ND-22-0142, ITAAC Closure Notification on Completion of ITAAC 2.2.05.06a (Index Number 263)

From kanterella
(Redirected from ML22059B055)
Jump to navigation Jump to search

ITAAC Closure Notification on Completion of ITAAC 2.2.05.06a (Index Number 263)
ML22059B055
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 02/28/2022
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ND-22-0142
Download: ML22059B055 (7)


Text

Michael J. Vox 7825 River Road Sk. Southern Nuclear Regulatory Affairs Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 tel FEB 2 8 2022 Docket No.: 52-025 ND-22-0142 10CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC 2.2.05.06a [Index Number 2631 Ladies and Gentlemen:

In accordarice with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC)of the completion of Vogtle Electric Generating Plant(VEGP) Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.2.05.06a [Index Number 263], for verifying that the Class 1E components identified in the Combined License (COL), Appendix C Table 2.2.5-1 are powered from their respective Class IE division. The closure process for this ITAAC is based on the guidance described in NEI 08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52," which was endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions, please contact Kelli Roberts at 706-848-6991.

Respectfully submitted.

Michael J. Vox Regulatory Affairs rector Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 3 Completion of ITAAC 2.2.05.06a [Index Number 263]

MJY/LBP/sfr

U.S. Nuclear Regulatory Commission ND-22-0142 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. J.B. Williams Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beiike Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 Nuclear Reoulatorv Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A. Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. O. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Mr. T. Fanelli Ms. K. McCurry Mr. J. Parent Mr. B. Griman Mr. V. Hall

U.S. Nuclear Regulatory Commission ND-22-0142 Page 3 of 3 Oqlethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Daiton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. OrlanI Mr. D. C. Durham Mr. M. M. CorlettI Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. 8. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-22-0142 Enclosure Page 1 of 4 Southern Nuclear Operating Company ND-22-0142 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 3 Completion of ITAAC 2.2.05.06a [Index Number 263]

U.S. Nuclear Regulatory Commission ND-22-0142 Enclosure Page 2 of 4 ITAAC Statement Desian Commitment 6.a) The Class 1E components Identified in Table 2.2.5-1 are powered from their respective Class 1E division.

Inspections/Tests/Analvses Testing will be performed by providing a simulated test signal in each Class 1E division.

Acceptance Criteria A simulated test signal exists at the Class 1E equipment identified in Table 2.2.5-1 when the assigned Class 1E division is provided the test signal.

ITAAC Determination Basis Testing was performed on the Class 1E components(equipment) identified in the VEGP Unit 3 COL Appendix C Table 2.2.5-1 (Attachment A)to demonstrate that they are powered from their respective Class IE division. This ITAAC performed testing on the Main Control Room Emergency Habitability System (VES)equipment identified in Table 2.2.5-1 by providing a simulated test signal in each Class 1E division.

Class 1E power verification testing of the Protection and Safety Monitoring System (PMS) cabinets, associated with the equipment identified in Attachment A, are verified through the applicable portion of ITAAC 2.5.02.05a testing (Reference 1) and confirmed the PMS cabinets are powered from their respective Class IE division. SV3-VES-ITR-800263(Reference 2) documents completion of power verification activities from the PMS cabinets and the Class 1E power distribution panels to the equipment identified in Attachment A. Reference 2 first verified that power supply cables/wiring were installed and terminated from the applicable PMS cabinet and Class 1E power distribution panel to the respective component identified in Attachment A using approved construction drawings and cable/wiring termination documentation. Reference 2 then confirmed, via cable/wiring termination inspection documentation, that continuity testing was performed on each of the installed cables/wiring to confirm current flow within the installed cable/wiring. The combination of cable/wiring installation and termination verification, with the installed cable/wiring continuity testing, confirmed that the equipment identified in Appendix A are powered from their respective Class 1E division.

The results of the testing are documented in SV3-VES-ITR-800263(Reference 2)and confirmed that a simulated test signal exists at the Class 1E equipment identified in Table 2.2.5-1 when the assigned Class 1E division provided the test signal.

References 1 and 2 are available for NRC inspection as part of the Unit 3 ITAAC 2.2.05.06a Completion Package (Reference 3).

U.S. Nuclear Regulatory Commission ND-22-0142 Enclosure Page 3 of 4 ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company(SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

The ITAAC completion review is documented in the Vogtle Unit 3 ITAAC Completion Package for ITAAC 2.2.05.06a (Reference 3)and is available for NRC inspection.

ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 2.2.05.06a was performed for VEGP Unit 3 and that the prescribed acceptance criteria were met.

Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.

References favallable for NRC Inspection)

1. SV3-PMS-ITR-800527-1 Rev. 0,"Unit 3 Protection & Safety Monitoring(PMS)System Equipment by Assigned Class 1E Division: ITAAC 2.5.02.05a"
2. SV3-VES-ITR-800263 Rev. 0,"Unit 3 Emergency Habitability System: ITAAC 2.2.05.06a NRC Index Number 263"
3. 2.2.05.06a-U3-CP-Rev0, ITAAC Completion Package

U.S. Nuclear Regulatory Commission ND-22-0142 Enclosure Page 4 of 4 Attachment A COL Appendix C Table 2.2.5-1 Equipment Name* Tag No.*

MCR Load Shed Panel 1 VES-EP-01 MCR Load Shed Panel 2 VES-EP-02 MCR Air Delivery Isolation Valve A VES-PL-V005A MCR Air Delivery Isolation Valve B VES-PL-V005B MCR Pressure Relief Isolation Valve A VES-PL-V022A MCR Pressure Relief Isolation Valve B VES-PL-V022B MCR Air Delivery Line Flow Sensor VES-003A MCR Air Delivery Line Flow Sensor VES-003B MCR Differential Pressure Sensor A VES-004A MCR Differential Pressure Sensor B VES-004B Excerpted from COL Appendix C Table 2.2.5-1