal melt. The estimates for the base case scenarios reflect the savings from waste recovery/volume reduction.

1.3.3 Radiological Criteria for License Termination In 1997, the NRC published Subpart E, Radiological Criteria for License Termination,[18] amending 10 CFR Part 20. This subpart provides radiological criteria for releasing a facility for unrestricted use. The regulation states that the site can be released for unrestricted use if radioactivity levels are such that the average member of a critical group

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section1, Page 10 of 10 TLG Services, LLC would not receive a Total Effective Dose Equivalent (TEDE) in excess of 25 millirem per year, and provided that residual radioactivity has been reduced to levels that are As Low As Reasonably Achievable (ALARA).

The decommissioning estimates assume that the Callaway site will be remediated to a residual level consistent with the NRC-prescribed level.

It should be noted that the NRC and the Environmental Protection Agency (EPA) differ on the amount of residual radioactivity considered acceptable in site remediation. The EPA has two limits that apply to radioactive materials. An EPA limit of 15 millirem per year is derived from criteria established by the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA or Superfund).[19] An additional and separate limit of 4 millirem per year, as defined in 40 CFR

§141.16, is applied to drinking water.[20]

On October 9, 2002, the NRC signed an agreement with the EPA on the radiological decommissioning and decontamination of NRC-licensed sites.

The Memorandum of Understanding (MOU)[21] provides that EPA will defer exercise of authority under CERCLA for the majority of facilities decommissioned under NRC authority. The MOU also includes provisions for NRC and EPA consultation for certain sites when, at the time of license termination, (1) groundwater contamination exceeds EPA-permitted levels; (2) NRC contemplates restricted release of the site; and/or (3) residual radioactive soil concentrations exceed levels defined in the MOU.

The MOU does not impose any new requirements on NRC licensees and should reduce the involvement of the EPA with NRC licensees who are decommissioning. Most sites are expected to meet the NRC criteria for unrestricted use, and the NRC believes that only a few sites will have groundwater or soil contamination in excess of the levels specified in the MOU that trigger consultation with the EPA. However, if there are other hazardous materials on the site, the EPA may be involved in the cleanup.

As such, the possibility of dual regulation remains for certain licensees.

The present study does not include any costs for this occurrence.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 2, Page 1 of 12 TLG Services, LLC

2. DECOMMISSIONING ALTERNATIVES Two decommissioning alternatives, DECON and SAFSTOR, were evaluated for the Callaway Energy Center. Although the alternatives differ with respect to technique, process, cost, and schedule, they attain the same result: the ultimate release of the site for unrestricted use. The scenarios selected are representative of alternatives currently available to the owner and are defined as follows:
1. The first scenario assumes that the nuclear unit is promptly decommissioned (DECON alternative) upon the expiration of the current operating license in 2044. Following the permanent cessation of operations, and over the first five and one-half years, the spent fuel is transferred directly from the wet storage pool to the DOE (the fuel stored on the ISFSI is also removed from the site during this time period). Concurrently, the majority of the plant components, including the nuclear NSSS components, are removed. Once the spent fuel stored in the fuel pool has been transferred off-site, the remaining portions of the power block are decommissioned and the surrounding site remediated. Following the termination of the operating license, all remaining site structures are dismantled.
2. In the second scenario, the nuclear unit is placed into safe storage (SAFSTOR alternative) upon the expiration of the current operating license in 2044. As with the first scenario, the spent fuel is removed from the site (transferred to the DOE) during the first five and one-half years following the permanent cessation of operations. The facility is then placed into safe storage (with non-essential systems de-energized and buildings secured).

The start of decontamination and dismantling activities is deferred to the maximum extent (approximately 50 years from the cessation of operations) such that the license is terminated within the required 60-year period following permanent cessation of operations.

The following sections describe the basic activities associated with each alternative.

Although detailed procedures for each activity identified are not provided, and the actual sequence of work may vary, the activity descriptions provide a basis not only for estimating but also for the expected scope of work, i.e., engineering and planning at the time of decommissioning.

In addition to the two decommissioning alternatives, two disposal options were assessed: recycling and direct disposal. Recycling is presented as the base option and considers the off-site processing of plant equipment and commodities with low levels of radiological contamination and/or material suspected to be contaminated for

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 2, Page 2 of 12 TLG Services, LLC volume reduction prior to disposal. The direct disposal option assumes that all contaminated and suspect material is packaged at the site for disposal at a regulated disposal facility. The scenarios are summarized as follows.

Alternative Low-Level Radioactive Waste Options Cost Summaries and/or Detailed Estimates DECON Recycling Sections 3, 6, Appendix C Direct Disposal Appendix E SAFSTOR Recycling Sections 3, 6, Appendix D Direct Disposal Appendix F The conceptual approach that the NRC has described in its regulations divides decommissioning into three phases. The initial phase commences with the effective date of permanent cessation of operations and involves the transition of both plant and licensee from reactor operations (i.e., power production) to facility de-activation and closure. During the first phase, notification is to be provided to the NRC certifying the permanent cessation of operations and the removal of fuel from the reactor vessel. The licensee is then prohibited from reactor operation.

The second phase encompasses activities during the storage period or during major decommissioning activities, or a combination of the two. The third phase pertains to the activities involved in license termination. The decommissioning estimates developed for Callaway are also divided into phases or periods; however, demarcation of the phases is based upon major milestones within the project or significant changes in the projected expenditures.

2.1 DECON The DECON alternative, as defined by the NRC, is "the alternative in which the equipment, structures, and portions of a facility and site containing radioactive contaminants are removed or decontaminated to a level that permits the property to be released for unrestricted use shortly after cessation of operations."

This study does not address the cost to dispose of the spent fuel residing at the site; such costs are funded through a surcharge on electrical generation. The study also assumes that the costs incurred with the removal of the spent fuel from the ISFSI are fully reimbursable, and are also not included.

2.1.1 Period 1 - Preparations In anticipation of the cessation of plant operations, detailed preparations are undertaken to provide a smooth transition from plant operations to site decommissioning. Through implementation of a staffing transition

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 2, Page 3 of 12 TLG Services, LLC plan, the organization required to manage the intended decommissioning activities is assembled from available plant staff and outside resources.

Preparations include the planning for permanent defueling of the reactor, revision of technical specifications applicable to the operating conditions and requirements, a characterization of the facility and major components, and the development of the PSDAR.

Engineering and Planning The PSDAR, required prior to or within two years of permanent cessation of operations, provides a description of the licensees planned decommissioning activities, a timetable, and the associated financial requirements of the intended decommissioning program. Upon receipt of the PSDAR, the NRC will make the document available to the public for comment in a local hearing to be held in the vicinity of the reactor site.

Ninety days following submittal and NRC receipt of the PSDAR, the licensee may begin to perform major decommissioning activities under a modified 10 CFR §50.59 procedure, i.e., without specific NRC approval.

Major activities are defined as any activity that results in permanent removal of major radioactive components, permanently modifies the structure of the containment, or results in dismantling components (for shipment) containing GTCC, as defined by 10 CFR §61. Major components are further defined as comprising the reactor vessel and internals, large bore reactor coolant system piping, and other large components that are radioactive. The NRC includes the following additional criteria for use of the §50.59 process in decommissioning. The proposed activity must not:

foreclose release of the site for possible unrestricted use, significantly increase decommissioning costs, cause any significant environmental impact, or violate the terms of the licensees existing license.

Existing operational technical specifications are reviewed and modified to reflect plant conditions and the safety concerns associated with permanent cessation of operations. The environmental impact associated with the planned decommissioning activities is also considered. Typically, a licensee will not be allowed to proceed if the consequences of a particular decommissioning activity are greater than that bounded by previously evaluated environmental assessments or impact statements. In this instance, the licensee would have to submit a license amendment for the specific activity and update the environmental report.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 2, Page 4 of 12 TLG Services, LLC The decommissioning program outlined in the PSDAR will be designed to accomplish the required tasks within the ALARA guidelines (as defined in 10 CFR §20) for protection of personnel from exposure to radiation hazards. It will also address the continued protection of the health and safety of the public and the environment during the dismantling activity.

Consequently, with the development of the

PSDAR, activity specifications, cost-benefit and safety analyses, work packages and procedures, would be assembled to support the proposed decontamination and dismantling activities.

Site Preparations Following final plant shutdown, and in preparation for actual decommissioning activities, the following activities are initiated:

Characterization of the site and surrounding environs. This includes radiation surveys of work areas, major components (including the reactor vessel and its internals), internal piping, and primary shield cores.

Isolation of the spent fuel storage pool and fuel handling systems, such that decommissioning operations can commence on the balance of the plant. The pool will remain operational for approximately five and one-half years following the cessation of operations before the inventory resident at shutdown can be transferred to the ISFSI.

Specification of transport and disposal requirements for activated materials and/or hazardous materials, including shielding and waste stabilization.

Development of procedures for occupational exposure control, control and release of liquid and gaseous effluent, processing of radwaste (including dry-active waste, resins, filter media, metallic and non-metallic components generated in decommissioning), site security and emergency programs, and industrial safety.

2.1.2 Period 2 - Decommissioning Operations This period includes the physical decommissioning activities associated with the removal and disposal of contaminated and activated components and structures, including the successful termination of the 10 CFR §50 operating license. Significant decommissioning activities in this phase include:

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 2, Page 5 of 12 TLG Services, LLC Construction of temporary facilities and/or modification of existing facilities to support dismantling activities. This may include a centralized processing area to facilitate equipment removal and component preparations for off-site disposal.

Reconfiguration and modification of site structures and facilities as needed to support decommissioning operations. This may include the upgrading of roads (on-and off-site) to facilitate hauling and transport.

Modifications may be required to the containment structure to facilitate access of large/heavy equipment. Modifications may also be required to the refueling area of the reactor building to support the segmentation of the reactor vessel internals and component extraction.

Design and fabrication of temporary and permanent shielding to support removal and transportation activities, construction of contamination control envelopes, and the procurement of specialty tooling.

Procurement (lease or purchase) of shipping canisters, cask liners, and industrial packages for the disposition of low-level radioactive waste.

Decontamination of components and piping systems as required to control (minimize) worker exposure.

Removal of piping and components no longer essential to support decommissioning operations.

Removal of control rod drive housings and the head service structure from the reactor vessel head. Segmentation of the vessel closure head.

Removal and segmentation of the upper internals assemblies.

Segmentation will maximize the loading of the shielded transport casks, i.e., by weight and activity. The operations are conducted under water using remotely operated tooling and contamination controls.

Disassembly and segmentation of the remaining reactor internals, including the core shroud and lower core support assembly. Some material is expected to exceed Class C disposal requirements. As such, the segments will be packaged in modified fuel storage canisters for geologic disposal.

Segmentation of the reactor vessel. A shielded platform is installed for segmentation as cutting operations are performed in-air using remotely operated equipment within a contamination control envelope. The water level is maintained just below the cut to minimize the working area dose rates. Segments are transferred in-air to containers that are stored under water, for example, in an isolated area of the refueling canal.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 2, Page 6 of 12 TLG Services, LLC Removal of the activated portions of the concrete biological shield and accessible contaminated concrete surfaces. If dictated by the steam generator and pressurizer removal scenarios, those portions of the associated cubicles necessary for access and component extraction are removed.

Removal of the steam generators and pressurizer for material recovery and controlled disposal. The steam generators will be moved to an on-site processing center, the steam domes removed and the internal components segregated for recycling. The lower shell and tube bundle will be packaged for direct disposal. These components can serve as their own burial containers provided that all penetrations are properly sealed and the internal contaminants are stabilized, e.g., with grout.

Steel shielding will be added, as necessary, to those external areas of the package to meet transportation limits and regulations. The pressurizer is disposed of intact.

At least two years prior to the anticipated date of license termination, an LTP is required. Submitted as a supplement to the Final Safety Analysis Report or its equivalent, the plan must include: a site characterization, description of the remaining dismantling activities, plans for site remediation, procedures for the final radiation survey, designation of the end use of the site, an updated cost estimate to complete the decommissioning, and any associated environmental concerns. The NRC will notice the receipt of the plan, make the plan available for public comment, and schedule a local hearing. LTP approval will be subject to any conditions and limitations as deemed appropriate by the Commission.

The licensee may then commence with the final remediation of site facilities and services, including:

Removal of remaining plant systems and associated components as they become nonessential to the decommissioning program or worker health and safety (e.g., waste collection and treatment systems, electrical power and ventilation systems).

Removal of the steel liners from refueling canal, disposing of the activated and contaminated sections as radioactive waste. Removal of any activated/ contaminated concrete.

Surveys of the decontaminated areas of the containment structure.

Remediation and removal of the contaminated equipment and material from the fuel building and any other contaminated facility.

Radiation and contamination controls will be utilized until residual levels indicate that the structures and equipment can be released for

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 2, Page 7 of 12 TLG Services, LLC unrestricted access and conventional demolition. This activity may necessitate the dismantling and disposition of most of the systems and components (both clean and contaminated) located within these buildings. This activity facilitates surface decontamination and subsequent verification surveys required prior to obtaining release for demolition.

Routing of material removed in the decontamination and dismantling to a central processing area. Material certified to be free of contamination is released for unrestricted disposition, e.g., as scrap, recycle, or general disposal. Contaminated material is characterized and segregated for additional off-site processing (disassembly, chemical cleaning, volume reduction, and waste treatment), and/or packaged for controlled disposal at a low-level radioactive waste disposal facility.

Incorporated into the LTP is the Final Survey Plan. This plan identifies the radiological surveys to be performed once the decontamination activities are completed and is developed using the guidance provided in the Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM).[22] This document incorporates the statistical approaches to survey design and data interpretation used by the EPA. It also identifies state-of-the-art, commercially available instrumentation and procedures for conducting radiological surveys. Use of this guidance ensures that the surveys are conducted in a manner that provides a high degree of confidence that applicable NRC criteria are satisfied. Once the survey is complete, the results are provided to the NRC in a format that can be verified. The NRC then reviews and evaluates the information, performs an independent confirmation of radiological site conditions, and makes a determination on the requested change to the operating license (that would release the property for unrestricted use).

The NRC will amend the operating licenses if it determines that site remediation has been performed in accordance with the LTP, and that the terminal radiation survey and associated documentation demonstrate that the property is suitable for release.

2.1.3 Period 3 - Site Restoration Following completion of decommissioning operations, site restoration activities will begin. Efficient removal of the contaminated materials and verification that residual radionuclide concentrations are below the NRC limits will result in substantial damage to many of the structures.

Although performed in a controlled, safe manner, blasting, coring,

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 2, Page 8 of 12 TLG Services, LLC drilling, scarification (surface removal), and the other decontamination activities will substantially degrade power block structures including the reactor, auxiliary, fuel, and radwaste buildings. Under certain circumstances, verifying that subsurface radionuclide concentrations meet NRC site release requirements will require removal of grade slabs and lower floors, potentially weakening footings and structural supports.

This removal activity will be necessary for those facilities and plant areas where historical records, when available, indicate the potential for radionuclides having been present in the soil, where system failures have been recorded, or where it is required to confirm that subsurface process and drain lines were not breached over the operating life of the station.

It is not currently anticipated that these structures would be repaired and preserved after the radiological contamination is removed. The cost to dismantle site structures, once remediation is complete, with a work force already mobilized on site is more efficient than if the process is deferred.

This cost study presumes that non-essential structures and site facilities are dismantled as a continuation of the decommissioning activity.

Foundations and exterior walls are removed to a nominal depth of three feet below grade. The three-foot depth allows for the placement of gravel for drainage, as well as topsoil, so that vegetation can be established for erosion control. Site areas affected by the dismantling activities are restored and the plant area graded as required to prevent ponding and inhibit the refloating of subsurface materials.

Non-contaminated concrete rubble produced by demolition activities is processed to remove reinforcing steel and miscellaneous embedments.

The processed material is then used on site to backfill foundation voids.

Excess non-contaminated materials are trucked to an off-site area for disposal as construction debris.

2.2 SAFSTOR The NRC defines SAFSTOR as "the alternative in which the nuclear facility is placed and maintained in a condition that allows the nuclear facility to be safely stored and subsequently decontaminated (deferred decontamination) to levels that permit release for unrestricted use." The facility is left intact (during the dormancy period), with structures maintained in a sound condition. Systems that are not required to support the spent fuel pool or site surveillance and security are drained, de-energized, and secured. Minimal cleaning/removal of loose contamination and/or fixation and sealing of remaining contamination is

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 2, Page 9 of 12 TLG Services, LLC performed. Access to contaminated areas is secured to provide controlled access for inspection and maintenance.

The engineering and planning requirements are similar to those for the DECON alternative, although a shorter period is expected for these activities due to the more limited work scope. Site preparations are also similar to those for the DECON alternative. However, with the exception of the required radiation surveys and site characterizations, the mobilization and preparation of site facilities is less extensive.

2.2.1 Period 1 - Preparations Preparations for long-term storage include the planning for permanent defueling of the reactor, revision of technical specifications appropriate to the operating conditions and requirements, a characterization of the facility and major components, and the development of the PSDAR.

The process of placing the plant in safe-storage includes, but is not limited to, the following activities:

Isolation of the spent fuel storage services and fuel handling systems so that safe-storage operations may commence on the balance of the plant. This activity may be carried out by plant personnel in accordance with existing operating technical specifications. Activities are scheduled around the fuel handling systems to the greatest extent possible.

Transfer of all spent fuel from the storage pool and the ISFSI to the DOE by the end of the minimum required cooling period.

Draining and de-energizing of the non-contaminated systems not required to support continued site operations or maintenance.

Disposing of contaminated filter elements and resin beds not required for processing wastes from layup activities for future operations.

Draining of the reactor vessel, with the internals left in place and the vessel head secured.

Draining and de-energizing non-essential, contaminated systems with decontamination as required for future maintenance and inspection.

Preparing lighting and alarm systems whose continued use is required; de-energizing portions of fire protection, electric power, and HVAC systems whose continued use is not required.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 2, Page 10 of 12 TLG Services, LLC Cleaning of the loose surface contamination from building access pathways.

Performing an interim radiation survey of plant, posting warning signs where appropriate.

Erecting physical barriers and/or securing all access to radioactive or contaminated areas, except as required for inspection and maintenance.

Installing security and surveillance monitoring equipment and relocating security fence around secured structures, as required.

2.2.2 Period 2 - Dormancy The second phase identified by the NRC in its rule addresses licensed activities during a storage period and is applicable to the dormancy phases of the deferred decommissioning alternative. Dormancy activities include a 24-hour security force, preventive and corrective maintenance on security systems, area lighting, general building maintenance, heating and ventilation of buildings, routine radiological inspections of contaminated structures, maintenance of structural integrity, and a site environmental and radiation monitoring program. Resident maintenance personnel perform equipment maintenance, inspection activities, routine services to maintain safe conditions, adequate lighting, heating, and ventilation, and periodic preventive maintenance on essential site services.

An environmental surveillance program is carried out during the dormancy period to ensure that releases of radioactive material to the environment are prevented and/or detected and controlled. Appropriate emergency procedures are established and initiated for potential releases that exceed prescribed limits. The environmental surveillance program constitutes an abbreviated version of the program in effect during normal plant operations.

Security during the dormancy period is conducted primarily to prevent unauthorized entry and to protect the public from the consequences of its own actions. The security fence, sensors, alarms, and other surveillance equipment provide security. Fire and radiation alarms are also monitored and maintained.

Consistent with the DECON scenario, the spent fuel storage pool is emptied within five and one-half years of the cessation of operations. The

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 2, Page 11 of 12 TLG Services, LLC pool is secured for storage and decommissioned along with the power block structures in Period 4.

After a period of storage (such that license termination is accomplished within 60 years of final shutdown), it is required that the licensee submit an application to terminate the license, along with an LTP (described in Section 2.1.2), thereby initiating the third phase.

2.2.3 Periods 3 and 4 - Delayed Decommissioning Prior to the commencement of decommissioning operations, preparations are undertaken to reactivate site services and prepare for decommissioning. Preparations include engineering and planning, a detailed site characterization, and the assembly of a decommissioning management organization. Final planning for activities and the writing of activity specifications and detailed procedures are also initiated at this time.

Much of the work in developing a termination plan is relevant to the development of the detailed engineering plans and procedures. The activities associated with this phase and the follow-on decontamination and dismantling processes are detailed in Sections 2.1.1 and 2.1.2. The primary difference between the sequences anticipated for the DECON and this deferred scenario is the absence, in the latter, of any constraint on the availability of the fuel storage facilities for decommissioning.

Variations in the length of the dormancy period are expected to have little effect upon the quantities of radioactive wastes generated from system and structure removal operations. Given the levels of radioactivity and spectrum of radionuclides expected from sixty years of plant operation, no plant process system identified as being contaminated upon final shutdown will become releasable due to the decay period alone, i.e., there is no significant reduction in the waste generated from the decommissioning activities. However, due to the lower activity levels, a greater percentage of the waste volume can be designated for off-site processing and recovery.

The delay in decommissioning also yields lower working area radiation levels. As such, the estimate for this delayed scenario incorporates reduced ALARA controls for the SAFSTOR's lower occupational exposure potential.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 2, Page 12 of 12 TLG Services, LLC Although the initial radiation levels due to 60Co will decrease during the dormancy period, the internal components of the reactor vessel will still exhibit sufficiently high radiation dose rates to require remote sectioning under water due to the presence of long-lived radionuclides such as 94Nb, 59Ni, and 63Ni. Therefore, the dismantling procedures described for the DECON alternative would still be employed during this scenario. Portions of the biological shield will still be radioactive due to the presence of activated trace elements with long half-lives (152Eu and 154Eu).

Decontamination will require controlled removal and disposal. It is assumed that radioactive corrosion products on inner surfaces of piping and components will not have decayed to levels that will permit unrestricted use or allow conventional removal. These systems and components will be surveyed as they are removed and disposed of in accordance with the existing radioactive release criteria.

2.2.4 Period 5 - Site Restoration Following completion of decommissioning operations, site-restoration activities can begin.

Dismantling, as a

continuation of the decommissioning process, is clearly the most appropriate and cost-effective option, as described in Section 2.1.3. The basis for the dismantling cost in this scenario is consistent with that described for DECON, presuming the removal of structures and site facilities to a nominal depth of three feet below grade and the limited restoration of the site.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 1 of 34 TLG Services, LLC

3. COST ESTIMATE The cost estimates prepared for decommissioning Callaway consider the unique features of the site, including the NSSS, power generation systems, support services, site buildings, and ancillary facilities. The basis of the estimates, including the sources of information relied upon, the estimating methodology employed, site-specific considerations, and other pertinent assumptions, is described in this section.

3.1 BASIS OF ESTIMATE The current estimates were developed using the site-specific, technical information relied upon in the decommissioning analysis prepared in 2020. This information was reviewed for the current analysis and updated as deemed appropriate. The site-specific considerations and assumptions used in the previous evaluation were also revisited. Modifications were incorporated where new information was available or experience from ongoing decommissioning programs provided viable alternatives or improved processes.

3.2 METHODOLOGY The methodology used to develop the estimates follows the basic approach originally presented in the AIF/NESP-036 study report, "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates,"[23] and the DOE "Decommissioning Handbook."[24] These documents present a unit factor method for estimating decommissioning activity costs, which simplifies the estimating calculations. Unit factors for concrete removal

($/cubic yard), steel removal ($/ton), and cutting costs ($/inch) are developed using local labor rates. The activity-dependent costs are estimated with the item quantities (cubic yards and tons), developed from plant drawings and inventory documents. Removal rates and material costs for the conventional disposition of components and structures rely upon information available in the industry publication, "Building Construction Cost with RSMeans Data," by Gordian.[25]

The unit factor method provides a demonstrable basis for establishing reliable cost estimates. The detail provided in the unit factors, including activity duration, labor costs (by craft), and equipment and consumable costs, ensures that essential elements have not been omitted. Appendix A presents the detailed development of a typical unit factor. Appendix B provides the values contained within one set of factors developed for this analysis.

Regulatory Guide 1.184 [26] Revision 1, issued in October 2013, describes the methods and procedures that are acceptable to the NRC staff for implementing

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 2 of 34 TLG Services, LLC the requirements that relate to the initial activities and the major phases of the decommissioning process. The costs and schedules presented in this analysis follow the general guidance and sequence in the regulations. The format and content of the estimates is also consistent with the recommendations of Regulatory Guide 1.202,[27] issued February 2005.

This analysis reflects lessons learned from TLGs involvement in the Shippingport Station Decommissioning Project, completed in 1989, as well as the decommissioning of the Cintichem reactor, hot cells and associated facilities, completed in 1997. In addition, the planning and engineering for the Rancho Seco, Trojan, Yankee Rowe, Big Rock Point, Maine Yankee, Humboldt Bay-3, Oyster Creek, Connecticut Yankee, Crystal River, Vermont Yankee, Fort Calhoun and Pilgrim, and Indian Point nuclear units have provided additional insight into the process, the regulatory aspects, and the technical challenges of decommissioning commercial nuclear units.

Work Difficulty Factors TLG has historically applied work difficulty adjustment factors (WDFs) to account for the inefficiencies in working in a power plant environment. WDFs are assigned to each unique set of unit factors, commensurate with the inefficiencies associated with working in confined, hazardous environments. The ranges used for the WDFs are as follows:

Access Factor 10% to 20%

Respiratory Protection Factor 10% to 50%

Radiation/ALARA Factor 10% to 37%

Protective Clothing Factor 10% to 30%

Work Break Factor 8.33%

The factors and their associated range of values were developed in conjunction with the AIF/NESP-036 study. The application of the factors is discussed in more detail in that publication.

Scheduling Program Durations The unit factors, adjusted by the WDFs as described above, are applied against the inventory of materials to be removed in the radiological controlled areas. The resulting person-hours, or crew-hours, are used in the development of the decommissioning program schedule, using resource loading and event sequencing considerations. The scheduling of conventional removal and

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 3 of 34 TLG Services, LLC dismantling activities is based upon productivity information available from the "Building Construction Cost Data" publication.

An activity duration critical path is used to determine the total decommissioning program schedule. The schedule is relied upon in calculating the carrying costs, which include program management, administration, field engineering, equipment rental, and support services such as quality control and security. This systematic approach for assembling decommissioning estimates ensures a high degree of confidence in the reliability of the resulting costs.

3.3 FINANCIAL COMPONENTS OF THE COST MODEL TLGs proprietary decommissioning cost model, DECCER, produces a number of distinct cost elements. These direct expenditures, however, do not comprise the total cost to accomplish the project goal, i.e., license termination and site restoration.

Inherent in any cost estimate that does not rely on historical data is the inability to specify the precise source of costs imposed by factors such as tool breakage, accidents, illnesses, weather delays, and labor stoppages. In the DECCER cost model, contingency fulfills this role. Contingency is added to each line item to account for costs that are difficult or impossible to develop analytically. Such costs are historically inevitable over the duration of a job of this magnitude; therefore, this cost analysis includes funds to cover these types of expenses.

3.3.1 Contingency The activity-and period-dependent costs are combined to develop the total decommissioning cost. A contingency is then applied on a line-item basis, using one or more of the contingency types listed in the AIF/NESP-036 study. "Contingencies" are defined in the American Association of Cost Engineers Project and Cost Engineers' Handbook[28] as "specific provision for unforeseeable elements of cost within the defined project scope; particularly important where previous experience relating estimates and actual costs has shown that unforeseeable events which will increase costs are likely to occur." The cost elements in this analysis are based upon ideal conditions and maximum efficiency; therefore, consistent with industry practice, contingency is included. In the AIF/NESP-036 study, the types of unforeseeable events that are likely to occur in decommissioning are discussed and guidelines are provided for percentage contingency in each category. It should be noted that contingency, as used in this analysis, does not account for price escalation

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 4 of 34 TLG Services, LLC and inflation in the cost of decommissioning over the remaining operating life of the station.

Contingency funds are an integral part of the total cost to complete the decommissioning process. Exclusion of this component puts at risk a successful completion of the intended tasks and, potentially, subsequent related activities. For this study, TLG examined the major activity-related problems (decontamination, segmentation, equipment handling, packaging, transport, and waste disposal) that necessitate a contingency.

Individual activity contingencies ranged from 10% to 75%, depending on the degree of difficulty judged to be appropriate from TLGs actual decommissioning experience. The contingency values used in this study are as follows:

Decontamination 50%

Contaminated Component Removal 25%

Contaminated Component Packaging 10%

Contaminated Component Transport 15%

Low-Level Radioactive Waste Disposal 25%

Low-Level Radioactive Waste Processing 15%

Reactor Segmentation 75%

NSSS Component Removal 25%

Reactor Waste Packaging 25%

Reactor Waste Transport 25%

Reactor Vessel Component Disposal 50%

GTCC Disposal 15%

Staffing 15%

Spent Fuel Management 15%

Non-Radioactive Component Removal 15%

Heavy Equipment and Tooling 15%

Supplies 25%

Engineering 15%

Energy 15%

Insurance and Fees 10%

Characterization and Termination Surveys 30%

Operations and Maintenance Expense 15%

Construction 15%

Property Taxes 10%

ISFSI Decommissioning 25%

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 5 of 34 TLG Services, LLC The contingency values are applied to the appropriate components of the estimates on a line item basis. A composite value is then reported at the end of each detailed estimate (as provided in Appendix C, D, E and F). A contingency of 25% is applied to the subtotal of the ISFSI decommissioning costs, as shown in Appendix G Table G-2 for ISFSI 72.30 decommissioning and license termination activities.

3.3.2 Financial Risk In addition to the routine uncertainties addressed by contingency, another cost element that is sometimes necessary to consider when bounding decommissioning costs relates to uncertainty, or risk. Examples can include changes in work scope, pricing, job performance, and other variations that could conceivably, but not necessarily, occur.

Consideration is sometimes necessary to generate a level of confidence in the estimate, within a range of probabilities. TLG considers these types of costs under the broad term financial risk. Included within the category of financial risk are:

Transition activities and costs: ancillary expenses associated with eliminating 50% to 80% of the site labor force shortly after the cessation of plant operations, added cost for worker separation packages throughout the decommissioning program, national or company-mandated retraining, and retention incentives for key personnel.

Delays in approval of the decommissioning plan due to intervention, public participation in local community meetings, legal challenges, and national and local hearings.

Changes in the project work scope from the baseline estimate, involving the discovery of unexpected levels of contaminants, contamination in places not previously expected, contaminated soil previously undiscovered (either radioactive or hazardous material contamination), variations in plant inventory or configuration not indicated by the as-built drawings.

Regulatory changes, for example, affecting worker health and safety, site release criteria, waste transportation, and disposal.

Policy decisions altering national commitments (e.g., in the ability to accommodate certain waste forms for disposition), or in the timetable for such, for example, the start and rate of acceptance of spent fuel by the DOE.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 6 of 34 TLG Services, LLC Pricing changes for basic inputs such as labor, energy, materials, and disposal. Items subject to widespread price competition (such as materials) may not show significant variation; however, others such as waste disposal could exhibit large pricing uncertainties, particularly in markets where limited access to services is available.

However this cost study does not add any additional costs to the estimate for financial risk, since there is insufficient historical data from which to project future liabilities. Consequently, the areas of uncertainty or risk are revisited periodically and addressed through repeated revisions or updates of the estimates.

3.4 SITE-SPECIFIC CONSIDERATIONS There are a number of site-specific considerations that affect the method for dismantling and removal of equipment from the site and the degree of restoration required. The cost impact of the considerations identified below is included in this cost study.

3.4.1 Spent Fuel Management The cost to dispose the spent fuel generated from plant operations is not reflected within the estimates to decommission Callaway. Ultimate disposition of the spent fuel is within the province of the DOEs Waste Management System, as defined by the Nuclear Waste Policy Act. Any delay in the transfer of spent fuel may increase the on-site management costs. As such, the disposal cost was being financed by a 1 mill/kWhr surcharge on nuclear generated energy delivered to customers, the fee being paid into the DOEs waste fund during operations. The D.C. Circuit ruling on November 19, 2013, ordered the DOE to submit a proposal to Congress to suspend the Nuclear Waste Fund fee until such time as either the Secretary chooses to comply with the Act as it is currently written, or until Congress enacts an alternative waste management plan.

The fee was reduced to 0.0 mill/kWh as of May 16, 2014. The fee is expected to be reinstated in the future.

The NRC requires licensees to establish a program to manage and provide funding for the management of all irradiated fuel at the reactor until title of the fuel is transferred to the Secretary of Energy. This funding requirement is fulfilled through inclusion of certain high-level waste cost elements within the estimates, as described below.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 7 of 34 TLG Services, LLC For estimating purposes, Ameren Services has assumed that all spent fuel will be transferred to the DOE within five and one-half years after shutdown.

This will allow Ameren Services to proceed with decommissioning (or safe-storage) operations in the shortest time possible. A delay in the start of fuel pickup, or a decrease in the spent fuel acceptance rate, will correspondingly prolong the transfer process and result in the fuel remaining at the Callaway site longer.

It is assumed that the five and one-half years provides the necessary cooling period for the final core to meet DOEs transport system requirements for decay heat. Once the pool is emptied, the spent fuel storage and handling facilities are available for decommissioning.

Operation and maintenance costs for the spent fuel pool are included within the estimate as well as the costs to transfer the spent fuel from the pool to the DOE.

Storage Canister Design A vertical underground dry storage system is used as a cost basis. The system consists of Holtec HI-STORM UMAX technology transportable Multi-Purpose Canisters (MPCs) stored within an underground metal and concrete structure, collectively known as Vertical Ventilated Modules (VVMs). A canister capacity of 37 pressurized water reactor fuel assemblies was assumed. All canisters are assumed to be in place at the time of decommissioning.

Canister Loading and Transfer The estimates include the cost for the labor and equipment to load and transfer to the DOE the spent fuel assemblies projected to reside in the pool at the cessation of plant operations. Costs for transfer of spent fuel from the ISFSI to the DOE are not included in this estimate. In addition, any capital cost associated with the dry storage system (including cask purchases) is not included in the estimates.

Operations and Maintenance The estimates include the cost of operating and maintaining the spent fuel pool for approximately five and one half years after the cessation of operations.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 8 of 34 TLG Services, LLC ISFSI Decommissioning In accordance with 10 CFR §72.30, licensees must have a proposed decommissioning plan for the ISFSI site and facilities that includes a cost estimate for the plan. The plan needs to contain sufficient information on the proposed practices and procedures for the decontamination of the ISFSI and for the disposal of residual radioactive materials after the spent fuel has been removed.

For purposes of this study only, the decommissioning cost for the ISFSI was included in the DECON and SAFSTOR estimates.

The decommissioning estimate is based on the conservative premise that a small percentage of the VVMs would contain very low levels of neutron-induced residual radioactivity that would necessitate remediation at the time of decommissioning. As an allowance, 6 of the 48 VVMs are assumed to be affected, i.e., contain residual radioactivity. The allowance quantity is based upon the number of MPCs required for the final core off-load (i.e.,

193 offloaded assemblies, 37 assemblies per MPC) which results in a total of 6 VVMs that contain residual radioactivity.

No contamination or activation of the balance of the ISFSI structures are assumed. It would be expected that this assumption would be confirmed as a result of good radiological practice of surveying potentially impacted areas after each spent fuel transfer campaign. As such, only verification surveys are included for the ISFSI in the decommissioning estimate. The estimate is limited to costs necessary to terminate the ISFSIs NRC license and meet the §20.1402 criteria for unrestricted use.

In accordance with the specific requirements of 10 CFR §72.30 for the ISFSI work scope, the cost estimate for decommissioning the ISFSI reflects: 1) the cost of an independent contractor performing the decommissioning activities; 2) an adequate contingency factor; and 3) the cost of meeting the criteria for unrestricted use.

GTCC The dismantling of the reactor internals is expected to generate radioactive waste considered unsuitable for shallow land disposal (i.e.,

low-level radioactive waste with concentrations of radionuclides that exceed the limits established by the NRC for Class C radioactive waste (GTCC)). The Low-Level Radioactive Waste Policy Amendments Act of 1985 assigned the federal government the responsibility for the disposal of this material. The Act also stated that the beneficiaries of the activities

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 9 of 34 TLG Services, LLC resulting in the generation of such radioactive waste bear all reasonable costs of disposing of such waste. Although the DOE is responsible for disposing of GTCC waste, any costs for that service have not been determined. For purposes of this estimate, the GTCC radioactive waste has been assumed to be packaged in the same canisters used to store spent fuel and disposed of as high-level waste, at a cost equivalent to that envisioned for the spent fuel. The number of canisters required and the packaged volume for GTCC was based upon experience at Maine Yankee (e.g., the payload constraints as identified in the canisters certificate of compliance).

For purposes of this study, GTCC is packaged into five transportable storage containers. It will be disposed of as it is generated during reactor vessel segmentation operations, and shipped to the DOE.

3.4.2 Reactor Vessel and Internal Components The reactor pressure vessel and internal components are segmented for disposal in shielded, reusable transportation casks. Segmentation is performed in the refueling canal, where a turntable and remote cutter are installed. The vessel is segmented in place, using a mast-mounted cutter supported off the lower head and directed from a shielded work platform installed overhead in the reactor cavity.

Transportation cask specifications and transportation regulations dictate the segmentation and packaging methodology.

Intact disposal of reactor vessel shells has been successfully demonstrated at several of the sites currently being decommissioned. Access to navigable waterways has allowed these large packages to be transported to the Barnwell, South Carolina and Hanford, Washington disposal sites with minimal overland travel. Intact disposal of the reactor vessel and internal components can provide savings in cost and worker exposure by eliminating the complex segmentation requirements, isolation of the GTCC material, and transport/storage of the resulting waste packages.

Portland General Electric (PGE) was able to dispose of the Trojan reactor as an intact package (including the internals). However, its location on the Columbia River simplified the transportation analysis since:

the reactor package could be secured to the transport vehicle for the entire journey, i.e., the package was not lifted during transport,

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 10 of 34 TLG Services, LLC there were no man-made or natural terrain features between the plant site and the disposal location that could produce a large drop, and transport speeds were very low, limited by the overland transport vehicle and the river barge.

As a member of the Northwest Compact, PGE had a site available for disposal of the package - the US Ecology facility in Washington State. The characteristics of this arid site proved favorable in demonstrating compliance with land disposal regulations.

It is not known whether this option will be available when Callaway ceases operation. Future viability of this option will depend upon the ultimate location of the disposal site, as well as the disposal site licensees ability to accept highly radioactive packages and effectively isolate them from the environment. Consequently, the study assumes the reactor vessel will require segmentation, as a bounding condition.

