ML21313A013
Letter Sequence Meeting | |
---|---|
EPID:L-2021-LLA-0173, Revision 35 to Updated Safety Analysis Report, Cover Letter and Information on Enclosures (Approved, Closed) | |
Initiation | |
MONTHYEARML21309A0332021-11-0505 November 2021
[Table View]NRR E-mail Capture - Acceptance Review - Wolf Creek Revision of Technical Specification 3.8.1, AC Sources - Operating Project stage: Acceptance Review ML21313A0132021-11-0909 November 2021 Teleconference with Wolf Creek Nuclear Operating Corporation Regarding the Diesel Generator Completion Time Extension License Amendment Request for Wolfcreek Generating Station, Unit 1 Project stage: Meeting ML21333A1312021-12-0707 December 2021 Summary of Meeting with Wolf Creek Nuclear Operating Corporation Diesel Generator Completion Time License Amendment Request for Wolf Creek Generating Station Project stage: Meeting ML22055A1142022-02-23023 February 2022 NRR E-mail Capture - Request for Additional Information - Wolf Creek Request to Revise Diesel Generator Completion Time Project stage: RAI ET 22-0005, Response to Request for Additional Information Regarding License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2022-04-13013 April 2022 Response to Request for Additional Information Regarding License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating Project stage: Response to RAI ML22152A0252022-05-18018 May 2022 Revision 35 to Updated Safety Analysis Report, Cover Letter and Information on Enclosures Project stage: Request ET 22-0012, Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2022-07-12012 July 2022 Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating Project stage: Supplement ML22252A1512022-11-0404 November 2022 Issuance of Amendment No. 234 Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating Project stage: Approval 2022-11-04 |
ML21313A013 | |
Person / Time | |
---|---|
Site: | Wolf Creek |
Issue date: | 11/09/2021 |
From: | Office of Nuclear Reactor Regulation |
To: | |
References | |
PMNS20211433 | |
Download: ML21313A013 (3) | |
Similar Documents at Wolf Creek | |
---|---|
Category:Meeting Notice
MONTHYEARPMNS20240892, Meeting to Discuss the Nuclear Regulatory Commissions (NRC) 2023 Annual Assessment of Safety Performance at Wolf Creek Generating Station2024-07-0202 July 2024
[Table view]Meeting to Discuss the Nuclear Regulatory Commissions (NRC) 2023 Annual Assessment of Safety Performance at Wolf Creek Generating Station ML24180A1252024-06-28028 June 2024 Teleconference with Wolf Creek Nuclear Operating Corporation Regarding Wolf Creek Generating Station Unit 1, Amendment No. 237, Allowing the Use of Portable Lighting ML24072A0062024-03-12012 March 2024 Teleconference with Wolf Creek Nuclear Operating Corporation Regarding Revised Safety Evaluation for Wolf Creek Generating Station Unit 1, Amendment No. 237, Allowing the Use of Portable Lighting ML23278A0262023-10-0505 October 2023 Presubmittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding a Planned License Amendment Request for Wolf Creek Generating Station, Unit 1 PMNS20230882, Meeting to Discuss the Nuclear Regulatory Commissions (NRC) 2022 Annual Assessment of Safety Performance at Wolf Creek Generating Station2023-08-0707 August 2023 Meeting to Discuss the Nuclear Regulatory Commissions (NRC) 2022 Annual Assessment of Safety Performance at Wolf Creek Generating Station PMNS20230777, Meeting to Discuss the Nuclear Regulatory Commissions (NRC) 2022 Annual Assessment of Safety Performance at Wolf Creek Generating Station2023-06-27027 June 2023 Meeting to Discuss the Nuclear Regulatory Commissions (NRC) 2022 Annual Assessment of Safety Performance at Wolf Creek Generating Station PMNS20220467, Public Webinar to Discuss the Nuclear Regulatory Commissions 2021 Annual Assessment of Safety Performance at Region IV Plants2022-05-0303 May 2022 Public Webinar to Discuss the Nuclear Regulatory Commissions 2021 Annual Assessment of Safety Performance at Region IV Plants ML21336A5292021-12-0202 December 2021 Pre-submittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding a License Amendment