Email from Z Cruz to J Fleming Request for Additional Information - HDI Indian Point Post-Shutdown Decommissioning Activities Report
ML22006A044
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 01/05/2022
From: Cruz-Perez Z
Reactor Decommissioning Branch
To: Fleming J
Holtec Decommissioning International
Cruz-Perez Z
Shared Package
ML22006A034 List:
References
Download: ML22006A044 (1)


Text

From:

To:

Cc:

Subject:

Date:

Attachments:

Cruz Perez, Zahira Jean Fleming Matthew Johnson Request for Additional Information - HDI Indian Point Post-Shutdown Decommissioning Activities Report Wednesday, January 5, 2022 2:59:00 PM

Dear Ms. Fleming,

By letter dated December 19, 2019 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML19354A698), Holtec Decommissioning International, LLC (HDI), submitted a Post-Shutdown Decommissioning Activities Report (PSDAR) and associated Decommissioning Cost Estimate for the Indian Point Energy Center (IPEC),

which consists of Indian Point Nuclear Generating Units 1, 2, and 3, to the U.S.Nuclear Regulatory Commission (NRC). HDI submitted the PSDAR pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 50.82(a)(4). HDI developed the IPEC PSDAR using the Regulatory Guide 1.185, Revision 1, Standard Format and Content for Post-Shutdown Decommissioning Activities Report (ADAMS Accession No. ML13140A038).

The NRC staff is reviewing the PSDAR and has determined that the following additional information is required to complete its review.

On December 16, 2021 the draft RAI questions were sent to you to ensure that they were understandable, the regulatory bases for the questions were clear, and to determine if the information was previously docketed. Teleconference was held on January 4, 2022 with your staff to clarify the RAI questions. HDI stated they would respond to the RAI within 30 days of the date of this email.

If you have any questions, please contact me.

Docket Nos.50-003, 50-247, 50-286,72-051

Enclosure:

Request for Additional Information Zahira Zahira Cruz (Pronouns: She/Her/Hers)

Project Manager U.S. Nuclear Regulatory Commission Office of Nuclear Material Safety and Safeguards Reactor Decommissioning Branch Mail Stop: T-5A10 Rockville, MD 20852 Zahira.Cruz@nrc.gov 301-415-3808