3.4.3 Primary System Components In the DECON scenario, the reactor coolant system components are assumed to be decontaminated using chemical agents prior to the start of dismantling operations. This type of decontamination can be expected to have a significant ALARA impact, since in this scenario the removal work is done within the first few years of shutdown. A decontamination factor (average reduction) of 10 is assumed for the process. In the SAFSTOR scenario, radionuclide decay is expected to provide the same benefit and, therefore, a chemical decontamination is not included.

The following discussion deals with the removal and disposition of the steam generators, but the techniques involved are also applicable to other large components, such as heat exchangers, component coolers, and the pressurizer. The steam generators size and weight, as well as their location within the reactor building, will ultimately determine the removal strategy.

A trolley crane is set up for the removal of the generators. It can also be used to move portions of the steam generator cubicle walls and floor slabs from the reactor building to a location where they can be decontaminated and transported to the material handling area. Interferences within the work area, such as grating, piping, and other components are removed to create sufficient laydown space for processing these large components.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 11 of 34 TLG Services, LLC The generators are rigged for removal, disconnected from the surrounding piping and supports, and maneuvered into the open area where they are lowered onto a dolly. Each generator is rotated into the horizontal position for extraction from the containment and placed onto a multi-wheeled vehicle for transport to an on-site processing and storage area.

The generators are disassembled on-site with the steam dome and lightly contaminated subassemblies designated for off-site recycling. The more highly contaminated tube sheet and tube bundle are packaged for direct disposal. The interior volume is filled with low-density cellular concrete for stabilization of the internal contamination.

Reactor coolant piping is cut from the reactor vessel once the water level in the vessel (used for personnel shielding during dismantling and cutting operations in and around the vessel) is dropped below the nozzle zone. The piping is boxed and transported by shielded van. The reactor coolant pumps and motors are lifted out intact, packaged, and transported for processing and/or disposal.

3.4.4 Retired Components The estimate includes the cost to dispose of four retired steam generators expected to be in storage at the site upon the cessation of plant operations.

The components are processed for disposal in the same manner as described for the installed units.

A retired reactor closure head, with service structure, is also included in the decommissioning waste inventory. The component is currently stored in the steam generator storage facility.

3.4.5 Main Turbine and Condenser The main turbine is dismantled using conventional maintenance procedures. The turbine rotors and shafts are removed to a laydown area.

The lower turbine casings are removed from their anchors by controlled demolition. The main condensers are also disassembled and moved to a laydown area. Material is then prepared for transportation to an off-site recycling facility where it is surveyed and designated for either decontamination or volume reduction, conventional disposal, or controlled disposal. Components are packaged and readied for transport in accordance with the intended disposition.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 12 of 34 TLG Services, LLC 3.4.6 Transportation Methods Contaminated piping, components, and structural material other than the highly activated reactor vessel and internal components will qualify as LSA-I, II or III or Surface Contaminated Object, SCO-I or II, as described in Title 49.[29] The contaminated material will be packaged in Industrial Packages (IP-1, IP-2, or IP-3, as defined in subpart 173.411) for transport unless demonstrated to qualify as their own shipping containers. The reactor vessel and internal components are expected to be transported in accordance with Part 71, as Type B. It is conceivable that the reactor, due to its limited specific activity, could qualify as LSA II or III. However, the high radiation levels on the outer surface would require that additional shielding be incorporated within the packaging so as to attenuate the dose to levels acceptable for transport.

Any fuel cladding failure that occurred during the lifetime of the plant is assumed to have released fission products at sufficiently low levels that the buildup of quantities of long-lived isotopes (e.g., 137Cs, 90Sr, or transuranics) has been prevented from reaching levels exceeding those that permit the major reactor components to be shipped under current transportation regulations and disposal requirements.

Transport of the highly activated metal, produced in the segmentation of the reactor vessel and internal components, will be by shielded truck cask.

Cask shipments may exceed 95,000 pounds, including vessel segment(s),

supplementary shielding, cask tie-downs, and tractor-trailer. The maximum level of activity per shipment assumed permissible was based upon the license limits of the available shielded transport casks. The segmentation scheme for the vessel and internal segments is designed to meet these limits.

The transport of large intact components (e.g., large heat exchangers and other oversized components) will be by a combination of truck, rail, and/or multi-wheeled transporter.

Transportation costs for Class A radioactive material requiring controlled disposal are based upon the mileage to the EnergySolutions facility in Clive, Utah. Transportation costs for the higher activity Class B and C radioactive material are based upon the mileage to the WCS facility in Andrews County, Texas. The transportation cost for the GTCC material is assumed to be contained within the disposal cost. Transportation costs for off-site waste processing are based upon the mileage to Oak Ridge,

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 13 of 34 TLG Services, LLC Tennessee. Truck transport costs were developed from published tariffs from Tri-State Motor Transit.[30]

3.4.7 Low-Level Radioactive Waste Disposal To the greatest extent practical, metallic material generated in the decontamination and dismantling processes is processed to reduce the total cost of controlled disposal. Material meeting the regulatory and/or site release criterion, is released as scrap, requiring no further cost consideration. Conditioning (preparing the material to meet the waste acceptance criteria of the disposal site) and recovery of the waste stream is performed off site at a licensed processing center. Any material leaving the site is subject to a survey and release charge, at a minimum.

The mass of radioactive waste generated during the various decommissioning activities at the site is shown on a line-item basis in the appendices and summarized in Section 5. The quantified waste summaries shown in these tables are consistent with 10 CFR Part 61 classifications. Commercially available steel containers are presumed to be used for the disposal of piping, small components, and concrete. Larger components can serve as their own containers, with proper closure of all openings, access ways, and penetrations. The volumes are calculated based on the exterior package dimensions for containerized material or a specific calculation for components serving as their own waste containers.

The more highly activated reactor components will be shipped in reusable, shielded truck casks with disposable liners. In calculating disposal costs, the burial fees are applied against the liner volume, as well as the special handling requirements of the payload. Packaging efficiencies are lower for the highly activated materials (greater than Type A quantity waste),

where high concentrations of gamma-emitting radionuclides limit the capacity of the shipping canisters.

The cost to dispose of the lowest level waste and the majority of the material generated from the decontamination and dismantling activities is based upon the current cost for disposal at EnergySolutions facility in Clive, Utah. Disposal costs for the higher activity waste (Class B and C) were based upon Ameren Services current agreement with WCS for the Andrews County facility.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 14 of 34 TLG Services, LLC 3.4.8 Site Conditions Following Decommissioning The NRC will terminate the site license when it determines that site remediation has been performed in accordance with the license termination plan, and that the terminal radiation survey and associated documentation demonstrate that the facility is suitable for release. The NRCs involvement in the decommissioning process will end at this point.

Local building codes and state environmental regulations will dictate the next step in the decommissioning process, as well as the owners own future plans for the site.

The estimates presented herein include the dismantling of the major structures to three feet below grade level, backfilling and the collapsing of below grade voids, and regrading such that the site upon which the power block and supplemental structures are located is transformed into a grassy plain.

Concrete rubble generated from demolition activities is processed and made available as clean fill for the power block foundations. Additional fill is brought in to cap the power block excavations and to permit seeding for erosion control.

A significant amount of the below grade piping is located around the perimeter of the power block. The estimate includes a cost to excavate this area to an average depth of six feet so as to expose the piping, duct bank, conduit, and any near-surface grounding grid. The overburden is surveyed and stockpiled on site for future use in backfilling the below grade voids.

The existing electrical switchyard and access roads will remain in support of the electrical transmission and distribution system. Site restoration does not include the remediation of the water treatment plants settling basins, if required.

Sludge removed from the sewage treatment plant lagoon was assumed to contain low levels of contamination that would require controlled disposal. As such, 3,600 cubic feet of material from the lagoon was designated for disposition at EnergySolutions facility.

The existing and replacement cooling tower discharge pipes will be left in place and assumed to be flow-filled with suitable material to prevent the pipes from collapsing. The intake line will also be filled.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 15 of 34 TLG Services, LLC The estimates do not assume the remediation of any significant volume of contaminated soil. This assumption may be affected by continued plant operations and/or future regulatory actions, such as the development of site-specific release criteria.

3.5 ASSUMPTIONS The following are the major assumptions made in the development of the estimates for decommissioning the site.

3.5.1 Estimating Basis Decommissioning costs are reported in the year of projected expenditure; however, the values are provided in 2023 dollars. Costs are not inflated, escalated, or discounted over the periods of performance.

The estimates rely upon the physical plant inventory that was the basis for the 2020 analysis. There were no substantive changes made to the plant inventory (that would impact decommissioning).

The study follows the principles of ALARA through the use of work duration adjustment factors. These factors address the impact of activities such as radiological protection instruction, mock-up training, and the use of respiratory protection and protective clothing. The factors lengthen a task's duration, increasing costs and lengthening the overall schedule.

ALARA planning is considered in the costs for engineering and planning, and in the development of activity specifications and detailed procedures.

Changes to worker exposure limits may impact the decommissioning cost and project schedule.

3.5.2 Labor Costs Ameren Services, as the operator, will continue to provide site operations support, including decommissioning program management, licensing, radiological protection, and site security. A Decommissioning Operations Contractor (DOC) will provide the supervisory staff needed to oversee the labor subcontractors, consultants, and specialty contractors needed to perform the work required for the decontamination and dismantling effort. The DOC will also provide the engineering services needed to develop activity specifications, detailed procedures, detailed activation analyses, and support field activities such as structural modifications.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 16 of 34 TLG Services, LLC Personnel costs are based upon average salary information provided by Ameren Services. Overhead costs were also provided by Ameren Services for site and corporate support; they are reduced commensurate with the staffing of the project.

The craft labor required to decontaminate and dismantle the nuclear unit is acquired through standard site contracting practices. The current cost of labor at the site is used as an estimating basis.

Security, while reduced from operating levels, is maintained throughout the decommissioning for access control, material control, and to safeguard the spent fuel.

A profile of the staffing levels for decommissioning, including contractors and craft, is provided in Figures 3.1 and 3.2 for the DECON and SAFSTOR scenarios, respectively. Utility staffing levels will gradually decrease after completing the removal of physical systems. Staffing levels and management support will vary based upon the amount and type of decommissioning work. Craft workforce levels decrease after systems removal and structures decontamination. Craft levels continue to decrease during the site restoration period as the work associated with structures demolition completes.

3.5.3 Design Conditions Any fuel cladding failure that occurred during the lifetime of the plant is assumed to have released fission products at sufficiently low levels that the buildup of quantities of long-lived isotopes (e.g., 137Cs, 90Sr, or transuranics) has been prevented from reaching levels exceeding those that permit the major NSSS components to be shipped under current transportation regulations and disposal requirements.

The curie contents of the vessel and internals at final shutdown are derived from those listed in NUREG/CR-3474.[31] Actual estimates are derived from the curie/gram values contained therein and adjusted for the different mass of the Callaway components, projected operating life, and different periods of decay. Additional short-lived isotopes are derived from CR-0130[32] and CR-0672,[33] and benchmarked to the long-lived values from CR-3474.

The control elements are disposed of along with the spent fuel, i.e., there is no additional cost provided for their disposal.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 17 of 34 TLG Services, LLC Activation of the containment building structure is confined to the biological shield.

3.5.4 General Transition Activities Existing warehouses are cleared of non-essential material and remain for use by Ameren Services and its subcontractors. The plant operating staff performs the following activities at no additional cost or credit to the project during the transition period:

Drain and collect fuel oils, lubricating oils, and transformer oils for recycle and/or sale.

Drain and collect acids, caustics, and other chemical stores for recycle and/or sale.

Process operating waste inventories, i.e., the estimates do not address the disposition of any legacy wastes; the disposal of operating wastes during this initial period is not considered a decommissioning expense.

Scrap and Salvage The existing plant equipment is considered obsolete and suitable for scrap as deadweight quantities only. Ameren Services will make economically reasonable efforts to salvage equipment following final plant shutdown.

However, dismantling techniques assumed by TLG for equipment in this analysis are not consistent with removal techniques required for salvage (resale) of equipment. Experience has indicated that some buyers wanted equipment stripped down to very specific requirements before they would consider purchase. This requires expensive rework after the equipment had been removed from its installed location. Since placing a salvage value on this machinery and equipment would be speculative, and the value would be small in comparison to the overall decommissioning expenses, this analysis does not attempt to quantify the value that an owner may realize based upon those efforts.

It is assumed, for purposes of this analysis, that any value received from the sale of scrap generated in the dismantling process would be more than offset by the on-site processing costs. The dismantling techniques assumed in the decommissioning estimates do not include the additional cost for size reduction and preparation to meet furnace ready conditions.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 18 of 34 TLG Services, LLC For example, the recovery of copper from electrical cabling may require the removal and disposition of any contaminated insulation, an added expense. With a volatile market, the potential profit margin in scrap recovery is highly speculative, regardless of the ability to free release this material. This assumption is an implicit recognition of scrap value in the disposal of clean metallic waste at no additional cost to the project.

Furniture, tools, mobile equipment such as forklifts, trucks, bulldozers, and other property is removed at no cost or credit to the decommissioning project. Disposition may include relocation to other facilities. Spare parts are also made available for alternative use.

Energy For estimating purposes, the plant is assumed to be de-energized, with the exception of those facilities associated with spent fuel storage.

Replacement power costs are used to calculate the cost of energy consumed during decommissioning for tooling, lighting, ventilation, and essential services.

Insurance Costs for continuing coverage (nuclear liability and property insurance) following cessation of plant operations and during decommissioning are included and based upon current operating premiums. Reductions in premiums, throughout the decommissioning process, are based upon the guidance provided in SECY-00-0145, Integrated Rulemaking Plan for Nuclear Power Plant Decommissioning[34] The NRCs financial protection requirements are based on various reactor (and spent fuel) configurations.

Taxes Property tax payments are included for the land only and will continue through the decommissioning project.

Site Modifications The perimeter fence and in-plant security barriers will be moved, as appropriate, to conform to the Site Security Plan in force during the various stages of the project.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 19 of 34 TLG Services, LLC 3.6 COST ESTIMATE

SUMMARY

Schedules of expenditures for the base case are provided in Tables 3.1 and 3.2.

The tables delineate the cost contributors by year of expenditures as well as cost contributor (labor, equipment and materials, energy, radioactive waste disposal, and other costs).

The cost elements are also assigned to one of three subcategories: License Termination, Spent Fuel Management, and Site Restoration. The subcategory License Termination is used to accumulate costs that are consistent with decommissioning as defined by the NRC in its financial assurance regulations (i.e., 10 CFR §50.75). The cost reported for this subcategory is generally sufficient to terminate the units operating license, recognizing that there may be some additional cost impact from spent fuel management. These costs are identified in Tables 3.1a and 3.2a.

The Spent Fuel Management subcategory contains costs associated with the five and one-half years of post-shutdown pool operations and the transfer of the fuel from the pool to the DOE. These costs are identified in Tables 3.1b and 3.2b.

Site Restoration is used to capture costs associated with the dismantling and demolition of buildings and facilities demonstrated to be free from contamination. This includes structures never exposed to radioactive materials, as well as those facilities that have been decontaminated to appropriate levels.

Structures are removed to a depth of three feet below grade and backfilled to conform to local grade. These costs are identified in Tables 3.1c and 3.2c.

It should be noted that the costs assigned to these subcategories are allocations.

Delegation of cost elements is for the purposes of comparison (e.g., with NRC financial guidelines) or to permit specific financial treatment (e.g., Asset Retirement Obligation determinations). In reality, there can be considerable interaction between the activities in the three subcategories. For example, an owner may decide to remove non-contaminated structures early in the project to improve access to highly contaminated facilities or plant components. In these instances, the non-contaminated removal costs could be reassigned from Site Restoration to an NRC License Termination support activity. However, in general, the allocations represent a reasonable accounting of those costs that can be expected to be incurred for the specific subcomponents of the total estimated program cost, if executed as described.

As discussed in Section 3.4.1, while designated for disposal at the geologic repository along with the spent fuel, GTCC waste is still classified as low-level radioactive waste and, as such, included as a License Termination expense.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 20 of 34 TLG Services, LLC The estimates were developed and costs are presented in 2023 dollars. As such, the estimates do not reflect the escalation of costs (due to inflationary and market forces) over the remaining operating life of the reactor or during the decommissioning period. The schedules are based upon the detailed activity costs reported in Appendices C and D, along with the timeline presented in Section 4.

For the purposes of this analysis, the costs presented in the following tables reflect plant decommissioning at the expiration of its current license (2044) and the use of off-site low-level radioactive waste processing to minimize the volume designated for controlled disposal. Costs for the direct disposal only scenarios are presented in the appendices (E and F).

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 21 of 34 TLG Services, LLC TABLE 3.1 DECON ALTERNATIVE TOTAL ANNUAL EXPENDITURES (thousands, 2023 dollars)

Equipment &

Year Labor Materials Energy Burial Other [1]

Total [2]

Plant Costs 2044 17,586 2,333 485 9

2,165 22,579 2045 88,781 15,072 2,846 1,145 17,266 125,110 2046 99,301 39,361 2,983 39,686 28,894 210,225 2047 98,521 43,581 2,243 54,284 22,769 221,397 2048 88,689 20,973 1,787 20,573 9,735 141,757 2049 88,193 20,345 1,771 19,666 9,379 139,353 2050 63,283 13,032 1,167 13,173 6,649 97,305 2051 39,977 9,504 405 25 3,197 53,107 2052 30,715 26,325 237 0

4,259 61,535 2053 6,630 5,682 51 0

919 13,282 Plant Subtotal 621,674 196,208 13,975 148,562 105,231 1,085,651 ISFSI 72.30 Costs 2050 768 279 0

4,433 5,075 10,556 ISFSI Subtotal 768 279 0

4,433 5,075 10,556 ISFSI Site Restoration Costs [3]

2051 192 116 0

0 21 330 2052 676 409 0

0 75 1,160 2053 146 88 0

0 16 250 Subtotal ISFSI SR 1,014 614 0

0 112 1,740 Total 623,457 197,101 13,975 152,995 110,418 1,097,947

[1] Includes property taxes, insurance, fees, surveys, and GTCC disposal

[2] Columns may not add due to rounding

[3] These costs reflect direct ISFSI restoration costs associated with restoring the ISFSI and associated structures/property. Supporting costs detailed in Table G-3 of this report are included in the Plant costs in the table above.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 22 of 34 TLG Services, LLC TABLE 3.1a DECON ALTERNATIVE LICENSE TERMINATION EXPENDITURES (thousands, 2023 dollars)

Equipment &

Year Labor Materials Energy Burial Other [1]

Total [2]

Plant Costs 2044 16,821 546 485 9

1,536 19,398 2045 84,767 6,393 2,846 1,145 14,202 109,353 2046 93,476 30,308 2,983 39,686 26,307 192,760 2047 92,403 34,344 2,243 54,284 20,386 203,660 2048 80,365 11,403 1,787 20,573 6,877 121,005 2049 79,836 10,793 1,771 19,666 6,517 118,582 2050 60,833 10,232 1,167 13,173 5,810 91,216 2051 31,303 2,024 338 25 1,987 35,676 2052 190 0

0 0

0 190 2053 41 0

0 0

0 41 Plant Subtotal 540,035 106,043 13,620 148,562 83,621 891,881 ISFSI 72.30 Costs 2050 768 279 0

4,433 5,075 10,556 ISFSI Subtotal 768 279 0

4,433 5,075 10,556 Total 540,803 106,322 13,620 152,995 88,696 902,437

[1] Includes property taxes, insurance, fees, surveys, and GTCC disposal

[2] Columns may not add due to rounding

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 23 of 34 TLG Services, LLC TABLE 3.1b DECON ALTERNATIVE SPENT FUEL MANAGEMENT EXPENDITURES (thousands, 2023 dollars)

Equipment &

Year Labor Materials Energy Burial Other Total [1]

2044 595 1,786 0

0 630 3,012 2045 2,893 8,679 0

0 3,064 14,637 2046 2,993 8,978 0

0 2,586 14,558 2047 3,043 9,130 0

0 2,383 14,556 2048 2,883 8,649 0

0 2,389 13,922 2049 2,871 8,613 0

0 2,383 13,867 2050 842 2,525 0

0 699 4,065 2051 0

0 0

0 0

0 2052 0

0 0

0 0

0 2053 0

0 0

0 0

0 Total 16,120 48,360 0

0 14,135 78,615

[1] Columns may not add due to rounding

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 24 of 34 TLG Services, LLC TABLE 3.1c DECON ALTERNATIVE SITE RESTORATION EXPENDITURES (thousands, 2023 dollars)

Equipment &

Year Labor Materials Energy Burial Other Total [1]

Plant Costs 2044 169 0

0 0

0 169 2045 1,120 0

0 0

0 1,120 2046 2,832 75 0

0 0

2,907 2047 3,074 107 0

0 0

3,181 2048 5,441 921 0

0 468 6,831 2049 5,486 939 0

0 479 6,904 2050 1,608 275 0

0 140 2,024 2051 8,674 7,480 67 0

1,210 17,431 2052 30,525 26,325 237 0

4,259 61,345 2053 6,589 5,682 51 0

919 13,241 Plant Subtotal 65,519 41,805 355 0

7,476 115,155 ISFSI Site Restoration Costs [2]

2051 192 116 0

0 21 330 2052 676 409 0

0 75 1,160 2053 146 88 0

0 16 250 Subtotal ISFSI SR 1,014 614 0

0 112 1,740 Total 66,533 42,419 355 0

7,588 116,895

[1] Columns may not add due to rounding

[2] These costs reflect direct ISFSI restoration costs associated with restoring the ISFSI and associated structures/property. Supporting costs detailed in Table G-3 of this report are included in the Plant costs in the table above.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 25 of 34 TLG Services, LLC TABLE 3.2 SAFSTOR ALTERNATIVE TOTAL ANNUAL EXPENDITURES (thousands, 2023 dollars)

Equipment &

Year Labor Materials Energy Burial Other [1]

Total [2]

Plant Costs 2044 14,639 2,193 485 9

2,106 19,432 2045 74,519 14,760 2,361 644 23,857 116,141 2046 41,298 11,867 1,036 913 9,706 64,821 2047 28,119 9,498 472 17 4,734 42,841 2048 28,196 9,524 473 17 4,747 42,958 2049 28,119 9,498 472 17 4,734 42,841 2050 11,875 3,080 305 10 2,043 17,313 2051 5,138 418 236 8

927 6,726 2052 5,152 419 237 8

929 6,744 2053 5,138 418 236 8

927 6,726 2054 5,138 418 236 8

927 6,726 2055 5,138 418 236 8

927 6,726 2056 5,152 419 237 8

929 6,744 2057 5,138 418 236 8

927 6,726 2058 5,138 418 236 8

927 6,726 2059 5,138 418 236 8

927 6,726 2060 5,152 419 237 8

929 6,744 2061 5,138 418 236 8

927 6,726 2062 5,138 418 236 8

927 6,726 2063 5,138 418 236 8

927 6,726 2064 5,152 419 237 8

929 6,744 2065 5,138 418 236 8

927 6,726 2066 5,138 418 236 8

927 6,726 2067 5,138 418 236 8

927 6,726 2068 5,152 419 237 8

929 6,744 2069 5,138 418 236 8

927 6,726 2070 5,138 418 236 8

927 6,726 2071 5,138 418 236 8

927 6,726 2072 5,152 419 237 8

929 6,744 2073 5,138 418 236 8

927 6,726

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 26 of 34 TLG Services, LLC TABLE 3.2 (continued)

SAFSTOR ALTERNATIVE TOTAL ANNUAL EXPENDITURES (thousands, 2023 dollars)

Equipment &

Year Labor Materials Energy Burial Other [1]

Total [2]

2074 5,138 418 236 8

927 6,726 2075 5,138 418 236 8

927 6,726 2076 5,152 419 237 8

929 6,744 2077 5,138 418 236 8

927 6,726 2078 5,138 418 236 8

927 6,726 2079 5,138 418 236 8

927 6,726 2080 5,152 419 237 8

929 6,744 2081 5,138 418 236 8

927 6,726 2082 5,138 418 236 8

927 6,726 2083 5,138 418 236 8

927 6,726 2084 5,152 419 237 8

929 6,744 2085 5,138 418 236 8

927 6,726 2086 5,138 418 236 8

927 6,726 2087 5,138 418 236 8

927 6,726 2088 5,152 419 237 8

929 6,744 2089 5,138 418 236 8

927 6,726 2090 5,138 418 236 8

927 6,726 2091 5,138 418 236 8

927 6,726 2092 5,152 419 237 8

929 6,744 2093 5,138 418 236 8

927 6,726 2094 5,138 418 236 8

927 6,726 2095 5,138 418 236 8

927 6,726 2096 5,152 419 237 8

929 6,744 2097 5,138 418 236 8

927 6,726 2098 14,411 1,214 632 13 1,165 17,435 2099 56,305 5,282 2,361 39 2,257 66,243 2100 72,860 28,556 2,280 39,310 16,526 159,532 2101 75,567 30,455 2,103 45,582 18,294 172,001 2102 70,398 12,028 1,771 16,974 6,939 108,110 2103 70,398 12,028 1,771 16,974 6,939 108,110

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 27 of 34 TLG Services, LLC TABLE 3.2 (continued)

SAFSTOR ALTERNATIVE TOTAL ANNUAL EXPENDITURES (thousands, 2023 dollars)

Equipment &

Year Labor Materials Energy Burial Other [1]

Total [2]

2104 40,588 8,456 432 212 2,438 52,127 2105 30,621 26,247 236 0

3,502 60,606 2106 8,222 7,047 63 0

940 16,272 Plant Subtotal 907,769 211,387 28,359 121,087 154,519 1,423,121 ISFSI 72.30 Costs 2101 99 36 0

569 651 1,354 2102 333 121 0

1,922 2,200 4,576 2103 333 121 0

1,922 2,200 4,576 2104 4

1 0

21 24 50 ISFSI Subtotal 768 279 0

4,433 5,075 10,556 ISFSI Site Restoration Costs [3]

2104 159 96 0

0 18 273 2105 674 408 0

0 75 1,157 2106 181 110 0

0 20 311 Subtotal ISFSI SR 1,014 614 0

0 112 1,740 Total 909,552 212,280 28,359 125,520 159,706 1,435,417

[1] Includes property taxes, insurance, fees, surveys, and GTCC disposal

[2] Columns may not add due to rounding

[3] These costs reflect direct ISFSI restoration costs associated with restoring the ISFSI and associated structures/property. Supporting costs detailed in Table G-3 of this report are included in the Plant costs in the table above.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 28 of 34 TLG Services, LLC TABLE 3.2a SAFSTOR ALTERNATIVE LICENSE TERMINATION EXPENDITURES (thousands, 2023 dollars)

Equipment &

Year Labor Materials Energy Burial Other [1]

Total [2]

Plant Costs 2044 14,044 407 485 9

1,476 16,421 2045 71,625 6,080 2,361 644 20,793 101,504 2046 35,432 3,095 871 913 7,119 47,431 2047 20,980 663 236 17 2,351 24,247 2048 21,037 664 237 17 2,358 24,313 2049 20,980 663 236 17 2,351 24,247 2050 9,782 490 236 10 1,344 11,862 2051 5,138 418 236 8

927 6,726 2052 5,152 419 237 8

929 6,744 2053 5,138 418 236 8

927 6,726 2054 5,138 418 236 8

927 6,726 2055 5,138 418 236 8

927 6,726 2056 5,152 419 237 8

929 6,744 2057 5,138 418 236 8

927 6,726 2058 5,138 418 236 8

927 6,726 2059 5,138 418 236 8

927 6,726 2060 5,152 419 237 8

929 6,744 2061 5,138 418 236 8

927 6,726 2062 5,138 418 236 8

927 6,726 2063 5,138 418 236 8

927 6,726 2064 5,152 419 237 8

929 6,744 2065 5,138 418 236 8

927 6,726 2066 5,138 418 236 8

927 6,726 2067 5,138 418 236 8

927 6,726 2068 5,152 419 237 8

929 6,744 2069 5,138 418 236 8

927 6,726 2070 5,138 418 236 8

927 6,726 2071 5,138 418 236 8

927 6,726 2072 5,152 419 237 8

929 6,744 2073 5,138 418 236 8

927 6,726

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 29 of 34 TLG Services, LLC TABLE 3.2a (continued)

SAFSTOR ALTERNATIVE LICENSE TERMINATION EXPENDITURES (thousands, 2023 dollars)

Equipment &

Year Labor Materials Energy Burial Other [1]

Total [2]

2074 5,138 418 236 8

927 6,726 2075 5,138 418 236 8

927 6,726 2076 5,152 419 237 8

929 6,744 2077 5,138 418 236 8

927 6,726 2078 5,138 418 236 8

927 6,726 2079 5,138 418 236 8

927 6,726 2080 5,152 419 237 8

929 6,744 2081 5,138 418 236 8

927 6,726 2082 5,138 418 236 8

927 6,726 2083 5,138 418 236 8

927 6,726 2084 5,152 419 237 8

929 6,744 2085 5,138 418 236 8

927 6,726 2086 5,138 418 236 8

927 6,726 2087 5,138 418 236 8

927 6,726 2088 5,152 419 237 8

929 6,744 2089 5,138 418 236 8

927 6,726 2090 5,138 418 236 8

927 6,726 2091 5,138 418 236 8

927 6,726 2092 5,152 419 237 8

929 6,744 2093 5,138 418 236 8

927 6,726 2094 5,138 418 236 8

927 6,726 2095 5,138 418 236 8

927 6,726 2096 5,152 419 237 8

929 6,744 2097 5,138 418 236 8

927 6,726 2098 14,249 1,214 632 13 1,165 17,273 2099 55,175 5,282 2,361 39 2,257 65,114 2100 69,529 28,469 2,280 39,310 16,526 156,115 2101 71,274 30,092 2,103 45,582 18,155 167,205 2102 64,997 11,103 1,771 16,974 6,468 101,313 2103 64,997 11,103 1,771 16,974 6,468 101,313

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 30 of 34 TLG Services, LLC TABLE 3.2a (continued)

SAFSTOR ALTERNATIVE LICENSE TERMINATION EXPENDITURES (thousands, 2023 dollars)

Equipment &

Year Labor Materials Energy Burial Other [1]

Total [2]

2104 33,359 2,262 376 212 1,608 37,817 2105 189 0

0 0

0 189 2106 51 0

0 0

0 51 Plant Subtotal 809,336 121,239 27,060 121,087 134,030 1,212,752 ISFSI 72.30 Costs 2101 99 36 0

569 651 1,354 2102 333 121 0

1,922 2,200 4,576 2103 333 121 0

1,922 2,200 4,576 2104 4

1 0

21 24 50 ISFSI Subtotal 768 279 0

4,433 5,075 10,556 Total 810,104 121,518 27,060 125,520 139,105 1,223,308

[1] Includes property taxes, insurance, fees, surveys, and GTCC disposal

[2] Columns may not add due to rounding

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 31 of 34 TLG Services, LLC TABLE 3.2b SAFSTOR ALTERNATIVE SPENT FUEL MANAGEMENT EXPENDITURES (thousands, 2023 dollars)

Equipment &

Year Labor Materials Energy Burial Other Total [1]

2044 595 1,786 0

0 630 3,012 2045 2,893 8,679 0

0 3,064 14,637 2046 5,866 8,772 166 0

2,586 17,390 2047 7,139 8,836 236 0

2,383 18,594 2048 7,159 8,860 237 0

2,389 18,645 2049 7,139 8,836 236 0

2,383 18,594 2050 2,093 2,590 69 0

699 5,451 Total 32,884 48,360 944 0

14,135 96,323

[1] Columns may not add due to rounding

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 32 of 34 TLG Services, LLC TABLE 3.2c SAFSTOR ALTERNATIVE SITE RESTORATION EXPENDITURES (thousands, 2023 dollars)

Equipment &

Year Labor Materials Energy Burial Other Total [1]

Plant Costs 2044-97 0

0 0

0 0

0 2098 162 0

0 0

0 162 2099 1,129 0

0 0

0 1,129 2100 3,331 87 0

0 0

3,417 2101 4,293 363 0

0 139 4,796 2102 5,401 925 0

0 471 6,797 2103 5,401 925 0

0 471 6,797 2104 7,229 6,194 56 0

830 14,310 2105 30,432 26,247 236 0

3,502 60,416 2106 8,171 7,047 63 0

940 16,221 Plant Subtotal 65,549 41,787 355 0

6,355 114,046 ISFSI Site Restoration Costs [2]

2104 159 96 0

0 18 273 2105 674 408 0

0 75 1,157 2106 181 110 0

0 20 311 Subtotal ISFSI SR 1,014 614 0

0 112 1,740 Total 66,563 42,401 355 0

6,467 115,786

[1] Columns may not add due to rounding

[2] These costs reflect direct ISFSI restoration costs associated with restoring the ISFSI and associated structures/property. Supporting costs detailed in Table G-3 of this report are included in the Plant costs in the table above.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 33 of 34 TLG Services, LLC FIGURE 3.1 DECOMMISSIONING PERSONNEL LEVELS DECON Note that the labor hour basis of this chart was taken from Appendix C; however not all line items in Appendix C have labor hour values available (e.g. spent fuel canister loading estimates) 0 50 100 150 200 250 300 350 400 450 500 FTEs Year Craft Utility DOC 103.1 Decommissioning Personnel Levels, DECON 13.1 Decommissioning Personnel Levels, DECON

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 3, Page 34 of 34 TLG Services, LLC FIGURE 3.2 DECOMMISSIONING PERSONNEL LEVELS SAFSTOR Note that the labor hour basis of this chart was taken from Appendix D; however not all line items in Appendix D have labor hour values available (e.g. spent fuel canister loading estimates) 0 50 100 150 200 250 300 350 400 FTEs Year Craft Utility DOC 2 3.2 Decommissioning Personnel Levels, SAFSTOR

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 4, Page 1 of 4 TLG Services, LLC

4. SCHEDULE ESTIMATE The schedules for the decommissioning scenarios considered in this study follow the sequences presented in the AIF/NESP-036 study, with minor changes to reflect recent experience and site-specific constraints. In addition, the scheduling has been revised to reflect the spent fuel management plan described in Section 3.4.1.

A schedule or sequence of activities for the DECON alternative is presented in Figure 4.1. The scheduling sequence assumes that fuel is removed from the spent fuel pool within five and one-half years. The key activities listed in the schedule do not reflect a one-to-one correspondence with those activities in the cost tables, but reflect dividing some activities for clarity and combining others for convenience. The schedule was prepared using the "Microsoft Project Professional" computer software.[35]

4.1 SCHEDULE ESTIMATE ASSUMPTIONS The schedule reflects the results of a precedence network developed for the site decommissioning activities, i.e., a PERT (Program Evaluation and Review Technique) Software Package. The work activity durations used in the precedence network reflect the actual person-hour estimates from the cost table, adjusted by stretching certain activities over their slack range and shifting the start and end dates of others. The following assumptions were made in the development of the decommissioning schedule:

The fuel building is isolated until such time that all spent fuel has been transferred from the spent fuel pool to the DOE. Decontamination and dismantling of the storage pool is initiated once the transfer of spent fuel is complete (DECON option).

All work (except vessel and internals removal) is performed during an 8-hour workday, 5 days per week, with no overtime. There are eleven paid holidays per year.

Reactor and internals removal activities are performed by using separate crews for different activities working on different shifts, with a corresponding backshift charge for the second shift.

Multiple crews work parallel activities to the maximum extent possible, consistent with optimum efficiency, adequate access for cutting, removal and laydown space, and with the stringent safety measures necessary during demolition of heavy components and structures.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 4, Page 2 of 4 TLG Services, LLC For plant systems removal, the systems with the longest removal durations in areas on the critical path are considered to determine the duration of the activity.

4.2 PROJECT SCHEDULE The period-dependent costs presented in the detailed cost tables are based upon the durations developed in the schedules for decommissioning. Durations are established between several milestones in each project period; these durations are used to establish a critical path for the entire project. In turn, the critical path duration for each period is used as the basis for determining the period-dependent costs. A second critical path is shown for the spent fuel storage period, which determines the release of the fuel building for final decontamination.

Project timelines are provided in Figures 4.2 and 4.3 with milestone dates based on a 2044 shutdown date. The fuel pool is emptied approximately five and one-half years after shutdown. Deferred decommissioning in the SAFSTOR scenarios is assumed to commence so that the operating license is terminated within a 60-year period from the cessation of plant operations.

Callaway Energy Center Decommissioning Cost Analysis FIGURE 4.1 ACTIVITY SCHEDULE Document A22-1819-001, Rev. 0 Section 4, Page 3 of 4 Task Name 2o44l2o4slzoaal2c'47l2o4nlznzpl2oso I 2onr I znsz I cnng I Callaway Plant Decon Project Schedule Shutdown plant Period la - Shutd.own through transition Certificate of permanent cessation of operations submitted Fuel storage pool operations Reconfrgure plant Prepare activity specifrcations Perform site characier ization PSDAR submitted Written certificate of permanent removal of fuel submitted Site specific decommissioning cost estimate Period lb - Decommissioning preparations Fuel storage pool operations Reconfigure plant (continued)

Prepare detailed work procedures Period 2a - Large component removal Fuel storage pool operations Preparation for reactor vessel removal Reactor vessel & internals Remaining large NSSS components disposition License termination plan submitted Period 2b - Decontamination (wet fuel)

Fuel storage pool operations Remove systems not supporting wet fuel storage Decon buildings not supporting wet fuel storage License termination plan approved Fuel storage pool available for decommissioning Period 2d - Decontamination following wet fuel storage Remove remaining systems Decon wet fuel storage area Period 2f - Plant license termination Final Site Survey NRC review & approval Part 50 license terminated Period 3b Sitc rcotoration Main condenser Decon NSSS Isolate spent fuel pool Non-essential systems Main turbine/generator submitted DOC staff mobilized I

r.-1 ar I

-r n

a l

a, a

a l-r t

I I

Fl---1 lt f,

r tt II tllt tttt Fi

  • l lt Ir Ia Il._1 if Ii-t:

L; a

a I

I I

a TLG Seruices, LLC

Callaut ay Energy Center D ecommieaioning Cost Analysis Shutdown october 1& 2044 Period I Preparations oct-2044 Apr-2045 Shutdown October 18, 2044 Period 1 SAFSTOR Preparations Oct-204 Apt-2046 Fuel Pool 0perations FIGURE 4.2 DE COMMISSIONING TIMELINE DECON Period 2 Decommissioning Operations Fuel Pool Operations Apr-2050 FIGURE 4.3 DECOMMISSIONING TIMELINE SAFSTOR Document A22-7819-001, Reu. 0 Section 4, Page 4 of 4 END Period 3 Site Restoration A

Mar-2053 Sept-2051 END A

Period 2 Dormancy Period 3 Decommisioning Prepantions Period 4 Decommissioning Operations Pedod 5 Site Restontion A

A Apr-2106 Oct-2104 TLG Serviceq LLC Apr-2050 0ct-20S Apr-2100

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 5, Page 1 of 6 TLG Services, LLC

5. RADIOACTIVE WASTES The objectives of the decommissioning process are the removal of all radioactive material from the site that would restrict its future use and the termination of the NRC license. This currently requires the remediation of all radioactive material at the site in excess of applicable legal limits. Under the Atomic Energy Act,[36] the NRC is responsible for protecting the public from sources of ionizing radiation. Title 10 of the Code of Federal Regulations delineates the production, utilization, and disposal of radioactive materials and processes. In particular, Part 71 defines radioactive material as it pertains to transportation and Part 61 specifies its disposition.