Request to Use Portable Lighting for Wolf Creek Generating Station, Unit 1 ML21313A0132021-11-0909 November 2021 Teleconference with Wolf Creek Nuclear Operating Corporation Regarding the Diesel Generator Completion Time Extension License Amendment Request for Wolfcreek Generating Station, Unit 1 ML21181A2982021-06-30030 June 2021 Pre-submittal Teleconference with Wolf Creek Nuclear Operating Corporation Regardingan Emergency Preparedness Exercise Exemption for Wolf Creek Generating Station, Unit 1 PMNS20210563, Public Webinar to Discuss the NRCs 2020 Annual Assessment of Safety Performance at Arkansas Nuclear One, Columbia, Comanche Peak, Cooper, Diablo Canyon, Palo Verde, River Bend Station, South Texas Project, Waterford, and Wolf Creek2021-04-29029 April 2021 Public Webinar to Discuss the NRCs 2020 Annual Assessment of Safety Performance at Arkansas Nuclear One, Columbia, Comanche Peak, Cooper, Diablo Canyon, Palo Verde, River Bend Station, South Texas Project, Waterford, and Wolf Creek ML20310A0302020-11-0505 November 2020 Presubmittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding an Emergency Response Organization Staffing License Amendment Request for Wolf Creek Generating Station, Unit 1 ML20297A3232020-10-23023 October 2020 Presubmittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding a Risk-Informed GSI-191 License Amendment Request for Wolf Creek Generating Station, Unit 1 ML20170B1872020-06-19019 June 2020 Public Webinar to Discuss the Nrc'S Assessment of Safety Performance at Region IV Plants for 2019 ML17331A8402017-11-27027 November 2017 December 12, 2017 - Closed Regulatory Conference with Wolf Creek Generating Station ML17019A2912017-01-19019 January 2017 Notice of Closed Regulatory Conference with Wolf Creek Generating Station ML17019A2932017-01-19019 January 2017 Notice of Closed Regulatory Conference with Wolf Creek Generating Station ML16089A1542016-03-28028 March 2016 Notice of Closed Predecisional Enforcement Conference with Former Contract Employee of Wolf Creek Nuclear Operating Corporation ML16064A1872016-03-0404 March 2016 Closed Pre-Decisional Enforcement Conference with Wolf Creek Nuclear Operating Corporation ML15161A6142015-06-10010 June 2015 Open House with Members of the Public / Wolf Creek Generating Station ML14261A2772014-09-18018 September 2014 Notice of Meeting with Wolf Creek Nuclear Operating Corporation to Present an Update on the Planned Actions to Address Design Problems with the Safety-Related Cooling Water System ML14160B2632014-06-0909 June 2014 Public Meeting Notice with Wolf Creek Nuclear Operating to Discuss the Performance Assessment Results for Wolf Creek Generating Station for 2013, & Progress in Addressing Corrosion and Water Hammer Issues in the Emergency Service Water Syst ML14106A6472014-04-16016 April 2014 Notice of Regulatory Conference with the Wolf Creek Nuclear Operating Corporation ML14013A0982014-01-13013 January 2014 Notice of Close Public Meeting Concurrence by Riv, to Discuss an Apparent Violation That Involves a Security-related Issue at Wolf Creek Generating Station ML14013A0232014-01-13013 January 2014 Notice of Meeting with Wolf Creek Nuclear Operating Corporation ML14013A0112014-01-10010 January 2014 WCNOC Mtg Notice EA-13-199 Wc Rc 1-22-14 ML14008A4042014-01-0808 January 2014 1/22/2014, Notice of Meeting with Wolf Creek Nuclear Operating Corporation ML13204A2432013-07-24024 July 2013 Notice of Preapplication Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Long-Term Corrective Actions for Water Hammer Events in the Essential Service Water System at Wolf Creek ML13179A1012013-07-0909 July 2013 7/30/13 Notice of Forthcoming Preapplication Meeting with Wolf Creek Nuclear Operating Company to Discuss Proposed Transition to Westinghouse Methodologies for Core Design and Non-LOCA Safety Analyses at Wolf Creek Generating Station ML13093A0592013-04-0202 April 2013 Public Meeting with Wolf Creek Nuclear Operating Corporation to Discuss the Performance Assessment Results for Wolf Creek Generating Station for 2012 ML12328A0772012-11-23023 November 2012 