March 31 - April 4, 2025, Regulatory Audit Plan for Framatome Inc. Topical Report, ANP-10357P, Revision 0, Txs Compact Platform Topical Report (EPID L-2024-TOP-0029) (Letter)
ML24352A142
Person / Time
Site: 99902041
Issue date: 03/13/2025
From: Gerond George
Licensing Processes Branch
To: Elliott G
Framatome
Shared Package
ML24352A156 List:
References
EPID L-2024-TOP-0029
Download: ML24352A142 (1)


Text

OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION March 13, 2025 Gayle Elliott, Director Licensing and Regulatory Affairs Framatome, Inc.

3315 Old Forest Road Lynchburg, VA 24501

SUBJECT:

MARCH 31 - APRIL 4, 2025, REGULATORY AUDIT PLAN FOR FRAMATOME INC. TOPICAL REPORT, ANP-10357P, REVISION 0, TXS COMPACT PLATFORM TOPICAL REPORT REGARDING EQUIPMENT QUALIFICATION AND SYSTEM DEVELOPMENT LIFE-CYCLE PROCESS MANAGEMENT (EPID L-2024-TOP-0029)

Dear Gayle Elliott:

By letter dated August 2, 2024 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML24218A279), Framatome, Inc. (Framatome) submitted Topical Report (TR) ANP-10357P, Revision 0, TXS Compact Platform Topical Report, for U.S.

Nuclear Regulatory Commission (NRC) staffs review. The NRC staff accepted the TR for review on October 7, 2024 (ADAMS Accession No. ML24256A027). As stated in the letter dated August 2, 2024, the TR presents the generic application of the TXS COMPACT which has been developed as a platform based on Field-Programmable Gate Array (FPGA) technology that could be integrated with different modules from the TXS portfolio to implement safety related instrumentation and control (I&C) systems in nuclear power plants. The NRC staff plans to conduct an in-person regulatory audit on March 31 - April 4, 2025, to facilitate its review of the TXS Compact Platform TR.

The in-person audit will be done at the EDF Tower, located at La Defense Paris, France. The NRC staffs audit will focus on the equipment qualification and system development life-cycle process management associated with the Compact Platform. Enclosed for your information is a copy of the audit plan and agenda that the NRC staff plans to follow. Additionally, the NRC staff plans to issue a report within 90 days after completion of the audit.

NOTICE: contains proprietary information, when this transmittal letter is separated from Enclosure 1, this letter becomes DECONTROLLED.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION G. Elliott OFFICIAL USE ONLY - PROPRIETARY INFORMATION Please contact Ngola Otto at 301-415-6695 or via e-mail at Ngola.Otto@nrc.gov with any questions you may have regarding this letter.

Sincerely, Gerond George, Chief Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 99902041

Enclosures:

1.

Audit Plan (proprietary) 2.

Audit Plan (non-proprietary)

/RA/

ML24352A156 (Package)

ML24352A142 (Letter)

ML24352A150 (Audit Plan) non-proprietary ML25065A059 (Audit Plan) proprietary OFFICE NRR/DORL/LLPB/PM NRR/DORL/LLPB/LA NRR/DEX/ECIB/BC NAME NOtto DHarrison FSacko DATE 3/6/2025 3/7/2025 3/10/2025 OFFICE NRR/DORL/LLPB/BC NRR/DORL/LLPB/PM NAME GGeorge NOtto DATE 3/11/2025 3/13/2025