Most of the materials being transported for controlled burial are categorized as Low Specific Activity (LSA) or Surface Contaminated Object (SCO) materials containing Type A quantities, as defined in 49 CFR Parts 173-178. Shipping containers are required to be Industrial Packages (IP-1, IP-2 or IP-3, as defined in 10 CFR §173.411).

For this study, commercially available steel containers are presumed to be used for the disposal of piping, small components, and concrete. Larger components can serve as their own containers, with proper closure of all openings, access ways, and penetrations.

The destinations for the various waste streams from decommissioning are identified in Figures 5.1 and 5.2. The volumes of radioactive waste generated during the various decommissioning activities at the site are shown on a line-item basis in appendices, and summarized in Tables 5.1 and 5.2 (base case). The quantified waste volume summaries shown in these tables are consistent with Part 61 classifications. The volumes are calculated based on the exterior dimensions for containerized material and on the displaced volume of components serving as their own waste containers.

The reactor vessel and internals are categorized as large quantity shipments and, accordingly, will be shipped in reusable, shielded truck casks with disposable liners.

In calculating disposal costs, the burial fees are applied against the liner volume, as well as the special handling requirements of the payload. Packaging efficiencies are lower for the highly activated materials (greater than Type A quantity waste), where high concentrations of gamma-emitting radionuclides limit the capacity of the shipping canisters.

No process system containing/handling radioactive substances at shutdown is presumed to meet material release criteria by decay alone (i.e., systems radioactive at shutdown will still be radioactive over the period during which the decommissioning is accomplished, due to the presence of long-lived radionuclides).

While the dose rates decrease with time, radionuclides such as 137Cs will still control the disposition requirements.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 5, Page 2 of 6 The waste material produced in the decontamination and dismantling of the nuclear units is primarily generated during Period 2 of DECON and Period 4 of SAFSTOR.

Material that is considered potentially contaminated when removed from the radiological controlled area is sent to processing facilities in Tennessee for conditioning and disposal. Heavily contaminated components and activated materials are routed for controlled disposal. The disposal volumes reported in the tables reflect the savings resulting from processing and recycling.

For purposes of constructing the estimates, the cost for disposal at the EnergySolutions facility was used as a proxy for future disposal facilities. Separate rates were used for containerized waste and large components, including the steam generators and reactor coolant pump motors. Demolition debris including miscellaneous steel, scaffolding, and concrete was disposed of at a bulk rate. The decommissioning waste stream also included resins and dry active waste.

Since EnergySolutions is not currently able to receive the more highly radioactive components generated in the decontamination and dismantling of the reactor, disposal costs for the Class B and C material were based upon Ameren Services current agreement with WCS for the Andrews County disposal facility.

A small quantity of material generated during the decommissioning will not be considered suitable for near-surface disposal, and is assumed to be disposed of in a geologic repository, in a manner similar to that envisioned for spent fuel disposal.

This GTCC material, is estimated to require five spent fuel storage canisters (or the equivalent) to dispose of the most radioactive portions of the reactor vessel internals.

The volume and weight reported in Tables 5.1 and 5.2 represent the packaged weight and volume of the GTCC storage canisters.

TLG Services, LLC

Callaway Energy Center D ecomm,issioning Cost Analy sis FIGURE 5.1 RADIOACTIVE WASTE DISPOSITION Docurnent A22-1819-001, Reu. 0 Section 5, Page 3 of 6 Rctor Waste (Clas Al Rsin / Filters (Class A)

Direct &rial Conta in rized Waste En ergysol utio ns Cliw, Utah Dsmmissioning Low-level Radioactive Waste Strearu Bulk Waste (Cdtamimted Soil and Goncrete)

DAW E n ergysol ut ions Oak Ri*e, TN Metal Prcessing Rector Waste (classes B/c)

Waste Cmtrcl Specialists Andrews County, TeEs Resin NSSS De@ntamination (clas B/c)

Reactor Waste (Cla$ GTCC)

Geologh Disposal Federal Facility Tuu serutceg, lrrL

Callaway Energy Center D ecomrnissioning Cost Analysis FIGURE 5.2 DE COMMISSIONING WASTE DESTINATIONS RADIOLOGICAL Docurnent A2 2-18 I 9-00 1, Rev. 0 Section 5, Page 4 of 6

/

I Waste Control Specialists Andrews County, TX Callaway Energy Center EnetgvSolutions Clive, UT EnergySolutions Oak Ridge, TN TLG Seruices, LLC

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 5, Page 5 of 6 TLG Services, LLC TABLE 5.1 DECON ALTERNATIVE DECOMMISSIONING WASTE

SUMMARY

Waste Cost Basis Class [1]

Waste Volume (cubic feet)

Mass (pounds)

Low-Level Radioactive Waste (near-surface disposal)

EnergySolutions A

235,150 15,504,509 WCS B

2,268 254,539 WCS C

393 47,411 Greater than Class C (geologic repository)

Spent Fuel Equivalent GTCC 2,217 433,180 Processed/Conditioned (off-site recycling center)

Recycling Vendors A

286,777 10,886,250 Totals [2]

526,805 27,125,890 7 5.1 DECON Alternative, Decommissioning Waste Summary

[1]

Waste is classified according to the requirements delineated in Title 10 CFR, Part 61.55

[2]

Columns may not add due to rounding.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 5, Page 6 of 6 TLG Services, LLC TABLE 5.2 SAFSTOR ALTERNATIVE DECOMMISSIONING WASTE

SUMMARY

Waste Cost Basis Class [1]

Waste Volume (cubic feet)

Mass (pounds)

Low-Level Radioactive Waste (near-surface disposal)

EnergySolutions A

196,099 12,966,272 WCS B

751 65,154 WCS C

406 46,747 Greater than Class C (geologic repository)

Spent Fuel Equivalent GTCC 2,217 433,180 Processed/Conditioned (off-site recycling center)

Recycling Vendors A

313,752 12,018,050 Totals [2]

513,224 25,529,404 8 5.2 SAFSTOR Alternative, Decommissioning Waste Summary

[1]

Waste is classified according to the requirements as delineated in Title 10 CFR, Part 61.55

[2]

Columns may not add due to rounding.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 6, Page 1 of 5 TLG Services, LLC

6. RESULTS The analysis to estimate the costs to decommission Callaway relied upon the site-specific, technical information developed for a previous analysis prepared in 2020.

While not an engineering study, the estimates provide the plant owner with sufficient information to assess its financial obligations, as they pertain to the eventual decommissioning of the nuclear station.

The estimates described in this report are based on numerous fundamental assumptions, including regulatory requirements, project contingencies, low-level radioactive waste disposal practices, high-level radioactive waste management options, and site restoration requirements. The decommissioning scenarios assume continued operation of the stations spent fuel pool for a minimum of five and one-half years following the cessation of operations for continued cooling of the assemblies. Once sufficiently cooled, the spent fuel will be packaged into canisters and transferred to the DOE. The spent fuel stored at the ISFSI will also be transferred to DOE during this period.

The cost projected to promptly decommission (DECON) Callaway, assuming the use of off-site low-level radioactive waste processing to reduce the volume requiring controlled disposal, is estimated to be $1,097.9 million. The majority of this cost (approximately 82.2%) is associated with the physical decontamination and dismantling of the nuclear unit so that the operating license can be terminated.

Another 7.2% is associated with the management, interim storage, and eventual transfer of the spent fuel. The remaining 10.6% is for the demolition of the designated structures and limited restoration of the site.

The cost projected for deferred decommissioning (SAFSTOR), assuming the use of off-site low-level radioactive waste processing to reduce the volume requiring controlled disposal, is estimated to be $1,435.4 million. The majority of this cost (approximately 85.2%) is associated with placing the unit in storage, ongoing caretaking of the unit during dormancy, and the eventual physical decontamination and dismantling of the nuclear unit so that the operating license can be terminated. Another 6.7% is associated with the management, interim storage, and eventual transfer of the spent fuel. The remaining 8.1% is for the demolition of the designated structures and limited restoration of the site.

The primary cost contributors, identified in Tables 6.1 and 6.2, are either labor-related or associated with the management and disposition of the radioactive waste.

Program management is the largest single contributor to the overall cost. The magnitude of the expense is a function of both the size of the organization required to manage the decommissioning, as well as the duration of the program. It is

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 6, Page 2 of 5 TLG Services, LLC assumed, for purposes of this analysis, that Ameren Services will oversee the decommissioning program, using a DOC to manage the decommissioning labor force and the associated subcontractors. The size and composition of the management organization varies with the decommissioning phase and associated site activities.

However, once the operating license is terminated, the staff is substantially reduced for the conventional demolition and restoration of the site (for the DECON alternative).

As described in this report, the spent fuel pool will remain operational for a minimum of five and one-half years following the cessation of operations. The pool will be isolated and an independent spent fuel island created. This will allow decommissioning operations to proceed in and around the pool area. Over the five and one-half year period, the spent fuel will be packaged into canisters and transferred to the DOE. The spent fuel stored at the ISFSI will also be transferred to DOE during this period.

The cost for waste disposal includes those costs associated with the controlled disposition of the low-level radioactive waste generated from decontamination and dismantling activities, including plant equipment and components, structural material, filters, resins and dry-active waste. As described in Section 5, disposition of the low-level radioactive material required controlled disposal is at the EnergySolutions facility. Highly activated components, requiring additional isolation from the environment (GTCC), are packaged for geologic disposal. The cost of geologic disposal is based upon a cost equivalent for spent fuel.

A significant portion of the metallic waste is designated for additional processing and treatment at an off-site facility. Processing reduces the volume of material requiring controlled disposal through such techniques and processes as survey and sorting, decontamination, and volume reduction. The material that cannot be unconditionally released is packaged for controlled disposal at one of the currently operating facilities.

The cost identified in the summary tables for processing is all-inclusive, incorporating the ultimate disposition of the material.

Removal costs reflect the labor-intensive nature of the decommissioning process, as well as the management controls required to ensure a safe and successful program.

Decontamination and packaging costs also have a large labor component that is based upon prevailing union wages. Non-radiological demolition is a natural extension of the decommissioning process. The methods employed in decontamination and dismantling are generally destructive and indiscriminate in inflicting collateral damage. With a work force mobilized to support decommissioning operations, non-radiological demolition can be an integrated activity and a logical expansion of the work being performed in the process of terminating the operating license. Prompt

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 6, Page 3 of 5 TLG Services, LLC demolition reduces future liabilities and can be more cost effective than deferral, due to the deterioration of the facilities (and therefore the working conditions) with time.

The reported cost for transport includes the tariffs and surcharges associated with moving large components and/or overweight shielded casks overland, as well as the general expense, e.g., labor and fuel, of transporting material to the destinations identified in this report. For purposes of this analysis, material is primarily moved overland by truck.

Decontamination is used to reduce the plant radiation fields and minimize worker exposure. Slightly contaminated material or material located within a contaminated area is sent to an off-site processing center, i.e., this analysis does not assume that contaminated plant components and equipment can be decontaminated for uncontrolled release in-situ. Centralized processing centers have proven to be a more economical means of handling the large volumes of material produced in the dismantling of a nuclear unit.

License termination survey costs are associated with the labor intensive and complex activity of verifying that contamination has been removed from the site to the levels specified by the regulating agency. This process involves a systematic survey of all remaining plant surface areas and surrounding environs, sampling, isotopic analysis, and documentation of the findings. The status of any plant components and materials not removed in the decommissioning process will also require confirmation and will add to the expense of surveying the facilities alone.

The remaining costs include allocations for heavy equipment and temporary services, as well as for other expenses such as regulatory fees and the premiums for nuclear insurance. While site operating costs are greatly reduced following the final cessation of plant operations, certain administrative functions do need to be maintained either at a basic functional or regulatory level.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 6, Page 4 of 5 TLG Services, LLC TABLE 6.1 DECON ALTERNATIVE DECOMMISSIONING COST ELEMENTS (thousands of 2023 dollars)

Cost Element Total Percentage Decontamination 24,795 2.3 Removal 206,170 18.8 Packaging 35,292 3.2 Transportation 25,123 2.3 Waste Disposal 130,929 11.9 Off-site Waste Processing 37,057 3.4 Program Management [1]

359,753 32.8 Security 100,102 9.1 Corporate Allocations 9,270 0.8 Spent Fuel Pool Isolation 16,480 1.5 Spent Fuel Management [2]

78,615 7.2 Insurance and Regulatory Fees 18,310 1.7 Energy 13,975 1.3 Characterization and Licensing Surveys 32,090 2.9 Property Taxes 1,112 0.1 Miscellaneous Equipment 8,875 0.8 Total [3]

1,097,947 100.0 Cost Element Total Percentage License Termination (excluding ISFSI) 891,881 81.2 ISFSI Decommissioning (License Termination) 10,556 1.0 Spent Fuel Management [2]

78,615 7.2 Site Restoration (excluding ISFSI) 115,155 10.5 ISFSI Demolition (Site Restoration) 1,740 0.2 Total [3]

1,097,947 100.0 4 6.1 DECON Alternative, Decommissioning Cost Elements

[1]

Includes engineering costs

[2] Direct costs only. Excludes program management costs (staffing) but includes costs for spent fuel loading/spent fuel pool O&M and Emergency Planning fees

[3] Columns may not add due to rounding

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 6, Page 5 of 5 TLG Services, LLC TABLE 6.2 SAFSTOR ALTERNATIVE DECOMMISSIONING COST ELEMENTS (thousands of 2023 dollars)

Cost Element Total Percentage Decontamination 22,031 1.5 Removal 210,552 14.7 Packaging 29,078 2.0 Transportation 20,724 1.4 Waste Disposal 99,601 6.9 Off-site Waste Processing 40,909 2.9 Program Management [1]

471,962 32.9 Security 279,243 19.5 Corporate Allocations 14,255 1.0 Spent Fuel Pool Isolation 16,480 1.1 Spent Fuel Management [2]

78,615 5.5 Insurance and Regulatory Fees 58,283 4.1 Energy 28,359 2.0 Characterization and Licensing Surveys 32,222 2.2 Property Taxes 8,114 0.6 Miscellaneous Equipment 24,989 1.7 Total [3]

1,435,417 100.0 Cost Element Total Percentage License Termination (excluding ISFSI) 1,212,752 84.5 ISFSI Decommissioning (License Termination) 10,556 0.7 Spent Fuel Management [4]

96,323 6.7 Site Restoration (excluding ISFSI) 114,046 7.9 ISFSI Demolition (Site Restoration) 1,740 0.1 Total [3]

1,435,417 100.0 12 6.2 SAFSTOR Alternative, Decommissioning Cost Elements

[1]

Includes engineering costs

[2]

Direct costs only. Excludes program management costs (staffing) but includes costs for spent fuel loading/spent fuel pool O&M and Emergency Planning fees

[3]

Columns may not add due to rounding

[4]

Includes percentage of Period 2a (dormancy) plant operating costs until spent fuel pool is emptied, in addition to the direct costs.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 7, Page 1 of 3 TLG Services, LLC

7. REFERENCES
1.

Decommissioning Cost Analysis for the Callaway Energy Center, Document A22-1782-001, Rev. 0, TLG Services, Inc., October 2020

2.

U.S. Code of Federal Regulations, Title 10, Parts 30, 40, 50, 51, 70 and 72, "General Requirements for Decommissioning Nuclear Facilities," Nuclear Regulatory Commission, 53 Fed. Reg. 24018, June 27, 1988 [Open]

3.

U.S. Nuclear Regulatory Commission, Regulatory Guide 1.159, "Assuring the Availability of Funds for Decommissioning Nuclear Reactors," Rev. 2, October 2011 [Open]

4.

U.S. Code of Federal Regulations, Title 10, Part 20, Subpart E, Radiological Criteria for License Termination [Open]

5.

U.S. Code of Federal Regulations, Title 10, Parts 20 and 50, Entombment Options for Power Reactors, Advance Notice of Proposed Rulemaking, 66 Fed.

Reg. 52551, October 16, 2001 [Open]

6.

U.S. Code of Federal Regulations, Title 10, Parts 2, 50 and 51, "Decommissioning of Nuclear Power Reactors,"

Nuclear Regulatory Commission, 61 Fed. Reg. 39278, July 29, 1996 [Open]

7.

U.S. Code of Federal Regulations, Title 10, Parts 20, 30, 40, 50, 70, and 72, "Decommissioning Planning," Nuclear Regulatory Commission, Federal Register Volume 76, (p 35512 et seq.), June 17, 2011 [Open]

8.

Nuclear Waste Policy Act of 1982, 42 U.S. Code 10101, et seq. [Open]

9.

Charter of the Blue Ribbon Commission on Americas Nuclear Future, Objectives and Scope of Activities [Open]

10. Blue Ribbon Commission on Americas Nuclear Future, Report to the Secretary of Energy, p. 27, 32, January 2012 [Open]
11. Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste, U.S. DOE, January 11, 2013 [Open]
12. United States Court of Appeals for the District of Columbia Circuit, In Re:

Aiken County, Et Al., August 2013 [Open]

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 7, Page 2 of 3 TLG Services, LLC

7. REFERENCES (continued)
13. U.S. Code of Federal Regulations, Title 10, Part 50, Domestic Licensing of Production and Utilization Facilities, Subpart 54 (bb), Conditions of Licenses

[Open]

14. Low-Level Radioactive Waste Policy Act, Public Law 96-573, 1980 [Open]
15. Low-Level Radioactive Waste Policy Amendments Act of 1985, Public Law 99-240, January 15, 1986 [Open]
16. U.S. Code of Federal Regulations, Title 10, Part 61, Licensing Requirements for Land Disposal of Radioactive Waste [Open]
17. Final Environmental Impact Statement for the Disposal of Greater-Than-Class C (GTCC) Low-Level Radioactive Waste and GTCC-Like Waste, (DOE/EIS-0375), January 2016 [Open]
18. U.S. Code of Federal Regulations, Title 10, Part 20, Subpart E, Final Rule, Radiological Criteria for License Termination, 62 Fed. Reg. 39058, July 21, 1997 [Open]
19. Establishment of Cleanup Levels for CERCLA Sites with Radioactive Contamination, EPA Memorandum OSWER No. 9200.4-18, August 22, 1997

[Open]

20. U.S. Code of Federal Regulations, Title 40, Part 141.66, Maximum contaminant levels for radionuclides [Open]
21. Memorandum of Understanding Between the Environmental Protection Agency and the Nuclear Regulatory Commission: Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites, OSWER 9295.8-06a, October 9, 2002 [Open]
22. Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM),

NUREG-1575, Rev. 1, EPA 402-R-97-016, Rev. 1, August 2000 [Open]

23. T.S. LaGuardia et al., "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986 [Open]
24. W.J. Manion and T.S. LaGuardia, "Decommissioning Handbook," U.S.

Department of Energy, DOE/EV/10128-1, November 1980 [Open]

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Section 7, Page 3 of 3 TLG Services, LLC

7. REFERENCES (continued)
25. "Building Construction Cost with RSMeans Data 2023," Gordian, Rockland, Massachusetts [Open]
26. Decommissioning of Nuclear Power Reactors, Regulatory Guide 1.184, Nuclear Regulatory Commission, October 2013 [Open]
27. Standard Format and Content of Decommissioning Cost Estimates for Nuclear Power Reactors, Regulatory Guide 1.202, Nuclear Regulatory Commission, February 2005 [Open]
28. Project and Cost Engineers Handbook, Second Edition, p. 239, American Association of Cost Engineers, Marcel Dekker, Inc., New York, New York, 1984

[Open]

29. U.S. Department of Transportation, Title 49 of the Code of Federal Regulations, "Transportation," Parts 173 through 178 [Open]
30. Tri-State Motor Transit Company, Radioactive Materials Tariffs, TSMT 7000, January 2023. [Open}
31. J.C. Evans et al., "Long-Lived Activation Products in Reactor Materials" NUREG/CR-3474, Pacific Northwest Laboratory for the Nuclear Regulatory Commission, August 1984 [Open]
32. R.I. Smith, G.J. Konzek, W.E. Kennedy, Jr., "Technology, Safety and Costs of Decommissioning a Reference Pressurized Water Reactor Power Station,"

NUREG/CR-0130 and addenda, Pacific Northwest Laboratory for the Nuclear Regulatory Commission, June 1978 [Open Main Report] [Open Appendices]

33. H.D. Oak, et al., "Technology, Safety and Costs of Decommissioning a Reference Boiling Water Reactor Power Station," NUREG/CR-0672 and addenda, Pacific Northwest Laboratory for the Nuclear Regulatory Commission, June 1980

[Open Main Report] [Open Appendices]

34. SECY-00-0145, Integrated Rulemaking Plan for Nuclear Power Plant Decommissioning, June 2000 [Open]
35. "Microsoft Project Professional," Microsoft Corporation, Redmond, WA
36. Atomic Energy Act of 1954, (68 Stat. 919) [Open]

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix A, Page 1 of 4 TLG Services, LLC APPENDIX A UNIT COST FACTOR DEVELOPMENT 1 A: Unit Cost Factor Development

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix A, Page 2 of 4 TLG Services, LLC APPENDIX A UNIT COST FACTOR DEVELOPMENT Example:

Unit Factor for Removal of Contaminated Heat Exchanger < 3,000 lbs.

1.

SCOPE Heat exchangers weighing < 3,000 lbs. will be removed in one piece using a crane or small hoist. They will be disconnected from the inlet and outlet piping. The heat exchanger will be sent to the waste processing area.

2.

CALCULATIONS Activity Critical Act Activity Duration Duration ID Description (minutes)

(minutes)*

a Remove insulation 60 (b) b Mount pipe cutters 60 60 c

Install contamination controls 20 (b) d Disconnect inlet and outlet lines 60 60 e

Cap openings 20 (d) f Rig for removal 30 30 g

Unbolt from mounts 30 30 h

Remove contamination controls 15 15 i

Remove, wrap, send to waste processing area 60 60 Totals (Activity/Critical) 355 255 Duration adjustment(s):

+ Respiratory protection adjustment (50% of critical duration) 128

+ Radiation/ALARA adjustment (37% of critical duration) 95 Adjusted work duration 478

+ Protective clothing adjustment (30% of adjusted duration) 143 Productive work duration 621

+ Work break adjustment (8.33 % of productive duration) 52 Total work duration (minutes) 673

      • Total duration = 11.217 hour0.00251 days <br />0.0603 hours <br />3.587963e-4 weeks <br />8.25685e-5 months <br /> ***
  • alpha designators indicate activities that can be performed in parallel

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix A, Page 3 of 4 TLG Services, LLC APPENDIX A (continued)

3.

LABOR REQUIRED Duration Rate Crew Number (hours)

($/hour)

Cost Laborers 3.00 11.217

$52.10

$1,753.22 Craftsmen 2.00 11.217

$80.03

$1,795.39 Foreman 1.00 11.217

$82.29

$923.05 General Foreman 0.25 11.217

$84.55

$237.10 Fire Watch 0.05 11.217

$52.10

$29.22 Health Physics Technician 1.00 11.217

$50.85

$570.38 Total Labor Cost

$5,308.36

4.

EQUIPMENT & CONSUMABLES COSTS Equipment Costs none Consumables/Materials Costs Universal Polypropylene Sorbent 50 @ $0.72/sq ft [1]

$36.00 Tarpaulin, oil resistant, fire retardant 50 @ $0.44/sq ft [2]

$22.00 Gas torch consumables 1 @ $21.31 1 /hr [3]

$21.31 Subtotal cost of equipment and materials

$79.31 Overhead & profit on equipment and materials @ 16.73%

$13.27 Total costs, equipment & material

$92.58 TOTAL COST:

Removal of contaminated heat exchanger <3000 pounds:

$5,400.94 Total labor cost:

$5,308.36 Total equipment/material costs:

$92.58 Total craft labor man-hours required per unit:

81.88

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix A, Page 4 of 4 TLG Services, LLC

5.

NOTES AND REFERENCES Work difficulty factors were developed in conjunction with the Atomic Industrial Forums (now NEI) program to standardize nuclear decommissioning cost estimates and are delineated in Volume 1, Chapter 5 of the Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986.

References for equipment & consumables costs:

1. www.mcmaster.com online catalog, McMaster Carr Spill Control (7193T88)
2. R.S. Means (2023) Division 01 56, Section 13.60-0600, page 23
3. R.S. Means (2023) Division 01 54 33, Section 40-6360, page 744 Material and consumable costs were adjusted using the regional indices for Jefferson City, MO.

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix B, Page 1 of 7 TLG Services, LLC APPENDIX B UNIT COST FACTOR LISTING (DECON: Power Block Structures Only) 2 B: Unit Cost Factor Listing

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix B, Page 2 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit($)

TLG Services, LLC Removal of clean instrument and sampling tubing, $/linear foot 0.60 Removal of clean pipe 0.25 to 2 inches diameter, $/linear foot 6.28 Removal of clean pipe >2 to 4 inches diameter, $/linear foot 9.11 Removal of clean pipe >4 to 8 inches diameter, $/linear foot 18.46 Removal of clean pipe >14 to 20 inches diameter, $/linear foot 45.67 Removal of clean pipe >20 to 36 inches diameter, $/linear foot 67.18 Removal of clean pipe >36 inches diameter, $/linear foot 79.80 Removal of clean valve >2 to 4 inches 120.45 Removal of clean valve >4 to 8 inches 184.64 Removal of clean valve >8 to 14 inches 350.85 Removal of clean valve >14 to 20 inches 456.72 Removal of clean valve >20 to 36 inches 671.84 Removal of clean valve >36 inches 797.99 Removal of clean pipe hanger for small bore piping 41.11 Removal of clean pipe hanger for large bore piping 142.83 Removal of clean pump, <300 pound 312.62 Removal of clean pump, 300-1000 pound 882.17 Removal of clean pump, 1000-10,000 pound 3,453.50 Removal of clean pump, >10,000 pound 6,682.87 Removal of clean pump motor, 300-1000 pound 368.74 Removal of clean pump motor, 1000-10,000 pound 1,434.98 Removal of clean pump motor, >10,000 pound 3,228.72 Removal of clean heat exchanger <3000 pound 1,855.11 Removal of clean heat exchanger >3000 pound 4,675.28 Removal of clean feedwater heater/deaerator 13,174.84 Removal of clean moisture separator/reheater 27,077.94 Removal of clean tank, <300 gallons 401.98 Removal of clean tank, 300-3000 gallon 1,265.34 Removal of clean tank, >3000 gallons, $/square foot surface area 10.84

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix B, Page 3 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit($)

TLG Services, LLC Removal of clean electrical equipment, <300 pound 149.62 Removal of clean electrical equipment, 300-1000 pound 530.96 Removal of clean electrical equipment, 1000-10,000 pound 1,061.94 Removal of clean electrical equipment, >10,000 pound 2,536.52 Removal of clean electrical transformer < 30 tons 1,761.58 Removal of clean electrical equipment, <300 pound 169.17 Removal of clean electrical equipment, 300-1000 pound 600.35 Removal of clean electrical equipment, 1000-10,000 pound 1,200.70 Removal of clean electrical equipment, >10,000 pound 2,867.96 Removal of clean electrical transformer < 30 tons 1,991.75 Removal of clean electrical transformer > 30 tons 5,735.93 Removal of clean standby diesel generator, <100 kW 2,034.41 Removal of clean standby diesel generator, 100 kW to 1 MW 4,540.94 Removal of clean standby diesel generator, >1 MW 9,400.66 Removal of clean electrical cable tray, $/linear foot 15.92 Removal of clean electrical conduit, $/linear foot 6.96 Removal of clean mechanical equipment, <300 pound 169.17 Removal of clean mechanical equipment, 300-1000 pound 600.35 Removal of clean mechanical equipment, 1000-10,000 pound 1,200.70 Removal of clean mechanical equipment, >10,000 pound 2,867.96 Removal of clean HVAC equipment, <300 pound 204.56 Removal of clean HVAC equipment, 300-1000 pound 721.37 Removal of clean HVAC equipment, 1000-10,000 pound 1,437.68 Removal of clean HVAC equipment, >10,000 pound 2,867.96 Removal of clean HVAC ductwork, $/pound 0.63 Removal of contaminated instrument and sampling tubing, $/linear foot 1.78 Removal of contaminated pipe 0.25 to 2 inches diameter, $/linear foot 25.82 Removal of contaminated pipe >2 to 4 inches diameter, $/linear foot 44.29 Removal of contaminated pipe >4 to 8 inches diameter, $/linear foot 71.40 Removal of contaminated pipe >8 to 14 inches diameter, $/linear foot 138.98

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix B, Page 4 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit($)

TLG Services, LLC Removal of contaminated pipe >14 to 20 inches diameter, $/linear foot 166.71 Removal of contaminated pipe >20 to 36 inches diameter, $/linear foot 230.09 Removal of contaminated pipe >36 inches diameter, $/linear foot 271.62 Removal of contaminated valve >2 to 4 inches 531.15 Removal of contaminated valve >4 to 8 inches 648.16 Removal of contaminated valve >8 to 14 inches 1,322.05 Removal of contaminated valve >14 to 20 inches 1,678.96 Removal of contaminated valve >20 to 36 inches 2,233.24 Removal of contaminated valve >36 inches 2,648.50 Removal of contaminated pipe hanger for small bore piping 169.92 Removal of contaminated pipe hanger for large bore piping 561.77 Removal of contaminated pump, <300 pound 1,158.39 Removal of contaminated pump, 300-1000 pound 2,744.26 Removal of contaminated pump, 1000-10,000 pound 8,978.74 Removal of contaminated pump, >10,000 pound 21,870.01 Removal of contaminated pump motor, 300-1000 pound 1,174.62 Removal of contaminated pump motor, 1000-10,000 pound 3,661.60 Removal of contaminated pump motor, >10,000 pound 8,220.81 Removal of contaminated heat exchanger <3000 pound 5,400.94 Removal of contaminated heat exchanger >3000 pound 15,681.18 Removal of contaminated tank, <300 gallons 1,927.64 Removal of contaminated tank, >300 gallons, $/square foot 38.37 Removal of contaminated electrical equipment, <300 pound 892.43 Removal of contaminated electrical equipment, 300-1000 pound 2,227.72 Removal of contaminated electrical equipment, 1000-10,000 pound 4,290.73 Removal of contaminated electrical equipment, >10,000 pound 8,488.19 Removal of contaminated electrical cable tray, $/linear foot 43.18 Removal of contaminated electrical conduit, $/linear foot 21.09 Removal of contaminated mechanical equipment, <300 pound 992.80 Removal of contaminated mechanical equipment, 300-1000 pound 2,460.28

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix B, Page 5 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit($)

TLG Services, LLC Removal of contaminated mechanical equipment, 1000-10,000 pound 4,730.94 Removal of contaminated mechanical equipment, >10,000 pound 8,488.19 Removal of contaminated HVAC equipment, <300 pound 992.80 Removal of contaminated HVAC equipment, 300-1000 pound 2,460.28 Removal of contaminated HVAC equipment, 1000-10,000 pound 4,730.94 Removal of contaminated HVAC equipment, >10,000 pound 8,488.19 Removal of contaminated HVAC ductwork, $/pound 2.55 Removal/plasma arc cut of contaminated thin metal components, $/linear in.

4.88 Additional decontamination of surface by washing, $/square foot 9.55 Additional decontamination of surfaces by hydrolasing, $/square foot 46.23 Decontamination rig hook up and flush, $/ 250 foot length 8,369.51 Chemical flush of components/systems, $/gallon 29.29 Removal of clean standard reinforced concrete, $/cubic yard 77.74 Removal of grade slab concrete, $/cubic yard 88.39 Removal of clean concrete floors, $/cubic yard 443.76 Removal of sections of clean concrete floors, $/cubic yard 1,336.96 Removal of clean heavily rein concrete w/#9 rebar, $/cubic yard 112.15 Removal of contaminated heavily rein concrete w/#9 rebar, $/cubic yard 2,614.89 Removal of clean heavily rein concrete w/#18 rebar, $/cubic yard 151.92 Removal of contaminated heavily rein concrete w/#18 rebar, $/cubic yard 3,460.01 Removal heavily rein concrete w/#18 rebar & steel embedments, $/cubic yard 607.92 Removal of below-grade suspended floors, $/cubic yard 212.95 Removal of clean monolithic concrete structures, $/cubic yard 1,122.15 Removal of contaminated monolithic concrete structures, $/cubic yard 2,602.37 Removal of clean foundation concrete, $/cubic yard 881.30 Removal of contaminated foundation concrete, $/cubic yard 2,424.29 Explosive demolition of bulk concrete, $/cubic yard 60.79 Removal of clean hollow masonry block wall, $/cubic yard 30.84 Removal of contaminated hollow masonry block wall, $/cubic yard 79.42 Removal of clean solid masonry block wall, $/cubic yard 30.84

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix B, Page 6 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit($)

TLG Services, LLC Removal of contaminated solid masonry block wall, $/cubic yard 79.42 Backfill of below-grade voids, $/cubic yard 37.05 Removal of subterranean tunnels/voids, $/linear foot 132.38 Placement of concrete for below-grade voids, $/cubic yard 177.58 Excavation of clean material, $/cubic yard 3.41 Excavation of contaminated material, $/cubic yard 49.89 Removal of clean concrete rubble (tipping fee included), $/cubic yard 29.51 Removal of contaminated concrete rubble, $/cubic yard 31.53 Removal of building by volume, $/cubic foot 0.42 Removal of clean building metal siding, $/square foot 1.59 Removal of contaminated building metal siding, $/square foot 5.11 Removal of standard asphalt roofing, $/square foot 2.80 Removal of transite panels, $/square foot 2.73 Scarifying contaminated concrete surfaces (drill & spall), $/square foot 15.13 Scabbling contaminated concrete floors, $/square foot 9.25 Scabbling contaminated concrete walls, $/square foot 24.52 Scabbling contaminated ceilings, $/square foot 84.23 Scabbling structural steel, $/square foot 7.71 Removal of clean overhead crane/monorail < 10 ton capacity 857.58 Removal of contaminated overhead crane/monorail < 10 ton capacity 2,297.48 Removal of clean overhead crane/monorail >10-50 ton capacity 2,058.22 Removal of contaminated overhead crane/monorail >10-50 ton capacity 5,513.02 Removal of polar crane > 50 ton capacity 8,615.54 Removal of gantry crane > 50 ton capacity 32,025.59 Removal of structural steel, $/pound 0.32 Removal of clean steel floor grating, $/square foot 6.41 Removal of contaminated steel floor grating, $/square foot 17.73 Removal of clean free standing steel liner, $/square foot 16.25 Removal of contaminated free standing steel liner, $/square foot 44.84 Removal of clean concrete-anchored steel liner, $/square foot 8.13

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix B, Page 7 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit($)

TLG Services, LLC Removal of contaminated concrete-anchored steel liner, $/square foot 52.28 Placement of scaffolding in clean areas, $/square foot 16.96 Placement of scaffolding in contaminated areas, $/square foot 28.62 Landscaping with topsoil, $/acre 27,052.63 Cost of CPC B-88 LSA box & preparation for use 2,132.80 Cost of CPC B-25 LSA box & preparation for use 1,832.59 Cost of CPC B-12V 12 gauge LSA box & preparation for use 1,662.57 Cost of CPC B-144 LSA box & preparation for use 10,445.35 Cost of LSA drum & preparation for use 380.87 Cost of cask liner for CNSI 8 120A cask (resins) 14,624.70 Cost of cask liner for CNSI 8 120A cask (filters) 10,523.30 Decontamination of surfaces with vacuuming, $/square foot 1.03

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix C, Page 1 of 10 TLG Services, LLC APPENDIX C DETAILED COST ANALYSIS DECON with LOW-LEVEL RADIOACTIVE WASTE PROCESSING 3C: DECON Decommissioning cost Estimate with Low-Level Radioactive Waste Processing

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix C, Page 2 of 10 TLG Services, LLC Table C Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:13:35 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours PERIOD 1a - Shutdown through Transition Period 1a Direct Decommissioning Activities 1a.1.1 Prepare preliminary decommissioning cost 206 31 237 237 1,300 1a.1.2 Notification of Cessation of Operations a

1a.1.3 Remove fuel & source material n/a 1a.1.4 Notification of Permanent Defueling a

1a.1.5 Deactivate plant systems & process waste a

1a.1.6 Prepare and submit PSDAR 317 48 365 365 2,000 1a.1.7 Review plant dwgs & specs.

730 110 840 840 4,600 1a.1.8 Perform detailed rad survey a

1a.1.9 Estimate by-product inventory 159 24 183 183 1,000 1a.1.10 End product description 159 24 183 183 1,000 1a.1.11 Detailed by-product inventory 206 31 237 237 1,300 1a.1.12 Define major work sequence 1,190 179 1,369 1,369 7,500 1a.1.13 Perform SER and EA 492 74 566 566 3,100 1a.1.14 Prepare/submit Defueled Technical Specifications 1,190 179 1,369 1,369 7,500 1a.1.15 Perform Site-Specific Cost Study 794 119 913 913 5,000 1a.1.16 Prepare/submit Irradiated Fuel Management Plan 159 24 183 183 1,000 Activity Specifications 1a.1.17.1 Plant & temporary facilities 781 117 898 808 90 4,920 1a.1.17.2 Plant systems 661 99 761 684 76 4,167 1a.1.17.3 NSSS Decontamination Flush 79 12 91 91 500 1a.1.17.4 Reactor internals 1,127 169 1,296 1,296 7,100 1a.1.17.5 Reactor vessel 1,032 155 1,186 1,186 6,500 1a.1.17.6 Biological shield 79 12 91 91 500 1a.1.17.7 Steam generators 495 74 569 569 3,120 1a.1.17.8 Reinforced concrete 254 38 292 146 146 1,600 1a.1.17.9 Main Turbine 63 10 73 73 400 1a.1.17.10 Main Condensers 63 10 73 73 400 1a.1.17.11 Plant structures & buildings 495 74 569 285 285 3,120 1a.1.17.12 Waste management 730 110 840 840 4,600 1a.1.17.13 Facility & site closeout 143 21 164 82 82 900 1a.1.17 Total 6,004 901 6,904 6,080 825 37,827 Planning & Site Preparations 1a.1.18 Prepare dismantling sequence 381 57 438 438 2,400 1a.1.19 Plant prep. & temp. svces 4,000 600 4,600 4,600 1a.1.20 Design water clean-up system 222 33 256 256 1,400 1a.1.21 Rigging/Cont. Cntrl Envlps/tooling/etc.