Notice of Meeting with Wolf Creek Nuclear Operating Corporation to Discuss an Update on the Initiatives Being Implemented to Improve Station Performance ML12249A0292012-09-0606 September 2012 9/20/12 Notice of Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Transition from Current to NRC-Approved Westinghouse Methodologies for Performing the Core Design and Non-LOCA Safety Wolf Creek Station ML12164A2982012-06-12012 June 2012 6/26/2012 Notice of Open House Meeting with Members of the Public to Discuss NRC Oversight Process Annual Assessment of Wolf Creek Generating Station ML12164A2932012-06-12012 June 2012 Notice of Public Meeting with Wolf Creek Nuclear Operating Corporation, to Discuss Corporation to Present an Update on the Initiatives Being Implemented to Improve Station Performance ML1205205442012-02-21021 February 2012 Notice of Meeting with Wolf Creek Nuclear Operating Corporation, for NRC Augmented Inspection Team to Discuss Results of Recent Inspection Following Complete Loss of Offsite Power and Reactor Trip Event ML1129405532011-10-20020 October 2011 Notice of Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Updates on the Initiatives Being Implemented to Improve Station Performance ML1129304522011-10-20020 October 2011 Notice of Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Update on the Initiatives Being Implemented to Improve Station Performance ML1108109742011-03-22022 March 2011 Notice of Public Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Performance Assessment Results ML1031407402010-11-10010 November 2010 Notice of Meeting with Wolf Creek Nuclear Operating Corporation, to Present an Update on Initiatives Being Implementing to Improve Performance in Area of Problem Identification & Resolution ML1021800652010-08-0606 August 2010 Notice of Meeting with Wolf Creek Nuclear Operating Corporation to Present an Update on the Initiatives Being Implemented to Improve Station Performance ML1011801162010-04-27027 April 2010 Updated Notice of End-of-Cycle Meeting with Wolf Creek Nuclear Operation, to Present and Discuss Performance Results of the Wolf Creek Generating Station Facility for the Period of January 1 Through December 31, 2009 ML1010407592010-04-14014 April 2010 Notice of Meeting with Wolf Creek Nuclear Operation Corporation to Discuss Performance Results of the Wolf Creek Generating Station Facility for the Period of January 1 Through December 31, 2009 ML0931607532009-11-12012 November 2009 Notice of Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Initiatives Being Implemented to Improve Performance in the Areas of Human Performance and Problem Identification & Resolution ML0929300152009-10-20020 October 2009 Revised Notice of Meeting with Union Electric Company and Wolf Creek Nuclear Operating Company to Discuss NRC Requests for Additional Information on Generic Letter 2004-02 ML0928003162009-10-16016 October 2009 Notice of Meeting with Union Electric Company and Wolf Creek Nuclear Operating Company to Discuss NRC Requests for Additional Information on Generic Letter 2004-02 Sent 7/31/0209 and 8/27/2009, Respectively ML0920306202009-07-31031 July 2009 Notice of Forthcoming Conference Call with Union Electric Company and Wolf Creek Nuclear Operating Company Re Draft Requests for Additional Information on Generic Letter 2004-02 for Callaway Plant and Wolf Creek Creek Generating Station ML0915305782009-06-0202 June 2009 Notice of Meeting with Wolf Creek Nuclear Operation Corporation, to Present Updates on Initiatives Implemented to Improve Problem Identification and Resolution and Human Performance ML0907004192009-03-11011 March 2009 Notice of Meeting with Wolf Creek Nuclear Operation Corporation to Discuss Performance Results of the Wolf Creek Generating Station Facility for the Period of January 1 Through December 31, 2008 ML0835705252008-12-24024 December 2008 Meeting Notice, Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Pre-Application of Post-fire Safe Shutdown Issues at Wolf Creek ML0827305152008-09-25025 September 2008 Meeting Notice with Wolf Creek Nuclear Operating Corporation to Present Updates on Initiatives Implemented to Improve Problem Identification and Resolution and Human Performance 2024-07-02 Category:Meeting Agenda MONTHYEARML24311A1572024-11-0606 November 2024
