Email Objection to Holtec IP2 Master Decommissioning Trust Agreement for Indian Point Nuclear Generating Facility Unit 1 and 2, EPID L-2022-LLA-0072
ML22269A345
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 09/22/2022
From: John Lubinski
Office of Nuclear Material Safety and Safeguards
To: Fleming J
Holtec Decommissioning International
Sturzebecher K; 301-415-8534
References
EPID L-2022-LLA-0072
Download: ML22269A345 (1)


Text

From: John Lubinski To: J.Fleming@holtec.com Cc: W.Noval@holtec.com; Shaun Anderson; Karl Sturzebecher

Subject:

Holtec letter dated August 10, 2022 Date: Thursday, September 22, 2022 7:44:13 AM

Dear Jean Fleming:

By letter dated August 10, 2022, Holtec Decommissioning International, LLC (HDI) provided notification to the NRC of its Amended and Restated Holtec Indian Point 2, LLC Master Decommissioning Trust Agreement for Indian Point Nuclear Generating Units 1 and 2 (Proposed Amended IP2 Master Trust).

The NRC staff reviewed the Proposed Amended IP2 Master Trust. Pursuant to 10 C.F.R. 50.75(h)(1)(iii), the NRC staff objects to the Proposed Amended IP2 Master Trust going into effect on September 23, 2022. The NRC staff needs additional information to determine whether it complies with the applicable regulations. Specifically, Section 3.07(a) of the Proposed Amended IP2 Master Trust does not appear to be consistent with 10 CFR 50.75(h)(1)(ii).

The staff will send RAIs within the next 30 days. If you have any questions, please contact Karl Sturzebecher at (301) 415-8534.

Thank you, John W. Lubinski, Director, NMSS