2,800 420 3,220 3,220 1a.1.22 Procure casks/liners & containers 195 29 225 225 1,230 1a.1 Subtotal Period 1a Activity Costs 19,205 2,881 22,086 21,261 825 78,157 Period 1a Collateral Costs 1a.3.1 Spent Fuel Capital and Transfer 10,080 1,512 11,592 11,592 1a.3 Subtotal Period 1a Collateral Costs 10,080 1,512 11,592 11,592 Period 1a Period-Dependent Costs 1a.4.1 Insurance 3,972 397 4,370 4,370 1a.4.2 Property taxes 120 12 132 132 1a.4.3 Health physics supplies 888 222 1,110 1,110 1a.4.4 Heavy equipment rental 657 99 755 755 1a.4.5 Disposal of DAW generated 12 7

36 11 67 67 610 12,190 20 1a.4.6 Plant energy budget 2,053 308 2,361 2,361 1a.4.7 NRC Fees 1,321 132 1,453 1,453 1a.4.8 Emergency Planning Fees 1,620 162 1,782 1,782 1a.4.9 INPO Fees 358 54 411 411 1a.4.10 Spent Fuel Pool O&M 988 148 1,136 1,136 1a.4.11 ISFSI Operating Costs 127 19 146 146 1a.4.12 Corporate Allocations 1,000 100 1,100 1,100 1a.4.13 Security Staff Cost 15,699 2,355 18,054 18,054 251,680 1a.4.14 Utility Staff Cost 37,678 5,652 43,329 43,329 422,240 1a.4 Subtotal Period 1a Period-Dependent Costs 1,545 12 7

36 64,936 9,670 76,207 73,142 3,064 610 12,190 20 673,920 1a.0 TOTAL PERIOD 1a COST 1,545 12 7

36 94,221 14,063 109,884 94,403 14,656 825 610 12,190 20 752,077

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix C, Page 3 of 10 TLG Services, LLC Table C Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:13:35 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours PERIOD 1b - Decommissioning Preparations Period 1b Direct Decommissioning Activities Detailed Work Procedures 1b.1.1.1 Plant systems 751 113 864 778 86 4,733 1b.1.1.2 NSSS Decontamination Flush 159 24 183 183 1,000 1b.1.1.3 Reactor internals 397 60 456 456 2,500 1b.1.1.4 Remaining buildings 214 32 246 62 185 1,350 1b.1.1.5 CRD cooling assembly 159 24 183 183 1,000 1b.1.1.6 CRD housings & ICI tubes 159 24 183 183 1,000 1b.1.1.7 Incore instrumentation 159 24 183 183 1,000 1b.1.1.8 Reactor vessel 576 86 663 663 3,630 1b.1.1.9 Facility closeout 190 29 219 110 110 1,200 1b.1.1.10 Missile shields 71 11 82 82 450 1b.1.1.11 Biological shield 190 29 219 219 1,200 1b.1.1.12 Steam generators 730 110 840 840 4,600 1b.1.1.13 Reinforced concrete 159 24 183 91 91 1,000 1b.1.1.14 Main Turbine 248 37 285 285 1,560 1b.1.1.15 Main Condensers 248 37 285 285 1,560 1b.1.1.16 Auxiliary building 433 65 498 448 50 2,730 1b.1.1.17 Reactor building 433 65 498 448 50 2,730 1b.1.1 Total 5,276 791 6,068 4,927 1,141 33,243 1b.1.2 Decon primary loop 973 486 1,459 1,459 1,067 1b.1 Subtotal Period 1b Activity Costs 973 5,276 1,278 7,527 6,386 1,141 1,067 33,243 Period 1b Additional Costs 1b.2.1 Spent Fuel Pool Isolation 14,330 2,150 16,480 16,480 1b.2.2 Site Characterization 3,198 959 4,158 4,158 19,100 7,852 1b.2 Subtotal Period 1b Additional Costs 17,529 3,109 20,638 20,638 19,100 7,852 Period 1b Collateral Costs 1b.3.1 Decon equipment 1,193 179 1,371 1,371 1b.3.2 DOC staff relocation expenses 1,641 246 1,887 1,887 1b.3.3 Process decommissioning water waste 49 35 87 144 77 392 392 283 16,989 55 1b.3.4 Process decommissioning chemical flush waste 2

92 369 2,012 569 3,044 3,044 788 83,917 147 1b.3.5 Small tool allowance 2

0 3

3 1b.3.6 Pipe cutting equipment 1,400 210 1,610 1,610 1b.3.7 Decon rig 2,451 368 2,819 2,819 1b.3.8 Spent Fuel Capital and Transfer 5,040 756 5,796 5,796 1b.3 Subtotal Period 1b Collateral Costs 3,696 1,402 127 456 2,156 6,681 2,405 16,922 11,126 5,796 283 788 100,906 203 Period 1b Period-Dependent Costs 1b.4.1 Decon supplies 43 11 54 54 1b.4.2 Insurance 2,002 200 2,203 2,203 1b.4.3 Property taxes 60 6

66 66 1b.4.4 Health physics supplies 502 126 628 628 1b.4.5 Heavy equipment rental 331 50 381 381 1b.4.6 Disposal of DAW generated 7

4 21 7

39 39 360 7,197 12 1b.4.7 Plant energy budget 2,070 310 2,380 2,380 1b.4.8 NRC Fees 400 40 440 440 1b.4.9 Emergency Planning Fees 817 82 899 899 1b.4.10 Spent Fuel Pool O&M 498 75 573 573 1b.4.11 ISFSI Operating Costs 64 10 73 73 1b.4.12 Corporate Allocations 504 50 555 555 1b.4.13 Security Staff Cost 7,914 1,187 9,101 9,101 126,874 1b.4.14 DOC Staff Cost 7,234 1,085 8,319 8,319 63,961 1b.4.15 Utility Staff Cost 19,087 2,863 21,950 21,950 213,904 1b.4 Subtotal Period 1b Period-Dependent Costs 43 833 7

4 21 40,652 6,101 47,662 46,117 1,545 360 7,197 12 404,740 1b.0 TOTAL PERIOD 1b COST 4,711 2,236 134 460 2,178 70,137 12,893 92,748 84,266 7,341 1,141 643 788 108,103 20,381 445,835 PERIOD 1 TOTALS 4,711 3,780 146 467 2,214 164,358 26,956 202,633 178,670 21,997 1,966 1,253 788 120,293 20,401 1,197,911

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix C, Page 4 of 10 TLG Services, LLC Table C Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:13:35 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours PERIOD 2a - Large Component Removal Period 2a Direct Decommissioning Activities Nuclear Steam Supply System Removal 2a.1.1.1 Reactor Coolant Piping 244 244 39 136 768 399 1,830 1,830 2,046 142,726 6,863 2a.1.1.2 Pressurizer Relief Tank 41 34 11 38 217 90 432 432 578 40,338 1,077 2a.1.1.3 Reactor Coolant Pumps & Motors 124 125 185 267 1,483 523 2,708 2,708 3,386 816,140 4,188 100 2a.1.1.4 Pressurizer 80 839 208 1,638 545 3,310 3,310 3,739 293,734 1,666 1,875 2a.1.1.5 Steam Generators 8,305 4,689 3,380 3,735 10,171 6,155 36,436 36,436 40,262 23,217 3,619,368 23,279 3,500 2a.1.1.6 Retired Steam Generator Units 3,353 3,319 3,735 9,877 3,863 24,146 24,146 40,262 22,546 3,398,523 10,852 2,250 2a.1.1.7 CRDMs/ICIs/Service Structure Removal 207 353 230 141 783 432 2,145 2,145 3,881 145,494 7,976 2a.1.1.8 Reactor Vessel Internals 112 6,004 12,696 1,844 18,156 393 17,331 56,535 56,535 2,764 1,230 393 336,142 32,573 1,461 2a.1.1.9 Vessel & Internals GTCC Disposal 13,035 1,955 14,990 14,990 2,217 433,180 2a.1.1.10 Reactor Vessel 141 7,737 3,180 1,898 5,983 393 10,193 29,525 29,525 13,715 973,586 32,573 1,461 2a.1.1 Totals 870 22,883 25,222 11,231 7,470 62,111 785 41,486 172,058 172,058 80,523 75,872 1,230 393 2,217 10,199,230 121,047 10,648 Removal of Major Equipment 2a.1.2 Main Turbine/Generator 686 398 56 874 885 572 3,471 3,471 4,921 2,740 469,360 9,888 2a.1.3 Main Condensers 1,923 226 209 1,026 1,099 963 5,446 5,446 7,701 3,216 550,847 27,762 Cascading Costs from Clean Building Demolition 2a.1.4.1 Reactor 612 92 704 704 4,832 2a.1.4.2 Auxiliary 318 48 366 366 2,113 2a.1.4.3 Hot Machine Shop 1

0 1

1 7

2a.1.4.4 Radwaste 61 9

70 70 387 2a.1.4.5 Fuel Building 129 19 149 149 795 2a.1.4 Totals 1,121 168 1,290 1,290 8,134 Disposal of Plant Systems 2a.1.5.1 100 Aux.Bldg Non-System Specific RCA 920 15 80 917 381 2,313 2,313 7,629 309,812 13,471 2a.1.5.2 100 Auxiliary Bldg Non-System Specific 151 6

15 57 96 73 399 399 474 282 37,164 2,282 2a.1.5.3 AB - Main Steam 366 55 420 420 5,833 2a.1.5.4 AB - Main Steam RCA 103 4

23 259 68 458 458 2,156 87,550 1,515 2a.1.5.5 AC - Main Turbine 361 54 415 415 5,641 2a.1.5.6 AD - Condensate 401 60 461 461 6,144 2a.1.5.7 AE - Feedwater 275 41 316 316 4,271 2a.1.5.8 AF - Feedwater Heater Extraction 337 51 388 388 5,352 2a.1.5.9 AK - Condensate Demineralizer 125 19 143 143 1,944 2a.1.5.10 AL - Auxiliary Feedwater 54 8

63 63 852 2a.1.5.11 AQ - Condensate & Feedwater Chem Addtn 30 5

35 35 468 2a.1.5.12 BM - Steam Generator Blowdown 158 6

17 107 66 75 429 429 892 191 48,463 2,394 2a.1.5.13 BM - Steam Generator Blowdown - RCA 491 8

43 494 204 1,240 1,240 4,109 166,857 7,066 2a.1.5.14 BN - Borated Refueling Water Storage 457 22 78 663 183 273 1,675 1,675 5,512 533 257,802 6,939 2a.1.5.15 CA - Steam Seal 29 4

33 33 455 2a.1.5.16 CB - Main Turbine Lube Oil 82 12 95 95 1,207 2a.1.5.17 CC - Generator Hydrogen Seal & CO2 13 2

15 15 198 2a.1.5.18 CD - Generator Seal Oil 19 3

22 22 287 2a.1.5.19 CE - Stator Cooling Water 16 2

19 19 241 2a.1.5.20 CF - Lube Oil Storage Xfer & Prfication 53 8

61 61 812 2a.1.5.21 CG - Condenser Air Removal 43 6

49 49 657 2a.1.5.22 CH - Main Turbine Control Oil 85 13 97 97 1,219 2a.1.5.23 DA - Circulating Water 473 71 544 544 7,502 2a.1.5.24 DB - Cooling Tower Makeup & Blowdown 80 12 92 92 1,260 2a.1.5.25 DD - Cooling Water Chemical Control Sys 71 11 81 81 1,084 2a.1.5.26 DD - Cooling Wtr Chem Control RCA 361 7

37 427 161 993 993 3,555 144,376 4,951 2a.1.5.27 EJ - Residual Heat Removal 524 57 119 330 828 411 2,269 2,269 2,744 2,413 265,386 8,042 2a.1.5.28 EM - High Pressure Coolant Injection 438 18 38 158 224 197 1,074 1,074 1,315 648 95,068 6,633 2a.1.5.29 EN - Containment Spray 288 6

32 364 132 821 821 3,026 122,874 4,134 2a.1.5.30 EP - Accumulator Safety Injection 231 11 27 192 98 116 676 676 1,599 283 83,200 3,478 2a.1.5.31 FA - Auxiliary Steam Generator 32 5

37 37 521 2a.1.5.32 FB - Auxiliary Steam 133 20 152 152 2,106 2a.1.5.33 FB - Auxiliary Steam RCA 109 2

9 98 43 260 260 816 33,148 1,537 2a.1.5.34 FC - Auxiliary Turbines 87 13 100 100 1,320 2a.1.5.35 FE - Auxiliary Steam Chemical Addition 7

1 8

8 105 2a.1.5.36 GE - Turbine Building HVAC 240 36 276 276 3,957 2a.1.5.37 GS - Containment Hydrogen Control 101 4

11 79 36 48 280 280 658 104 33,502 1,559 2a.1.5.38 HE - Boron Recycle 529 668 39 80 313 487 616 2,733 2,733 2,600 1,411 196,130 16,660 2a.1.5.39 HF - Secondary Liquid Waste 975 1,319 87 185 744 1,104 1,241 5,655 5,655 6,186 3,203 456,359 31,896

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix C, Page 5 of 10 TLG Services, LLC Table C Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:13:35 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours 2a.1.5.40 JA - Auxiliary Oil & Transfer 43 7

50 50 690 2a.1.5.41 KS - Bulk Chemical Storage 122 13 68 775 158 1,136 1,136 6,449 261,890 1,825 2a.1.5.42 LE - Oily Waste 246 37 282 282 3,865 2a.1.5.43 LE - Oily Waste RCA 313 4

24 271 123 735 735 2,256 91,628 4,296 2a.1.5.44 Turbine Bldg Non-System Specific 1,031 155 1,185 1,185 15,405 2a.1.5 Totals 1,504 11,484 311 885 6,248 3,123 5,032 28,587 23,148 5,440 51,976 9,068 2,691,208 192,076 2a.1.6 Scaffolding in support of decommissioning 2,067 27 18 164 37 556 2,871 2,871 1,233 109 62,391 36,741 2a.1 Subtotal Period 2a Activity Costs 2,374 40,164 26,185 12,400 15,782 67,255 785 48,778 213,724 208,284 5,440 146,354 91,005 1,230 393 2,217 13,973,040 395,647 10,648 Period 2a Additional Costs 2a.2.1 Remedial Action Surveys 1,824 547 2,372 2,372 35,877 2a.2 Subtotal Period 2a Additional Costs 1,824 547 2,372 2,372 35,877 Period 2a Collateral Costs 2a.3.1 Process decommissioning water waste 214 152 382 634 338 1,719 1,719 1,246 74,741 243 2a.3.2 Process decommissioning chemical flush waste 1

48 192 371 127 739 739 410 43,711 77 2a.3.3 Small tool allowance 449 67 516 465 52 2a.3.4 Spent Fuel Capital and Transfer 18,270 2,741 21,011 21,011 2a.3.5 On-site survey and release of 60.87 tons clean metallic waste 111 11 122 122 2a.3 Subtotal Period 2a Collateral Costs 215 449 200 574 1,004 18,381 3,284 24,107 3,045 21,011 52 1,656 118,451 320 Period 2a Period-Dependent Costs 2a.4.1 Decon supplies 147 37 184 184 2a.4.2 Insurance 1,169 117 1,286 1,286 2a.4.3 Property taxes 207 21 228 228 2a.4.4 Health physics supplies 5,120 1,280 6,399 6,399 2a.4.5 Heavy equipment rental 3,836 575 4,411 4,411 2a.4.6 Disposal of DAW generated 132 74 385 121 712 712 6,501 130,017 212 2a.4.7 Plant energy budget 3,366 505 3,871 3,871 2a.4.8 NRC Fees 1,246 125 1,370 1,370 2a.4.9 Emergency Planning Fees 1,728 173 1,900 1,900 2a.4.10 Spent Fuel Pool O&M 1,706 256 1,962 1,962 2a.4.11 ISFSI Operating Costs 218 33 251 251 2a.4.12 Corporate Allocations 1,726 173 1,899 1,899 2a.4.13 Security Staff Cost 25,225 3,784 29,008 29,008 387,735 2a.4.14 DOC Staff Cost 30,559 4,584 35,143 35,143 272,850 2a.4.15 Utility Staff Cost 46,358 6,954 53,311 53,311 508,004 2a.4 Subtotal Period 2a Period-Dependent Costs 147 8,955 132 74 385 113,507 18,735 141,936 137,823 4,113 6,501 130,017 212 1,168,590 2a.0 TOTAL PERIOD 2a COST 2,737 49,568 26,517 13,049 15,782 68,645 134,497 71,344 382,138 351,523 25,124 5,491 146,354 99,162 1,230 393 2,217 14,221,500 432,056 1,179,237 PERIOD 2b - Site Decontamination Period 2b Direct Decommissioning Activities Disposal of Plant Systems 2b.1.1.1 200 Reactor Bldg Non-System Specific 120 4

10 32 63 53 283 283 269 186 22,727 1,760 2b.1.1.2 200 Reactor Bldg Non-System Specific RCA 752 9

50 573 282 1,667 1,667 4,768 193,612 10,425 2b.1.1.3 300 Control Bldg Non-System Specific 236 4

22 257 101 621 621 2,139 86,849 3,413 2b.1.1.4 300 Control Bldg Non-System Specific Cln 1,836 275 2,111 2,111 29,076 2b.1.1.5 700 Radwaste Bldg Non-Sys Specific RCA 1,514 25 133 1,525 630 3,826 3,826 12,684 515,103 21,919 2b.1.1.6 700 Radwaste Bldg Non-System Specific 243 11 26 85 170 121 655 655 705 497 60,190 3,653 2b.1.1.7 AN - Demineralized Wtr Storage & Xfer 208 31 239 239 3,283 2b.1.1.8 AN - Demineralized Wtr Strg & Xfer RCA 53 1

3 38 19 114 114 314 12,759 740 2b.1.1.9 AP -HCST/Condensate Stor.& Transfr 275 41 316 316 4,018 2b.1.1.10 BB - Reactor Coolant System 453 39 82 218 577 306 1,674 1,674 1,812 1,685 180,839 7,074 2b.1.1.11 BG - Chemical & Volume Control 1,143 1,276 120 237 593 1,696 1,451 6,515 6,515 4,931 4,928 515,455 28,147 2b.1.1.12 BL - Reactor Makeup Water 408 24 52 232 293 220 1,229 1,229 1,928 850 132,796 6,136 2b.1.1.13 DE - Intake & Water Treatment 166 25 191 191 2,517 2b.1.1.14 DE - Intake & Water Treatment RCA 331 24 125 1,433 319 2,232 2,232 11,923 484,206 5,014 2b.1.1.15 EA - Service Water 197 30 227 227 3,145 2b.1.1.16 EA - Service Water RCA 59 2

13 150 39 264 264 1,248 50,693 839 2b.1.1.17 EB - Closed Cooling Water 80 12 92 92 1,267 2b.1.1.18 EF - Essential Service Water 458 69 527 527 7,244 2b.1.1.19 EF - Essential Service Water RCA 263 11 56 640 171 1,141 1,141 5,326 216,287 3,862 2b.1.1.20 EG - Component Cooling Water RCA 336 50 386 386 5,335 2b.1.1.21 GA - Plant Heating 120 18 138 138 1,912

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix C, Page 6 of 10 TLG Services, LLC Table C Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:13:35 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours 2b.1.1.22 GA - Plant Heating RCA 126 1

7 77 44 255 255 638 25,924 1,765 2b.1.1.23 GB - Central Chilled Water 113 17 130 130 1,803 2b.1.1.24 GB - Central Chilled Water RCA 34 0

2 22 12 71 71 187 7,591 482 2b.1.1.25 GD - Essential Serv Wtr Pumphouse HVAC 25 4

29 29 427 2b.1.1.26 GF - Miscellaneous Building HVAC 155 4

21 245 79 504 504 2,034 82,602 2,026 2b.1.1.27 GH - Radwaste Building HVAC 240 7

29 291 34 117 717 717 2,425 98 104,702 3,455 2b.1.1.28 GK - Control Building HVAC 231 35 266 266 3,959 2b.1.1.29 GL - Auxiliary Building HVAC 592 15 62 609 78 270 1,625 1,625 5,064 228 220,197 8,491 2b.1.1.30 GM - Diesel Generator Building HVAC 40 6

46 46 695 2b.1.1.31 GN - Containment Cooling 661 27 101 886 220 371 2,267 2,267 7,367 643 340,122 9,601 2b.1.1.32 GP - Containment Intgratd Leak Rate Test 52 1

6 70 24 153 153 580 23,570 750 2b.1.1.33 GR - Containment Atmospheric Control 26 3

13 130 14 32 219 219 1,086 41 46,686 392 2b.1.1.34 GT - Containment Purge HVAC 155 7

27 234 58 93 574 574 1,948 170 89,946 2,259 2b.1.1.35 HA - Gaseous Radwaste 476 25 55 334 233 238 1,360 1,360 2,782 666 156,216 7,037 2b.1.1.36 HB - Liquid Radwaste 1,055 1,161 80 162 668 949 1,187 5,263 5,263 5,560 2,745 402,251 30,903 2b.1.1.37 HC - Solid Radwaste 495 37 78 254 511 305 1,681 1,681 2,114 1,487 180,874 7,445 2b.1.1.38 HD - Decontamination 138 6

17 118 59 70 409 409 983 171 50,973 2,051 2b.1.1.39 JE - Emergency Fuel Oil 86 13 99 99 1,260 2b.1.1.40 KA - Compressed Air 262 39 301 301 4,187 2b.1.1.41 KA - Compressed Air RCA 169 2

8 96 58 334 334 801 32,538 2,339 2b.1.1.42 KB - Breathing Air 33 5

38 38 516 2b.1.1.43 KB - Breathing Air RCA 26 0

1 9

8 43 43 71 2,874 402 2b.1.1.44 KC - Fire Protection 514 77 591 591 8,376 2b.1.1.45 KC - Fire Protection RCA 530 9

46 530 220 1,335 1,335 4,411 179,151 7,064 2b.1.1.46 KD - Domestic Water 239 36 275 275 3,837 2b.1.1.47 KD - Domestic Water RCA 34 0

3 30 13 80 80 247 10,039 459 2b.1.1.48 KE - Fuel Handling & Storage Rctor vssl 25 4

13 80 54 34 210 210 661 158 36,889 375 2b.1.1.49 KH - Service Gas (CO2 N2 H2 & O2) 76 11 87 87 1,226 2b.1.1.50 KH - Service Gas (CO2 N2 H2 & O2) RCA 333 5

25 292 131 787 787 2,433 98,813 4,481 2b.1.1.51 KJ - Standby Diesel Engine 454 68 523 523 6,749 2b.1.1.52 LA - Sanitary Drains 61 9

70 70 972 2b.1.1.53 LA - Sanitary Drains RCA 140 3

13 153 60 369 369 1,273 51,684 1,811 2b.1.1.54 LB - Roof Drains 81 12 93 93 1,276 2b.1.1.55 LB - Roof Drains RCA 190 4

22 257 90 563 563 2,139 86,858 2,694 2b.1.1.56 LD - Chemical & Detergent Waste 92 159 6

13 61 73 116 519 519 504 211 33,951 3,490 2b.1.1.57 LF - Floor & Equipment Drains 1,970 125 253 449 1,962 1,101 5,861 5,861 3,739 5,724 516,484 29,320 2b.1.1.58 RM - Process Sampling & Analysis 182 9

16 79 84 82 453 453 661 240 42,525 2,774 2b.1.1.59 SJ - Nuclear Sampling 106 6

11 51 65 53 292 292 423 184 29,191 1,620 2b.1.1.60 UB - Servces Stores Site Security Bldg 245 37 282 282 3,815 2b.1.1.61 Yard Non-System Specific 41 6

47 47 603 2b.1.1 Totals 2,290 20,061 662 1,814 11,802 7,193 9,449 53,270 46,167 7,104 98,179 20,912 5,324,166 323,967 2b.1.2 Scaffolding in support of decommissioning 2,584 34 23 205 46 695 3,588 3,588 1,541 136 77,989 45,926 Decontamination of Site Buildings 2b.1.3.1 Reactor 1,628 2,446 165 1,639 721 8,443 3,907 18,949 18,949 5,995 57,454 2,681,023 55,906 2b.1.3.2 Auxiliary 842 489 28 255 247 457 736 3,053 3,053 2,058 6,938 412,089 19,438 2b.1.3.3 Communication Corridor - Contaminated 19 8

1 5

2 10 15 59 59 17 152 7,854 395 2b.1.3.4 Hot Machine Shop 23 17 1

6 12 20 79 79 188 8,892 597 2b.1.3.5 RAM Storage Building 58 20 1

13 2

25 42 162 162 19 389 19,136 1,162 2b.1.3.6 Radioactive and Personnel Tunnel 8

16 0

4 7

10 44 44 106 5,022 335 2b.1.3.7 Radwaste 448 236 14 133 102 240 380 1,552 1,552 844 3,681 208,617 10,005 2b.1.3.8 Radwaste Drum Storage 50 24 1

15 8

27 41 167 167 66 413 22,243 1,093 2b.1.3.9 Reactor Head Assembly Building 44 22 66 66 691 2b.1.3.10 Steam Generator Replacement Bldgs 331 165 496 496 4,358 2b.1.3 Totals 3,450 3,257 211 2,070 1,082 9,219 5,338 24,628 24,628 8,999 69,322 3,364,877 93,979 2b.1.4 Prepare/submit License Termination Plan 650 98 748 748 4,096 2b.1.5 Receive NRC approval of termination plan a

2b.1 Subtotal Period 2b Activity Costs 5,740 25,902 907 3,907 13,089 16,459 650 15,580 82,234 75,130 7,104 108,720 90,370 8,767,032 463,873 4,096 Period 2b Additional Costs 2b.2.1 Remedial Action Surveys 2,401 720 3,121 3,121 47,209 2b.2.2 Sanitary Treatment Lagoon 7

92 235 540 181 1,054 1,054 4,608 392,140 423 2b.2.3 Cooling Tower Asbestos Panel Removal 6,512 305 641 1,119 8,576 8,576 71,419 2b.2.4 Operational Equipment 22 103 866 148 1,139 1,139 11,700 292,500 32 2b.2.5 Retired Reactor Closure Head 151 847 1,330 1,110 599 4,037 4,037 2,764 338,540 3,157 2,000 2b.2.6 Spent Fuel Pool Legacy Waste 108 163 67 2,617 14 710 3,680 3,680 250 14,900 1,333 53

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix C, Page 7 of 10 TLG Services, LLC Table C Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:13:35 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours 2b.2 Subtotal Period 2b Additional Costs 6,778 1,124 2,039 866 4,267 3,056 3,477 21,606 13,031 8,576 11,700 7,372 250 1,038,080 123,574 2,053 Period 2b Collateral Costs 2b.3.1 Process decommissioning water waste 187 136 342 568 300 1,533 1,533 1,116 66,951 218 2b.3.2 Process decommissioning chemical flush waste 4

157 626 1,209 414 2,409 2,409 1,338 142,540 250 2b.3.3 Small tool allowance 583 87 670 670 2b.3.4 Spent Fuel Capital and Transfer 22,680 3,402 26,082 26,082 2b.3.5 On-site survey and release of 309.6 tons clean metallic waste 564 56 620 620 2b.3 Subtotal Period 2b Collateral Costs 190 583 292 969 1,776 23,244 4,260 31,314 5,232 26,082 2,453 209,491 468 Period 2b Period-Dependent Costs 2b.4.1 Decon supplies 1,889 472 2,362 2,362 2b.4.2 Insurance 1,539 154 1,693 1,693 2b.4.3 Property taxes 272 27 300 300 2b.4.4 Health physics supplies 6,870 1,717 8,587 8,587 2b.4.5 Heavy equipment rental 5,176 776 5,952 5,952 2b.4.6 Disposal of DAW generated 135 76 392 123 725 725 6,613 132,265 216 2b.4.7 Plant energy budget 3,497 525 4,022 4,022 2b.4.8 NRC Fees 1,639 164 1,803 1,803 2b.4.9 Emergency Planning Fees 2,273 227 2,501 2,501 2b.4.10 Spent Fuel Pool O&M 2,244 337 2,581 2,581 2b.4.11 Liquid Radwaste Processing Equipment/Services 566 85 651 651 2b.4.12 ISFSI Operating Costs 287 43 331 331 2b.4.13 Corporate Allocations 2,271 227 2,498 2,498 2b.4.14 Security Staff Cost 30,845 4,627 35,472 35,472 510,210 2b.4.15 DOC Staff Cost 38,792 5,819 44,611 44,611 344,864 2b.4.16 Utility Staff Cost 58,488 8,773 67,261 67,261 640,124 2b.4 Subtotal Period 2b Period-Dependent Costs 1,889 12,045 135 76 392 142,715 24,096 181,348 175,936 5,412 6,613 132,265 216 1,495,198 2b.0 TOTAL PERIOD 2b COST 7,820 45,308 2,458 6,990 13,955 22,894 169,665 47,413 316,502 269,328 31,494 15,680 120,420 106,808 250 10,146,870 588,130 1,501,347 PERIOD 2d - Decontamination Following Wet Fuel Storage Period 2d Direct Decommissioning Activities 2d.1.1 Remove spent fuel racks 1,060 112 294 261 2,389 1,223 5,338 5,338 6,988 443,960 1,925 Disposal of Plant Systems 2d.1.2.1 600 Fuel Bldg Non-Specific Systems RCA 411 6

34 385 166 1,002 1,002 3,200 129,974 5,859 2d.1.2.2 600 Fuel Bldg Non-System Specific 64 3

6 20 41 31 165 165 170 120 14,568 954 2d.1.2.3 EC - Fuel Pool Cooling & Cleanup 535 28 68 313 374 287 1,606 1,606 2,602 1,090 175,237 8,051 2d.1.2.4 GA-Plant Heating Fuel Building 30 1

2 6

14 12 66 66 50 41 4,700 449 2d.1.2.5 GG - Fuel Building HVAC 326 10 45 448 53 170 1,053 1,053 3,729 155 161,297 4,673 2d.1.2.6 KC-Fire Protection Fuel Building 157 2

13 149 64 385 385 1,239 50,329 2,115 2d.1.2 Totals 1,523 51 168 1,321 483 730 4,276 4,276 10,991 1,407 536,105 22,102 Decontamination of Site Buildings 2d.1.3.1 Fuel Building 1,070 1,141 14 88 325 147 920 3,706 3,706 2,705 1,864 199,762 31,564 2d.1.3 Totals 1,070 1,141 14 88 325 147 920 3,706 3,706 2,705 1,864 199,762 31,564 2d.1.4 Scaffolding in support of decommissioning 517 7

5 41 9

139 718 718 308 27 15,598 9,185 2d.1 Subtotal Period 2d Activity Costs 2,130 3,292 366 521 1,687 3,028 3,013 14,038 14,038 14,004 10,287 1,195,425 64,776 Period 2d Additional Costs 2d.2.1 License Termination Survey Planning 1,778 533 2,311 2,311 12,480 2d.2.2 License Termination ISFSI 684 154 166 3,547 3,894 2,111 10,556 10,556 14,077 1,053,456 17,572 10,920 2d.2.3 Excavation of Underground Services 1,879 551 552 2,982 2,982 12,396 2d.2.4 Remedial Action Surveys 704 211 915 915 13,838 2d.2 Subtotal Period 2d Additional Costs 2,562 154 166 3,547 6,927 3,408 16,764 16,764 14,077 1,053,456 43,806 23,400 Period 2d Collateral Costs 2d.3.1 Process decommissioning water waste 100 73 184 306 161 824 824 601 36,064 117 2d.3.2 Process decommissioning chemical flush waste 2d.3.3 Small tool allowance 114 17 131 131 2d.3.4 Decommissioning Equipment Disposition 133 101 799 181 194 1,408 1,408 6,000 529 303,608 147 2d.3 Subtotal Period 2d Collateral Costs 100 114 207 285 799 487 372 2,362 2,362 6,000 1,130 339,672 264

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix C, Page 8 of 10 TLG Services, LLC Table C Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:13:35 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Period 2d Period-Dependent Costs 2d.4.1 Decon supplies 276 69 345 345 2d.4.2 Insurance 451 45 496 496 2d.4.3 Property taxes 80 8

88 88 2d.4.4 Health physics supplies 1,388 347 1,735 1,735 2d.4.5 Heavy equipment rental 1,517 228 1,745 1,745 2d.4.6 Disposal of DAW generated 42 24 123 39 228 228 2,081 41,624 68 2d.4.7 Plant energy budget 547 82 629 629 2d.4.8 NRC Fees 454 45 499 499 2d.4.9 Liquid Radwaste Processing Equipment/Services 332 50 382 382 2d.4.10 Corporate Allocations 666 67 732 732 2d.4.11 Security Staff Cost 1,850 277 2,127 2,127 20,772 2d.4.12 DOC Staff Cost 7,766 1,165 8,931 8,931 69,238 2d.4.13 Utility Staff Cost 12,053 1,808 13,861 13,861 130,861 2d.4 Subtotal Period 2d Period-Dependent Costs 276 2,905 42 24 123 24,198 4,229 31,798 31,798 2,081 41,624 68 220,870 2d.0 TOTAL PERIOD 2d COST 2,505 8,873 770 996 2,487 7,184 31,124 11,022 64,962 64,962 20,004 27,575 2,630,177 108,914 244,270 PERIOD 2f - License Termination Period 2f Direct Decommissioning Activities 2f.1.1 ORISE confirmatory survey 168 50 218 218 2f.1.2 Terminate license a

2f.1 Subtotal Period 2f Activity Costs 168 50 218 218 Period 2f Additional Costs 2f.2.1 License Termination Survey 10,211 3,063 13,274 13,274 153,878 6,240 2f.2 Subtotal Period 2f Additional Costs 10,211 3,063 13,274 13,274 153,878 6,240 Period 2f Collateral Costs 2f.3.1 DOC staff relocation expenses 1,641 246 1,887 1,887 2f.3 Subtotal Period 2f Collateral Costs 1,641 246 1,887 1,887 Period 2f Period-Dependent Costs 2f.4.1 Insurance 512 51 564 564 2f.4.2 Property taxes 91 9

100 100 2f.4.3 Health physics supplies 1,316 329 1,645 1,645 2f.4.4 Disposal of DAW generated 7

4 21 7

39 39 353 7,050 11 2f.4.5 Plant energy budget 310 47 357 357 2f.4.6 NRC Fees 546 55 601 601 2f.4.7 Corporate Allocations 756 76 832 832 2f.4.8 Security Staff Cost 2,101 315 2,416 2,416 23,592 2f.4.9 DOC Staff Cost 6,532 980 7,511 7,511 57,408 2f.4.10 Utility Staff Cost 7,153 1,073 8,226 8,226 74,709 2f.4 Subtotal Period 2f Period-Dependent Costs 1,316 7

4 21 18,001 2,941 22,290 22,290 353 7,050 11 155,709 2f.0 TOTAL PERIOD 2f COST 1,316 7

4 21 30,021 6,300 37,669 37,669 353 7,050 153,889 161,949 PERIOD 2 TOTALS 13,062 105,066 29,752 21,039 32,223 98,744 365,307 136,079 801,271 723,483 56,618 21,171 286,777 233,897 1,481 393 2,217 27,005,600 1,282,989 3,086,805 PERIOD 3b - Site Restoration Period 3b Direct Decommissioning Activities Demolition of Remaining Site Buildings 3b.1.1.1 Reactor 3,482 522 4,004 4,004 27,502 3b.1.1.2 Auxiliary 2,865 430 3,295 3,295 19,024 3b.1.1.3 Auxiliary Boiler 26 4

30 30 248 3b.1.1.4 Barge Facility 957 144 1,101 1,101 4,290 3b.1.1.5 Circulating & Service Water Pumphouse 233 35 268 268 1,996 3b.1.1.6 Communication Corridor - Clean 1,079 162 1,241 1,241 8,280 3b.1.1.7 Communication Corridor - Contaminated 35 5

40 40 184 3b.1.1.8 Cooling Tower Concrete 451 68 519 519 2,332 3b.1.1.9 Diesel Generator 329 49 378 378 2,185 3b.1.1.10 Essential Service Water Pumphouse 176 26 203 203 955 3b.1.1.11 Fire Water Pumphouse 23 3

26 26 151 3b.1.1.12 Flex Building Storage 337 51 388 388 1,972 3b.1.1.13 Hardened Condensate Storage Tank - HCST 243 36 279 279 1,870

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix C, Page 9 of 10 TLG Services, LLC Table C Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:13:35 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours 3b.1.1.14 Hot Machine Shop 21 3

24 24 243 3b.1.1.15 Intake 219 33 252 252 1,411 3b.1.1.16 Misc. Structures 2,722 408 3,130 3,130 18,774 3b.1.1.17 Miscellaneous Site Foundations 194 29 223 223 1,011 3b.1.1.18 Outage Maintenance 140 21 161 161 1,570 3b.1.1.19 RAM Storage Building 59 9

68 68 624 3b.1.1.20 Radioactive and Personnel Tunnel 34 5

39 39 386 3b.1.1.21 Radwaste 1,196 179 1,375 1,375 8,111 3b.1.1.22 Radwaste Drum Storage 171 26 197 197 1,449 3b.1.1.23 Reactor Head Assembly Building 98 15 113 113 1,108 3b.1.1.24 Security Additions 1,655 248 1,903 1,903 6,051 3b.1.1.25 Service 522 78 600 600 3,485 3b.1.1.26 Sludge Pump Station & Lagoon 1,678 252 1,930 1,930 10,601 3b.1.1.27 Steam Generator Replacement Bldgs 976 146 1,122 1,122 6,874 3b.1.1.28 Turbine Building 4,906 736 5,642 5,642 47,075 3b.1.1.29 Turbine Pedestal 561 84 646 646 2,934 3b.1.1.30 U.H.S. Cooling Tower 343 51 395 395 1,814 3b.1.1.31 Water Treatment Plant 1

0 1

1 9

3b.1.1.32 Fuel Building 1,229 184 1,414 1,414 8,068 3b.1.1 Totals 26,963 4,044 31,007 31,007 192,587 Site Closeout Activities 3b.1.2 Remove Rubble 1,558 234 1,792 1,792 7,233 3b.1.3 Grade & landscape site 129 19 148 148 592 3b.1.4 Final report to NRC 248 37 285 285 1,560 3b.1 Subtotal Period 3b Activity Costs 28,650 248 4,335 33,232 285 32,947 200,413 1,560 Period 3b Additional Costs 3b.2.1 Concrete Crushing 1,546 19 235 1,800 1,800 6,035 3b.2.2 Mine Area Backfill 6,441 966 7,407 7,407 15,960 3b.2.3 Construction Debris 2,950 443 3,393 3,393 3b.2.4 Cooling Tower Discharge & Intake Pipe Flow Fill 5,020 753 5,772 5,772 9,588 3b.2.5 Cooling Tower Demolition 5,495 824 6,320 6,320 21,619 3b.2.6 Site Restoration ISFSI 1,416 97 227 1,740 1,740 10,514 160 3b.2 Subtotal Period 3b Additional Costs 19,918 3,067 3,448 26,432 26,432 63,716 160 Period 3b Collateral Costs 3b.3.1 Small tool allowance 329 49 379 379 3b.3 Subtotal Period 3b Collateral Costs 329 49 379 379 Period 3b Period-Dependent Costs 3b.4.1 Insurance 1,019 102 1,121 1,121 3b.4.2 Property taxes 180 18 198 198 3b.4.3 Heavy equipment rental 4,790 718 5,508 5,508 3b.4.4 Plant energy budget 309 46 355 355 3b.4.5 Corporate Allocations 1,504 150 1,655 1,655 3b.4.6 Security Staff Cost 3,412 512 3,924 3,924 37,543 3b.4.7 DOC Staff Cost 12,661 1,899 14,560 14,560 106,371 3b.4.8 Utility Staff Cost 5,808 871 6,679 6,679 61,007 3b.4 Subtotal Period 3b Period-Dependent Costs 4,790 24,893 4,317 34,000 34,000 204,920 3b.0 TOTAL PERIOD 3b COST 53,687 28,207 12,149 94,043 285 93,758 264,129 206,640 PERIOD 3 TOTALS 53,687 28,207 12,149 94,043 285 93,758 264,129 206,640 TOTAL COST TO DECOMMISSION 17,773 162,533 29,898 21,506 32,223 100,958 557,872 175,184 1,097,947 902,437 78,615 116,895 286,777 235,150 2,268 393 2,217 27,125,890 1,567,519 4,491,356

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix C, Page 10 of 10 TLG Services, LLC Table C Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:13:35 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours TOTAL COST TO DECOMMISSION WITH 18.98% CONTINGENCY:

$1,097,947 thousands of 2023 dollars TOTAL NRC LICENSE TERMINATION COST IS 82.19% OR:

$902,437 thousands of 2023 dollars SPENT FUEL MANAGEMENT COST IS 7.16% OR:

$78,615 thousands of 2023 dollars NON-NUCLEAR DEMOLITION COST IS 10.65% OR:

$116,895 thousands of 2023 dollars TOTAL LOW-LEVEL RADIOACTIVE WASTE VOLUME BURIED (EXCLUDING GTCC):

237,811 Cubic Feet TOTAL GREATER THAN CLASS C RADWASTE VOLUME GENERATED:

2,217 Cubic Feet TOTAL SCRAP METAL REMOVED:

71,073 Tons TOTAL CRAFT LABOR REQUIREMENTS:

1,567,519 Man-hours End Notes:

n/a - indicates that this activity not charged as decommissioning expense a - indicates that this activity performed by decommissioning staff 0 - indicates that this value is less than 0.5 but is non-zero A cell containing " - " indicates a zero value

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix D, Page 1 of 12 TLG Services, LLC APPENDIX D DETAILED COST ANALYSIS SAFSTOR with LOW-LEVEL RADIOACTIVE WASTE PROCESSING 4D: SAFSTOR Decommissioning cost Estimate with Low-Level Radioactive Waste Processing

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix D, Page 2 of 12 TLG Services, LLC Table D Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:15:15 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours PERIOD 1a - Shutdown through Transition Period 1a Direct Decommissioning Activities 1a.1.1 SAFSTOR site characterization survey 394 118 512 512 1a.1.2 Prepare preliminary decommissioning cost 206 31 237 237 1,300 1a.1.3 Notification of Cessation of Operations a

1a.1.4 Remove fuel & source material n/a 1a.1.5 Notification of Permanent Defueling a

1a.1.6 Deactivate plant systems & process waste a

1a.1.7 Prepare and submit PSDAR 317 48 365 365 2,000 1a.1.8 Review plant dwgs & specs.

