Letter Sequence Other |
---|
EPID:L-2023-SLE-0000, Presentation Slide for Monticello Public Scoping Meeting, March 22, 2023 (Approved, Closed) |
|
MONTHYEARPMNS20230213, Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application2023-03-14014 March 2023 Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application Project stage: Meeting ML23110A0132023-03-14014 March 2023, 22 March 2023, 18 April 2023, 1 May 2023 Public March 22 Public Meeting Summary Project stage: Request ML23081A0392023-03-22022 March 2023 Presentation Slide for Monticello Public Scoping Meeting, March 22, 2023 Project stage: Request PMNS20230237, Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application2023-03-28028 March 2023 Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application Project stage: Meeting ML23108A3132023-04-18018 April 2023 March 22, 2023, Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application Public Environmental Scoping Meeting Transcript Project stage: Meeting ML23110A0152023-05-0101 May 2023 Summary March 22, 2023, Monticello Units 1 Subsequent License Renewal Application Public Environmental Scoping Meeting Project stage: Meeting ML23115A4382023-05-0101 May 2023 March 29, 2023, Meeting Summary for Environmental Review of Subsequent License Renewal Application for Monticello Nuclear Generating Plant, Unit 1 Project stage: Meeting ML23110A0142023-05-0101 May 2023 Memo March 22, 2023, Monticello Unit 1, Subsequent License Renewal Application Public Environmental Scoping Meeting Project stage: Meeting ML23047A1182023-06-0202 June 2023 Notice of Intent to Conduct Scoping Process and Prepare an EIS Project stage: Other ML23199A2802023-07-0303 July 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application Wright and Sherburne Counties, Minnesota Project stage: Request ML23215A1312023-08-0909 August 2023 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Project stage: Approval ML23291A1102023-10-23023 October 2023 Environmental Audit Summary and RCIs and RAIs Project stage: Other ML24059A2882024-03-18018 March 2024, 31 March 2024 Scoping Summary Project stage: Request ML24059A3292024-03-18018 March 2024 Scoping Summary Report Cover Letter Project stage: Other ML24059A3422024-03-31031 March 2024 Scoping Summary Report Project stage: Request NRC-2023-0031, Comment (5) of Diane and Jim Schrack on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Northern States Power Company-Minnesota; Monticello Nuclear Generating Plant, Unit 12024-05-29029 May 2024 Comment (5) of Diane and Jim Schrack on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Northern States Power Company-Minnesota; Monticello Nuclear Generating Plant, Unit 1 Project stage: Request 2023-05-01
[Table View] |
|
---|
Category:Letter
MONTHYEARML24283A1192024-10-28028 October 2024 Letter to Shawn Hafen, Re Monticello Subsequent License Renewal Schedule Change L-MT-24-038, Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI2024-10-15015 October 2024 Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI ML24277A0202024-10-0303 October 2024 Operator Licensing Examination Approval Monticello Nuclear Generating Plant, October 2024 IR 05000263/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000263/2024011 ML24199A1752024-10-0101 October 2024 Issuance of Amendment No. 212 Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 L-MT-24-025, Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements2024-09-26026 September 2024 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements L-MT-24-029, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI2024-09-13013 September 2024 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI IR 05000263/20240052024-08-30030 August 2024 Updated Inspection Plan and Follow-Up Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2024005) L-MT-24-028, Response to RCI for RR-017 ISI Impracticality2024-08-28028 August 2024 Response to RCI for RR-017 ISI Impracticality ML24222A1822024-08-27027 August 2024 – Proposed Alternative Request VR-09 to the Inservice Testing Requirements of the ASME OM Code for Main Steam Safety Relief Valves 05000263/LER-2024-002, Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure2024-08-27027 August 2024 Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure IR 05000263/20244202024-08-21021 August 2024 Security Baseline Inspection Report 05000263/2024420 - Cover Letter IR 05000263/20240022024-08-14014 August 2024 Integrated Inspection Report 05000263/2024002 ML24218A2282024-08-0505 August 2024 Request for Confirmation of Information for Relief Request RR-017, Inservice Inspection Impracticality During the Fifth Ten-Year Interval ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24215A2992024-07-23023 July 2024 Minnesota State Historic Preservation Office Comments on Monticello SLR Draft EIS ML24198A2372024-07-18018 July 2024 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Monticello Nuclear Generating Plant L-MT-24-022, – Preparation and Scheduling of Operator Licensing Examinations2024-07-0909 July 2024 – Preparation and Scheduling of Operator Licensing Examinations ML24164A2402024-06-10010 June 2024 Minnesota State Historic Preservation Office- Comments on Draft Monticello SLR Draft EIS L-MT-24-019, Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii)2024-06-10010 June 2024 Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii) L-MT-24-017, Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-01602024-06-0404 June 