[Table view]Slides for Pre-submittal Public Teleconference Meeting for License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors PMNS20240892, Meeting to Discuss the Nuclear Regulatory Commissions (NRC) 2023 Annual Assessment of Safety Performance at Wolf Creek Generating Station2024-07-0202 July 2024 Meeting to Discuss the Nuclear Regulatory Commissions (NRC) 2023 Annual Assessment of Safety Performance at Wolf Creek Generating Station ML24180A1252024-06-28028 June 2024 Teleconference with Wolf Creek Nuclear Operating Corporation Regarding Wolf Creek Generating Station Unit 1, Amendment No. 237, Allowing the Use of Portable Lighting ML24072A0062024-03-12012 March 2024 Teleconference with Wolf Creek Nuclear Operating Corporation Regarding Revised Safety Evaluation for Wolf Creek Generating Station Unit 1, Amendment No. 237, Allowing the Use of Portable Lighting ML23275A1712023-10-16016 October 2023 October 16, 2023, Licensee Pre-submittal Meeting Slides - License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505-A, Revision 2 for Wolf Creek Generating Station ML23278A0262023-10-0505 October 2023 Presubmittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding a Planned License Amendment Request for Wolf Creek Generating Station, Unit 1 PMNS20230882, Meeting to Discuss the Nuclear Regulatory Commissions (NRC) 2022 Annual Assessment of Safety Performance at Wolf Creek Generating Station2023-08-0707 August 2023 Meeting to Discuss the Nuclear Regulatory Commissions (NRC) 2022 Annual Assessment of Safety Performance at Wolf Creek Generating Station PMNS20230777, Meeting to Discuss the Nuclear Regulatory Commissions (NRC) 2022 Annual Assessment of Safety Performance at Wolf Creek Generating Station2023-06-27027 June 2023 Meeting to Discuss the Nuclear Regulatory Commissions (NRC) 2022 Annual Assessment of Safety Performance at Wolf Creek Generating Station PMNS20220467, Public Webinar to Discuss the Nuclear Regulatory Commissions 2021 Annual Assessment of Safety Performance at Region IV Plants2022-05-0303 May 2022 Public Webinar to Discuss the Nuclear Regulatory Commissions 2021 Annual Assessment of Safety Performance at Region IV Plants ML21336A5292021-12-0202 December 2021 Pre-submittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding a License Amendment Request to Use Portable Lighting for Wolf Creek Generating Station, Unit 1 ML21313A0132021-11-0909 November 2021 Teleconference with Wolf Creek Nuclear Operating Corporation Regarding the Diesel Generator Completion Time Extension License Amendment Request for Wolfcreek Generating Station, Unit 1 ML21181A2982021-06-30030 June 2021 Pre-submittal Teleconference with Wolf Creek Nuclear Operating Corporation Regardingan Emergency Preparedness Exercise Exemption for Wolf Creek Generating Station, Unit 1 PMNS20210563, Public Webinar to Discuss the NRCs 2020 Annual Assessment of Safety Performance at Arkansas Nuclear One, Columbia, Comanche Peak, Cooper, Diablo Canyon, Palo Verde, River Bend Station, South Texas Project, Waterford, and Wolf Creek2021-04-29029 April 2021 Public Webinar to Discuss the NRCs 2020 Annual Assessment of Safety Performance at Arkansas Nuclear One, Columbia, Comanche Peak, Cooper, Diablo Canyon, Palo Verde, River Bend Station, South Texas Project, Waterford, and Wolf Creek ML20310A0302020-11-0505 November 2020 Presubmittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding an Emergency Response Organization Staffing License Amendment Request for Wolf Creek Generating Station, Unit 1 ML20297A3232020-10-23023 October 2020 Presubmittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding a Risk-Informed GSI-191 License Amendment Request for Wolf Creek Generating Station, Unit 1 ML20170B1872020-06-19019 June 2020 Public Webinar to Discuss the Nrc'S Assessment of Safety Performance at Region IV Plants for 2019 ML17331A8402017-11-27027 November 2017 