206 31 237 237 1,300 1a.1.9 Perform detailed rad survey a

1a.1.10 Estimate by-product inventory 159 24 183 183 1,000 1a.1.11 End product description 159 24 183 183 1,000 1a.1.12 Detailed by-product inventory 238 36 274 274 1,500 1a.1.13 Define major work sequence 159 24 183 183 1,000 1a.1.14 Perform SER and EA 492 74 566 566 3,100 1a.1.15 Perform Site-Specific Cost Study 794 119 913 913 5,000 Activity Specifications 1a.1.16.1 Prepare plant and facilities for SAFSTOR 781 117 898 898 4,920 1a.1.16.2 Plant systems 661 99 761 761 4,167 1a.1.16.3 Plant structures and buildings 495 74 569 569 3,120 1a.1.16.4 Waste management 317 48 365 365 2,000 1a.1.16.5 Facility and site dormancy 317 48 365 365 2,000 1a.1.16 Total 2,572 386 2,958 2,958 16,207 Detailed Work Procedures 1a.1.17.1 Plant systems 188 28 216 216 1,183 1a.1.17.2 Facility closeout & dormancy 190 29 219 219 1,200 1a.1.17 Total 378 57 435 435 2,383 1a.1.18 Procure vacuum drying system 16 2

18 18 100 1a.1.19 Drain/de-energize non-cont. systems a

1a.1.20 Drain & dry NSSS a

1a.1.21 Drain/de-energize contaminated systems a

1a.1.22 Decon/secure contaminated systems a

1a.1 Subtotal Period 1a Activity Costs 6,090 973 7,063 7,063 35,890 Period 1a Collateral Costs 1a.3.1 Spent Fuel Capital and Transfer 10,080 1,512 11,592 11,592 1a.3 Subtotal Period 1a Collateral Costs 10,080 1,512 11,592 11,592 Period 1a Period-Dependent Costs 1a.4.1 Insurance 3,972 397 4,370 4,370 1a.4.2 Property taxes 120 12 132 132 1a.4.3 Health physics supplies 888 222 1,110 1,110 1a.4.4 Heavy equipment rental 657 99 755 755 1a.4.5 Disposal of DAW generated 12 7

36 11 67 67 610 12,190 20 1a.4.6 Plant energy budget 2,053 308 2,361 2,361 1a.4.7 NRC Fees 1,057 106 1,163 1,163 1a.4.8 Emergency Planning Fees 1,620 162 1,782 1,782 1a.4.9 INPO Fees 358 54 411 411 1a.4.10 Spent Fuel Pool O&M 988 148 1,136 1,136 1a.4.11 ISFSI Operating Costs 127 19 146 146 1a.4.12 Corporate Allocations 1,000 100 1,100 1,100 1a.4.13 Security Staff Cost 15,699 2,355 18,054 18,054 251,680 1a.4.14 Utility Staff Cost 37,678 5,652 43,329 43,329 422,240 1a.4 Subtotal Period 1a Period-Dependent Costs 1,545 12 7

36 64,672 9,644 75,916 72,852 3,064 610 12,190 20 673,920 1a.0 TOTAL PERIOD 1a COST 1,545 12 7

36 80,842 12,129 94,571 79,915 14,656 610 12,190 20 709,810

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix D, Page 3 of 12 TLG Services, LLC Table D Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:15:15 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours PERIOD 1b - SAFSTOR Limited DECON Activities Period 1b Direct Decommissioning Activities Decontamination of Site Buildings 1b.1.1.1 Reactor 1,604 802 2,407 2,407 24,102 1b.1.1.2 Auxiliary 792 396 1,188 1,188 12,527 1b.1.1.3 Communication Corridor - Contaminated 17 9

26 26 276 1b.1.1.4 Fuel Building 1,056 528 1,584 1,584 14,371 1b.1.1.5 Hot Machine Shop 22 11 33 33 344 1b.1.1.6 RAM Storage Building 55 27 82 82 865 1b.1.1.7 Radioactive and Personnel Tunnel 6

3 10 10 102 1b.1.1.8 Radwaste 422 211 633 633 6,671 1b.1.1.9 Radwaste Drum Storage 47 24 71 71 750 1b.1.1.10 Reactor Head Assembly Building 44 22 66 66 691 1b.1.1 Totals 4,067 2,033 6,100 6,100 60,700 1b.1 Subtotal Period 1b Activity Costs 4,067 2,033 6,100 6,100 60,700 Period 1b Additional Costs 1b.2.1 Spent Fuel Pool Isolation 14,330 2,150 16,480 16,480 1b.2 Subtotal Period 1b Additional Costs 14,330 2,150 16,480 16,480 Period 1b Collateral Costs 1b.3.1 Decon equipment 1,193 179 1,371 1,371 1b.3.2 Process decommissioning water waste 190 132 333 552 296 1,504 1,504 1,085 65,127 212 1b.3.3 Process decommissioning chemical flush waste 1b.3.4 Small tool allowance 67 10 77 77 1b.3.5 Spent Fuel Capital and Transfer 2,520 378 2,898 2,898 1b.3 Subtotal Period 1b Collateral Costs 1,382 67 132 333 552 2,520 863 5,850 2,952 2,898 1,085 65,127 212 Period 1b Period-Dependent Costs 1b.4.1 Decon supplies 1,772 443 2,215 2,215 1b.4.2 Insurance 1,001 100 1,101 1,101 1b.4.3 Property taxes 30 3

33 33 1b.4.4 Health physics supplies 725 181 906 906 1b.4.5 Heavy equipment rental 166 25 190 190 1b.4.6 Disposal of DAW generated 15 9

45 14 82 82 752 15,043 25 1b.4.7 Plant energy budget 517 78 595 595 1b.4.8 NRC Fees 200 20 220 220 1b.4.9 Emergency Planning Fees 408 41 449 449 1b.4.10 Spent Fuel Pool O&M 249 37 286 286 1b.4.11 ISFSI Operating Costs 32 5

37 37 1b.4.12 Corporate Allocations 252 25 277 277 1b.4.13 Security Staff Cost 3,957 594 4,551 4,551 63,437 1b.4.14 Utility Staff Cost 9,497 1,425 10,921 10,921 106,428 1b.4 Subtotal Period 1b Period-Dependent Costs 1,772 890 15 9

45 16,144 2,990 21,866 21,093 772 752 15,043 25 169,865 1b.0 TOTAL PERIOD 1b COST 7,221 958 148 342 597 32,995 8,036 50,296 46,625 3,670 1,838 80,170 60,936 169,865 PERIOD 1c - Preparations for SAFSTOR Dormancy Period 1c Direct Decommissioning Activities 1c.1.1 Prepare support equipment for storage 588 88 676 676 3,000 1c.1.2 Install containment pressure equal. lines 56 8

64 64 700 1c.1.3 Interim survey prior to dormancy 733 220 953 953 13,566 1c.1.4 Secure building accesses a

1c.1.5 Prepare & submit interim report 93 14 106 106 583 1c.1 Subtotal Period 1c Activity Costs 644 825 330 1,800 1,800 17,266 583 Period 1c Collateral Costs 1c.3.1 Process decommissioning water waste 206 144 363 602 322 1,637 1,637 1,183 70,953 231 1c.3.2 Process decommissioning chemical flush waste 1c.3.3 Small tool allowance 5

1 6

6 1c.3.4 Spent Fuel Capital and Transfer 2,520 378 2,898 2,898 1c.3 Subtotal Period 1c Collateral Costs 206 5

144 363 602 2,520 701 4,541 1,643 2,898 1,183 70,953 231

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix D, Page 4 of 12 TLG Services, LLC Table D Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:15:15 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Period 1c Period-Dependent Costs 1c.4.1 Insurance 1,001 100 1,101 1,101 1c.4.2 Property taxes 30 3

33 33 1c.4.3 Health physics supplies 368 92 460 460 1c.4.4 Heavy equipment rental 166 25 190 190 1c.4.5 Disposal of DAW generated 3

2 9

3 17 17 154 3,073 5

1c.4.6 Plant energy budget 517 78 595 595 1c.4.7 NRC Fees 200 20 220 220 1c.4.8 Emergency Planning Fees 408 41 449 449 1c.4.9 Spent Fuel Pool O&M 249 37 286 286 1c.4.10 ISFSI Operating Costs 32 5

37 37 1c.4.11 Corporate Allocations 252 25 277 277 1c.4.12 Security Staff Cost 3,957 594 4,551 4,551 63,437 1c.4.13 Utility Staff Cost 9,497 1,425 10,921 10,921 106,428 1c.4 Subtotal Period 1c Period-Dependent Costs 533 3

2 9

16,144 2,447 19,138 18,366 772 154 3,073 5

169,865 1c.0 TOTAL PERIOD 1c COST 206 1,183 147 364 611 19,490 3,478 25,480 21,809 3,670 1,336 74,026 17,502 170,448 PERIOD 1 TOTALS 7,428 3,685 307 713 1,244 133,327 23,643 170,346 148,349 21,997 3,783 166,386 78,458 1,050,123 PERIOD 2a - SAFSTOR Dormancy with Wet Spent Fuel Storage Period 2a Direct Decommissioning Activities 2a.1.1 Quarterly Inspection a

2a.1.2 Semi-annual environmental survey a

2a.1.3 Prepare reports a

2a.1.4 Bituminous roof replacement 326 49 374 374 2a.1.5 Maintenance supplies 615 154 769 769 2a.1 Subtotal Period 2a Activity Costs 941 203 1,143 1,143 Period 2a Collateral Costs 2a.3.1 Spent Fuel Capital and Transfer 40,950 6,143 47,093 47,093 2a.3 Subtotal Period 2a Collateral Costs 40,950 6,143 47,093 47,093 Period 2a Period-Dependent Costs 2a.4.1 Insurance 2,708 271 2,979 2,979 2a.4.2 Property taxes 479 48 527 527 2a.4.3 Health physics supplies 1,423 356 1,779 1,779 2a.4.4 Disposal of DAW generated 19 11 54 17 101 101 920 18,394 30 2a.4.5 Plant energy budget 1,641 246 1,887 944 944 2a.4.6 NRC Fees 1,304 130 1,434 1,434 2a.4.7 Emergency Planning Fees 4,001 400 4,401 4,401 2a.4.8 Spent Fuel Pool O&M 3,950 593 4,543 4,543 2a.4.9 ISFSI Operating Costs 506 76 582 582 2a.4.10 Corporate Allocations 3,997 400 4,397 4,397 2a.4.11 Security Staff Cost 56,070 8,410 64,480 54,035 10,446 897,945 2a.4.12 Utility Staff Cost 31,218 4,683 35,900 29,582 6,318 328,415 2a.4 Subtotal Period 2a Period-Dependent Costs 1,423 19 11 54 105,874 15,630 123,011 95,778 27,233 920 18,394 30 1,226,360 2a.0 TOTAL PERIOD 2a COST 1,423 19 11 54 147,765 21,975 171,247 96,921 74,326 920 18,394 30 1,226,360 PERIOD 2c - SAFSTOR Dormancy without Spent Fuel Storage Period 2c Direct Decommissioning Activities 2c.1.1 Quarterly Inspection a

2c.1.2 Semi-annual environmental survey a

2c.1.3 Prepare reports a

2c.1.4 Bituminous roof replacement 3,955 593 4,548 4,548 2c.1.5 Maintenance supplies 7,471 1,868 9,338 9,338 2c.1 Subtotal Period 2c Activity Costs 11,425 2,461 13,886 13,886 Period 2c Collateral Costs 2c.3 Subtotal Period 2c Collateral Costs Period 2c Period-Dependent Costs 2c.4.1 Insurance 20,383 2,038 22,422 22,422 2c.4.2 Property taxes 5,822 582 6,405 6,405 2c.4.3 Health physics supplies 7,889 1,972 9,862 9,862

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix D, Page 5 of 12 TLG Services, LLC Table D Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:15:15 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours 2c.4.4 Disposal of DAW generated 101 57 293 92 541 541 4,942 98,844 161 2c.4.5 Plant energy budget 9,968 1,495 11,463 11,463 2c.4.6 NRC Fees 14,105 1,410 15,515 15,515 2c.4.7 Security Staff Cost 134,884 20,233 155,117 155,117 1,514,867 2c.4.8 Utility Staff Cost 79,438 11,916 91,353 91,353 883,672 2c.4 Subtotal Period 2c Period-Dependent Costs 7,889 101 57 293 264,601 39,739 312,679 312,679 4,942 98,844 161 2,398,539 2c.0 TOTAL PERIOD 2c COST 7,889 101 57 293 276,026 42,199 326,565 326,565 4,942 98,844 161 2,398,539 PERIOD 2 TOTALS 9,313 119 67 347 423,791 64,174 497,811 423,486 74,326 5,862 117,238 191 3,624,899 PERIOD 3a - Reactivate Site Following SAFSTOR Dormancy Period 3a Direct Decommissioning Activities 3a.1.1 Prepare preliminary decommissioning cost 206 31 237 237 1,300 3a.1.2 Review plant dwgs & specs.

730 110 840 840 4,600 3a.1.3 Perform detailed rad survey a

3a.1.4 End product description 159 24 183 183 1,000 3a.1.5 Detailed by-product inventory 206 31 237 237 1,300 3a.1.6 Define major work sequence 1,190 179 1,369 1,369 7,500 3a.1.7 Perform SER and EA 492 74 566 566 3,100 3a.1.8 Prepare/submit Defueled Technical Specifications 1,190 179 1,369 1,369 7,500 3a.1.9 Perform Site-Specific Cost Study 794 119 913 913 5,000 3a.1.10 Prepare/submit Irradiated Fuel Management Plan 159 24 183 183 1,000 Activity Specifications 3a.1.11.1 Re-activate plant & temporary facilities 1,170 175 1,345 1,211 135 7,370 3a.1.11.2 Plant systems 661 99 761 684 76 4,167 3a.1.11.3 Reactor internals 1,127 169 1,296 1,296 7,100 3a.1.11.4 Reactor vessel 1,032 155 1,186 1,186 6,500 3a.1.11.5 Biological shield 79 12 91 91 500 3a.1.11.6 Steam generators 495 74 569 569 3,120 3a.1.11.7 Reinforced concrete 254 38 292 146 146 1,600 3a.1.11.8 Main Turbine 63 10 73 73 400 3a.1.11.9 Main Condensers 63 10 73 73 400 3a.1.11.10 Plant structures & buildings 495 74 569 285 285 3,120 3a.1.11.11 Waste management 730 110 840 840 4,600 3a.1.11.12 Facility & site closeout 143 21 164 82 82 900 3a.1.11 Total 6,313 947 7,260 6,391 870 39,777 Planning & Site Preparations 3a.1.12 Prepare dismantling sequence 381 57 438 438 2,400 3a.1.13 Plant prep. & temp. svces 4,000 600 4,600 4,600 3a.1.14 Design water clean-up system 222 33 256 256 1,400 3a.1.15 Rigging/Cont. Cntrl Envlps/tooling/etc.

2,800 420 3,220 3,220 3a.1.16 Procure casks/liners & containers 195 29 225 225 1,230 3a.1 Subtotal Period 3a Activity Costs 19,038 2,856 21,894 21,025 870 77,107 Period 3a Additional Costs 3a.2.1 Site Characterization 3,198 959 4,158 4,158 19,100 7,852 3a.2 Subtotal Period 3a Additional Costs 3,198 959 4,158 4,158 19,100 7,852 Period 3a Collateral Costs 3a.3 Subtotal Period 3a Collateral Costs Period 3a Period-Dependent Costs 3a.4.1 Insurance 420 42 462 462 3a.4.2 Property taxes 120 12 132 132 3a.4.3 Health physics supplies 776 194 970 970 3a.4.4 Heavy equipment rental 657 99 755 755 3a.4.5 Disposal of DAW generated 10 6

30 10 56 56 514 10,287 17 3a.4.6 Plant energy budget 2,053 308 2,361 2,361 3a.4.7 NRC Fees 458 46 504 504 3a.4.8 Corporate Allocations 1,000 100 1,100 1,100 3a.4.9 Security Staff Cost 4,449 667 5,117 5,117 65,000 3a.4.10 Utility Staff Cost 23,216 3,482 26,699 26,699 257,920 3a.4 Subtotal Period 3a Period-Dependent Costs 1,433 10 6

30 31,716 4,960 38,156 38,156 514 10,287 17 322,920 3a.0 TOTAL PERIOD 3a COST 1,433 10 6

30 53,953 8,775 64,207 63,338 870 514 10,287 19,117 407,879

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix D, Page 6 of 12 TLG Services, LLC Table D Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:15:15 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours PERIOD 3b - Decommissioning Preparations Period 3b Direct Decommissioning Activities Detailed Work Procedures 3b.1.1.1 Plant systems 751 113 864 778 86 4,733 3b.1.1.2 Reactor internals 397 60 456 456 2,500 3b.1.1.3 Remaining buildings 214 32 246 62 185 1,350 3b.1.1.4 CRD cooling assembly 159 24 183 183 1,000 3b.1.1.5 CRD housings & ICI tubes 159 24 183 183 1,000 3b.1.1.6 Incore instrumentation 159 24 183 183 1,000 3b.1.1.7 Reactor vessel 576 86 663 663 3,630 3b.1.1.8 Facility closeout 190 29 219 110 110 1,200 3b.1.1.9 Missile shields 71 11 82 82 450 3b.1.1.10 Biological shield 190 29 219 219 1,200 3b.1.1.11 Steam generators 730 110 840 840 4,600 3b.1.1.12 Reinforced concrete 159 24 183 91 91 1,000 3b.1.1.13 Main Turbine 248 37 285 285 1,560 3b.1.1.14 Main Condensers 248 37 285 285 1,560 3b.1.1.15 Auxiliary building 433 65 498 448 50 2,730 3b.1.1.16 Reactor building 433 65 498 448 50 2,730 3b.1.1 Total 5,118 768 5,885 4,744 1,141 32,243 3b.1 Subtotal Period 3b Activity Costs 5,118 768 5,885 4,744 1,141 32,243 Period 3b Collateral Costs 3b.3.1 Decon equipment 1,193 179 1,371 1,371 3b.3.2 DOC staff relocation expenses 1,641 246 1,887 1,887 3b.3.3 Pipe cutting equipment 1,400 210 1,610 1,610 3b.3 Subtotal Period 3b Collateral Costs 1,193 1,400 1,641 635 4,868 4,868 Period 3b Period-Dependent Costs 3b.4.1 Decon supplies 43 11 54 54 3b.4.2 Insurance 342 34 376 376 3b.4.3 Property taxes 60 6

66 66 3b.4.4 Health physics supplies 431 108 539 539 3b.4.5 Heavy equipment rental 331 50 381 381 3b.4.6 Disposal of DAW generated 6

3 17 5

32 32 293 5,866 10 3b.4.7 Plant energy budget 1,035 155 1,190 1,190 3b.4.8 NRC Fees 231 23 254 254 3b.4.9 Corporate Allocations 504 50 555 555 3b.4.10 Security Staff Cost 2,243 336 2,579 2,579 32,767 3b.4.11 DOC Staff Cost 6,642 996 7,639 7,639 58,719 3b.4.12 Utility Staff Cost 11,704 1,756 13,459 13,459 130,020 3b.4 Subtotal Period 3b Period-Dependent Costs 43 762 6

3 17 22,761 3,531 27,124 27,124 293 5,866 10 221,506 3b.0 TOTAL PERIOD 3b COST 1,235 2,162 6

3 17 29,519 4,934 37,877 36,736 1,141 293 5,866 10 253,749 PERIOD 3 TOTALS 1,235 3,595 16 9

48 83,472 13,708 102,084 100,074 2,011 808 16,153 19,126 661,628 PERIOD 4a - Large Component Removal Period 4a Direct Decommissioning Activities Nuclear Steam Supply System Removal 4a.1.1.1 Reactor Coolant Piping 46 222 39 73 191 384 218 1,171 1,171 967 1,023 135,750 3,982 4a.1.1.2 Pressurizer Relief Tank 8

31 11 21 54 109 51 284 284 273 289 38,367 602 4a.1.1.3 Reactor Coolant Pumps & Motors 26 111 95 249 1,483 458 2,423 2,423 3,386 816,140 2,474 80 4a.1.1.4 Pressurizer 80 548 193 1,638 513 2,973 2,973 3,739 241,053 1,346 1,500 4a.1.1.5 Steam Generators 8,305 3,254 3,319 3,735 9,877 5,929 34,418 34,418 40,262 22,546 3,398,523 20,559 2,250 4a.1.1.6 Retired Steam Generator Units 3,254 3,319 3,735 9,877 3,853 24,037 24,037 40,262 22,546 3,398,523 10,852 2,250 4a.1.1.7 CRDMs/ICIs/Service Structure Removal 39 311 225 101 83 609 299 1,667 1,667 753 2,947 141,134 5,231 4a.1.1.8 Reactor Vessel Internals 48 5,349 11,276 1,031 11,929 306 13,123 43,063 43,063 5,623 501 406 342,863 24,523 1,139 4a.1.1.9 Vessel & Internals GTCC Disposal 13,035 1,955 14,990 14,990 2,217 433,180 4a.1.1.10 Reactor Vessel 7,025 2,076 1,382 6,848 306 9,603 27,239 27,239 15,631 979,036 24,523 1,139 4a.1.1 Totals 166 21,433 20,780 9,687 7,797 55,789 612 36,002 152,266 152,266 82,516 77,730 501 406 2,217 9,924,571 94,092 8,359

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix D, Page 7 of 12 TLG Services, LLC Table D Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:15:15 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Removal of Major Equipment 4a.1.2 Main Turbine/Generator 606 269 33 920 321 2,150 2,150 5,180 310,807 8,721 4a.1.3 Main Condensers 1,723 165 94 1,080 623 3,685 3,685 8,106 364,767 24,802 Cascading Costs from Clean Building Demolition 4a.1.4.1 Reactor 612 92 704 704 4,832 4a.1.4.2 Auxiliary 318 48 366 366 2,113 4a.1.4.3 Fuel Building 127 19 146 146 773 4a.1.4.4 Hot Machine Shop 1

0 1

1 7

4a.1.4.5 Radwaste 61 9

70 70 387 4a.1.4 Totals 1,119 168 1,287 1,287 8,113 Disposal of Plant Systems 4a.1.5.1 100 Aux.Bldg Non-System Specific RCA 920 15 80 917 381 2,313 2,313 7,629 309,812 13,471 4a.1.5.2 100 Auxiliary Bldg Non-System Specific 136 2

10 99 11 53 310 310 824 31 35,454 2,031 4a.1.5.3 AB - Main Steam 366 55 420 420 5,833 4a.1.5.4 AB - Main Steam RCA 103 4

23 259 68 458 458 2,156 87,550 1,515 4a.1.5.5 AC - Main Turbine 361 54 415 415 5,641 4a.1.5.6 AD - Condensate 401 60 461 461 6,144 4a.1.5.7 AE - Feedwater 275 41 316 316 4,271 4a.1.5.8 AF - Feedwater Heater Extraction 337 51 388 388 5,352 4a.1.5.9 AK - Condensate Demineralizer 125 19 143 143 1,944 4a.1.5.10 AL - Auxiliary Feedwater 54 8

63 63 852 4a.1.5.11 AQ - Condensate & Feedwater Chem Addtn 30 5

35 35 468 4a.1.5.12 BM - Steam Generator Blowdown 143 2

12 139 59 355 355 1,157 46,993 2,137 4a.1.5.13 BM - Steam Generator Blowdown - RCA 491 8

43 494 204 1,240 1,240 4,109 166,857 7,066 4a.1.5.14 BN - Borated Refueling Water Storage 409 12 66 752 226 1,465 1,465 6,255 254,024 6,161 4a.1.5.15 CA - Steam Seal 29 4

33 33 455 4a.1.5.16 CB - Main Turbine Lube Oil 82 12 95 95 1,207 4a.1.5.17 CC - Generator Hydrogen Seal & CO2 13 2

15 15 198 4a.1.5.18 CD - Generator Seal Oil 19 3

22 22 287 4a.1.5.19 CE - Stator Cooling Water 16 2

19 19 241 4a.1.5.20 CF - Lube Oil Storage Xfer & Prfication 53 8

61 61 812 4a.1.5.21 CG - Condenser Air Removal 43 6

49 49 657 4a.1.5.22 CH - Main Turbine Control Oil 85 13 97 97 1,219 4a.1.5.23 DA - Circulating Water 473 71 544 544 7,502 4a.1.5.24 DB - Cooling Tower Makeup & Blowdown 80 12 92 92 1,260 4a.1.5.25 DD - Cooling Water Chemical Control Sys 71 11 81 81 1,084 4a.1.5.26 DD - Cooling Wtr Chem Control RCA 361 7

37 427 161 993 993 3,555 144,376 4,951 4a.1.5.27 EJ - Residual Heat Removal 473 34 91 539 400 316 1,852 1,852 4,481 1,166 256,354 7,147 4a.1.5.28 EM - High Pressure Coolant Injection 398 4

23 266 143 835 835 2,214 89,903 5,913 4a.1.5.29 EN - Containment Spray 288 6

32 364 132 821 821 3,026 122,874 4,134 4a.1.5.30 EP - Accumulator Safety Injection 210 4

21 239 92 566 566 1,989 80,762 3,112 4a.1.5.31 FA - Auxiliary Steam Generator 32 5

37 37 521 4a.1.5.32 FB - Auxiliary Steam 133 20 152 152 2,106 4a.1.5.33 FB - Auxiliary Steam RCA 109 2

9 98 43 260 260 816 33,148 1,537 4a.1.5.34 FC - Auxiliary Turbines 87 13 100 100 1,320 4a.1.5.35 FE - Auxiliary Steam Chemical Addition 7

1 8

8 105 4a.1.5.36 GE - Turbine Building HVAC 240 36 276 276 3,957 4a.1.5.37 GS - Containment Hydrogen Control 91 2

8 96 39 236 236 801 32,539 1,395 4a.1.5.38 HE - Boron Recycle 607 27 66 416 275 295 1,686 1,686 3,460 794 191,531 8,970 4a.1.5.39 HF - Secondary Liquid Waste 1,194 54 148 1,014 548 615 3,572 3,572 8,431 1,588 444,251 17,832 4a.1.5.40 JA - Auxiliary Oil & Transfer 43 7

50 50 690 4a.1.5.41 KS - Bulk Chemical Storage 122 13 68 775 158 1,136 1,136 6,449 261,890 1,825 4a.1.5.42 LE - Oily Waste 246 37 282 282 3,865 4a.1.5.43 LE - Oily Waste RCA 313 4

24 271 123 735 735 2,256 91,628 4,296 4a.1.5.44 Turbine Bldg Non-System Specific 1,031 155 1,185 1,185 15,405 4a.1.5 Totals 11,097 200 759 7,165 1,233 3,818 24,273 18,833 5,440 59,608 3,579 2,649,944 166,890 4a.1.6 Scaffolding in support of decommissioning 1,897 27 18 164 37 514 2,658 2,658 1,233 109 62,391 33,634 4a.1 Subtotal Period 4a Activity Costs 166 37,875 21,441 10,592 17,126 57,059 612 41,447 186,318 180,879 5,440 156,643 81,418 501 406 2,217 13,312,480 336,251 8,359 Period 4a Additional Costs 4a.2.1 Remedial Action Surveys 1,465 440 1,905 1,905 28,815 4a.2 Subtotal Period 4a Additional Costs 1,465 440 1,905 1,905 28,815

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix D, Page 8 of 12 TLG Services, LLC Table D Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:15:15 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Period 4a Collateral Costs 4a.3.1 Process decommissioning water waste 5

9 23 39 17 93 93 76 4,560 15 4a.3.2 Process decommissioning chemical flush waste 4a.3.3 Small tool allowance 375 56 431 388 43 4a.3.4 On-site survey and release of 60.87 tons clean metallic waste 111 11 122 122 4a.3 Subtotal Period 4a Collateral Costs 5

375 9

23 39 111 84 646 603 43 76 4,560 15 Period 4a Period-Dependent Costs 4a.4.1 Decon supplies 118 30 148 148 4a.4.2 Insurance 939 94 1,033 1,033 4a.4.3 Property taxes 166 17 183 183 4a.4.4 Health physics supplies 4,216 1,054 5,270 5,270 4a.4.5 Heavy equipment rental 3,081 462 3,543 3,543 4a.4.6 Disposal of DAW generated 106 60 310 97 573 573 5,233 104,653 171 4a.4.7 Plant energy budget 2,704 406 3,109 3,109 4a.4.8 NRC Fees 818 82 900 900 4a.4.9 Liquid Radwaste Processing Equipment/Services 691 104 795 795 4a.4.10 Corporate Allocations 1,386 139 1,525 1,525 4a.4.11 Security Staff Cost 6,168 925 7,094 7,094 90,110 4a.4.12 DOC Staff Cost 21,985 3,298 25,283 25,283 198,962 4a.4.13 Utility Staff Cost 32,471 4,871 37,341 37,341 360,438 4a.4 Subtotal Period 4a Period-Dependent Costs 118 7,296 106 60 310 67,329 11,577 86,797 86,797 5,233 104,653 171 649,510 4a.0 TOTAL PERIOD 4a COST 289 45,546 21,557 10,675 17,126 57,408 69,517 53,547 275,666 270,183 5,483 156,643 86,727 501 406 2,217 13,421,690 365,252 657,869 PERIOD 4b - Site Decontamination Period 4b Direct Decommissioning Activities 4b.1.1 Remove spent fuel racks 959 112 294 261 2,389 1,173 5,187 5,187 6,988 443,960 1,925 Disposal of Plant Systems 4b.1.2.1 200 Reactor Bldg Non-System Specific 109 1

6 60 6

39 222 222 502 19 21,590 1,569 4b.1.2.2 200 Reactor Bldg Non-System Specific RCA 752 9

50 573 282 1,667 1,667 4,768 193,612 10,425 4b.1.2.3 300 Control Bldg Non-System Specific 236 4

22 257 101 621 621 2,139 86,849 3,413 4b.1.2.4 300 Control Bldg Non-System Specific Cln 1,836 275 2,111 2,111 29,076 4b.1.2.5 600 Fuel Bldg Non-Specific Systems RCA 411 6

34 385 166 1,002 1,002 3,200 129,974 5,859 4b.1.2.6 600 Fuel Bldg Non-System Specific 58 1

4 39 4

22 127 127 322 12 13,829 850 4b.1.2.7 700 Radwaste Bldg Non-Sys Specific RCA 1,514 25 133 1,525 630 3,826 3,826 12,684 515,103 21,919 4b.1.2.8 700 Radwaste Bldg Non-System Specific 219 4

16 160 17 86 501 501 1,329 50 57,145 3,253 4b.1.2.9 AN - Demineralized Wtr Storage & Xfer 208 31 239 239 3,283 4b.1.2.10 AN - Demineralized Wtr Strg & Xfer RCA 53 1

3 38 19 114 114 314 12,759 740 4b.1.2.11 AP-HCST/Condensate Stor.& Transfr 275 41 316 316 4,018 4b.1.2.12 BB - Reactor Coolant System 408 28 69 311 387 259 1,462 1,462 2,586 1,130 176,949 6,323 4b.1.2.13 BG - Chemical & Volume Control 1,157 76 183 985 891 695 3,987 3,987 8,192 2,586 498,359 17,275 4b.1.2.14 BL - Reactor Makeup Water 370 16 42 304 145 182 1,059 1,059 2,529 418 129,620 5,494 4b.1.2.15 DE - Intake & Water Treatment 166 25 191 191 2,517 4b.1.2.16 DE - Intake & Water Treatment RCA 331 24 125 1,433 319 2,232 2,232 11,923 484,206 5,014 4b.1.2.17 EA - Service Water 197 30 227 227 3,145 4b.1.2.18 EA - Service Water RCA 59 2

13 150 39 264 264 1,248 50,693 839 4b.1.2.19 EB - Closed Cooling Water 80 12 92 92 1,267 4b.1.2.20 EC - Fuel Pool Cooling & Cleanup 484 8

43 495 203 1,233 1,233 4,119 167,293 7,163 4b.1.2.21 EF - Essential Service Water 458 69 527 527 7,244 4b.1.2.22 EF - Essential Service Water RCA 263 11 56 640 171 1,141 1,141 5,326 216,287 3,862 4b.1.2.23 EG - Component Cooling Water RCA 336 50 386 386 5,335 4b.1.2.24 GA - Plant Heating 120 18 138 138 1,912 4b.1.2.25 GA - Plant Heating RCA 126 1

7 77 44 255 255 638 25,924 1,765 4b.1.2.26 GA-Plant Heating Fuel Building 27 0

1 13 9

50 50 107 4,351 400 4b.1.2.27 GB - Central Chilled Water 113 17 130 130 1,803 4b.1.2.28 GB - Central Chilled Water RCA 34 0

2 22 12 71 71 187 7,591 482 4b.1.2.29 GD - Essential Serv Wtr Pumphouse HVAC 25 4

29 29 427 4b.1.2.30 GF - Miscellaneous Building HVAC 155 4

21 245 79 504 504 2,034 82,602 2,026 4b.1.2.31 GG - Fuel Building HVAC 295 8

41 474 152 970 970 3,945 160,195 4,052 4b.1.2.32 GH - Radwaste Building HVAC 217 5

27 308 105 661 661 2,561 104,012 3,004 4b.1.2.33 GK - Control Building HVAC 231 35 266 266 3,959 4b.1.2.34 GL - Auxiliary Building HVAC 535 10 56 647 240 1,489 1,489 5,381 218,514 7,364 4b.1.2.35 GM - Diesel Generator Building HVAC 40 6

46 46 695 4b.1.2.36 GN - Containment Cooling 599 16 87 993 313 2,008 2,008 8,264 335,602 8,405 4b.1.2.37 GP - Containment Intgratd Leak Rate Test 52 1

6 70 24 153 153 580 23,570 750 4b.1.2.38 GR - Containment Atmospheric Control 24 2

12 137 29 204 204 1,143 46,407 350

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix D, Page 9 of 12 TLG Services, LLC Table D Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:15:15 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours 4b.1.2.39 GT - Containment Purge HVAC 140 4

