Letter Sequence Other |
---|
EPID:L-2023-SLE-0000, Application for Subsequent License Renewal Appendix E - Applicants Environmental Report (Approved, Closed) |
|
MONTHYEARPMNS20230213, Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application2023-03-14014 March 2023 Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application Project stage: Meeting ML23081A0392023-03-22022 March 2023 Presentation Slide for Monticello Public Scoping Meeting, March 22, 2023 Project stage: Request PMNS20230237, Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application2023-03-28028 March 2023 Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application Project stage: Meeting ML23108A3132023-04-18018 April 2023 March 22, 2023, Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application Public Environmental Scoping Meeting Transcript Project stage: Meeting ML23110A0152023-05-0101 May 2023 Summary March 22, 2023, Monticello Units 1 Subsequent License Renewal Application Public Environmental Scoping Meeting Project stage: Meeting ML23115A4382023-05-0101 May 2023 March 29, 2023, Meeting Summary for Environmental Review of Subsequent License Renewal Application for Monticello Nuclear Generating Plant, Unit 1 Project stage: Meeting ML23110A0142023-05-0101 May 2023 Memo March 22, 2023, Monticello Unit 1, Subsequent License Renewal Application Public Environmental Scoping Meeting Project stage: Meeting ML23047A1182023-06-0202 June 2023 Notice of Intent to Conduct Scoping Process and Prepare an EIS Project stage: Other ML23215A1312023-08-0909 August 2023 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Project stage: Approval ML23291A1102023-10-23023 October 2023 Environmental Audit Summary and RCIs and RAIs Project stage: Other 2023-03-28
[Table View] |
|
---|
Category:Letter
MONTHYEARML24025A9362024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0055 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000263/20230042024-01-31031 January 2024 Integrated Inspection Report 05000263/2023004 ML24024A0722024-01-24024 January 2024 Independent Spent Fuel Storage Installation, Onticello, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000263/20244012024-01-22022 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2024401 L-MT-23-054, Subsequent License Renewal Application Supplement 82024-01-11011 January 2024 Subsequent License Renewal Application Supplement 8 L-MT-23-047, License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data2023-12-29029 December 2023 License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data L-MT-23-056, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 22023-12-18018 December 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 2 ML23349A0572023-12-15015 December 2023 and Independent Spent Fuel Storage Installation, Revision to Correspondence Service List for Northern States Power - Minnesota IR 05000263/20234022023-12-13013 December 2023 Security Baseline Inspection Report 05000263/2023402 L-MT-23-042, 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462023-12-11011 December 2023 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 L-MT-23-052, Subsequent License Renewal Application Supplement 72023-11-30030 November 2023 Subsequent License Renewal Application Supplement 7 L-MT-23-051, Update to the Technical Specification Bases2023-11-28028 November 2023 Update to the Technical Specification Bases L-MT-23-049, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 12023-11-21021 November 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 ML23319A3182023-11-15015 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000263/20230032023-11-13013 November 2023 Integrated Inspection Report 05000263/2023003 and 07200058/2023001 L-MT-23-043, 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-092023-11-13013 November 2023 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-09 L-MT-23-038, License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.62023-11-10010 November 2023 License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 L-MT-23-046, Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 12023-11-0909 November 2023 Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 1 ML23291A1102023-10-23023 October 2023 Environmental Audit Summary and RCIs and RAIs ML23285A3062023-10-12012 October 2023 Implementation of the Fleet Standard Emergency Plan for the Monticello Nuclear Generating Plant and the Prairie Island Nuclear Generating Plant L-MT-23-041, Subsequent License Renewal Application Response to Request for Confirmation of Information Set 22023-10-0303 October 2023 Subsequent License Renewal Application Response to Request for Confirmation of Information Set 2 L-MT-23-037, Subsequent License Renewal Application Response to Request for Additional Information Set 32023-09-22022 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 3 ML23262B0372023-09-19019 September 2023 Response to NRC Request for Additional Information Regarding the 2023 Monticello and Prairie Island Plant Decommissioning Funding Status Reports ML23248A2092023-09-18018 September 2023 Proposed Alternative VR-11 to the Requirements of the ASME OM Code Associated with Periodic Verification Testing of MO-2397, Reactor Water Cleanup Inboard Isolation Valve ML23256A1682023-09-13013 September 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Voluntary Security