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-0160 ML24137A2792024-06-0303 June 2024 Audit Summary for License Amendment Request to Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 IR 05000263/20244012024-05-30030 May 2024 Public - Monticello Nuclear Generating Plant - Cyber Security Inspection Report 05000263/2024401 ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information ML24141A1782024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-MT-24-015, Response to Request for Additional Information - Alternative Request VR-09 for OMN-172024-05-16016 May 2024 Response to Request for Additional Information - Alternative Request VR-09 for OMN-17 L-MT-24-013, 2023 Annual Radiological Environmental Operating Report2024-05-14014 May 2024 2023 Annual Radiological Environmental Operating Report ML24135A1902024-05-14014 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report IR 05000263/20240102024-05-13013 May 2024 Age-Related Degrading Inspection Report 05000263/2024010 ML24127A1472024-05-0909 May 2024 Letter to Mille Lacs Band- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renew. Application ML24128A0042024-05-0909 May 2024 Letter to Minnesota State Historic Preservation Office- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renewal Application L-MT-24-016, 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP)2024-05-0808 May 2024 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP) ML24089A2382024-04-29029 April 2024 Summary of Nuclear Property Insurance IR 05000263/20240012024-04-29029 April 2024 Plan - Integrated Inspection Report 05000263/2024001 ML24115A3032024-04-25025 April 2024 Sec106 Tribal, Taylor, Louis-Lac Courte Oreilles Band of Lake Superior Chippewa Indians ML24115A2892024-04-25025 April 2024 Sec106 Tribal, Fowler, Thomas-St. Croix Chippewa of Wisconsin ML24115A2902024-04-25025 April 2024 Sec106 Tribal, Jackson-Street, Lonna-Spirit Lake Nation ML24115A3062024-04-25025 April 2024 Sec106 Tribal, Wassana, Reggie-Cheyenne and Arapaho Tribes ML24115A2952024-04-25025 April 2024 Sec106 Tribal, Kakkak, Gena-Menominee Indian Tribe of Wisconsin ML24115A2992024-04-25025 April 2024 Sec106 Tribal, Renville, J. Garret-Sisseton Wahpeton Oyate of the Lake Travers Reservation ML24115A2932024-04-25025 April 2024 Sec106 Tribal, Johnson, Grant-Prairie Island Indian Community ML24115A2872024-04-25025 April 2024 Sec106 Tribal, Dupuis, Kevin-Fond Du Lac Band of Lake Superior Chippewa ML24115A3002024-04-25025 April 2024 Sec106 Tribal, Rhodd, Timothy-Iowa Tribe of Kansas and Nebraska ML24115A3072024-04-25025 April 2024 Sec106 Tribal, Williams, Jr., James-Lac Vieux Desert Band of Lake Superior Chippewa Indians ML24115A3022024-04-25025 April 2024 Sec106 Tribal, Stiffarm, Jeffrey-Fort Belknap Indian Community ML24115A2912024-04-25025 April 2024 Sec106 Tribal, Jacskon, Sr., Faron-Leech Lake Band of Ojibwe 05000263/LER-2024-001, Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component2024-04-25025 April 2024 Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component ML24115A3052024-04-25025 April 2024 Sec106 Tribal, Vanzile, Jr., Robert-Sokaogon Chippewa Community ML24115A2962024-04-25025 April 2024 Sec106 Tribal, Larsen, Robert-Lower Sioux Indian Community ML24115A2942024-04-25025 April 2024 Sec106 Tribal, Johnson, John-Lac Du Flambeau Band of Lake Superior Chippewa Indians 2024-09-26
[Table view] |
Text
Shawn Hafen Site Vice President Northern States Power Company - Minnesota Monticello Nuclear Generating Plant 2807 West County Rd 75 Monticello, MN 55362
SUBJECT:
ISSUANCE OF ENVIRONMENTAL SCOPING
SUMMARY
REPORT ASSOCIATED WITH THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS REVIEW OF THE MONTICELLO NUCLEAR GENERATING PLANT, UNIT 1, SUBSEQUENT LICENSE RENEWAL APPLICATION (EPID NUMBER: L-2023-SLE-0000) (DOCKET NUMBER: 50-263)
Dear Shawn Hafen:
The U.S. Nuclear Regulatory Commission (NRC) staff conducted the environmental scoping process and solicited public comments pursuant to Section 51.29 of Title 10 of the Code of Federal Regulations (10 CFR) from March 10, 2023, to April 10, 2023. This process helped determine the scope of the staffs environmental review of the application for subsequent renewal of the renewed facility operating licenses for Monticello Nuclear Generating Plant, Unit 1. The scoping process is the first step in the development of a Monticello Plant-specific supplement to NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 26 (Agencywide Documents Access and Management System No. ML062490078).
At the conclusion of the scoping process, the staff prepared the enclosed environmental scoping summary report identifying comments received during the scoping period. In accordance with 10 CFR 51.29(b), the NRC staff will send a copy of the scoping summary report to each participant in the scoping process.
March 18, 2024 S. Hafen 2 If you have any questions concerning the staffs environmental review of this subsequent license renewal application, please contact Jessica Umana by telephone at 301-415-5207or via email at Jessica.Umana@nrc.gov.
Sincerely, Stephen S. Koenick, Chief Environmental Project Management Branch 1 Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards Docket No. 50-263
Enclosure:
As stated cc: Listserv Signed by Koenick, Stephen on 03/18/24
Pkg.ML24059A288, Ltr.ML24059A329, Rpt.ML24059A342 OFFICE PM:REFS LA:REFS OGC (NLO) BC:REFS NAME JUmana AWalker-Smith STurk SKoenick DATE 3/01/2024 03/01/2024 3/13/2024 3/18/2024