23 263 78 508 508 2,185 88,746 1,973 4b.1.2.40 HA - Gaseous Radwaste 434 7

39 445 182 1,106 1,106 3,699 150,219 6,296 4b.1.2.41 HB - Liquid Radwaste 1,054 53 132 885 504 547 3,176 3,176 7,362 1,450 392,564 15,506 4b.1.2.42 HC - Solid Radwaste 450 25 64 359 297 252 1,446 1,446 2,985 862 176,332 6,652 4b.1.2.43 HD - Decontamination 125 6

17 118 59 67 392 392 983 171 50,973 1,835 4b.1.2.44 JE - Emergency Fuel Oil 86 13 99 99 1,260 4b.1.2.45 KA - Compressed Air 262 39 301 301 4,187 4b.1.2.46 KA - Compressed Air RCA 169 2

8 96 58 334 334 801 32,538 2,339 4b.1.2.47 KB - Breathing Air 33 5

38 38 516 4b.1.2.48 KB - Breathing Air RCA 26 0

1 9

8 43 43 71 2,874 402 4b.1.2.49 KC - Fire Protection 514 77 591 591 8,376 4b.1.2.50 KC - Fire Protection RCA 530 9

46 530 220 1,335 1,335 4,411 179,151 7,064 4b.1.2.51 KC-Fire Protection Fuel Building 157 2

13 149 64 385 385 1,239 50,329 2,115 4b.1.2.52 KD - Domestic Water 239 36 275 275 3,837 4b.1.2.53 KD - Domestic Water RCA 34 0

3 30 13 80 80 247 10,039 459 4b.1.2.54 KE - Fuel Handling & Storage Rctor vssl 23 2

9 106 23 163 163 882 35,813 332 4b.1.2.55 KH - Service Gas (CO2 N2 H2 & O2) 76 11 87 87 1,226 4b.1.2.56 KH - Service Gas (CO2 N2 H2 & O2) RCA 333 5

25 292 131 787 787 2,433 98,813 4,481 4b.1.2.57 KJ - Standby Diesel Engine 454 68 523 523 6,749 4b.1.2.58 LA - Sanitary Drains 61 9

70 70 972 4b.1.2.59 LA - Sanitary Drains RCA 140 3

13 153 60 369 369 1,273 51,684 1,811 4b.1.2.60 LB - Roof Drains 81 12 93 93 1,276 4b.1.2.61 LB - Roof Drains RCA 190 4

22 257 90 563 563 2,139 86,858 2,694 4b.1.2.62 LD - Chemical & Detergent Waste 144 2

8 96 52 302 302 797 32,369 2,139 4b.1.2.63 LF - Floor & Equipment Drains 1,788 86 205 801 1,242 917 5,039 5,039 6,660 3,627 501,387 26,164 4b.1.2.64 RM - Process Sampling & Analysis 162 2

10 119 60 354 354 990 40,200 2,450 4b.1.2.65 SJ - Nuclear Sampling 94 1

7 81 37 221 221 677 27,501 1,430 4b.1.2.66 UB - Servces Stores Site Security Bldg 245 37 282 282 3,815 4b.1.2.67 Yard Non-System Specific 41 6

47 47 603 4b.1.2 Totals 20,658 479 1,706 15,129 3,553 8,008 49,533 42,429 7,104 125,856 10,326 5,771,424 306,237 4b.1.3 Scaffolding in support of decommissioning 2,846 41 28 246 56 771 3,987 3,987 1,849 163 93,587 50,451 Decontamination of Site Buildings 4b.1.4.1 Reactor 1,458 2,094 161 1,596 721 2,910 2,344 11,283 11,283 5,995 45,300 2,386,838 48,576 4b.1.4.2 Auxiliary 739 294 17 138 247 242 563 2,240 2,240 2,058 3,514 250,317 15,255 4b.1.4.3 Communication Corridor - Contaminated 16 4

0 3

2 5

11 42 42 17 76 4,296 306 4b.1.4.4 Fuel Building 955 969 11 58 325 92 801 3,211 3,211 2,705 984 158,200 27,457 4b.1.4.5 Hot Machine Shop 20 8

0 3

6 14 52 52 94 4,446 421 4b.1.4.6 RAM Storage Building 51 10 1

7 2

12 32 115 115 19 195 9,974 920 4b.1.4.7 Radioactive and Personnel Tunnel 6

7 0

2 3

6 25 25 54 2,532 195 4b.1.4.8 Radwaste 394 134 8

71 102 125 288 1,122 1,122 844 1,857 122,469 7,815 4b.1.4.9 Radwaste Drum Storage 44 13 1

8 8

14 31 119 119 66 208 12,565 850 4b.1.4.10 Reactor Head Assembly Building 40 20 59 59 614 4b.1.4.11 Steam Generator Replacement Bldgs 295 147 442 442 3,885 4b.1.4 Totals 4,019 3,532 200 1,886 1,407 3,409 4,258 18,711 18,711 11,704 52,283 2,951,637 106,295 4b.1.5 Prepare/submit License Termination Plan 650 98 748 748 4,096 4b.1.6 Receive NRC approval of termination plan a

4b.1 Subtotal Period 4b Activity Costs 4,977 27,148 1,013 3,881 16,782 9,406 650 14,308 78,165 71,062 7,104 139,409 69,760 9,260,607 464,907 4,096 Period 4b Additional Costs 4b.2.1 License Termination Survey Planning 1,778 533 2,311 2,311 12,480 4b.2.2 Operational Tools & Equipment 22 103 866 148 1,139 1,139 11,700 292,500 32 4b.2.3 Excavation of Underground Services 1,879 551 552 2,982 2,982 12,396 4b.2.4 License Termination ISFSI 684 154 166 3,547 3,894 2,111 10,556 10,556 14,077 1,053,456 17,572 10,920 4b.2.5 Remedial Action Surveys 2,438 731 3,170 3,170 47,950 4b.2.6 Sanitary Treatment Lagoon 7

92 235 540 181 1,054 1,054 4,608 392,140 423 4b.2.7 Cooling Tower Asbestos Panel Removal 6,512 305 641 1,119 8,576 8,576 71,419 4b.2.8 Retired Reactor Closure Head 151 847 1,330 1,110 599 4,037 4,037 2,764 338,540 3,157 2,000 4b.2.9 Spent Fuel Pool Legacy Waste 108 163 67 2,617 14 710 3,680 3,680 250 14,900 1,333 53 4b.2 Subtotal Period 4b Additional Costs 9,340 1,278 2,206 866 7,814 9,316 6,685 37,504 28,928 8,576 11,700 21,449 250 2,091,536 154,282 25,453 Period 4b Collateral Costs 4b.3.1 Process decommissioning water waste 14 26 66 109 47 261 261 214 12,834 42 4b.3.2 Process decommissioning chemical flush waste 4b.3.3 Small tool allowance 625 94 719 719 4b.3.4 Decommissioning Equipment Disposition 133 101 799 181 194 1,408 1,408 6,000 529 303,608 147

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix D, Page 10 of 12 TLG Services, LLC Table D Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:15:15 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours 4b.3.5 On-site survey and release of 309.6 tons clean metallic waste 564 56 620 620 4b.3 Subtotal Period 4b Collateral Costs 14 625 160 166 799 290 564 390 3,007 3,007 6,000 743 316,441 189 Period 4b Period-Dependent Costs 4b.4.1 Decon supplies 1,947 487 2,434 2,434 4b.4.2 Insurance 1,563 156 1,719 1,719 4b.4.3 Property taxes 277 28 304 304 4b.4.4 Health physics supplies 7,041 1,760 8,801 8,801 4b.4.5 Heavy equipment rental 5,257 789 6,045 6,045 4b.4.6 Disposal of DAW generated 135 76 392 123 725 725 6,615 132,302 216 4b.4.7 Plant energy budget 3,552 533 4,085 4,085 4b.4.8 NRC Fees 1,362 136 1,498 1,498 4b.4.9 Liquid Radwaste Processing Equipment/Services 1,150 172 1,322 1,322 4b.4.10 Corporate Allocations 2,307 231 2,538 2,538 4b.4.11 Security Staff Cost 10,264 1,540 11,804 11,804 149,945 4b.4.12 DOC Staff Cost 35,739 5,361 41,100 41,100 321,483 4b.4.13 Utility Staff Cost 51,214 7,682 58,896 58,896 566,193 4b.4 Subtotal Period 4b Period-Dependent Costs 1,947 12,297 135 76 392 107,428 18,997 141,272 141,272 6,615 132,302 216 1,037,621 4b.0 TOTAL PERIOD 4b COST 6,939 49,411 2,586 6,328 18,447 17,901 117,958 40,380 259,949 244,269 15,680 157,109 98,567 250 11,800,890 619,593 1,067,170 PERIOD 4f - License Termination Period 4f Direct Decommissioning Activities 4f.1.1 ORISE confirmatory survey 168 50 218 218 4f.1.2 Terminate license a

4f.1 Subtotal Period 4f Activity Costs 168 50 218 218 Period 4f Additional Costs 4f.2.1 License Termination Survey 10,211 3,063 13,274 13,274 153,878 6,240 4f.2 Subtotal Period 4f Additional Costs 10,211 3,063 13,274 13,274 153,878 6,240 Period 4f Collateral Costs 4f.3.1 DOC staff relocation expenses 1,641 246 1,887 1,887 4f.3 Subtotal Period 4f Collateral Costs 1,641 246 1,887 1,887 Period 4f Period-Dependent Costs 4f.4.1 Insurance 4f.4.2 Property taxes 91 9

100 100 4f.4.3 Health physics supplies 1,316 329 1,645 1,645 4f.4.4 Disposal of DAW generated 7

4 21 7

39 39 353 7,050 11 4f.4.5 Plant energy budget 310 47 357 357 4f.4.6 NRC Fees 546 55 601 601 4f.4.7 Corporate Allocations 756 76 832 832 4f.4.8 Security Staff Cost 1,715 257 1,973 1,973 18,874 4f.4.9 DOC Staff Cost 6,532 980 7,511 7,511 57,408 4f.4.10 Utility Staff Cost 7,153 1,073 8,226 8,226 74,709 4f.4 Subtotal Period 4f Period-Dependent Costs 1,316 7

4 21 17,104 2,831 21,283 21,283 353 7,050 11 150,991 4f.0 TOTAL PERIOD 4f COST 1,316 7

4 21 29,123 6,191 36,662 36,662 353 7,050 153,889 157,231 PERIOD 4 TOTALS 7,228 96,274 24,150 17,007 35,573 75,330 216,598 100,118 572,277 551,114 21,162 313,752 185,646 751 406 2,217 25,229,630 1,138,735 1,882,270 PERIOD 5b - Site Restoration Period 5b Direct Decommissioning Activities Demolition of Remaining Site Buildings 5b.1.1.1 Reactor 3,482 522 4,004 4,004 27,502 5b.1.1.2 Auxiliary 2,865 430 3,295 3,295 19,024 5b.1.1.3 Auxiliary Boiler 26 4

30 30 248 5b.1.1.4 Barge Facility 957 144 1,101 1,101 4,290 5b.1.1.5 Circulating & Service Water Pumphouse 233 35 268 268 1,996 5b.1.1.6 Communication Corridor - Clean 1,079 162 1,241 1,241 8,280 5b.1.1.7 Communication Corridor - Contaminated 35 5

40 40 184 5b.1.1.8 Cooling Tower Concrete 451 68 519 519 2,332 5b.1.1.9 Diesel Generator 329 49 378 378 2,185 5b.1.1.10 Essential Service Water Pumphouse 176 26 203 203 955

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix D, Page 11 of 12 TLG Services, LLC Table D Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:15:15 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours 5b.1.1.11 Fire Water Pumphouse 23 3

26 26 151 5b.1.1.12 Flex Building Storage 337 51 388 388 1,972 5b.1.1.13 Fuel Building 1,209 181 1,390 1,390 7,874 5b.1.1.14 Hardened Condensate Storage Tank - HCST 243 36 279 279 1,870 5b.1.1.15 Hot Machine Shop 21 3

24 24 243 5b.1.1.16 Intake 219 33 252 252 1,411 5b.1.1.17 Misc. Structures 2,722 408 3,130 3,130 18,774 5b.1.1.18 Miscellaneous Site Foundations 194 29 223 223 1,011 5b.1.1.19 Outage Maintenance 140 21 161 161 1,570 5b.1.1.20 RAM Storage Building 59 9

68 68 624 5b.1.1.21 Radioactive and Personnel Tunnel 34 5

39 39 386 5b.1.1.22 Radwaste 1,196 179 1,375 1,375 8,111 5b.1.1.23 Radwaste Drum Storage 171 26 197 197 1,449 5b.1.1.24 Reactor Head Assembly Building 98 15 113 113 1,108 5b.1.1.25 Security Additions 1,655 248 1,903 1,903 6,051 5b.1.1.26 Service 522 78 600 600 3,485 5b.1.1.27 Sludge Pump Station & Lagoon 1,678 252 1,930 1,930 10,601 5b.1.1.28 Steam Generator Replacement Bldgs 976 146 1,122 1,122 6,874 5b.1.1.29 Turbine Building 4,906 736 5,642 5,642 47,075 5b.1.1.30 Turbine Pedestal 561 84 646 646 2,934 5b.1.1.31 U.H.S. Cooling Tower 343 51 395 395 1,814 5b.1.1.32 Water Treatment Plant 1

0 1

1 9

5b.1.1 Totals 26,942 4,041 30,983 30,983 192,393 Site Closeout Activities 5b.1.2 Remove Rubble 1,558 234 1,792 1,792 7,233 5b.1.3 Grade & landscape site 129 19 148 148 592 5b.1.4 Final report to NRC 248 37 285 285 1,560 5b.1 Subtotal Period 5b Activity Costs 28,629 248 4,331 33,208 285 32,923 200,218 1,560 Period 5b Additional Costs 5b.2.1 Concrete Crushing 1,546 19 235 1,800 1,800 6,035 5b.2.2 Mine Area Backfill 6,441 966 7,407 7,407 15,960 5b.2.3 Construction Debris 2,950 443 3,393 3,393 5b.2.4 Site Restoration ISFSI 1,416 97 227 1,740 1,740 10,514 160 5b.2.5 Cooling Tower Discharge & Intake Pipe Flow Fill 5,020 753 5,772 5,772 9,588 5b.2.6 Cooling Tower Demolition 5,495 824 6,320 6,320 21,619 5b.2 Subtotal Period 5b Additional Costs 19,918 3,067 3,448 26,432 26,432 63,716 160 Period 5b Collateral Costs 5b.3.1 Small tool allowance 329 49 379 379 5b.3 Subtotal Period 5b Collateral Costs 329 49 379 379 Period 5b Period-Dependent Costs 5b.4.1 Insurance 5b.4.2 Property taxes 180 18 198 198 5b.4.3 Heavy equipment rental 4,790 718 5,508 5,508 5b.4.4 Plant energy budget 309 46 355 355 5b.4.5 Corporate Allocations 1,504 150 1,655 1,655 5b.4.6 Security Staff Cost 3,412 512 3,924 3,924 37,543 5b.4.7 DOC Staff Cost 12,661 1,899 14,560 14,560 106,371 5b.4.8 Utility Staff Cost 5,808 871 6,679 6,679 61,007 5b.4 Subtotal Period 5b Period-Dependent Costs 4,790 23,874 4,215 32,879 32,879 204,920 5b.0 TOTAL PERIOD 5b COST 53,666 27,188 12,044 92,898 285 92,613 263,934 206,640 PERIOD 5 TOTALS 53,666 27,188 12,044 92,898 285 92,613 263,934 206,640 TOTAL COST TO DECOMMISSION 15,891 166,532 24,592 17,796 35,573 76,968 884,376 213,688 1,435,417 1,223,308 96,323 115,786 313,752 196,099 751 406 2,217 25,529,410 1,500,444 7,425,559

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix D, Page 12 of 12 TLG Services, LLC Table D Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Tue, Aug 8, 2023 at 10:15:15 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours TOTAL COST TO DECOMMISSION WITH 17.49% CONTINGENCY:

$1,435,417 thousands of 2023 dollars TOTAL NRC LICENSE TERMINATION COST IS 85.22% OR:

$1,223,308 thousands of 2023 dollars SPENT FUEL MANAGEMENT COST IS 6.71% OR:

$96,323 thousands of 2023 dollars NON-NUCLEAR DEMOLITION COST IS 8.07% OR:

$115,786 thousands of 2023 dollars TOTAL LOW-LEVEL RADIOACTIVE WASTE VOLUME BURIED (EXCLUDING GTCC):

197,255 Cubic Feet TOTAL GREATER THAN CLASS C RADWASTE VOLUME GENERATED:

2,217 Cubic Feet TOTAL SCRAP METAL REMOVED:

71,143 Tons TOTAL CRAFT LABOR REQUIREMENTS:

1,500,444 Man-hours End Notes:

n/a - indicates that this activity not charged as decommissioning expense a - indicates that this activity performed by decommissioning staff 0 - indicates that this value is less than 0.5 but is non-zero A cell containing " - " indicates a zero value

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix E, Page 1 of 10 TLG Services, LLC APPENDIX E DETAILED COST ANALYSIS DECON with DIRECT DISPOSAL OF LOW-LEVEL RADIOACTIVE WASTE 5 E: DECON Decommissioning Cost Estimate with Direct Disposal of Low-Level Radioactive Waste

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix E, Page 2 of 10 Table E Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:21:57 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours PERIOD 1a - Shutdown through Transition Period 1a Direct Decommissioning Activities 1a.1.1 Prepare preliminary decommissioning cost 206 31 237 237 1,300 1a.1.2 Notification of Cessation of Operations a

1a.1.3 Remove fuel & source material n/a 1a.1.4 Notification of Permanent Defueling a

1a.1.5 Deactivate plant systems & process waste a

1a.1.6 Prepare and submit PSDAR 317 48 365 365 2,000 1a.1.7 Review plant dwgs & specs.

730 110 840 840 4,600 1a.1.8 Perform detailed rad survey a

1a.1.9 Estimate by-product inventory 159 24 183 183 1,000 1a.1.10 End product description 159 24 183 183 1,000 1a.1.11 Detailed by-product inventory 206 31 237 237 1,300 1a.1.12 Define major work sequence 1,190 179 1,369 1,369 7,500 1a.1.13 Perform SER and EA 492 74 566 566 3,100 1a.1.14 Prepare/submit Defueled Technical Specifications 1,190 179 1,369 1,369 7,500 1a.1.15 Perform Site-Specific Cost Study 794 119 913 913 5,000 1a.1.16 Prepare/submit Irradiated Fuel Management Plan 159 24 183 183 1,000 Activity Specifications 1a.1.17.1 Plant & temporary facilities 781 117 898 808 90 4,920 1a.1.17.2 Plant systems 661 99 761 684 76 4,167 1a.1.17.3 NSSS Decontamination Flush 79 12 91 91 500 1a.1.17.4 Reactor internals 1,127 169 1,296 1,296 7,100 1a.1.17.5 Reactor vessel 1,032 155 1,186 1,186 6,500 1a.1.17.6 Biological shield 79 12 91 91 500 1a.1.17.7 Steam generators 495 74 569 569 3,120 1a.1.17.8 Reinforced concrete 254 38 292 146 146 1,600 1a.1.17.9 Main Turbine 63 10 73 73 400 1a.1.17.10 Main Condensers 63 10 73 73 400 1a.1.17.11 Plant structures & buildings 495 74 569 285 285 3,120 1a.1.17.12 Waste management 730 110 840 840 4,600 1a.1.17.13 Facility & site closeout 143 21 164 82 82 900 1a.1.17 Total 6,004 901 6,904 6,080 825 37,827 Planning & Site Preparations 1a.1.18 Prepare dismantling sequence 381 57 438 438 2,400 1a.1.19 Plant prep. & temp. svces 4,000 600 4,600 4,600 1a.1.20 Design water clean-up system 222 33 256 256 1,400 1a.1.21 Rigging/Cont. Cntrl Envlps/tooling/etc.

2,800 420 3,220 3,220 1a.1.22 Procure casks/liners & containers 195 29 225 225 1,230 1a.1 Subtotal Period 1a Activity Costs 19,205 2,881 22,086 21,261 825 78,157 Period 1a Collateral Costs 1a.3.1 Spent Fuel Capital and Transfer 10,080 1,512 11,592 11,592 1a.3 Subtotal Period 1a Collateral Costs 10,080 1,512 11,592 11,592 Period 1a Period-Dependent Costs 1a.4.1 Insurance 3,972 397 4,370 4,370 1a.4.2 Property taxes 120 12 132 132 1a.4.3 Health physics supplies 888 222 1,110 1,110 1a.4.4 Heavy equipment rental 657 99 755 755 1a.4.5 Disposal of DAW generated 12 7

36 11 67 67 610 12,190 20 1a.4.6 Plant energy budget 2,053 308 2,361 2,361 1a.4.7 NRC Fees 1,321 132 1,453 1,453 1a.4.8 Emergency Planning Fees 1,620 162 1,782 1,782 1a.4.9 INPO Fees 358 54 411 411 1a.4.10 Spent Fuel Pool O&M 988 148 1,136 1,136 1a.4.11 ISFSI Operating Costs 127 19 146 146 1a.4.12 Corporate Allocations 1,000 100 1,100 1,100 1a.4.13 Security Staff Cost 15,699 2,355 18,054 18,054 251,680 1a.4.14 Utility Staff Cost 37,678 5,652 43,329 43,329 422,240 1a.4 Subtotal Period 1a Period-Dependent Costs 1,545 12 7

36 64,936 9,670 76,207 73,142 3,064 610 12,190 20 673,920 1a.0 TOTAL PERIOD 1a COST 1,545 12 7

36 94,221 14,063 109,884 94,403 14,656 825 610 12,190 20 752,077 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix E, Page 3 of 10 Table E Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:21:57 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours PERIOD 1b - Decommissioning Preparations Period 1b Direct Decommissioning Activities Detailed Work Procedures 1b.1.1.1 Plant systems 751 113 864 778 86 4,733 1b.1.1.2 NSSS Decontamination Flush 159 24 183 183 1,000 1b.1.1.3 Reactor internals 397 60 456 456 2,500 1b.1.1.4 Remaining buildings 214 32 246 62 185 1,350 1b.1.1.5 CRD cooling assembly 159 24 183 183 1,000 1b.1.1.6 CRD housings & ICI tubes 159 24 183 183 1,000 1b.1.1.7 Incore instrumentation 159 24 183 183 1,000 1b.1.1.8 Reactor vessel 576 86 663 663 3,630 1b.1.1.9 Facility closeout 190 29 219 110 110 1,200 1b.1.1.10 Missile shields 71 11 82 82 450 1b.1.1.11 Biological shield 190 29 219 219 1,200 1b.1.1.12 Steam generators 730 110 840 840 4,600 1b.1.1.13 Reinforced concrete 159 24 183 91 91 1,000 1b.1.1.14 Main Turbine 248 37 285 285 1,560 1b.1.1.15 Main Condensers 248 37 285 285 1,560 1b.1.1.16 Auxiliary building 433 65 498 448 50 2,730 1b.1.1.17 Reactor building 433 65 498 448 50 2,730 1b.1.1 Total 5,276 791 6,068 4,927 1,141 33,243 1b.1.2 Decon primary loop 973 486 1,459 1,459 1,067 1b.1 Subtotal Period 1b Activity Costs 973 5,276 1,278 7,527 6,386 1,141 1,067 33,243 Period 1b Additional Costs 1b.2.1 Spent Fuel Pool Isolation 14,330 2,150 16,480 16,480 1b.2.2 Site Characterization 3,198 959 4,158 4,158 19,100 7,852 1b.2 Subtotal Period 1b Additional Costs 17,529 3,109 20,638 20,638 19,100 7,852 Period 1b Collateral Costs 1b.3.1 Decon equipment 1,193 179 1,371 1,371 1b.3.2 DOC staff relocation expenses 1,641 246 1,887 1,887 1b.3.3 Process decommissioning water waste 49 35 87 144 77 392 392 283 16,989 55 1b.3.4 Process decommissioning chemical flush waste 2

92 369 2,012 569 3,044 3,044 788 83,917 147 1b.3.5 Small tool allowance 2

0 3

3 1b.3.6 Pipe cutting equipment 1,400 210 1,610 1,610 1b.3.7 Decon rig 2,451 368 2,819 2,819 1b.3.8 Spent Fuel Capital and Transfer 5,040 756 5,796 5,796 1b.3 Subtotal Period 1b Collateral Costs 3,696 1,402 127 456 2,156 6,681 2,405 16,922 11,126 5,796 283 788 100,906 203 Period 1b Period-Dependent Costs 1b.4.1 Decon supplies 43 11 54 54 1b.4.2 Insurance 2,002 200 2,203 2,203 1b.4.3 Property taxes 60 6

66 66 1b.4.4 Health physics supplies 502 126 628 628 1b.4.5 Heavy equipment rental 331 50 381 381 1b.4.6 Disposal of DAW generated 7

4 21 7

39 39 360 7,197 12 1b.4.7 Plant energy budget 2,070 310 2,380 2,380 1b.4.8 NRC Fees 400 40 440 440 1b.4.9 Emergency Planning Fees 817 82 899 899 1b.4.10 Spent Fuel Pool O&M 498 75 573 573 1b.4.11 ISFSI Operating Costs 64 10 73 73 1b.4.12 Corporate Allocations 504 50 555 555 1b.4.13 Security Staff Cost 7,914 1,187 9,101 9,101 126,874 1b.4.14 DOC Staff Cost 7,234 1,085 8,319 8,319 63,961 1b.4.15 Utility Staff Cost 19,087 2,863 21,950 21,950 213,904 1b.4 Subtotal Period 1b Period-Dependent Costs 43 833 7

4 21 40,652 6,101 47,662 46,117 1,545 360 7,197 12 404,740 1b.0 TOTAL PERIOD 1b COST 4,711 2,236 134 460 2,178 70,137 12,893 92,748 84,266 7,341 1,141 643 788 108,103 20,381 445,835 PERIOD 1 TOTALS 4,711 3,780 146 467 2,214 164,358 26,956 202,633 178,670 21,997 1,966 1,253 788 120,293 20,401 1,197,911 PERIOD 2a - Large Component Removal TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix E, Page 4 of 10 Table E Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:21:57 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Period 2a Direct Decommissioning Activities Nuclear Steam Supply System Removal 2a.1.1.1 Reactor Coolant Piping 244 244 39 136 768 399 1,830 1,830 2,046 142,726 6,863 2a.1.1.2 Pressurizer Relief Tank 41 34 11 38 217 90 432 432 578 40,338 1,077 2a.1.1.3 Reactor Coolant Pumps & Motors 124 125 185 267 1,483 523 2,708 2,708 3,386 816,140 4,188 100 2a.1.1.4 Pressurizer 80 839 208 1,638 545 3,310 3,310 3,739 293,734 1,666 1,875 2a.1.1.5 Steam Generators 8,305 4,689 3,380 16,197 7,102 39,674 39,674 63,478 3,570,150 23,279 3,500 2a.1.1.6 Retired Steam Generator Units 3,353 3,319 16,000 4,833 27,505 27,505 62,808 3,349,305 10,852 2,250 2a.1.1.7 CRDMs/ICIs/Service Structure Removal 207 353 230 141 783 432 2,145 2,145 3,881 145,494 7,976 2a.1.1.8 Reactor Vessel Internals 112 6,004 12,696 1,844 18,156 393 17,331 56,535 56,535 2,764 1,230 393 336,142 32,573 1,461 2a.1.1.9 Vessel & Internals GTCC Disposal 13,035 1,955 14,990 14,990 2,217 433,180 2a.1.1.10 Reactor Vessel 141 7,737 3,180 1,898 5,983 393 10,193 29,525 29,525 13,715 973,586 32,573 1,461 2a.1.1 Totals 870 22,883 25,222 11,231 74,261 785 43,403 178,655 178,655 156,395 1,230 393 2,217 10,100,790 121,047 10,648 Removal of Major Equipment 2a.1.2 Main Turbine/Generator 686 2,848 491 17,692 4,953 26,671 26,671 54,809 3,481,857 9,888 2a.1.3 Main Condensers 1,923 1,386 2,399 21,985 6,475 34,167 34,167 64,324 4,086,353 27,762 Cascading Costs from Clean Building Demolition 2a.1.4.1 Reactor 612 92 704 704 4,832 2a.1.4.2 Auxiliary 318 48 366 366 2,113 2a.1.4.3 Hot Machine Shop 1

0 1

1 7

2a.1.4.4 Radwaste 61 9

70 70 387 2a.1.4.5 Fuel Building 129 19 149 149 795 2a.1.4 Totals 1,121 168 1,290 1,290 8,134 Disposal of Plant Systems 2a.1.5.1 100 Aux.Bldg Non-System Specific RCA 920 108 204 1,867 738 3,838 3,838 5,463 347,071 13,677 2a.1.5.2 100 Auxiliary Bldg Non-System Specific 151 12 23 212 95 494 494 621 39,480 2,291 2a.1.5.3 AB - Main Steam 366 55 420 420 5,833 2a.1.5.4 AB - Main Steam RCA 103 33 58 531 171 896 896 1,547 98,672 1,580 2a.1.5.5 AC - Main Turbine 361 54 415 415 5,641 2a.1.5.6 AD - Condensate 401 60 461 461 6,144 2a.1.5.7 AE - Feedwater 275 41 316 316 4,271 2a.1.5.8 AF - Feedwater Heater Extraction 337 51 388 388 5,352 2a.1.5.9 AK - Condensate Demineralizer 125 19 143 143 1,944 2a.1.5.10 AL - Auxiliary Feedwater 54 8

63 63 852 2a.1.5.11 AQ - Condensate & Feedwater Chem Addtn 30 5

35 35 468 2a.1.5.12 BM - Steam Generator Blowdown 158 19 31 287 118 613 613 832 53,260 2,415 2a.1.5.13 BM - Steam Generator Blowdown - RCA 491 75 112 1,024 403 2,105 2,105 2,963 190,396 7,221 2a.1.5.14 BN - Borated Refueling Water Storage 457 95 167 1,535 533 2,787 2,787 4,482 285,246 7,044 2a.1.5.15 CA - Steam Seal 29 4

33 33 455 2a.1.5.16 CB - Main Turbine Lube Oil 82 12 95 95 1,207 2a.1.5.17 CC - Generator Hydrogen Seal & CO2 13 2

15 15 198 2a.1.5.18 CD - Generator Seal Oil 19 3

22 22 287 2a.1.5.19 CE - Stator Cooling Water 16 2

19 19 241 2a.1.5.20 CF - Lube Oil Storage Xfer & Prfication 53 8

61 61 812 2a.1.5.21 CG - Condenser Air Removal 43 6

49 49 657 2a.1.5.22 CH - Main Turbine Control Oil 85 13 97 97 1,219 2a.1.5.23 DA - Circulating Water 473 71 544 544 7,502 2a.1.5.24 DB - Cooling Tower Makeup & Blowdown 80 12 92 92 1,260 2a.1.5.25 DD - Cooling Water Chemical Control Sys 71 11 81 81 1,084 2a.1.5.26 DD - Cooling Wtr Chem Control RCA 361 69 97 891 335 1,753 1,753 2,569 165,613 5,095 2a.1.5.27 EJ - Residual Heat Removal 524 95 164 1,506 542 2,831 2,831 4,385 280,003 8,105 2a.1.5.28 EM - High Pressure Coolant Injection 438 41 60 554 261 1,356 1,356 1,599 103,047 6,672 2a.1.5.29 EN - Containment Spray 288 53 82 752 277 1,452 1,452 2,179 139,742 4,242 2a.1.5.30 EP - Accumulator Safety Injection 231 35 54 495 193 1,008 1,008 1,433 91,944 3,516 2a.1.5.31 FA - Auxiliary Steam Generator 32 5

37 37 521 2a.1.5.32 FB - Auxiliary Steam 133 20 152 152 2,106 2a.1.5.33 FB - Auxiliary Steam RCA 109 15 22 204 83 433 433 589 37,925 1,569 2a.1.5.34 FC - Auxiliary Turbines 87 13 100 100 1,320 2a.1.5.35 FE - Auxiliary Steam Chemical Addition 7

1 8

8 105 2a.1.5.36 GE - Turbine Building HVAC 240 36 276 276 3,957 2a.1.5.37 GS - Containment Hydrogen Control 101 13 22 199 80 414 414 577 36,925 1,574 2a.1.5.38 HE - Boron Recycle 529 668 77 123 1,129 740 3,267 3,267 3,280 209,922 16,718 2a.1.5.39 HF - Secondary Liquid Waste 975 1,319 175 287 2,629 1,535 6,920 6,920 7,644 488,595 32,027 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix E, Page 5 of 10 Table E Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:21:57 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Disposal of Plant Systems (continued) 2a.1.5.40 JA - Auxiliary Oil & Transfer 43 7

50 50 690 2a.1.5.41 KS - Bulk Chemical Storage 122 94 172 1,580 461 2,429 2,429 4,620 293,686 2,002 2a.1.5.42 LE - Oily Waste 246 37 282 282 3,865 2a.1.5.43 LE - Oily Waste RCA 313 38 61 559 231 1,201 1,201 1,623 103,828 4,372 2a.1.5.44 Turbine Bldg Non-System Specific 1,031 155 1,185 1,185 15,405 2a.1.5 Totals 1,504 11,484 1,049 1,741 15,954 7,505 39,236 33,797 5,440 46,409 2,965,355 193,518 2a.1.6 Scaffolding in support of decommissioning 2,067 23 41 372 618 3,121 3,121 1,087 69,064 36,741 2a.1 Subtotal Period 2a Activity Costs 2,374 40,164 30,528 15,902 130,263 785 63,122 283,140 277,700 5,440 323,024 1,230 393 2,217 20,703,420 397,090 10,648 Period 2a Additional Costs 2a.2.1 Remedial Action Surveys 1,824 547 2,372 2,372 35,877 2a.2 Subtotal Period 2a Additional Costs 1,824 547 2,372 2,372 35,877 Period 2a Collateral Costs 2a.3.1 Process decommissioning water waste 214 152 382 634 338 1,720 1,720 1,246 74,768 243 2a.3.2 Process decommissioning chemical flush waste 1

48 192 371 127 739 739 410 43,711 77 2a.3.3 Small tool allowance 449 67 516 465 52 2a.3.4 Spent Fuel Capital and Transfer 18,270 2,741 21,011 21,011 2a.3 Subtotal Period 2a Collateral Costs 215 449 200 574 1,005 18,270 3,273 23,986 2,923 21,011 52 1,656 118,478 320 Period 2a Period-Dependent Costs 2a.4.1 Decon supplies 147 37 184 184 2a.4.2 Insurance 1,169 117 1,286 1,286 2a.4.3 Property taxes 207 21 228 228 2a.4.4 Health physics supplies 5,131 1,283 6,414 6,414 2a.4.5 Heavy equipment rental 3,836 575 4,411 4,411 2a.4.6 Disposal of DAW generated 132 74 385 121 712 712 6,501 130,017 212 2a.4.7 Plant energy budget 3,366 505 3,871 3,871 2a.4.8 NRC Fees 1,246 125 1,370 1,370 2a.4.9 Emergency Planning Fees 1,728 173 1,900 1,900 2a.4.10 Spent Fuel Pool O&M 1,706 256 1,962 1,962 2a.4.11 ISFSI Operating Costs 218 33 251 251 2a.4.12 Corporate Allocations 1,726 173 1,899 1,899 2a.4.13 Security Staff Cost 25,225 3,784 29,008 29,008 387,735 2a.4.14 DOC Staff Cost 30,559 4,584 35,143 35,143 272,850 2a.4.15 Utility Staff Cost 46,358 6,954 53,311 53,311 508,004 2a.4 Subtotal Period 2a Period-Dependent Costs 147 8,967 132 74 385 113,507 18,738 141,951 137,838 4,113 6,501 130,017 212 1,168,590 2a.0 TOTAL PERIOD 2a COST 2,737 49,580 30,860 16,551 131,653 134,387 85,680 451,447 420,833 25,124 5,491 331,181 1,230 393 2,217 20,951,920 433,498 1,179,237 PERIOD 2b - Site Decontamination Period 2b Direct Decommissioning Activities Disposal of Plant Systems 2b.1.1.1 200 Reactor Bldg Non-System Specific 120 7

14 129 65 337 337 378 24,042 1,765 2b.1.1.2 200 Reactor Bldg Non-System Specific RCA 752 68 127 1,167 506 2,620 2,620 3,414 216,897 10,554 2b.1.1.3 300 Control Bldg Non-System Specific 236 30 57 523 202 1,049 1,049 1,532 97,294 3,471 2b.1.1.4 300 Control Bldg Non-System Specific Cln 1,836 275 2,111 2,111 29,076 2b.1.1.5 700 Radwaste Bldg Non-Sys Specific RCA 1,514 180 339 3,105 1,223 6,361 6,361 9,083 577,051 22,261 2b.1.1.6 700 Radwaste Bldg Non-System Specific 243 19 37 342 154 796 796 1,002 63,635 3,667 2b.1.1.7 AN - Demineralized Wtr Storage & Xfer 208 31 239 239 3,283 2b.1.1.8 AN - Demineralized Wtr Strg & Xfer RCA 53 6

9 79 35 182 182 227 14,650 753 2b.1.1.9 AP -HCST/Condensate Stor.& Transfr 275 41 316 316 4,018 2b.1.1.10 BB - Reactor Coolant System 453 65 112 1,025 393 2,047 2,047 2,987 190,474 7,115 2b.1.1.11 BG - Chemical & Volume Control 1,143 1,276 193 318 2,918 1,687 7,535 7,535 8,476 542,341 28,266 2b.1.1.12 BL - Reactor Makeup Water 408 52 84 768 312 1,624 1,624 2,234 142,818 6,176 2b.1.1.13 DE - Intake & Water Treatment 166 25 191 191 2,517 2b.1.1.14 DE - Intake & Water Treatment RCA 331 175 319 2,925 879 4,630 4,630 8,546 543,623 5,351 2b.1.1.15 EA - Service Water 197 30 227 227 3,145 2b.1.1.16 EA - Service Water RCA 59 19 33 307 98 516 516 895 57,005 876 2b.1.1.17 EB - Closed Cooling Water 80 12 92 92 1,267 2b.1.1.18 EF - Essential Service Water 458 69 527 527 7,244 2b.1.1.19 EF - Essential Service Water RCA 263 81 143 1,309 422 2,218 2,218 3,820 243,301 4,018 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix E, Page 6 of 10 Table E Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:21:57 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Disposal of Plant Systems (continued) 2b.1.1.20 EG - Component Cooling Water RCA 336 50 386 386 5,335 2b.1.1.21 GA - Plant Heating 120 18 138 138 1,912 2b.1.1.22 GA - Plant Heating RCA 126 14 18 162 76 395 395 463 30,040 1,795 2b.1.1.23 GB - Central Chilled Water 113 17 130 130 1,803 2b.1.1.24 GB - Central Chilled Water RCA 34 4