Clearance Program 2023 Insider Threat Program Self-Inspection IR 05000263/20230102023-09-0707 September 2023 Commercial Grade Dedication Inspection Report 05000263/2023010 L-MT-23-036, Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 62023-09-0505 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 6 ML23214A2412023-08-31031 August 2023 Letter: Aging Management Audit - Monticello Unit 1 - Subsequent License Renewal Application IR 05000263/20230052023-08-30030 August 2023 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2023005) L-MT-23-035, Subsequent License Renewal Application Supplement 52023-08-28028 August 2023 Subsequent License Renewal Application Supplement 5 ML23241A9732023-08-21021 August 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application (Docket No. 50-263) L-MT-23-034, Subsequent License Renewal Application Response to Request for Additional Information Set 12023-08-15015 August 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 1 ML23222A0122023-08-10010 August 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Changes in Foreign Ownership, Control or Influence ML23215A1312023-08-0909 August 2023 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application IR 05000263/20230022023-08-0707 August 2023 Plantintegrated Inspection Report 05000263/2023002 L-MT-23-028, 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report2023-07-31031 July 2023 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report L-MT-23-032, 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-112023-07-31031 July 2023 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-11 ML23198A0412023-07-28028 July 2023 LRA Availability Letter ML23206A2342023-07-25025 July 2023 Independent Spent Fuel Storage Installation, and Monticello Nuclear Generating Plant, Changes in Foreign Ownership, Control or Influence ML23201A0352023-07-24024 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23202A0032023-07-21021 July 2023 Independent Spent Fuel and Independent Spent Fuel Storage Installation, Monticello Nuclear Generating Plant, Submittal of Quality Assurance Topical Report (NSPM-1) L-MT-23-031, Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 12023-07-18018 July 2023 Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 1 ML23195A1732023-07-14014 July 2023 Revision of Standard Practice Procedures Plan IR 05000263/20235012023-07-13013 July 2023 Emergency Preparedness Inspection Report 05000263/2023501 2024-01-31
[Table view] |
Text
June 2, 2023 Christopher P. Domingos Site Vice President Northern States Power Company - Minnesota Monticello Nuclear Generating Plant 2807 West County Road 75 Monticello, MN 55362
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT, UNIT 1 - NOTICE OF INTENT TO CONDUCT SCOPING PROCESS AND PREPARE AN ENVIRONMENTAL IMPACT STATEMENT (EPID NUMBER: L-2023-SLE-0000)
Dear Christopher Domingos:
By letter dated January 9, 2023, (Agencywide Documents Access and Management System (ADAMS) ML23009A353), Northern States Power Company submitted an application for subsequent license renewal of Renewed Facility Operating License No. DPR-22 for Monticello Nuclear Generating Plant, Unit 1 (Monticello), to the U.S. Nuclear Regulatory Commission (NRC). As stated in a letter to you dated January 24, 2023, (ML23010A007), the NRC staff determined that the application is acceptable for docketing and that the staff will proceed with its detailed technical review. In support of the application and in accordance with title 10 of the Code of Federal Regulations (10 CFR) part 51 and Part 54, Monticello also submitted an environmental report. This letter provides information related to the NRC staffs environmental review of the application.
The NRC staff prepared a Notice of Intent (NOI) advising the public of the NRC scoping process to gather the information necessary to prepare a plant-specific supplement to NUREG1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (ML13107A023), related to the review of the application for the subsequent renewal of the Monticellos operating license. Enclosed is a copy of the NOI that was published by the Office of the Federal Register.
Pursuant to 10 CFR 51.28, Northern States Power Company was invited to participate in the environmental scoping process. As discussed in the NOI, the NRC staff provided the public with the opportunity to participate in an in-person environmental scoping meeting which was held on March 22, 2023 (ML23073A041), followed by a public scoping webinar held on March 29, 2023 (ML23087A102). The in-person meeting was transcribed (ML23108A313). The NRC staff presented an overview of the safety and environmental review processes and described how these processes would be implemented for the review of the Monticello subsequent license renewal application (ML23081A039). The NRC staff provided members of the public an opportunity to provide comments. The meeting summary can be found in ADAMS (ML23110A015).
C. Domingos If you have any questions on this matter, please contact Jessica Umana via email at Jessica.Umana@nrc.gov.
Sincerely, Signed by Smith, Theodore on 06/02/23 Theodore Smith, Chief Environmental Review License Renewal Branch Division of Rulemaking, Environment, and Financial Support Office of Nuclear Material Safety and Safeguards Docket No. 50-263
Enclosure:
Federal Register Notice cc w/encl: Listserv