ML25085A003
| ML25085A003 | |
| Person / Time | |
|---|---|
| Site: | Callaway |
| Issue date: | 03/26/2025 |
| From: | Ameren Missouri, Union Electric Co |
| To: | Office of Nuclear Reactor Regulation |
| Shared Package | |
| ML25085A001 | List: |
| References | |
| ULNRC-06931 | |
| Download: ML25085A003 (1) | |
Text
ULNRC-06931 March 26, 2025 NRC Plant Decommissioning Funding Status Report - 2025 (7 pages follow this cover page) to ULNRC-06931 Page 1 of 7 NRC Plant Decommissioning Funding Status Report - 2025 10 CFR 50.75(f)(1) requires each power reactor licensee to report to the NRC on a calendar year basis, beginning on March 31, 1999, and every 2 years thereafter, on the status of its decommissioning funding for each reactor or share of reactor it owns. Union Electric Company
("Ameren Missouri) hereby reports the decommissioning funding status for its Callaway Energy Center (Plant).
The scope of this Enclosure pertains only to the decommissioning funding status of the Callaway Energy Center, i.e., the Plant. The decommissioning funding plan for the independent spent fuel storage installation (ISFSI) was submitted on December 18, 2024, to the NRC via Reference 6 (listed on page 6 of this Enclosure).
Ameren Missouri is required to file updates regarding decommissioning cost estimates and funding adequacy projections on a triennial basis with the Missouri Public Service Commission (MPSC) as discussed more fully in Section 2 below. The scope of these triennial filings includes both the Plant and the ISFSI. Ameren Missouri obtains separate, updated site-specific decommissioning cost estimates and prepares separate, updated, funding adequacy analyses for the Plant and for the ISFSI for the MPSC triennial filings. When making these filings, Ameren Missouri has requested that the MPSC address the Plant and ISFSI separately in their orders issued pursuant to the filings. The decommissioning trust fund established by Ameren Missouri has separate, segregated sub-accounts for Plant and ISFSI decommissioning funding.
The site-specific decommissioning study referenced in this decommissioning funding status report is provided for information only and is included for reference as Enclosure 3 of this letter.
This site-specific study was part of the documentation presented to the MPSC in the Companys 2023 MPSC triennial update filing.
- 1. Amount of Decommissioning Funds Estimated to be Required Pursuant to 10 CFR 50.75(b) and (c)
For the purposes of this 2025 NRC biennial plant decommissioning funding status report, Ameren Missouri is using the three-factor formula specified in 10 CFR 50.75(b) and (c)1 for determining decommissioning funding adequacy.
The minimum decommissioning cost estimate, pursuant to the 10 CFR 50.75(b) and (c) methodology, is $558,775,000, in terms of December 2024 dollars.
The detailed calculations from which the above estimate is derived are contained in.
Ameren Missouri also has site-specific decommissioning cost estimates for decommissioning of the Callaway Energy Center prepared by TLG Services, Inc. of Bridgewater, Connecticut.
The specific studies are conducted to comply with Missouri Law:
to ULNRC-06931 Page 2 of 7 20 CSR 4240-20.070 Decommissioning Trust Funds (4) Every three (3) years, utilities with decommissioning trust funds shall perform and file with the commission cost studies detailing the utilities latest cost estimates for decommissioning their nuclear generating unit(s) along with the funding levels necessary to defray these decommissioning costs. These studies shall be filed along with appropriate tariff(s) effectuating the change in rates necessary to accomplish the funding required. In addition, the commission, at any time for just cause, may require a utility to file an updated decommissioning cost study, funding requirement, and associated tariff(s).
The current site-specific analysis filed with the MPSC in File No. EO-2023-0448 was completed in September 2023. It calculated a Plant decommissioning cost estimate of
$1,097.947,000 in terms of 2023 dollars.2 Ameren Missouri considers this site-specific Plant decommissioning cost estimate of $1,097,947,000 as the estimate for which funding adequacy must be assured for MPSC funding adequacy purposes. Due to its site-specific nature, it is a more accurate estimate of projected decommissioning costs.
