IR 05000255/2024013

From kanterella
(Redirected from ML25024A083)
Jump to navigation Jump to search
Restart Inspection Report 05000255/2024013
ML25024A083
Person / Time
Site: Palisades Entergy icon.png
Issue date: 01/24/2025
From: April Nguyen
NRC/RGN-III/DORS
To: Mlynarek M
Holtec Decommissioning International
References
IR 2024013
Download: ML25024A083 (1)


Text

SUBJECT:

PALISADES NUCLEAR PLANT - RESTART INSPECTION REPORT 05000255/2024013

Dear Mike Mlynarek:

On December 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the Palisades Nuclear Plant. The enclosed inspection report documents the inspection results, which the inspectors discussed on January 8, 2024, with and other members of your staff.

No violations of more than minor significance were identified during this inspection.

On June 13, 2022, Palisades ceased permanent power operations and subsequently removed all fuel from the reactor, as detailed in the letter from Entergy to the NRC, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel, (ADAMS Accession No. ML22164A067). On September 28, 2023, Holtec Decommissioning International, LLC (Holtec) submitted a letter to the NRC requesting exemptions from certain portions of the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 50.82(a)(2) to pursue the potential reauthorization of power operations at Palisades (ADAMS Accession No. ML23271A140). The NRCs initial acceptance to review Palisades request for exemptions was documented in ADAMS at Accession No. ML23291A440 on November 3, 2023.

January 24, 2025 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, April M. Nguyen, Lead Palisades Restart Team Division of Operating Reactor Safety Docket No. 05000255 License No. DPR-20

Enclosure:

As stated

Inspection Report

Docket Number:

05000255

License Number:

DPR-20

Report Number:

05000255/2024013

Licensee:

Holtec Decommissioning International, LLC

Facility:

Palisades Nuclear Plant

Location:

Covert, MI

Inspection Dates:

October 01, 2024 to December 31, 2024

Inspectors:

J. Austin, Senior Project Engineer, Region II

E. Fernandez, Senior Reactor Inspector, Region III

E. Magnuson, Reactor Inspector, Region III

J. Mancuso, Senior Resident Inspector

T. Okamoto, Resident Inspector

A. Sanchez, Senior Project Engineer, Region IV

S. Schwind, Senior Resident Inspector, Callaway

C. Speer, Reactor Systems Engineer, NRR

T. Steadham, Senior Resident Inspector, Browns Ferry

D. Werkheiser, Senior Reactor Analyst, Region I

J. Winslow, Senior Project Engineer, Restart Team

Approved By:

April M. Nguyen, Lead

Palisades Restart Team

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) performed inspections of the licensees activities to verify that the reactor coolant system boundary, reactor vessel head, and risk-significant piping system boundaries are appropriately monitored for degradation and that required repairs and replacements are appropriately examined and accepted; systems, structures, and components (SSCs) are appropriately inspected, maintained, and tested to ensure they can perform their required safety functions for potential restart; and human performance issues are being appropriately addressed at a low threshold to prevent more significant issues from occurring.

List of Findings and Violations

None.

Additional Tracking Items

None.

PLANT STATUS

The Palisades Nuclear Plant ceased power operations and subsequently removed all fuel from the reactor, as certified in a letter to the NRC on June 13, 2022. On September 28, 2023, Holtec Decommissioning International, LLC (Holtec) submitted a letter to the NRC requesting exemptions from certain portions of the requirements of 10 CFR 50.82(a)(2) to pursue the potential reauthorization of power operations. The NRC is conducting inspections to evaluate and assess the licensees activities for potential restoration to an operational status.

The Resident Inspector office was staffed in December 2024 to provide daily, on-site oversight and inspection of Holtecs potential restart activities.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the referenced inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

REACTOR SAFETY

CORNERSTONES 71111.08P - Inservice Inspection Activities (PWR)

From November 14, 2024, to December 18, 2024, the inspectors observed and verified Holtec Palisades nondestructive examination (NDE) and repair/replacement activities of the reactor pressure vessel head and Alloy 600 welds, conducted in accordance with the requirements of the ASME Code Section XI. The purpose of these inspections was to verify that the reactor coolant system boundary, reactor pressure vessel head, and risk-significant piping system boundaries are appropriately monitored for degradation. The inspectors also verified that the examination results were thoroughly reviewed and appropriately evaluated, and that required corrective actions to address identified indications and defects will be appropriately implemented. During this quarter, the licensee completed NDE activities and evaluation of data for both the reactor pressure vessel head and Alloy 600 welds in the primary coolant system and began repair/replacement activities in both areas. Further NRC inspections will monitor repair/replacement activities as they are conducted.

The inspectors verified that the following nondestructive examination and repair/replacement activities were conducted appropriately per the ASME Code or required standard, and that any potential indications and defects were identified and evaluated at the proper thresholds:

Nondestructive Examination and Welding Activities (IP Section 03.01)

Alloy 600 Weld Inspection and Mitigation (November 14, 2024-December 18, 2024)

  • Phased Array Ultrasonic Testing (PAUT) of safety injection piping

Reactor Pressure Vessel Head (November 14, 2024-December 18, 2024)

  • Preparatory machining activities for control rod drive mechanism (CRDM) nozzle repairs
  • PT examination of reactor vessel head vent line
  • Inner diameter (ID) profilometry of CRDM nozzle #5 OTHER BASELINE ACTIVITIES

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) PAL-02885, Adverse Trend in Human Performance Incidents, August 9, 2024 A summary of this review and the inspectors observations are documented in the Results Section below.

