MONTHYEARML22228A1332022-08-0909 August 2022 Acknowledgement for License Amendment Request to Modify Staffing Requirements Following SFP Transfer to Dry Storage Project stage: Other ML22259A1992022-09-0202 September 2022 Acceptance for License Amendment Request to Modify Staffing Requirements Following SFP Transfer to Dry Storage Project stage: Acceptance Review ML23055A1112023-02-23023 February 2023 Alyse Peterson Email- NYSERDA No Comments on Indian Point Unit 2 - Regarding Holtec License Amendment Request to Revise Permanently Defueled Technical Specifications and Staffing Requirements with Spent Fuel Transfer to ISFSI (Dockets 50-24 Project stage: Request NRC-23-0061, Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water..2023-08-30030 August 2023 Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water.. Project stage: Response to RAI NRC-23-0064, Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (EESW) System and Ultimate Heat Sink (UHS)2023-09-11011 September 2023 Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (EESW) System and Ultimate Heat Sink (UHS) Project stage: Supplement ML23243A8852023-09-18018 September 2023 Issuance of Amendment No. 225 Regarding Revision of Technical Specifications 3.7.2, Emergency Equipment Cooling Water, Emergency Equipment Service Water and System and Ultimate Heat Sink (Exigent Circumstances) Project stage: Approval ML23050A0032023-11-17017 November 2023 Letter - Issuance Indian Point Unit 2 License Amendment Request to Modify Tech Specs for Staffing Requirements Following Spent Fuel Transfer to Dry Storage Project stage: Other ML23050A0022023-11-17017 November 2023 Enclosure 2 - Safety Evaluation for Indian Point Unit 2 License Amendment Request to Modify Technical Specifications for Staffing Requirements Following Spent Fuel Transfer to Dry Storage Project stage: Approval ML22307A0452023-11-17017 November 2023 Enclosure 1 - Amendment No. 297 to Rfl No. DPR-26 for Indian Point Unit 2 License Amendment Request to Modify Tech Specs for Staffing Requirements with Spent Fuel Transfer to Dry Storage Project stage: Other ML23050A0012023-11-17017 November 2023 NRC Issuance for Approval - Holtec Request for Indian Point Unit 2 License Amendment to Revise Permanently Defueled Technical Specifications to Modify Staffing Requirements with Transfer of Spent Fuel to Dry Storage (Docket Nos. 50-003, 50- Project stage: Request 2023-02-23
[Table View] |
Text
From:
Sturzebecher, Karl To:
Jean Fleming Cc:
Bill Noval; Matthew Johnson; Walter Wittich; Anderson, Shaun
Subject:
Acceptance Review: IPEC License Amendment Request - Indian Point Nuclear Generating Unit No. 2 Permanently Defueled Technical Specifications to Modify Staffing Requirements along with Specific Spent Fuel Storage and Transfers Date:
Friday, September 2, 2022 12:09:00 PM
Dear Ms. Fleming:
The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed your letter dated August 2, 2022, requesting the U.S. Nuclear Regulatory Commission (NRC) to approve an amendment to modify the IP2 staffing, prohibit storing spent fuel in IP2, and IP3 spent fuel transfers to IP2 prior to implementation.
The document is available in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML22214A128.
We have completed our acceptance review of your submittal and have identified no administrative omissions or deficiencies that would prevent us from proceeding with a detailed review. Your submittal has been assigned Enterprise Project Identification Number (EPID)
L-2022-LLA-0112. Please reference this EPID number and Docket Number 50-247 in any future correspondence associated with this request.
Please note that the NRC staffs technical review of your submittal may identify issues that require additional information. Based on our preliminary evaluation and projection of current review schedules, we anticipate completing our formal review by February 1, 2023. This date could change depending on the findings of our technical review, urgent assignments, or other factors. We will promptly communicate any significant changes to this schedule. In addition, the NRC staff estimates that completing the review of your submittal will require approximately 200 staff hours.
In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this email will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs ADAMS. ADAMS is accessible from the NRC Web site at https://www.nrc.gov/reading-rm/adams.html.
If you have any questions regarding this License Amendment Request, please contact me.
Thank you, Karl Sturzebecher
NMSS/DUWP/Reactor Decommissioning Branch U.S. Nuclear Regulatory Commission Washington, DC 20555 Mail Stop: T5A10
C: 443-676-3495 T: 301-415-8534 E: Karl.Sturzebecher@nrc.gov