For Plant decommissioning in the 2023 study, approximately 82.2% ($902,437,000) of the
$1,097,947,000 site-specific cost estimate is associated with physical decontamination and dismantling of radioactive systems and structures such that the license can be terminated.
Management and transfer of spent fuel accounts for 7.2% ($78,615,000) of the site-specific cost estimate. The remaining 10.6% ($116,895,000) is for demolition of designated non-radioactive structures and limited site restoration.
These studies are considered snap shots of the decommissioning cost and are used to determine if any changes are required in the contributions to the decommissioning fund. Due to the complexity of the study, the use of any cost escalation factors would introduce considerable uncertainty into the escalated cost. Since this study is conducted every three years, Ameren does not escalate the study cost estimates for the years between study periods.
An informational only copy of the September 2023 Site-Specific Decommissioning Cost Analysis for the Callaway Energy Center is provided in Enclosure 3.
- 2. Amount of Decommissioning Funds Accumulated to the End of the Calendar Year Preceding the Date of this Report Separate subaccounts have been established and are maintained for Plant and ISFSI decommissioning. The total amount accumulated in the Plant decommissioning fund as of December 31, 2024, is $1,198,667,094.87. This is an after tax liquidation value which reflects the final funds that would be received upon liquidation of the funds assets and the payment of income taxes on realized capital gains. This is calculated as follows:
to ULNRC-06931 Page 3 of 7 Copies of the trustees Book and Market Summary (Statement of Net Assets Available for Benefits) as of December 31, 2024, confirming the foregoing valuation amounts are provided in Enclosure 4.
This decommissioning fund balance indicated above is a total amount intended to cover the full decommissioning of the plant as defined under 20 CSR 4240-20.070. The funds in the trust fund are not segregated into sub-accounts for radiological decommissioning versus non-radiological decommissioning.
Based on the estimated Plant decommissioning costs contained in the 2023 site specific decommissioning cost estimate, allocation percentages for License Termination, Spent Fuel Management and Site Restoration can be calculated. By applying these percentages to the after-tax liquidation value of the jurisdictional subaccounts, the dollar amounts of the overall jurisdictional subaccounts allocated for the decommissioning cost categories can be derived:
License Termination:
82.2%
of
$ 1,198,667,095
=
$ 985,304,352 Spent Fuel Management:
7.2%
of
$ 1,198,667,095
=
$ 86,304,031 Site Restoration:
10.6%
of
$1,198,667,095
=
$127,058,712 Missouris definition of decommissioning encompasses both the radiological and non-radiological structures, systems and components of the plant, as stated in the following section from the Missouri Code of State Regulations:
20 CSR 4240-20.070 Decommissioning Trust Funds (1) As used in this rule, decommissioning means those activities undertaken in connection with a nuclear generating units retirement from service to ensure that the final removal, disposal, entombment, or other disposition of the unit and of any radioactive components and materials associated with the unit, are accomplished in compliance with all applicable laws, and to ensure that the final disposition does not pose any undue threat to the public health and safety. Decommissioning includes the removal and disposal of the Missouri Jurisdictional Sub Account FERC Jurisdictional Sub Account TOTAL Total Net Assets:
1,309,754,170 32,415,967 1,342,170,136 Less Book Value:
607,566,060 17,088,868 624,654,929 Equals Unrealized Gain 702,188,109 15,327,099 717,515,208 Income Tax 20% on Unrealized Gain 140,437,622 3,065,420 143,503,042 After Tax Liquidation Value 1,169,316,548 29,350,547 1,198,667,095 to ULNRC-06931 Page 4 of 7 structures, systems, and components of a nuclear generating unit at the time of decommissioning.
