Letter Sequence Other |
|---|
EPID:L-2023-SLE-0000, Application for Subsequent License Renewal Appendix E - Applicant’S Environmental Report (Approved, Closed) |
|
MONTHYEARPMNS20230213, Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application2023-03-14014 March 2023 Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application Project stage: Meeting ML23110A0132023-03-14014 March 2023, 22 March 2023, 18 April 2023, 1 May 2023 Public March 22 Public Meeting Summary Project stage: Request ML23081A0392023-03-22022 March 2023 Presentation Slide for Monticello Public Scoping Meeting, March 22, 2023 Project stage: Request PMNS20230237, Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application2023-03-28028 March 2023 Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application Project stage: Meeting ML23108A3132023-04-18018 April 2023 March 22, 2023, Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application Public Environmental Scoping Meeting Transcript Project stage: Meeting ML23110A0152023-05-0101 May 2023 Summary March 22, 2023, Monticello Units 1 Subsequent License Renewal Application Public Environmental Scoping Meeting Project stage: Meeting ML23115A4382023-05-0101 May 2023 March 29, 2023, Meeting Summary for Environmental Review of Subsequent License Renewal Application for Monticello Nuclear Generating Plant, Unit 1 Project stage: Meeting ML23110A0142023-05-0101 May 2023 Memo March 22, 2023, Monticello Unit 1, Subsequent License Renewal Application Public Environmental Scoping Meeting Project stage: Meeting ML23047A1182023-06-0202 June 2023 Notice of Intent to Conduct Scoping Process and Prepare an EIS Project stage: Other ML23199A2802023-07-0303 July 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application Wright and Sherburne Counties, Minnesota Project stage: Request ML23215A1312023-08-0909 August 2023 – License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Project stage: Approval ML23291A1102023-10-23023 October 2023 Environmental Audit Summary and RCIs and RAIs Project stage: Other ML24059A2882024-03-18018 March 2024, 31 March 2024 Scoping Summary Project stage: Request ML24059A3292024-03-18018 March 2024 Scoping Summary Report Cover Letter Project stage: Other ML24059A3422024-03-31031 March 2024 Scoping Summary Report Project stage: Request ML24312A1732024-11-18018 November 2024 Ltr. to Shawn Hafen, Site Vice President, Monticello Nuclear Generating Plant, Re., NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR Project stage: Other 2023-05-01
[Table View] |
Text
Shawn Hafen Site Vice President Northern States Power Company - Minnesota Monticello Nuclear Generating Plant 2807 West County Rd 75 Monticello, MN 55362
SUBJECT:
ISSUANCE OF ENVIRONMENTAL SCOPING
SUMMARY
REPORT ASSOCIATED WITH THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS REVIEW OF THE MONTICELLO NUCLEAR GENERATING PLANT, UNIT 1, SUBSEQUENT LICENSE RENEWAL APPLICATION (EPID NUMBER: L-2023-SLE-0000) (DOCKET NUMBER: 50-263)
Dear Shawn Hafen:
The U.S. Nuclear Regulatory Commission (NRC) staff conducted the environmental scoping process and solicited public comments pursuant to Section 51.29 of Title 10 of the Code of Federal Regulations (10 CFR) from March 10, 2023, to April 10, 2023. This process helped determine the scope of the staffs environmental review of the application for subsequent renewal of the renewed facility operating licenses for Monticello Nuclear Generating Plant, Unit 1. The scoping process is the first step in the development of a Monticello Plant-specific supplement to NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 26 (Agencywide Documents Access and Management System No. ML062490078).
At the conclusion of the scoping process, the staff prepared the enclosed environmental scoping summary report identifying comments received during the scoping period. In accordance with 10 CFR 51.29(b), the NRC staff will send a copy of the scoping summary report to each participant in the scoping process.
March 18, 2024
S. Hafen 2
If you have any questions concerning the staffs environmental review of this subsequent license renewal application, please contact Jessica Umana by telephone at 301-415-5207or via email at Jessica.Umana@nrc.gov.
Sincerely, Stephen S. Koenick, Chief Environmental Project Management Branch 1 Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards Docket No. 50-263
Enclosure:
As stated cc: Listserv Signed by Koenick, Stephen on 03/18/24
Pkg.ML24059A288, Ltr.ML24059A329, Rpt.ML24059A342 OFFICE PM:REFS LA:REFS OGC (NLO)
BC:REFS NAME JUmana AWalker-Smith STurk SKoenick DATE 3/01/2024 03/01/2024 3/13/2024 3/18/2024