5 47 22 112 112 136 8,778 490 2b.1.1.25 GD - Essential Serv Wtr Pumphouse HVAC 25 4

29 29 427 2b.1.1.26 GF - Miscellaneous Building HVAC 155 29 54 498 174 911 911 1,457 92,563 2,081 2b.1.1.27 GH - Radwaste Building HVAC 240 35 68 627 230 1,201 1,201 1,834 116,569 3,502 2b.1.1.28 GK - Control Building HVAC 231 35 266 266 3,959 2b.1.1.29 GL - Auxiliary Building HVAC 592 75 144 1,318 507 2,636 2,636 3,855 245,020 8,590 2b.1.1.30 GM - Diesel Generator Building HVAC 40 6

46 46 695 2b.1.1.31 GN - Containment Cooling 661 118 221 2,027 717 3,744 3,744 5,923 376,780 9,749 2b.1.1.32 GP - Containment Intgratd Leak Rate Test 52 9

16 143 52 272 272 417 26,623 768 2b.1.1.33 GR - Containment Atmospheric Control 26 16 31 280 83 435 435 818 51,989 413 2b.1.1.34 GT - Containment Purge HVAC 155 31 58 535 184 963 963 1,566 99,513 2,297 2b.1.1.35 HA - Gaseous Radwaste 476 65 100 919 370 1,929 1,929 2,664 170,799 7,097 2b.1.1.36 HB - Liquid Radwaste 1,055 1,161 159 253 2,319 1,451 6,397 6,397 6,735 430,985 31,019 2b.1.1.37 HC - Solid Radwaste 495 67 113 1,033 406 2,114 2,114 3,006 192,060 7,493 2b.1.1.38 HD - Decontamination 138 20 33 302 117 609 609 877 56,053 2,072 2b.1.1.39 JE - Emergency Fuel Oil 86 13 99 99 1,260 2b.1.1.40 KA - Compressed Air 262 39 301 301 4,187 2b.1.1.41 KA - Compressed Air RCA 169 19 22 204 99 513 513 583 37,947 2,380 2b.1.1.42 KB - Breathing Air 33 5

38 38 516 2b.1.1.43 KB - Breathing Air RCA 26 2

2 18 12 60 60 52 3,401 406 2b.1.1.44 KC - Fire Protection 514 77 591 591 8,376 2b.1.1.45 KC - Fire Protection RCA 530 86 121 1,106 436 2,279 2,279 3,189 205,625 7,245 2b.1.1.46 KD - Domestic Water 239 36 275 275 3,837 2b.1.1.47 KD - Domestic Water RCA 34 5

7 62 25 132 132 178 11,465 468 2b.1.1.48 KE - Fuel Handling & Storage Rctor vssl 25 12 24 216 65 342 342 632 40,119 388 2b.1.1.49 KH - Service Gas (CO2 N2 H2 & O2) 76 11 87 87 1,226 2b.1.1.50 KH - Service Gas (CO2 N2 H2 & O2) RCA 333 45 66 608 250 1,302 1,302 1,756 112,949 4,575 2b.1.1.51 KJ - Standby Diesel Engine 454 68 523 523 6,749 2b.1.1.52 LA - Sanitary Drains 61 9

70 70 972 2b.1.1.53 LA - Sanitary Drains RCA 140 21 34 315 121 632 632 916 58,593 1,854 2b.1.1.54 LB - Roof Drains 81 12 93 93 1,276 2b.1.1.55 LB - Roof Drains RCA 190 32 57 526 191 996 996 1,534 97,740 2,757 2b.1.1.56 LD - Chemical & Detergent Waste 92 159 14 22 198 140 625 625 574 36,840 3,503 2b.1.1.57 LF - Floor & Equipment Drains 1,970 183 316 2,893 1,281 6,643 6,643 8,419 537,647 29,417 2b.1.1.58 RM - Process Sampling & Analysis 182 20 27 249 114 592 592 717 46,349 2,792 2b.1.1.59 SJ - Nuclear Sampling 106 14 19 171 73 382 382 491 31,744 1,632 2b.1.1.60 UB - Servces Stores Site Security Bldg 245 37 282 282 3,815 2b.1.1.61 Yard Non-System Specific 41 6

47 47 603 2b.1.1 Totals 2,290 20,061 1,989 3,424 31,373 14,098 73,233 66,129 7,104 91,385 5,831,320 326,556 2b.1.2 Scaffolding in support of decommissioning 2,584 29 51 464 773 3,901 3,901 1,359 86,330 45,926 Decontamination of Site Buildings 2b.1.3.1 Reactor 1,628 2,446 258 1,747 9,929 4,196 20,204 20,204 61,873 2,713,720 56,041 2b.1.3.2 Auxiliary 842 489 58 291 963 834 3,478 3,478 8,629 422,631 19,470 2b.1.3.3 Communication Corridor - Contaminated 19 8

1 6

14 16 63 63 164 7,935 395 2b.1.3.4 Hot Machine Shop 23 17 1

6 12 20 79 79 188 8,892 597 2b.1.3.5 RAM Storage Building 58 20 2

14 29 43 166 166 415 19,255 1,162 2b.1.3.6 Radioactive and Personnel Tunnel 8

16 0

4 7

10 44 44 106 5,022 335 2b.1.3.7 Radwaste 448 236 26 148 447 420 1,724 1,724 4,322 212,823 10,019 2b.1.3.8 Radwaste Drum Storage 50 24 2

16 43 45 180 180 460 22,567 1,094 2b.1.3.9 Reactor Head Assembly Building 44 22 66 66 691 2b.1.3.10 Steam Generator Replacement Bldgs 331 165 496 496 4,358 2b.1.3 Totals 3,450 3,257 348 2,231 11,444 5,770 26,500 26,500 76,157 3,412,845 94,163 2b.1.4 Prepare/submit License Termination Plan 650 98 748 748 4,096 2b.1.5 Receive NRC approval of termination plan a

2b.1 Subtotal Period 2b Activity Costs 5,740 25,902 2,366 5,705 43,281 650 20,738 104,382 97,278 7,104 168,901 9,330,495 466,645 4,096 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix E, Page 7 of 10 Table E Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:21:57 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Period 2b Additional Costs 2b.2.1 Remedial Action Surveys 2,401 720 3,121 3,121 47,209 2b.2.2 Sanitary Treatment Lagoon 7

92 235 540 181 1,054 1,054 4,608 392,140 423 2b.2.3 Cooling Tower Asbestos Panel Removal 6,512 305 641 1,119 8,576 8,576 71,419 2b.2.4 Operational Equipment 22 235 1,574 431 2,261 2,261 11,700 292,500 32 2b.2.5 Retired Reactor Closure Head 151 847 1,330 1,110 599 4,037 4,037 2,764 338,540 3,157 2,000 2b.2.6 Spent Fuel Pool Legacy Waste 108 163 67 2,617 14 710 3,680 3,680 250 14,900 1,333 53 2b.2 Subtotal Period 2b Additional Costs 6,778 1,124 2,171 5,841 3,056 3,760 22,729 14,153 8,576 19,072 250 1,038,080 123,574 2,053 Period 2b Collateral Costs 2b.3.1 Process decommissioning water waste 187 136 342 568 300 1,534 1,534 1,117 66,992 218 2b.3.2 Process decommissioning chemical flush waste 4

157 626 1,209 414 2,409 2,409 1,338 142,540 250 2b.3.3 Small tool allowance 583 87 670 670 2b.3.4 Spent Fuel Capital and Transfer 22,680 3,402 26,082 26,082 2b.3 Subtotal Period 2b Collateral Costs 191 583 293 969 1,777 22,680 4,204 30,695 4,613 26,082 2,454 209,532 468 Period 2b Period-Dependent Costs 2b.4.1 Decon supplies 1,889 472 2,362 2,362 2b.4.2 Insurance 1,539 154 1,693 1,693 2b.4.3 Property taxes 272 27 300 300 2b.4.4 Health physics supplies 6,892 1,723 8,615 8,615 2b.4.5 Heavy equipment rental 5,176 776 5,952 5,952 2b.4.6 Disposal of DAW generated 135 76 392 123 725 725 6,613 132,265 216 2b.4.7 Plant energy budget 3,497 525 4,022 4,022 2b.4.8 NRC Fees 1,639 164 1,803 1,803 2b.4.9 Emergency Planning Fees 2,273 227 2,501 2,501 2b.4.10 Spent Fuel Pool O&M 2,244 337 2,581 2,581 2b.4.11 Liquid Radwaste Processing Equipment/Services 566 85 651 651 2b.4.12 ISFSI Operating Costs 287 43 331 331 2b.4.13 Corporate Allocations 2,271 227 2,498 2,498 2b.4.14 Security Staff Cost 30,845 4,627 35,472 35,472 510,210 2b.4.15 DOC Staff Cost 38,792 5,819 44,611 44,611 344,864 2b.4.16 Utility Staff Cost 58,488 8,773 67,261 67,261 640,124 2b.4 Subtotal Period 2b Period-Dependent Costs 1,889 12,068 135 76 392 142,715 24,102 181,376 175,964 5,412 6,613 132,265 216 1,495,198 2b.0 TOTAL PERIOD 2b COST 7,820 45,331 3,917 8,921 51,290 169,101 52,803 339,183 292,009 31,494 15,680 197,041 250 10,710,370 590,902 1,501,347 PERIOD 2d - Decontamination Following Wet Fuel Storage Period 2d Direct Decommissioning Activities 2d.1.1 Remove spent fuel racks 1,060 112 294 261 2,389 1,223 5,338 5,338 6,988 443,960 1,925 Disposal of Plant Systems 2d.1.2.1 600 Fuel Bldg Non-Specific Systems RCA 411 46 85 783 316 1,641 1,641 2,292 145,605 5,946 2d.1.2.2 600 Fuel Bldg Non-System Specific 64 5

9 83 39 199 199 242 15,399 957 2d.1.2.3 EC - Fuel Pool Cooling & Cleanup 535 68 111 1,021 413 2,148 2,148 2,965 189,813 8,118 2d.1.2.4 GA-Plant Heating Fuel Building 30 2

3 27 15 77 77 78 5,037 451 2d.1.2.5 GG - Fuel Building HVAC 326 55 105 966 344 1,796 1,796 2,825 179,529 4,745 2d.1.2.6 KC-Fire Protection Fuel Building 157 24 34 311 124 650 650 896 57,758 2,166 2d.1.2 Totals 1,523 199 348 3,191 1,251 6,512 6,512 9,298 593,141 22,383 Decontamination of Site Buildings 2d.1.3.1 Fuel Building 1,070 1,141 74 140 841 1,059 4,324 4,324 3,849 218,838 31,668 2d.1.3 Totals 1,070 1,141 74 140 841 1,059 4,324 4,324 3,849 218,838 31,668 2d.1.4 Scaffolding in support of decommissioning 517 6

10 93 155 780 780 272 17,266 9,185 2d.1 Subtotal Period 2d Activity Costs 2,130 3,292 573 759 6,513 3,687 16,954 16,954 20,407 1,273,206 65,161 Period 2d Additional Costs 2d.2.1 License Termination Survey Planning 1,778 533 2,311 2,311 12,480 2d.2.2 License Termination ISFSI 684 154 166 3,547 3,894 2,111 10,556 10,556 14,077 1,053,456 17,572 10,920 2d.2.3 Excavation of Underground Services 1,879 551 552 2,982 2,982 12,396 2d.2.4 Remedial Action Surveys 704 211 915 915 13,838 2d.2 Subtotal Period 2d Additional Costs 2,562 154 166 3,547 6,927 3,408 16,764 16,764 14,077 1,053,456 43,806 23,400 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix E, Page 8 of 10 Table E Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:21:57 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Period 2d Collateral Costs 2d.3.1 Process decommissioning water waste 100 73 184 306 161 824 824 601 36,070 117 2d.3.2 Process decommissioning chemical flush waste 2d.3.3 Small tool allowance 114 17 131 131 2d.3.4 Decommissioning Equipment Disposition 114 197 1,808 493 2,612 2,612 5,290 336,079 147 2d.3 Subtotal Period 2d Collateral Costs 100 114 187 382 2,114 671 3,567 3,567 5,891 372,149 264 Period 2d Period-Dependent Costs 2d.4.1 Decon supplies 276 69 345 345 2d.4.2 Insurance 451 45 496 496 2d.4.3 Property taxes 80 8

88 88 2d.4.4 Health physics supplies 1,392 348 1,739 1,739 2d.4.5 Heavy equipment rental 1,517 228 1,745 1,745 2d.4.6 Disposal of DAW generated 42 24 123 39 228 228 2,081 41,624 68 2d.4.7 Plant energy budget 547 82 629 629 2d.4.8 NRC Fees 454 45 499 499 2d.4.9 Liquid Radwaste Processing Equipment/Services 332 50 382 382 2d.4.10 Corporate Allocations 666 67 732 732 2d.4.11 Security Staff Cost 1,850 277 2,127 2,127 20,772 2d.4.12 DOC Staff Cost 7,766 1,165 8,931 8,931 69,238 2d.4.13 Utility Staff Cost 12,053 1,808 13,861 13,861 130,861 2d.4 Subtotal Period 2d Period-Dependent Costs 276 2,909 42 24 123 24,198 4,230 31,802 31,802 2,081 41,624 68 220,870 2d.0 TOTAL PERIOD 2d COST 2,505 8,877 956 1,330 12,297 31,124 11,997 69,087 69,087 42,457 2,740,434 109,300 244,270 PERIOD 2f - License Termination Period 2f Direct Decommissioning Activities 2f.1.1 ORISE confirmatory survey 168 50 218 218 2f.1.2 Terminate license a

2f.1 Subtotal Period 2f Activity Costs 168 50 218 218 Period 2f Additional Costs 2f.2.1 License Termination Survey 10,211 3,063 13,274 13,274 153,878 6,240 2f.2 Subtotal Period 2f Additional Costs 10,211 3,063 13,274 13,274 153,878 6,240 Period 2f Collateral Costs 2f.3.1 DOC staff relocation expenses 1,641 246 1,887 1,887 2f.3 Subtotal Period 2f Collateral Costs 1,641 246 1,887 1,887 Period 2f Period-Dependent Costs 2f.4.1 Insurance 512 51 564 564 2f.4.2 Property taxes 91 9

100 100 2f.4.3 Health physics supplies 1,316 329 1,645 1,645 2f.4.4 Disposal of DAW generated 7

4 21 7

39 39 353 7,050 11 2f.4.5 Plant energy budget 310 47 357 357 2f.4.6 NRC Fees 546 55 601 601 2f.4.7 Corporate Allocations 756 76 832 832 2f.4.8 Security Staff Cost 2,101 315 2,416 2,416 23,592 2f.4.9 DOC Staff Cost 6,532 980 7,511 7,511 57,408 2f.4.10 Utility Staff Cost 7,153 1,073 8,226 8,226 74,709 2f.4 Subtotal Period 2f Period-Dependent Costs 1,316 7

4 21 18,001 2,941 22,290 22,290 353 7,050 11 155,709 2f.0 TOTAL PERIOD 2f COST 1,316 7

4 21 30,021 6,300 37,669 37,669 353 7,050 153,889 161,949 PERIOD 2 TOTALS 13,062 105,104 35,741 26,806 195,260 364,632 156,780 897,386 819,597 56,618 21,171 571,031 1,481 393 2,217 34,409,770 1,287,589 3,086,805 PERIOD 3b - Site Restoration Period 3b Direct Decommissioning Activities Demolition of Remaining Site Buildings 3b.1.1.1 Reactor 3,482 522 4,004 4,004 27,502 3b.1.1.2 Auxiliary 2,865 430 3,295 3,295 19,024 3b.1.1.3 Auxiliary Boiler 26 4

30 30 248 3b.1.1.4 Barge Facility 957 144 1,101 1,101 4,290 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix E, Page 9 of 10 Table E Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:21:57 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Demolition of Remaining Site Buildings (continued) 3b.1.1.5 Circulating & Service Water Pumphouse 233 35 268 268 1,996 3b.1.1.6 Communication Corridor - Clean 1,079 162 1,241 1,241 8,280 3b.1.1.7 Communication Corridor - Contaminated 35 5

40 40 184 3b.1.1.8 Cooling Tower Concrete 451 68 519 519 2,332 3b.1.1.9 Diesel Generator 329 49 378 378 2,185 3b.1.1.10 Essential Service Water Pumphouse 176 26 203 203 955 3b.1.1.11 Fire Water Pumphouse 23 3

26 26 151 3b.1.1.12 Flex Building Storage 337 51 388 388 1,972 3b.1.1.13 Hardened Condensate Storage Tank - HCST 243 36 279 279 1,870 3b.1.1.14 Hot Machine Shop 21 3

24 24 243 3b.1.1.15 Intake 219 33 252 252 1,411 3b.1.1.16 Misc. Structures 2,722 408 3,130 3,130 18,774 3b.1.1.17 Miscellaneous Site Foundations 194 29 223 223 1,011 3b.1.1.18 Outage Maintenance 140 21 161 161 1,570 3b.1.1.19 RAM Storage Building 59 9

68 68 624 3b.1.1.20 Radioactive and Personnel Tunnel 34 5

39 39 386 3b.1.1.21 Radwaste 1,196 179 1,375 1,375 8,111 3b.1.1.22 Radwaste Drum Storage 171 26 197 197 1,449 3b.1.1.23 Reactor Head Assembly Building 98 15 113 113 1,108 3b.1.1.24 Security Additions 1,655 248 1,903 1,903 6,051 3b.1.1.25 Service 522 78 600 600 3,485 3b.1.1.26 Sludge Pump Station & Lagoon 1,678 252 1,930 1,930 10,601 3b.1.1.27 Steam Generator Replacement Bldgs 976 146 1,122 1,122 6,874 3b.1.1.28 Turbine Building 4,906 736 5,642 5,642 47,075 3b.1.1.29 Turbine Pedestal 561 84 646 646 2,934 3b.1.1.30 U.H.S. Cooling Tower 343 51 395 395 1,814 3b.1.1.31 Water Treatment Plant 1

0 1

1 9

3b.1.1.32 Fuel Building 1,229 184 1,414 1,414 8,068 3b.1.1 Totals 26,963 4,044 31,007 31,007 192,587 Site Closeout Activities 3b.1.2 Remove Rubble 1,558 234 1,792 1,792 7,233 3b.1.3 Grade & landscape site 129 19 148 148 592 3b.1.4 Final report to NRC 248 37 285 285 1,560 3b.1 Subtotal Period 3b Activity Costs 28,650 248 4,335 33,232 285 32,947 200,413 1,560 Period 3b Additional Costs 3b.2.1 Concrete Crushing 1,546 19 235 1,800 1,800 6,035 3b.2.2 Mine Area Backfill 6,441 966 7,407 7,407 15,960 3b.2.3 Construction Debris 2,950 443 3,393 3,393 3b.2.4 Cooling Tower Discharge & Intake Pipe Flow Fill 5,020 753 5,772 5,772 9,588 3b.2.5 Cooling Tower Demolition 5,495 824 6,320 6,320 21,619 3b.2.6 Site Restoration ISFSI 1,416 97 227 1,740 1,740 10,514 160 3b.2 Subtotal Period 3b Additional Costs 19,918 3,067 3,448 26,432 26,432 63,716 160 Period 3b Collateral Costs 3b.3.1 Small tool allowance 329 49 379 379 3b.3 Subtotal Period 3b Collateral Costs 329 49 379 379 Period 3b Period-Dependent Costs 3b.4.1 Insurance 1,019 102 1,121 1,121 3b.4.2 Property taxes 180 18 198 198 3b.4.3 Heavy equipment rental 4,790 718 5,508 5,508 3b.4.4 Plant energy budget 309 46 355 355 3b.4.5 Corporate Allocations 1,504 150 1,655 1,655 3b.4.6 Security Staff Cost 3,412 512 3,924 3,924 37,543 3b.4.7 DOC Staff Cost 12,661 1,899 14,560 14,560 106,371 3b.4.8 Utility Staff Cost 5,808 871 6,679 6,679 61,007 3b.4 Subtotal Period 3b Period-Dependent Costs 4,790 24,893 4,317 34,000 34,000 204,920 3b.0 TOTAL PERIOD 3b COST 53,687 28,207 12,149 94,043 285 93,758 264,129 206,640 PERIOD 3 TOTALS 53,687 28,207 12,149 94,043 285 93,758 264,129 206,640 TOTAL COST TO DECOMMISSION 17,773 162,571 35,887 27,273 197,474 557,198 195,885 1,194,061 998,551 78,615 116,895 572,283 2,268 393 2,217 34,530,070 1,572,119 4,491,356 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix E, Page 10 of 10 Table E Callaway Plant DECON Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:21:57 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours TOTAL COST TO DECOMMISSION WITH 19.62% CONTINGENCY:

$1,194,061 thousands of 2023 dollars TOTAL NRC LICENSE TERMINATION COST IS 83.63% OR:

$998,551 thousands of 2023 dollars SPENT FUEL MANAGEMENT COST IS 6.58% OR:

$78,615 thousands of 2023 dollars NON-NUCLEAR DEMOLITION COST IS 9.79% OR:

$116,895 thousands of 2023 dollars TOTAL LOW-LEVEL RADIOACTIVE WASTE VOLUME BURIED (EXCLUDING GTCC):

574,944 Cubic Feet TOTAL GREATER THAN CLASS C RADWASTE VOLUME GENERATED:

2,217 Cubic Feet TOTAL SCRAP METAL REMOVED:

69,040 Tons TOTAL CRAFT LABOR REQUIREMENTS:

1,572,119 Man-hours End Notes:

n/a - indicates that this activity not charged as decommissioning expense a - indicates that this activity performed by decommissioning staff 0 - indicates that this value is less than 0.5 but is non-zero A cell containing " - " indicates a zero value TLG Services, LLC

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix F, Page 1 of 12 TLG Services, LLC APPENDIX F DETAILED COST ANALYSIS SAFSTOR with DIRECT DISPOSAL OF LOW-LEVEL RADIOACTIVE WASTE 6 f: SAFSTOR decommissioning cost Estimate with Direct Disposal of Low-Level Radioactive Waste

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix F, Page 2 of 12 Table F Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:23:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours PERIOD 1a - Shutdown through Transition Period 1a Direct Decommissioning Activities 1a.1.1 SAFSTOR site characterization survey 394 118 512 512 1a.1.2 Prepare preliminary decommissioning cost 206 31 237 237 1,300 1a.1.3 Notification of Cessation of Operations a

1a.1.4 Remove fuel & source material n/a 1a.1.5 Notification of Permanent Defueling a

1a.1.6 Deactivate plant systems & process waste a

1a.1.7 Prepare and submit PSDAR 317 48 365 365 2,000 1a.1.8 Review plant dwgs & specs.

206 31 237 237 1,300 1a.1.9 Perform detailed rad survey a

1a.1.10 Estimate by-product inventory 159 24 183 183 1,000 1a.1.11 End product description 159 24 183 183 1,000 1a.1.12 Detailed by-product inventory 238 36 274 274 1,500 1a.1.13 Define major work sequence 159 24 183 183 1,000 1a.1.14 Perform SER and EA 492 74 566 566 3,100 1a.1.15 Perform Site-Specific Cost Study 794 119 913 913 5,000 Activity Specifications 1a.1.16.1 Prepare plant and facilities for SAFSTOR 781 117 898 898 4,920 1a.1.16.2 Plant systems 661 99 761 761 4,167 1a.1.16.3 Plant structures and buildings 495 74 569 569 3,120 1a.1.16.4 Waste management 317 48 365 365 2,000 1a.1.16.5 Facility and site dormancy 317 48 365 365 2,000 1a.1.16 Total 2,572 386 2,958 2,958 16,207 Detailed Work Procedures 1a.1.17.1 Plant systems 188 28 216 216 1,183 1a.1.17.2 Facility closeout & dormancy 190 29 219 219 1,200 1a.1.17 Total 378 57 435 435 2,383 1a.1.18 Procure vacuum drying system 16 2

18 18 100 1a.1.19 Drain/de-energize non-cont. systems a

1a.1.20 Drain & dry NSSS a

1a.1.21 Drain/de-energize contaminated systems a

1a.1.22 Decon/secure contaminated systems a

1a.1 Subtotal Period 1a Activity Costs 6,090 973 7,063 7,063 35,890 Period 1a Collateral Costs 1a.3.1 Spent Fuel Capital and Transfer 10,080 1,512 11,592 11,592 1a.3 Subtotal Period 1a Collateral Costs 10,080 1,512 11,592 11,592 Period 1a Period-Dependent Costs 1a.4.1 Insurance 3,972 397 4,370 4,370 1a.4.2 Property taxes 120 12 132 132 1a.4.3 Health physics supplies 888 222 1,110 1,110 1a.4.4 Heavy equipment rental 657 99 755 755 1a.4.5 Disposal of DAW generated 12 7

36 11 67 67 610 12,190 20 1a.4.6 Plant energy budget 2,053 308 2,361 2,361 1a.4.7 NRC Fees 1,057 106 1,163 1,163 1a.4.8 Emergency Planning Fees 1,620 162 1,782 1,782 1a.4.9 INPO Fees 358 54 411 411 1a.4.10 Spent Fuel Pool O&M 988 148 1,136 1,136 1a.4.11 ISFSI Operating Costs 127 19 146 146 1a.4.12 Corporate Allocations 1,000 100 1,100 1,100 1a.4.13 Security Staff Cost 15,699 2,355 18,054 18,054 251,680 1a.4.14 Utility Staff Cost 37,678 5,652 43,329 43,329 422,240 1a.4 Subtotal Period 1a Period-Dependent Costs 1,545 12 7

36 64,672 9,644 75,916 72,852 3,064 610 12,190 20 673,920 1a.0 TOTAL PERIOD 1a COST 1,545 12 7

36 80,842 12,129 94,571 79,915 14,656 610 12,190 20 709,810 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix F, Page 3 of 12 Table F Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:23:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours PERIOD 1b - SAFSTOR Limited DECON Activities Period 1b Direct Decommissioning Activities Decontamination of Site Buildings 1b.1.1.1 Reactor 1,604 802 2,407 2,407 24,102 1b.1.1.2 Auxiliary 792 396 1,188 1,188 12,527 1b.1.1.3 Communication Corridor - Contaminated 17 9

26 26 276 1b.1.1.4 Fuel Building 1,056 528 1,584 1,584 14,371 1b.1.1.5 Hot Machine Shop 22 11 33 33 344 1b.1.1.6 RAM Storage Building 55 27 82 82 865 1b.1.1.7 Radioactive and Personnel Tunnel 6

3 10 10 102 1b.1.1.8 Radwaste 422 211 633 633 6,671 1b.1.1.9 Radwaste Drum Storage 47 24 71 71 750 1b.1.1.10 Reactor Head Assembly Building 44 22 66 66 691 1b.1.1 Totals 4,067 2,033 6,100 6,100 60,700 1b.1 Subtotal Period 1b Activity Costs 4,067 2,033 6,100 6,100 60,700 Period 1b Additional Costs 1b.2.1 Spent Fuel Pool Isolation 14,330 2,150 16,480 16,480 1b.2 Subtotal Period 1b Additional Costs 14,330 2,150 16,480 16,480 Period 1b Collateral Costs 1b.3.1 Decon equipment 1,193 179 1,371 1,371 1b.3.2 Process decommissioning water waste 190 132 333 552 296 1,504 1,504 1,085 65,127 212 1b.3.3 Process decommissioning chemical flush waste 1b.3.4 Small tool allowance 67 10 77 77 1b.3.5 Spent Fuel Capital and Transfer 2,520 378 2,898 2,898 1b.3 Subtotal Period 1b Collateral Costs 1,382 67 132 333 552 2,520 863 5,850 2,952 2,898 1,085 65,127 212 Period 1b Period-Dependent Costs 1b.4.1 Decon supplies 1,772 443 2,215 2,215 1b.4.2 Insurance 1,001 100 1,101 1,101 1b.4.3 Property taxes 30 3

33 33 1b.4.4 Health physics supplies 725 181 906 906 1b.4.5 Heavy equipment rental 166 25 190 190 1b.4.6 Disposal of DAW generated 15 9

45 14 82 82 752 15,043 25 1b.4.7 Plant energy budget 517 78 595 595 1b.4.8 NRC Fees 200 20 220 220 1b.4.9 Emergency Planning Fees 408 41 449 449 1b.4.10 Spent Fuel Pool O&M 249 37 286 286 1b.4.11 ISFSI Operating Costs 32 5

37 37 1b.4.12 Corporate Allocations 252 25 277 277 1b.4.13 Security Staff Cost 3,957 594 4,551 4,551 63,437 1b.4.14 Utility Staff Cost 9,497 1,425 10,921 10,921 106,428 1b.4 Subtotal Period 1b Period-Dependent Costs 1,772 890 15 9

45 16,144 2,990 21,866 21,093 772 752 15,043 25 169,865 1b.0 TOTAL PERIOD 1b COST 7,221 958 148 342 597 32,995 8,036 50,296 46,625 3,670 1,838 80,170 60,936 169,865 PERIOD 1c - Preparations for SAFSTOR Dormancy Period 1c Direct Decommissioning Activities 1c.1.1 Prepare support equipment for storage 588 88 676 676 3,000 1c.1.2 Install containment pressure equal. lines 56 8

64 64 700 1c.1.3 Interim survey prior to dormancy 733 220 953 953 13,566 1c.1.4 Secure building accesses a

1c.1.5 Prepare & submit interim report 93 14 106 106 583 1c.1 Subtotal Period 1c Activity Costs 644 825 330 1,800 1,800 17,266 583 Period 1c Collateral Costs 1c.3.1 Process decommissioning water waste 206 144 363 602 322 1,637 1,637 1,183 70,953 231 1c.3.2 Process decommissioning chemical flush waste 1c.3.3 Small tool allowance 5

1 6

6 1c.3.4 Spent Fuel Capital and Transfer 2,520 378 2,898 2,898 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix F, Page 4 of 12 Table F Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:23:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours 1c.3 Subtotal Period 1c Collateral Costs 206 5

144 363 602 2,520 701 4,541 1,643 2,898 1,183 70,953 231 Period 1c Period-Dependent Costs 1c.4.1 Insurance 1,001 100 1,101 1,101 1c.4.2 Property taxes 30 3

33 33 1c.4.3 Health physics supplies 368 92 460 460 1c.4.4 Heavy equipment rental 166 25 190 190 1c.4.5 Disposal of DAW generated 3

2 9

3 17 17 154 3,073 5

1c.4.6 Plant energy budget 517 78 595 595 1c.4.7 NRC Fees 200 20 220 220 1c.4.8 Emergency Planning Fees 408 41 449 449 1c.4.9 Spent Fuel Pool O&M 249 37 286 286 1c.4.10 ISFSI Operating Costs 32 5

37 37 1c.4.11 Corporate Allocations 252 25 277 277 1c.4.12 Security Staff Cost 3,957 594 4,551 4,551 63,437 1c.4.13 Utility Staff Cost 9,497 1,425 10,921 10,921 106,428 1c.4 Subtotal Period 1c Period-Dependent Costs 533 3

2 9

16,144 2,447 19,138 18,366 772 154 3,073 5

169,865 1c.0 TOTAL PERIOD 1c COST 206 1,183 147 364 611 19,490 3,478 25,480 21,809 3,670 1,336 74,026 17,502 170,448 PERIOD 1 TOTALS 7,428 3,685 307 713 1,244 133,327 23,643 170,346 148,349 21,997 3,783 166,386 78,458 1,050,123 PERIOD 2a - SAFSTOR Dormancy with Wet Spent Fuel Storage Period 2a Direct Decommissioning Activities 2a.1.1 Quarterly Inspection a

2a.1.2 Semi-annual environmental survey a

2a.1.3 Prepare reports a

2a.1.4 Bituminous roof replacement 326 49 374 374 2a.1.5 Maintenance supplies 615 154 769 769 2a.1 Subtotal Period 2a Activity Costs 941 203 1,143 1,143 Period 2a Collateral Costs 2a.3.1 Spent Fuel Capital and Transfer 40,950 6,143 47,093 47,093 2a.3 Subtotal Period 2a Collateral Costs 40,950 6,143 47,093 47,093 Period 2a Period-Dependent Costs 2a.4.1 Insurance 2,708 271 2,979 2,979 2a.4.2 Property taxes 479 48 527 527 2a.4.3 Health physics supplies 1,423 356 1,779 1,779 2a.4.4 Disposal of DAW generated 19 11 54 17 101 101 920 18,394 30 2a.4.5 Plant energy budget 1,641 246 1,887 944 944 2a.4.6 NRC Fees 1,304 130 1,434 1,434 2a.4.7 Emergency Planning Fees 4,001 400 4,401 4,401 2a.4.8 Spent Fuel Pool O&M 3,950 593 4,543 4,543 2a.4.9 ISFSI Operating Costs 506 76 582 582 2a.4.10 Corporate Allocations 3,997 400 4,397 4,397 2a.4.11 Security Staff Cost 56,070 8,410 64,480 54,035 10,446 897,945 2a.4.12 Utility Staff Cost 31,218 4,683 35,900 29,582 6,318 328,415 2a.4 Subtotal Period 2a Period-Dependent Costs 1,423 19 11 54 105,874 15,630 123,011 95,778 27,233 920 18,394 30 1,226,360 2a.0 TOTAL PERIOD 2a COST 1,423 19 11 54 147,765 21,975 171,247 96,921 74,326 920 18,394 30 1,226,360 PERIOD 2c - SAFSTOR Dormancy without Spent Fuel Storage Period 2c Direct Decommissioning Activities 2c.1.1 Quarterly Inspection a

2c.1.2 Semi-annual environmental survey a

2c.1.3 Prepare reports a

2c.1.4 Bituminous roof replacement 3,955 593 4,548 4,548 2c.1.5 Maintenance supplies 7,471 1,868 9,338 9,338 2c.1 Subtotal Period 2c Activity Costs 11,425 2,461 13,886 13,886 Period 2c Period-Dependent Costs 2c.4.1 Insurance 20,383 2,038 22,422 22,422 2c.4.2 Property taxes 5,822 582 6,405 6,405 2c.4.3 Health physics supplies 7,889 1,972 9,862 9,862 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix F, Page 5 of 12 Table F Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:23:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Period 2c Period-Dependent Costs (continued) 2c.4.4 Disposal of DAW generated 101 57 293 92 541 541 4,942 98,844 161 2c.4.5 Plant energy budget 9,968 1,495 11,463 11,463 2c.4.6 NRC Fees 14,105 1,410 15,515 15,515 2c.4.7 Security Staff Cost 134,884 20,233 155,117 155,117 1,514,867 2c.4.8 Utility Staff Cost 79,438 11,916 91,353 91,353 883,672 2c.4 Subtotal Period 2c Period-Dependent Costs 7,889 101 57 293 264,601 39,739 312,679 312,679 4,942 98,844 161 2,398,539 2c.0 TOTAL PERIOD 2c COST 7,889 101 57 293 276,026 42,199 326,565 326,565 4,942 98,844 161 2,398,539 PERIOD 2 TOTALS 9,313 119 67 347 423,791 64,174 497,811 423,486 74,326 5,862 117,238 191 3,624,899 PERIOD 3a - Reactivate Site Following SAFSTOR Dormancy Period 3a Direct Decommissioning Activities 3a.1.1 Prepare preliminary decommissioning cost 206 31 237 237 1,300 3a.1.2 Review plant dwgs & specs.

730 110 840 840 4,600 3a.1.3 Perform detailed rad survey a

3a.1.4 End product description 159 24 183 183 1,000 3a.1.5 Detailed by-product inventory 206 31 237 237 1,300 3a.1.6 Define major work sequence 1,190 179 1,369 1,369 7,500 3a.1.7 Perform SER and EA 492 74 566 566 3,100 3a.1.8 Prepare/submit Defueled Technical Specifications 1,190 179 1,369 1,369 7,500 3a.1.9 Perform Site-Specific Cost Study 794 119 913 913 5,000 3a.1.10 Prepare/submit Irradiated Fuel Management Plan 159 24 183 183 1,000 Activity Specifications 3a.1.11.1 Re-activate plant & temporary facilities 1,170 175 1,345 1,211 135 7,370 3a.1.11.2 Plant systems 661 99 761 684 76 4,167 3a.1.11.3 Reactor internals 1,127 169 1,296 1,296 7,100 3a.1.11.4 Reactor vessel 1,032 155 1,186 1,186 6,500 3a.1.11.5 Biological shield 79 12 91 91 500 3a.1.11.6 Steam generators 495 74 569 569 3,120 3a.1.11.7 Reinforced concrete 254 38 292 146 146 1,600 3a.1.11.8 Main Turbine 63 10 73 73 400 3a.1.11.9 Main Condensers 63 10 73 73 400 3a.1.11.10 Plant structures & buildings 495 74 569 285 285 3,120 3a.1.11.11 Waste management 730 110 840 840 4,600 3a.1.11.12 Facility & site closeout 143 21 164 82 82 900 3a.1.11 Total 6,313 947 7,260 6,391 870 39,777 Planning & Site Preparations 3a.1.12 Prepare dismantling sequence 381 57 438 438 2,400 3a.1.13 Plant prep. & temp. svces 4,000 600 4,600 4,600 3a.1.14 Design water clean-up system 222 33 256 256 1,400 3a.1.15 Rigging/Cont. Cntrl Envlps/tooling/etc.