Missouri law requires triennial updates of the decommissioning cost estimate and of funding adequacy. Missouri law also provides for the changing of rates charged to ratepayers to recover any changes in funding levels necessitated by the triennial update analyses. For these reasons, Ameren Missouri considers the amount in the fund to be fully adequate to cover radiological decommissioning with an excess that could be applied to non-radiological decommissioning. The triennial update process required by Missouri statutes is considered adequate to ensure that any funding shortfalls will be addressed and corrected in a timely manner. The applicable sections from the Missouri Code of State Regulations are as follows:
20 CSR 4240-20.070 Decommissioning Trust Funds (4) Every three (3) years, utilities with decommissioning trust funds shall perform and file with the commission cost studies detailing the utilities latest cost estimates for decommissioning their nuclear generating unit(s) along with the funding levels necessary to defray these decommissioning costs. These studies shall be filed along with appropriate tariff(s) effectuating the change in rates necessary to accomplish the funding required. In addition, the commission, at any time for just cause, may require a utility to file an updated decommissioning cost study, funding requirement and associated tariff(s).
and (9) Upon the filing of the appropriate tariff(s) as set forth in this rule, the commission shall establish a schedule of proceedings which shall be limited in scope to the following issues:
(A) The extent of any change in the level or annual accrual of funding necessary for the utilitys decommissioning trust fund; and (B) The changes in rates which would reflect any change in the funding level or accrual rate.
In past triennial filings, the MPSC has accepted the site-specific decommissioning cost estimates and the funding adequacy analyses based on full decommissioning of the site as defined under 20 CSR 4240-20.070, as would be indicated under Missouri's legal definition of decommissioning. There is no basis for assuming any change in this practice in the future.
Consequently, it can be considered that the indicated trust fund balance is a total balance, not segregated on the basis of radiological versus non-radiological funding. As the Missouri mechanism for assuring funding adequacy and for recovering decommissioning expenses from ratepayers includes the non-radiological decommissioning expenses as well as the radiological expenses, it is not necessary to segregate the decommissioning fund balances.
Any shortfalls in funding for full decommissioning of the site as defined under 20 CSR 4240-20.070 are expected to be recovered from ratepayers as part of the triennial funding adequacy updating process.
to ULNRC-06931 Page 5 of 7
- 3. Schedule of the Annual Amounts Remaining to be Collected:
As of January 1, 2025, the schedule of the total Plant annual decommissioning expense amounts remaining to be collected from ratepayers is $6,242,226 annually as determined in the stipulation agreement in February 2021.
On February 24, 2021, the MPSC issued an "Order Approving Stipulation and Agreement" (effective March 26, 2021) that approved the foregoing "Non-Unanimous Stipulation and Agreement" as well as continuing the contribution to the decommissioning trust fund at the current level of $6,758,605 annually (with $6,242,226 allocated to Plant decommissioning and $516,379 allocated to ISFSI decommissioning) and affirming that Missouri is 100%
responsible for the decommissioning liability.
File No. EO-2023-0448 is currently pending before the MPSC. Under the terms of the Non-Unanimous Stipulation and Agreement filed in EO-2023-0448 on February 7, 2025, the contribution levels will be reduced to zero.
- 4. Actions by Regulatory Rate Setting Authorities, Assumptions Used Regarding Rates of Escalation in Decommissioning Costs, Rates of Earnings on Decommissioning Funds, and Rates of Other Factors Used in Funding Projections:
In accordance with the previously cited 20 CSR 4240-20.070 requirement, Ameren Missouri filed its latest updated decommissioning cost estimate and funding adequacy analysis with the MPSC on December 1, 2023.