System Return to Service On December 2, 2024, the inspectors commenced reviews of Phases I and II of the licensees system return to service (SRTS) plans. The SRTS plans document licensee activities to verify that the configuration and condition of Systems, Structures, and Components (SSCs) are consistent with the design and licensing bases to support potential restart. The inspectors began initial reviews on Phases I and II of the SRTS plans, which include areas such as licensing and design-basis functions, system material conditions, reviewing open and deferred work prior to shutdown, and program applicability. The inspectors conducted these reviews using IP 71152, Problem Identification and Resolution, and IP 71111.21M, Comprehensive Engineering Team Inspection (CETI), as applicable.

The inspectors commenced reviews of the SRTS plans for the following systems:

  • AC Power Systems
  • DC Power Systems
  • Low Pressure Safety Injection and Shutdown Cooling These systems were selected based on the importance of the SSCs during normal and emergency plant operating conditions, risk significance and defense-in-depth of the SSCs specific functions and required work/modifications of the SSCs scheduled prior to potential restart.

INSPECTION RESULTS

Assessment: Adverse Trend in Human Performance Incidents 71152 On August 9, 2024, the licensee wrote issue report (IR) PAL-02885 identifying an adverse trend in human performance incidents at the site. Five incidents in July and August 2024 were noted as part of the trend. An apparent cause evaluation (ACE) was performed to understand the incidents and implement actions to arrest the trend. As part of the ACE analysis, the licensee reviewed additional IRs that identified similar human performance incidents. Additionally, a previous safety and human performance trend identified in IR PAL-01857 on February 21, 2024, and associated corrective actions were reviewed.

The licensee identified five causal factors documented in the ACE associated with reinforcement of standards, guidance for procedures on hold, standards and expectations for new personnel, ineffective communications on safety and human performance issues, and less than adequate evaluation and corrective actions from previously identified issue reports.

Corrective actions completed or planned include, but are not limited to, development of a safety and human performance monitoring and communications plan, reinforcement of expectations for site employees, and performance of an effectiveness review.

The inspectors reviewed the licensees ACE, including IRs for the human performance incidents reviewed as part of the ACE. They also reviewed the identified causal factors and completed and planned corrective actions discussed in the ACE. The inspectors determined that the corrective actions were appropriate to the circumstances.

The licensee has planned to perform an effectiveness review of the corrective actions after all actions have been implemented. The inspectors noted that the methods of verification, process attributes, and success criteria for the effectiveness review are still being identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 8, 2024, the inspectors presented the inspection results to M. Mlynarek, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PAL-04217

PT Indications for Alloy 600 Weld Overlay

11/18/2024

PAL-04220

PT Indications on the Stainless on 1A Safety Injection

11/18/2024

PAL-04282

PT Indications on 2B Safety Injection Stainless Steel Valve

11/22/2024

PAL-04303

As-measured Palisades RVCH Thickness

11/25/2024

PAL-04316

PT Indication on 2A Cold Leg SI Nozzle

11/25/2024

Corrective Action

Documents

PAL-04614

PT Indications Following Vent Line Machining

2/18/2024

CR-2024-3181-

10-UT-001

UT Thickness Measurements of RVCH

11/15/2024

CR-2024-3181-

10-UT-002

UT Thickness Measurements of RVCH

11/22/2024

CR-2024-3406-

07-UT-001

UT Thickness Measurements of RVCH

11/26/2024

CR-2024-3406-

08-UT-001

UT Thickness Measurements of RVCH

2/02/2024

SI-1A-80-00-PT-

001

Liquid Penetrant Examination of 1A SI Nozzle

11/16/2024

SI-1B-80-00-PT-

001

Liquid Penetrant Examination of 1B SI Nozzle

11/26/2024

SI-2A-80-00-PT-

001

Liquid Penetrant Examination of 2A SI Nozzle

11/25/2024

NDE Reports

SI-2B-80-00-PT-

001

Liquid Penetrant Examination of 2B SI Nozzle

11/22/2024

54-PT-200-026

Color Contrast Solvent Removable Liquid Penetrant

Examination of Components

LMT-10-PAUT-

007

Fully Encoded Phased Array Ultrasonic Examination of

Dissimilar Metal Piping Welds

71111.08P

Procedures

LMT-10-PAUT-

019

Manual Phased Array Ultrasonic Examination of Dissimilar

Metal Piping Welds

71152

Corrective Action

Documents

PAL-02643

Westinghouse PCS Decon Skid Operator Entered Incorrect

Value

07/10/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PAL-02768

Wire Rope Contacting Electrical Cable

07/30/2024

PAL-02770

Extraction of Personnel from Spider Man Basket

07/30/2024

PAL-02885

Adverse Trend in Human Performance Incidents

08/09/2024

PAL-02911

Personal Vehicle/Forklift Incident

08/12/2024

PAL-03651

NSRB Issue - Human Performance

10/17/2024

ENG-105

System Return to Service Plans

OM-126

Management and Oversight of Supplemental Personnel

Procedures

RA-102

Corrective Action Program

0