2,800 420 3,220 3,220 3a.1.16 Procure casks/liners & containers 195 29 225 225 1,230 3a.1 Subtotal Period 3a Activity Costs 19,038 2,856 21,894 21,025 870 77,107 Period 3a Additional Costs 3a.2.1 Site Characterization 3,198 959 4,158 4,158 19,100 7,852 3a.2 Subtotal Period 3a Additional Costs 3,198 959 4,158 4,158 19,100 7,852 Period 3a Period-Dependent Costs 3a.4.1 Insurance 420 42 462 462 3a.4.2 Property taxes 120 12 132 132 3a.4.3 Health physics supplies 776 194 970 970 3a.4.4 Heavy equipment rental 657 99 755 755 3a.4.5 Disposal of DAW generated 10 6

30 10 56 56 514 10,287 17 3a.4.6 Plant energy budget 2,053 308 2,361 2,361 3a.4.7 NRC Fees 458 46 504 504 3a.4.8 Corporate Allocations 1,000 100 1,100 1,100 3a.4.9 Security Staff Cost 4,449 667 5,117 5,117 65,000 3a.4.10 Utility Staff Cost 23,216 3,482 26,699 26,699 257,920 3a.4 Subtotal Period 3a Period-Dependent Costs 1,433 10 6

30 31,716 4,960 38,156 38,156 514 10,287 17 322,920 3a.0 TOTAL PERIOD 3a COST 1,433 10 6

30 53,953 8,775 64,207 63,338 870 514 10,287 19,117 407,879 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix F, Page 6 of 12 Table F Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:23:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours PERIOD 3b - Decommissioning Preparations Period 3b Direct Decommissioning Activities Detailed Work Procedures 3b.1.1.1 Plant systems 751 113 864 778 86 4,733 3b.1.1.2 Reactor internals 397 60 456 456 2,500 3b.1.1.3 Remaining buildings 214 32 246 62 185 1,350 3b.1.1.4 CRD cooling assembly 159 24 183 183 1,000 3b.1.1.5 CRD housings & ICI tubes 159 24 183 183 1,000 3b.1.1.6 Incore instrumentation 159 24 183 183 1,000 3b.1.1.7 Reactor vessel 576 86 663 663 3,630 3b.1.1.8 Facility closeout 190 29 219 110 110 1,200 3b.1.1.9 Missile shields 71 11 82 82 450 3b.1.1.10 Biological shield 190 29 219 219 1,200 3b.1.1.11 Steam generators 730 110 840 840 4,600 3b.1.1.12 Reinforced concrete 159 24 183 91 91 1,000 3b.1.1.13 Main Turbine 248 37 285 285 1,560 3b.1.1.14 Main Condensers 248 37 285 285 1,560 3b.1.1.15 Auxiliary building 433 65 498 448 50 2,730 3b.1.1.16 Reactor building 433 65 498 448 50 2,730 3b.1.1 Total 5,118 768 5,885 4,744 1,141 32,243 3b.1 Subtotal Period 3b Activity Costs 5,118 768 5,885 4,744 1,141 32,243 Period 3b Collateral Costs 3b.3.1 Decon equipment 1,193 179 1,371 1,371 3b.3.2 DOC staff relocation expenses 1,641 246 1,887 1,887 3b.3.3 Pipe cutting equipment 1,400 210 1,610 1,610 3b.3 Subtotal Period 3b Collateral Costs 1,193 1,400 1,641 635 4,868 4,868 Period 3b Period-Dependent Costs 3b.4.1 Decon supplies 43 11 54 54 3b.4.2 Insurance 342 34 376 376 3b.4.3 Property taxes 60 6

66 66 3b.4.4 Health physics supplies 431 108 539 539 3b.4.5 Heavy equipment rental 331 50 381 381 3b.4.6 Disposal of DAW generated 6

3 17 5

32 32 293 5,866 10 3b.4.7 Plant energy budget 1,035 155 1,190 1,190 3b.4.8 NRC Fees 231 23 254 254 3b.4.9 Corporate Allocations 504 50 555 555 3b.4.10 Security Staff Cost 2,243 336 2,579 2,579 32,767 3b.4.11 DOC Staff Cost 6,642 996 7,639 7,639 58,719 3b.4.12 Utility Staff Cost 11,704 1,756 13,459 13,459 130,020 3b.4 Subtotal Period 3b Period-Dependent Costs 43 762 6

3 17 22,761 3,531 27,124 27,124 293 5,866 10 221,506 3b.0 TOTAL PERIOD 3b COST 1,235 2,162 6

3 17 29,519 4,934 37,877 36,736 1,141 293 5,866 10 253,749 PERIOD 3 TOTALS 1,235 3,595 16 9

48 83,472 13,708 102,084 100,074 2,011 808 16,153 19,126 661,628 PERIOD 4a - Large Component Removal Period 4a Direct Decommissioning Activities Nuclear Steam Supply System Removal 4a.1.1.1 Reactor Coolant Piping 46 222 39 101 768 289 1,464 1,464 2,046 142,726 3,982 4a.1.1.2 Pressurizer Relief Tank 8

31 11 28 217 71 366 366 578 40,338 603 4a.1.1.3 Reactor Coolant Pumps & Motors 26 111 95 249 1,483 458 2,423 2,423 3,386 816,140 2,474 80 4a.1.1.4 Pressurizer 80 548 193 1,638 513 2,973 2,973 3,739 241,053 1,346 1,500 4a.1.1.5 Steam Generators 8,305 3,254 3,319 16,197 6,949 38,024 38,024 62,808 3,349,305 20,559 2,250 4a.1.1.6 Retired Steam Generator Units 3,254 3,319 16,000 4,823 27,395 27,395 62,808 3,349,305 10,852 2,250 4a.1.1.7 CRDMs/ICIs/Service Structure Removal 39 311 230 107 783 332 1,801 1,801 3,881 145,494 5,232 4a.1.1.8 Reactor Vessel Internals 48 5,349 11,276 1,031 11,929 306 13,123 43,063 43,063 5,623 501 406 342,863 24,523 1,139 4a.1.1.9 Vessel & Internals GTCC Disposal 13,035 1,955 14,990 14,990 2,217 433,180 4a.1.1.10 Reactor Vessel 7,025 2,076 1,382 6,848 306 9,603 27,239 27,239 15,631 979,036 24,523 1,139 4a.1.1 Totals 166 21,433 20,784 9,730 68,898 612 38,117 159,740 159,740 160,499 501 406 2,217 9,839,439 94,094 8,359 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix F, Page 7 of 12 Table F Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:23:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Removal of Major Equipment 4a.1.2 Main Turbine/Generator 606 2,848 491 17,692 4,933 26,570 26,570 54,809 3,481,857 8,721 4a.1.3 Main Condensers 1,723 1,386 2,399 21,985 6,425 33,917 33,917 64,324 4,086,353 24,802 Cascading Costs from Clean Building Demolition 4a.1.4.1 Reactor 612 92 704 704 4,832 4a.1.4.2 Auxiliary 318 48 366 366 2,113 4a.1.4.3 Fuel Building 127 19 146 146 773 4a.1.4.4 Hot Machine Shop 1

0 1

1 7

4a.1.4.5 Radwaste 61 9

70 70 387 4a.1.4 Totals 1,119 168 1,287 1,287 8,113 Disposal of Plant Systems 4a.1.5.1 100 Aux.Bldg Non-System Specific RCA 920 108 204 1,867 738 3,838 3,838 5,463 347,071 13,677 4a.1.5.2 100 Auxiliary Bldg Non-System Specific 136 12 23 212 92 475 475 621 39,480 2,047 4a.1.5.3 AB - Main Steam 366 55 420 420 5,833 4a.1.5.4 AB - Main Steam RCA 103 33 58 531 171 896 896 1,547 98,672 1,580 4a.1.5.5 AC - Main Turbine 361 54 415 415 5,641 4a.1.5.6 AD - Condensate 401 60 461 461 6,144 4a.1.5.7 AE - Feedwater 275 41 316 316 4,271 4a.1.5.8 AF - Feedwater Heater Extraction 337 51 388 388 5,352 4a.1.5.9 AK - Condensate Demineralizer 125 19 143 143 1,944 4a.1.5.10 AL - Auxiliary Feedwater 54 8

63 63 852 4a.1.5.11 AQ - Condensate & Feedwater Chem Addtn 30 5

35 35 468 4a.1.5.12 BM - Steam Generator Blowdown 143 19 31 287 114 594 594 832 53,260 2,164 4a.1.5.13 BM - Steam Generator Blowdown - RCA 491 75 112 1,024 403 2,105 2,105 2,963 190,396 7,221 4a.1.5.14 BN - Borated Refueling Water Storage 409 95 167 1,535 520 2,726 2,726 4,482 285,246 6,282 4a.1.5.15 CA - Steam Seal 29 4

33 33 455 4a.1.5.16 CB - Main Turbine Lube Oil 82 12 95 95 1,207 4a.1.5.17 CC - Generator Hydrogen Seal & CO2 13 2

15 15 198 4a.1.5.18 CD - Generator Seal Oil 19 3

22 22 287 4a.1.5.19 CE - Stator Cooling Water 16 2

19 19 241 4a.1.5.20 CF - Lube Oil Storage Xfer & Prfication 53 8

61 61 812 4a.1.5.21 CG - Condenser Air Removal 43 6

49 49 657 4a.1.5.22 CH - Main Turbine Control Oil 85 13 97 97 1,219 4a.1.5.23 DA - Circulating Water 473 71 544 544 7,502 4a.1.5.24 DB - Cooling Tower Makeup & Blowdown 80 12 92 92 1,260 4a.1.5.25 DD - Cooling Water Chemical Control Sys 71 11 81 81 1,084 4a.1.5.26 DD - Cooling Wtr Chem Control RCA 361 69 97 891 335 1,753 1,753 2,569 165,613 5,095 4a.1.5.27 EJ - Residual Heat Removal 473 95 164 1,506 529 2,767 2,767 4,385 280,003 7,249 4a.1.5.28 EM - High Pressure Coolant Injection 398 41 60 554 251 1,305 1,305 1,599 103,047 5,976 4a.1.5.29 EN - Containment Spray 288 53 82 752 277 1,452 1,452 2,179 139,742 4,242 4a.1.5.30 EP - Accumulator Safety Injection 210 35 54 495 188 982 982 1,433 91,944 3,163 4a.1.5.31 FA - Auxiliary Steam Generator 32 5

37 37 521 4a.1.5.32 FB - Auxiliary Steam 133 20 152 152 2,106 4a.1.5.33 FB - Auxiliary Steam RCA 109 15 22 204 83 433 433 589 37,925 1,569 4a.1.5.34 FC - Auxiliary Turbines 87 13 100 100 1,320 4a.1.5.35 FE - Auxiliary Steam Chemical Addition 7

1 8

8 105 4a.1.5.36 GE - Turbine Building HVAC 240 36 276 276 3,957 4a.1.5.37 GS - Containment Hydrogen Control 91 13 22 199 77 402 402 577 36,925 1,415 4a.1.5.38 HE - Boron Recycle 607 77 123 1,129 460 2,397 2,397 3,280 209,922 9,046 4a.1.5.39 HF - Secondary Liquid Waste 1,194 175 287 2,629 1,016 5,300 5,300 7,644 488,595 18,015 4a.1.5.40 JA - Auxiliary Oil & Transfer 43 7

50 50 690 4a.1.5.41 KS - Bulk Chemical Storage 122 94 172 1,580 461 2,429 2,429 4,620 293,686 2,002 4a.1.5.42 LE - Oily Waste 246 37 282 282 3,865 4a.1.5.43 LE - Oily Waste RCA 313 38 61 559 231 1,201 1,201 1,623 103,828 4,372 4a.1.5.44 Turbine Bldg Non-System Specific 1,031 155 1,185 1,185 15,405 4a.1.5 Totals 11,097 1,049 1,741 15,954 6,656 36,496 31,056 5,440 46,409 2,965,355 168,513 4a.1.6 Scaffolding in support of decommissioning 1,897 23 41 372 576 2,908 2,908 1,087 69,064 33,634 4a.1 Subtotal Period 4a Activity Costs 166 37,875 26,090 14,401 124,900 612 56,875 260,919 255,479 5,440 327,128 501 406 2,217 20,442,070 337,876 8,359 Period 4a Additional Costs 4a.2.1 Remedial Action Surveys 1,465 440 1,905 1,905 28,815 4a.2 Subtotal Period 4a Additional Costs 1,465 440 1,905 1,905 28,815 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix F, Page 8 of 12 Table F Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:23:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Period 4a Collateral Costs 4a.3.1 Process decommissioning water waste 5

9 23 39 17 93 93 76 4,564 15 4a.3.2 Process decommissioning chemical flush waste 4a.3.3 Small tool allowance 375 56 431 388 43 4a.3 Subtotal Period 4a Collateral Costs 5

375 9

23 39 73 524 481 43 76 4,564 15 Period 4a Period-Dependent Costs 4a.4.1 Decon supplies 118 30 148 148 4a.4.2 Insurance 939 94 1,033 1,033 4a.4.3 Property taxes 166 17 183 183 4a.4.4 Health physics supplies 4,229 1,057 5,286 5,286 4a.4.5 Heavy equipment rental 3,081 462 3,543 3,543 4a.4.6 Disposal of DAW generated 106 60 310 97 573 573 5,233 104,652 171 4a.4.7 Plant energy budget 2,704 406 3,109 3,109 4a.4.8 NRC Fees 818 82 900 900 4a.4.9 Liquid Radwaste Processing Equipment/Services 691 104 795 795 4a.4.10 Corporate Allocations 1,386 139 1,525 1,525 4a.4.11 Security Staff Cost 6,168 925 7,094 7,094 90,110 4a.4.12 DOC Staff Cost 21,985 3,298 25,283 25,283 198,962 4a.4.13 Utility Staff Cost 32,471 4,871 37,341 37,341 360,438 4a.4 Subtotal Period 4a Period-Dependent Costs 118 7,310 106 60 310 67,329 11,580 86,813 86,813 5,233 104,652 171 649,510 4a.0 TOTAL PERIOD 4a COST 289 45,560 26,206 14,484 125,249 69,407 68,967 350,161 344,678 5,483 332,437 501 406 2,217 20,551,280 366,877 657,869 PERIOD 4b - Site Decontamination Period 4b Direct Decommissioning Activities 4b.1.1 Remove spent fuel racks 959 112 294 261 2,389 1,173 5,187 5,187 6,988 443,960 1,925 Disposal of Plant Systems 4b.1.2.1 200 Reactor Bldg Non-System Specific 109 7

14 129 62 322 322 378 24,042 1,579 4b.1.2.2 200 Reactor Bldg Non-System Specific RCA 752 68 127 1,167 506 2,620 2,620 3,414 216,897 10,554 4b.1.2.3 300 Control Bldg Non-System Specific 236 30 57 523 202 1,049 1,049 1,532 97,294 3,471 4b.1.2.4 300 Control Bldg Non-System Specific Cln 1,836 275 2,111 2,111 29,076 4b.1.2.5 600 Fuel Bldg Non-Specific Systems RCA 411 46 85 783 316 1,641 1,641 2,292 145,605 5,946 4b.1.2.6 600 Fuel Bldg Non-System Specific 58 5

9 83 37 191 191 242 15,399 856 4b.1.2.7 700 Radwaste Bldg Non-Sys Specific RCA 1,514 180 339 3,105 1,223 6,361 6,361 9,083 577,051 22,261 4b.1.2.8 700 Radwaste Bldg Non-System Specific 219 19 37 342 148 766 766 1,002 63,635 3,278 4b.1.2.9 AN - Demineralized Wtr Storage & Xfer 208 31 239 239 3,283 4b.1.2.10 AN - Demineralized Wtr Strg & Xfer RCA 53 6

9 79 35 182 182 227 14,650 753 4b.1.2.11 AP-HCST/Condensate Stor.& Transfr 275 41 316 316 4,018 4b.1.2.12 BB - Reactor Coolant System 408 65 112 1,025 382 1,991 1,991 2,987 190,474 6,379 4b.1.2.13 BG - Chemical & Volume Control 1,157 193 318 2,918 1,086 5,672 5,672 8,476 542,341 17,466 4b.1.2.14 BL - Reactor Makeup Water 370 52 84 768 302 1,576 1,576 2,234 142,818 5,547 4b.1.2.15 DE - Intake & Water Treatment 166 25 191 191 2,517 4b.1.2.16 DE - Intake & Water Treatment RCA 331 175 319 2,925 879 4,630 4,630 8,546 543,623 5,351 4b.1.2.17 EA - Service Water 197 30 227 227 3,145 4b.1.2.18 EA - Service Water RCA 59 19 33 307 98 516 516 895 57,005 876 4b.1.2.19 EB - Closed Cooling Water 80 12 92 92 1,267 4b.1.2.20 EC - Fuel Pool Cooling & Cleanup 484 68 111 1,021 400 2,085 2,085 2,965 189,813 7,264 4b.1.2.21 EF - Essential Service Water 458 69 527 527 7,244 4b.1.2.22 EF - Essential Service Water RCA 263 81 143 1,309 422 2,218 2,218 3,820 243,301 4,018 4b.1.2.23 EG - Component Cooling Water RCA 336 50 386 386 5,335 4b.1.2.24 GA - Plant Heating 120 18 138 138 1,912 4b.1.2.25 GA - Plant Heating RCA 126 14 18 162 76 395 395 463 30,040 1,795 4b.1.2.26 GA-Plant Heating Fuel Building 27 2

3 27 14 74 74 78 5,037 404 4b.1.2.27 GB - Central Chilled Water 113 17 130 130 1,803 4b.1.2.28 GB - Central Chilled Water RCA 34 4

5 47 22 112 112 136 8,778 490 4b.1.2.29 GD - Essential Serv Wtr Pumphouse HVAC 25 4

29 29 427 4b.1.2.30 GF - Miscellaneous Building HVAC 155 29 54 498 174 911 911 1,457 92,563 2,081 4b.1.2.31 GG - Fuel Building HVAC 295 55 105 966 336 1,757 1,757 2,825 179,529 4,129 4b.1.2.32 GH - Radwaste Building HVAC 217 35 68 627 225 1,172 1,172 1,834 116,569 3,054 4b.1.2.33 GK - Control Building HVAC 231 35 266 266 3,959 4b.1.2.34 GL - Auxiliary Building HVAC 535 75 144 1,318 493 2,565 2,565 3,855 245,020 7,470 4b.1.2.35 GM - Diesel Generator Building HVAC 40 6

46 46 695 4b.1.2.36 GN - Containment Cooling 599 118 221 2,027 701 3,666 3,666 5,923 376,780 8,572 4b.1.2.37 GP - Containment Intgratd Leak Rate Test 52 9

16 143 52 272 272 417 26,623 768 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix F, Page 9 of 12 Table F Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:23:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Disposal of Plant Systems (continued) 4b.1.2.38 GR - Containment Atmospheric Control 24 16 31 280 82 432 432 818 51,989 372 4b.1.2.39 GT - Containment Purge HVAC 140 31 58 535 181 945 945 1,566 99,513 2,016 4b.1.2.40 HA - Gaseous Radwaste 434 65 100 919 360 1,877 1,877 2,664 170,799 6,388 4b.1.2.41 HB - Liquid Radwaste 1,054 159 253 2,319 897 4,682 4,682 6,735 430,985 15,662 4b.1.2.42 HC - Solid Radwaste 450 67 113 1,033 394 2,057 2,057 3,006 192,060 6,719 4b.1.2.43 HD - Decontamination 125 20 33 302 113 592 592 877 56,053 1,855 4b.1.2.44 JE - Emergency Fuel Oil 86 13 99 99 1,260 4b.1.2.45 KA - Compressed Air 262 39 301 301 4,187 4b.1.2.46 KA - Compressed Air RCA 169 19 22 204 99 513 513 583 37,947 2,380 4b.1.2.47 KB - Breathing Air 33 5

38 38 516 4b.1.2.48 KB - Breathing Air RCA 26 2

2 18 12 60 60 52 3,401 406 4b.1.2.49 KC - Fire Protection 514 77 591 591 8,376 4b.1.2.50 KC - Fire Protection RCA 530 86 121 1,106 436 2,279 2,279 3,189 205,625 7,245 4b.1.2.51 KC-Fire Protection Fuel Building 157 24 34 311 124 650 650 896 57,758 2,166 4b.1.2.52 KD - Domestic Water 239 36 275 275 3,837 4b.1.2.53 KD - Domestic Water RCA 34 5

7 62 25 132 132 178 11,465 468 4b.1.2.54 KE - Fuel Handling & Storage Rctor vssl 23 12 24 216 64 339 339 632 40,119 349 4b.1.2.55 KH - Service Gas (CO2 N2 H2 & O2) 76 11 87 87 1,226 4b.1.2.56 KH - Service Gas (CO2 N2 H2 & O2) RCA 333 45 66 608 250 1,302 1,302 1,756 112,949 4,575 4b.1.2.57 KJ - Standby Diesel Engine 454 68 523 523 6,749 4b.1.2.58 LA - Sanitary Drains 61 9

70 70 972 4b.1.2.59 LA - Sanitary Drains RCA 140 21 34 315 121 632 632 916 58,593 1,854 4b.1.2.60 LB - Roof Drains 81 12 93 93 1,276 4b.1.2.61 LB - Roof Drains RCA 190 32 57 526 191 996 996 1,534 97,740 2,757 4b.1.2.62 LD - Chemical & Detergent Waste 144 14 22 198 90 468 468 574 36,840 2,159 4b.1.2.63 LF - Floor & Equipment Drains 1,788 183 316 2,893 1,236 6,415 6,415 8,419 537,647 26,325 4b.1.2.64 RM - Process Sampling & Analysis 162 20 27 249 109 567 567 717 46,349 2,481 4b.1.2.65 SJ - Nuclear Sampling 94 14 19 171 70 368 368 491 31,744 1,451 4b.1.2.66 UB - Servces Stores Site Security Bldg 245 37 282 282 3,815 4b.1.2.67 Yard Non-System Specific 41 6

47 47 603 4b.1.2 Totals 20,658 2,188 3,772 34,564 13,972 75,154 68,050 7,104 100,683 6,424,461 309,491 4b.1.3 Scaffolding in support of decommissioning 2,846 35 61 557 863 4,363 4,363 1,631 103,596 50,451 Decontamination of Site Buildings 4b.1.4.1 Reactor 1,458 2,094 254 1,704 4,395 2,633 12,538 12,538 49,719 2,419,534 48,711 4b.1.4.2 Auxiliary 739 294 47 175 748 661 2,664 2,664 5,204 260,859 15,287 4b.1.4.3 Communication Corridor - Contaminated 16 4

1 3

9 12 45 45 88 4,377 307 4b.1.4.4 Fuel Building 955 969 71 110 785 939 3,829 3,829 2,969 177,276 27,561 4b.1.4.5 Hot Machine Shop 20 8

0 3

6 14 52 52 94 4,446 421 4b.1.4.6 RAM Storage Building 51 10 1

7 17 33 120 120 221 10,093 920 4b.1.4.7 Radioactive and Personnel Tunnel 6

7 0

2 3

6 25 25 54 2,532 195 4b.1.4.8 Radwaste 394 134 20 86 333 328 1,295 1,295 2,498 126,675 7,830 4b.1.4.9 Radwaste Drum Storage 44 13 2

9 30 34 132 132 256 12,889 851 4b.1.4.10 Reactor Head Assembly Building 40 20 59 59 614 4b.1.4.11 Steam Generator Replacement Bldgs 295 147 442 442 3,885 4b.1.4 Totals 4,019 3,532 397 2,098 6,327 4,828 21,201 21,201 61,102 3,018,682 106,582 4b.1.5 Prepare/submit License Termination Plan 650 98 748 748 4,096 4b.1.6 Receive NRC approval of termination plan a

4b.1 Subtotal Period 4b Activity Costs 4,977 27,148 2,913 6,192 43,836 650 20,935 106,652 99,548 7,104 170,405 9,990,698 468,448 4,096 Period 4b Additional Costs 4b.2.1 License Termination Survey Planning 1,778 533 2,311 2,311 12,480 4b.2.2 Operational Tools & Equipment 22 235 1,574 431 2,261 2,261 11,700 292,500 32 4b.2.3 Excavation of Underground Services 1,879 551 552 2,982 2,982 12,396 4b.2.4 License Termination ISFSI 684 154 166 3,547 3,894 2,111 10,556 10,556 14,077 1,053,456 17,572 10,920 4b.2.5 Remedial Action Surveys 2,438 731 3,170 3,170 47,950 4b.2.6 Sanitary Treatment Lagoon 7

92 235 540 181 1,054 1,054 4,608 392,140 423 4b.2.7 Cooling Tower Asbestos Panel Removal 6,512 305 641 1,119 8,576 8,576 71,419 4b.2.8 Retired Reactor Closure Head 151 847 1,330 1,110 599 4,037 4,037 2,764 338,540 3,157 2,000 4b.2.9 Spent Fuel Pool Legacy Waste 108 163 67 2,617 14 710 3,680 3,680 250 14,900 1,333 53 4b.2 Subtotal Period 4b Additional Costs 9,340 1,278 2,337 9,387 9,316 6,968 38,627 30,051 8,576 33,149 250 2,091,536 154,282 25,453 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix F, Page 10 of 12 Table F Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:23:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Period 4b Collateral Costs 4b.3.1 Process decommissioning water waste 14 26 66 109 47 261 261 214 12,843 42 4b.3.2 Process decommissioning chemical flush waste 4b.3.3 Small tool allowance 625 94 719 719 4b.3.4 Decommissioning Equipment Disposition 114 197 1,808 493 2,612 2,612 5,290 336,079 147 4b.3 Subtotal Period 4b Collateral Costs 14 625 140 263 1,917 633 3,593 3,593 5,504 348,922 189 Period 4b Period-Dependent Costs 4b.4.1 Decon supplies 1,947 487 2,434 2,434 4b.4.2 Insurance 1,563 156 1,719 1,719 4b.4.3 Property taxes 277 28 304 304 4b.4.4 Health physics supplies 7,070 1,767 8,837 8,837 4b.4.5 Heavy equipment rental 5,257 789 6,045 6,045 4b.4.6 Disposal of DAW generated 135 76 392 123 725 725 6,615 132,302 216 4b.4.7 Plant energy budget 3,552 533 4,085 4,085 4b.4.8 NRC Fees 1,362 136 1,498 1,498 4b.4.9 Liquid Radwaste Processing Equipment/Services 1,150 172 1,322 1,322 4b.4.10 Corporate Allocations 2,307 231 2,538 2,538 4b.4.11 Security Staff Cost 10,264 1,540 11,804 11,804 149,945 4b.4.12 DOC Staff Cost 35,739 5,361 41,100 41,100 321,483 4b.4.13 Utility Staff Cost 51,214 7,682 58,896 58,896 566,193 4b.4 Subtotal Period 4b Period-Dependent Costs 1,947 12,327 135 76 392 107,428 19,004 141,308 141,308 6,615 132,302 216 1,037,621 4b.0 TOTAL PERIOD 4b COST 6,939 49,441 4,466 8,868 55,532 117,394 47,541 290,179 274,500 15,680 215,673 250 12,563,460 623,134 1,067,170 PERIOD 4f - License Termination Period 4f Direct Decommissioning Activities 4f.1.1 ORISE confirmatory survey 168 50 218 218 4f.1.2 Terminate license a

4f.1 Subtotal Period 4f Activity Costs 168 50 218 218 Period 4f Additional Costs 4f.2.1 License Termination Survey 10,211 3,063 13,274 13,274 153,878 6,240 4f.2 Subtotal Period 4f Additional Costs 10,211 3,063 13,274 13,274 153,878 6,240 Period 4f Collateral Costs 4f.3.1 DOC staff relocation expenses 1,641 246 1,887 1,887 4f.3 Subtotal Period 4f Collateral Costs 1,641 246 1,887 1,887 Period 4f Period-Dependent Costs 4f.4.1 Insurance 4f.4.2 Property taxes 91 9

100 100 4f.4.3 Health physics supplies 1,316 329 1,645 1,645 4f.4.4 Disposal of DAW generated 7

4 21 7

39 39 353 7,050 11 4f.4.5 Plant energy budget 310 47 357 357 4f.4.6 NRC Fees 546 55 601 601 4f.4.7 Corporate Allocations 756 76 832 832 4f.4.8 Security Staff Cost 1,715 257 1,973 1,973 18,874 4f.4.9 DOC Staff Cost 6,532 980 7,511 7,511 57,408 4f.4.10 Utility Staff Cost 7,153 1,073 8,226 8,226 74,709 4f.4 Subtotal Period 4f Period-Dependent Costs 1,316 7

4 21 17,104 2,831 21,283 21,283 353 7,050 11 150,991 4f.0 TOTAL PERIOD 4f COST 1,316 7

4 21 29,123 6,191 36,662 36,662 353 7,050 153,889 157,231 PERIOD 4 TOTALS 7,228 96,316 30,679 23,356 180,802 215,924 122,699 677,003 655,840 21,162 548,462 751 406 2,217 33,121,790 1,143,901 1,882,270 PERIOD 5b - Site Restoration Period 5b Direct Decommissioning Activities Demolition of Remaining Site Buildings 5b.1.1.1 Reactor 3,482 522 4,004 4,004 27,502 5b.1.1.2 Auxiliary 2,865 430 3,295 3,295 19,024 5b.1.1.3 Auxiliary Boiler 26 4

30 30 248 5b.1.1.4 Barge Facility 957 144 1,101 1,101 4,290 5b.1.1.5 Circulating & Service Water Pumphouse 233 35 268 268 1,996 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix F, Page 11 of 12 Table F Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:23:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours Demolition of Remaining Site Buildings (continued) 5b.1.1.6 Communication Corridor - Clean 1,079 162 1,241 1,241 8,280 5b.1.1.7 Communication Corridor - Contaminated 35 5

40 40 184 5b.1.1.8 Cooling Tower Concrete 451 68 519 519 2,332 5b.1.1.9 Diesel Generator 329 49 378 378 2,185 5b.1.1.10 Essential Service Water Pumphouse 176 26 203 203 955 5b.1.1.11 Fire Water Pumphouse 23 3

26 26 151 5b.1.1.12 Flex Building Storage 337 51 388 388 1,972 5b.1.1.13 Fuel Building 1,209 181 1,390 1,390 7,874 5b.1.1.14 Hardened Condensate Storage Tank - HCST 243 36 279 279 1,870 5b.1.1.15 Hot Machine Shop 21 3

24 24 243 5b.1.1.16 Intake 219 33 252 252 1,411 5b.1.1.17 Misc. Structures 2,722 408 3,130 3,130 18,774 5b.1.1.18 Miscellaneous Site Foundations 194 29 223 223 1,011 5b.1.1.19 Outage Maintenance 140 21 161 161 1,570 5b.1.1.20 RAM Storage Building 59 9

68 68 624 5b.1.1.21 Radioactive and Personnel Tunnel 34 5

39 39 386 5b.1.1.22 Radwaste 1,196 179 1,375 1,375 8,111 5b.1.1.23 Radwaste Drum Storage 171 26 197 197 1,449 5b.1.1.24 Reactor Head Assembly Building 98 15 113 113 1,108 5b.1.1.25 Security Additions 1,655 248 1,903 1,903 6,051 5b.1.1.26 Service 522 78 600 600 3,485 5b.1.1.27 Sludge Pump Station & Lagoon 1,678 252 1,930 1,930 10,601 5b.1.1.28 Steam Generator Replacement Bldgs 976 146 1,122 1,122 6,874 5b.1.1.29 Turbine Building 4,906 736 5,642 5,642 47,075 5b.1.1.30 Turbine Pedestal 561 84 646 646 2,934 5b.1.1.31 U.H.S. Cooling Tower 343 51 395 395 1,814 5b.1.1.32 Water Treatment Plant 1

0 1

1 9

5b.1.1 Totals 26,942 4,041 30,983 30,983 192,393 Site Closeout Activities 5b.1.2 Remove Rubble 1,558 234 1,792 1,792 7,233 5b.1.3 Grade & landscape site 129 19 148 148 592 5b.1.4 Final report to NRC 248 37 285 285 1,560 5b.1 Subtotal Period 5b Activity Costs 28,629 248 4,331 33,208 285 32,923 200,218 1,560 Period 5b Additional Costs 5b.2.1 Concrete Crushing 1,546 19 235 1,800 1,800 6,035 5b.2.2 Mine Area Backfill 6,441 966 7,407 7,407 15,960 5b.2.3 Construction Debris 2,950 443 3,393 3,393 5b.2.4 Site Restoration ISFSI 1,416 97 227 1,740 1,740 10,514 160 5b.2.5 Cooling Tower Discharge & Intake Pipe Flow Fill 5,020 753 5,772 5,772 9,588 5b.2.6 Cooling Tower Demolition 5,495 824 6,320 6,320 21,619 5b.2 Subtotal Period 5b Additional Costs 19,918 3,067 3,448 26,432 26,432 63,716 160 Period 5b Collateral Costs 5b.3.1 Small tool allowance 329 49 379 379 5b.3 Subtotal Period 5b Collateral Costs 329 49 379 379 Period 5b Period-Dependent Costs 5b.4.1 Insurance 5b.4.2 Property taxes 180 18 198 198 5b.4.3 Heavy equipment rental 4,790 718 5,508 5,508 5b.4.4 Plant energy budget 309 46 355 355 5b.4.5 Corporate Allocations 1,504 150 1,655 1,655 5b.4.6 Security Staff Cost 3,412 512 3,924 3,924 37,543 5b.4.7 DOC Staff Cost 12,661 1,899 14,560 14,560 106,371 5b.4.8 Utility Staff Cost 5,808 871 6,679 6,679 61,007 5b.4 Subtotal Period 5b Period-Dependent Costs 4,790 23,874 4,215 32,879 32,879 204,920 5b.0 TOTAL PERIOD 5b COST 53,666 27,188 12,044 92,898 285 92,613 263,934 206,640 PERIOD 5 TOTALS 53,666 27,188 12,044 92,898 285 92,613 263,934 206,640 TOTAL COST TO DECOMMISSION 15,891 166,575 31,122 24,145 182,441 883,701 236,268 1,540,143 1,328,034 96,323 115,786 558,915 751 406 2,217 33,421,570 1,505,610 7,425,559 TLG Services, LLC

Callaway Energy Center 2023 Decommissioning Cost Analysis Document A22-1890-001, Rev. 0 Appendix F, Page 12 of 12 Table F Callaway Plant SAFSTOR Decommissioning Cost Estimate (Thousands of 2023 Dollars)

Costs run: Mon, Aug 28, 2023 at 13:23:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial /

Utility and Activity DECCER Version 2016.08.16d Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term.

Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs.

Manhours Manhours TOTAL COST TO DECOMMISSION WITH 18.12% CONTINGENCY:

$1,540,143 thousands of 2023 dollars TOTAL NRC LICENSE TERMINATION COST IS 86.23% OR:

$1,328,034 thousands of 2023 dollars SPENT FUEL MANAGEMENT COST IS 6.25% OR:

$96,323 thousands of 2023 dollars NON-NUCLEAR DEMOLITION COST IS 7.52% OR:

$115,786 thousands of 2023 dollars TOTAL LOW-LEVEL RADIOACTIVE WASTE VOLUME BURIED (EXCLUDING GTCC):

560,071 Cubic Feet TOTAL GREATER THAN CLASS C RADWASTE VOLUME GENERATED:

2,217 Cubic Feet TOTAL SCRAP METAL REMOVED:

69,004 Tons TOTAL CRAFT LABOR REQUIREMENTS:

1,505,610 Man-hours End Notes:

n/a - indicates that this activity not charged as decommissioning expense a - indicates that this activity performed by decommissioning staff 0 - indicates that this value is less than 0.5 but is non-zero A cell containing " - " indicates a zero value TLG Services, LLC

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix G, Page 1 of 4 TLG Services, LLC APPENDIX G DETAILED COST ANALYSIS ISFSI DECOMMISSIONING AND DEMOLITION 7G ISFSI Decommissioning and Demolition

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix G, Page 2 of 4 TLG Services, LLC TABLE G-1 SIGNIFICANT QUANTITIES AND PHYSICAL DIMENSIONS ISFSI Pad Item Length (feet)

Width (feet)

Depth (feet)

Residual Radioactivity ISFSI Pad 157.5 143.5 2.5 No ISFSI HI-STORM UMAX Item Value Notes (all dimensions are nominal)

Cavity Enclosure Container Inside Height 181 inches Cavity Enclosure Container Inside Diameter 86 inches Quantity (total) 53 Spent Fuel (48) + GTCC (5)

Quantity (with residual radioactivity) 6 Equivalent to the number of VVMs used to store last complete core offload)

Potentially Activated Steel and Concrete 847,767 pounds Misc. Low-Level Radioactive Waste 3,289 pounds Low-Level Radioactive Waste 13,299 cubic feet (excluding transfer cask)

Low-Level Radioactive Waste (packaged density) 75 pounds per cubic foot average weight density Other Potentially Impacted Items Item Value Notes Number of VVMs used for GTCC storage 5

No residual radioactivity

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix G, Page 3 of 4 TLG Services, LLC TABLE G-2 ISFSI DECOMMISSIONING COST (thousands, 2023 dollars)

Costs Waste Volume Person-Hours Removal Packaging Transport Disposal Other Total Cubic Feet Craft Oversight and Contractor Decommissioning Contractor Planning (characterization, specifications and procedures) 280 280 1,048 Remediation (activated metal removal) 684 154 166 3,547 4,551 14,077 7,706 License Termination (radiological surveys) 1,588 1,588 9,866 Subtotal 684 154 166 3,547 1,868 6,418 14,077 17,572 1,048 Supporting Costs NRC and NRC Contractor Fees 572 572 1,153 Insurance 144 144 Property Taxes 39 39 Plant Energy Budget 13 13 Corporate A&G 329 329 Security (industrial) 557 557 4,958 Ameren Services Oversight 372 372 3,761 Subtotal 2,026 2,026 9,872 Total (w/o contingency) 684 154 166 3,547 3,894 8,444 14,077 17,572 10,920 Total (w/25% contingency) 854 193 208 4,433 4,867 10,556 The application of contingency (25%) is consistent with the evaluation criteria referenced by the NRC in NUREG-1757 (""Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping, and Timeliness,"" U.S. NRC's Office of Nuclear Material Safety and Safeguards, NUREG-1757, Vol. 3, Rev. 1, February 2012)"

Callaway Energy Center Document A22-1819-001, Rev. 0 Decommissioning Cost Analysis Appendix G, Page 4 of 4 TLG Services, LLC TABLE G-3 ISFSI DEMOLITION COSTS 1 Note 1: For funding planning purposes demolition costs are incurred in the time period 2051-53 (for the DECON alternative)

Costs (thousands, 2023 dollars)

Person-Hours Removal Packaging Transport Disposal Other Total Craft Oversight and Contractor Decommissioning Contractor Excavation and Demolition 178 178 965 Steel Removal 724 724 8,419 Concrete Processing 156 29 185 512 Backfill 357 357 618 Tooling 42 42 Final Report 26 26 160 Subtotal 1,416 97 1,513 10,514 160 Supporting Costs Property Taxes 20 20 Heavy Equipment 131 131 Plant Energy Budget 7

7 Corporate A&G 164 164 Security (industrial) 278 278 2,479 Ameren Services Oversight 153 153 1,539 Subtotal 131 622 753 4,018 Total (w/o contingency) 1,547 720 2,266 10,514 4,178 Total (w/15% contingency) 1,779 828 2,606