In accordance with the previously cited 20 CSR 4240-20.070 requirement, on December 1, 2023, Ameren Missouri filed its Application for Acceptance of Decommissioning Cost Estimates for Callaway Energy Center, Including Independent Spent Fuel Storage Installation, and Approval of Funding Level for Nuclear Decommissioning Trust Fund with the MPSC (File No. EO-2023-0448). Attachment 3 to this application contained the updated site-specific decommissioning cost estimate prepared by TLG Services, Inc. titled "Decommissioning Cost Analysis for the Callaway Energy Center" and dated September 2023. Attachment 4 to the application contained Ameren Missouris analysis of the required funding level for the decommissioning trust fund, including all of the financial and economic assumptions on which the funding analysis was based. Copies of the "Application for Acceptance of Decommissioning Cost Estimates for Callaway Energy Center, Including Independent Spent Fuel Storage Installation" the "Approval of Funding Level for Nuclear Decommissioning Trust Fund" and the "Non-Unanimous Stipulation and Agreement" filed on February 7, 2025, are provided in Enclosures 5 through 7.
This filing is still pending with the MPSC, and the Company anticipates a final decision will be issued in the Spring of 2025 by MPSC.
to ULNRC-06931 Page 6 of 7
- 5. Any Contracts Upon Which the Licensee is Relying on Pursuant to 10 CFR 50.75(E)(L)(V):
None.
- 6. Any Modifications Occurring to a Licensees Current Method of Providing Financial Assurance Since the Last Submitted Report:
None.
The Company has used the External Sinking Fund method since 1985.
- 7. Any Material Changes to Trust Agreements:
There have been no material changes to the qualified trust agreement since the last report.
The non-qualified trust that was required by Illinois has been eliminated, as Ameren Missouri no longer has customers in Illinois. This non-qualified trust was never funded. 3
- 8. References
- 1. ULNRC-06201, "Status of Decommissioning Funding," dated March 30, 2015
- 2. ULNRC-06349, " Status of Decommissioning Funding," dated March 30, 2017
- 3. ULNRC-06494, " Status of Decommissioning Funding," dated March 22, 2019
- 4. ULNRC-06644, " Status of Decommissioning Funding," dated March 30, 2021
- 5. ULNRC-06798, " Status of Decommissioning Funding," dated March 30, 2023
- 6. ULNRC-06911, "ISFSI Decommissioning Funding Plan," dated December 18, 2024 1 The NRC formulas in section 10 CFR 50.75(c) include only those decommissioning costs incurred by licensees to remove a facility or site safely from service and reduce residual radioactivity to levels that permit: (1) release of the property for unrestricted use and termination of the license; or (2) release of the property under restricted conditions and termination of the license. The cost of dismantling or demolishing non-radiological systems and structures and the costs of managing and storing spent fuel on site until transfer to DOE are not included in the 10 CFR 50.75(c) cost formulas.
2 This estimate is applicable to the 60-year operating life, DECON decommissioning alternative scenario with low-level radioactive waste processing, and is presented in Appendix C of the August 2017 site specific decommissioning cost estimate. This is the option Ameren Missouri intends to utilize for plant decommissioning.
to ULNRC-06931 Page 7 of 7 3 On February 10, 2005, the MPSC approved Ameren Missouri's proposed transfer of its Illinois electric and gas properties to an Illinois affiliate, Ameren Illinois. The closing date for the property transfer was May 2, 2005. In accordance with the MPSC Order, the tax-qualified decommissioning trust's Illinois jurisdictional sub-account was eliminated following the closing.
Ninety-eight percent of the assets in the existing Illinois subaccount as of the closing date were reallocated to the Missouri sub-account, and the remaining two percent of the assets were reallocated to the Wholesale sub-account. As a result of the transfer, Ameren Missouri no longer has any Illinois ratepayers and will no longer collect decommissioning contributions in Illinois for its Callaway Plant, which is located in Missouri. The decommissioning liability previously borne by the Illinois ratepayers was transferred to Ameren Missouri and Wholesale customers.
Decommissioning expenses collected from Missouri jurisdictional ratepayers was increased by
$272,194 annually in accordance with the MPSC Order to account for the increased decommissioning liability borne by the Missouri ratepayers following the property transfer.