December 12, 2017 - Closed Regulatory Conference with Wolf Creek Generating Station ML17019A2912017-01-19019 January 2017 Notice of Closed Regulatory Conference with Wolf Creek Generating Station ML17019A2932017-01-19019 January 2017 Notice of Closed Regulatory Conference with Wolf Creek Generating Station ML16089A1542016-03-28028 March 2016 Notice of Closed Predecisional Enforcement Conference with Former Contract Employee of Wolf Creek Nuclear Operating Corporation ML16064A1872016-03-0404 March 2016 Closed Pre-Decisional Enforcement Conference with Wolf Creek Nuclear Operating Corporation ML14106A6472014-04-16016 April 2014 Notice of Regulatory Conference with the Wolf Creek Nuclear Operating Corporation ML14013A0112014-01-10010 January 2014 WCNOC Mtg Notice EA-13-199 Wc Rc 1-22-14 ML13204A2432013-07-24024 July 2013 Notice of Preapplication Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Long-Term Corrective Actions for Water Hammer Events in the Essential Service Water System at Wolf Creek ML13179A1012013-07-0909 July 2013 7/30/13 Notice of Forthcoming Preapplication Meeting with Wolf Creek Nuclear Operating Company to Discuss Proposed Transition to Westinghouse Methodologies for Core Design and Non-LOCA Safety Analyses at Wolf Creek Generating Station ML12249A0292012-09-0606 September 2012 9/20/12 Notice of Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Transition from Current to NRC-Approved Westinghouse Methodologies for Performing the Core Design and Non-LOCA Safety Wolf Creek Station ML1207601012012-03-16016 March 2012 Summary of Public Meeting with Wolf Creek Nuclear Operating Corporation ML12011A1012012-01-19019 January 2012 Summary of Meeting with NEI and to Address Di&C Issues ML0929300152009-10-20020 October 2009 Revised Notice of Meeting with Union Electric Company and Wolf Creek Nuclear Operating Company to Discuss NRC Requests for Additional Information on Generic Letter 2004-02 ML0928003162009-10-16016 October 2009 Notice of Meeting with Union Electric Company and Wolf Creek Nuclear Operating Company to Discuss NRC Requests for Additional Information on Generic Letter 2004-02 Sent 7/31/0209 and 8/27/2009, Respectively ML0920306202009-07-31031 July 2009 Notice of Forthcoming Conference Call with Union Electric Company and Wolf Creek Nuclear Operating Company Re Draft Requests for Additional Information on Generic Letter 2004-02 for Callaway Plant and Wolf Creek Creek Generating Station ML0834700222008-12-11011 December 2008 Slides, Category 2 Public Meeting Digital Instrumentation and Control Steering Committee M080717, M080717-Commission Briefing Slides/Exhibits Briefing on Fire Protection2008-07-17017 July 2008 M080717-Commission Briefing Slides/Exhibits Briefing on Fire Protection ML0816908822008-06-17017 June 2008 Meeting Notice, Briefing on Fire Protection Issues ML0807300242008-02-22022 February 2008 Status Report and Proposed Agenda for the ACRS Subcommittee on March 5, 2008 Related to the License Renewal Application of Wolf Creek Generating Stations Unit 1 ML0733103642007-11-27027 November 2007 Revised Notice of Meeting with Wolf Creek Nuclear Operating Corp, to Discuss NRC Staff'S Request for Information on Licensee'S Supplemental Letter Dated September 27, 2007, to the Application Dated February 21, 2006, to Revise TS 5.5.9 ML0733101982007-11-27027 November 2007 Notice of Meeting with Wolf Creek Nuclear Operating Corporation, to Discuss NRC Staff'S Request for Additional Information on Licensee'S Proposed Main Steam and Feedwater Isolation System Modification in Its Application Dated March 14, 2007 ML0732001042007-11-16016 November 2007 Notice of Meeting with Representatives of Wolf Creek Nuclear Operating Corporation to Discuss Main Steam and Feedwater Isolation System (Tac No. MD4839) ML0730901272007-11-0808 November 2007 Notice of Meeting with Wolf Creek Nuclear Operating Corporation to Discuss NRC Staff'S Request for Additional Information on Licensee'S Supplemental Letter to Letter Dated September 27, 2007, to Application Dated February 21, 2006 ML0729204682007-10-29029 October 2007 09/25/2007, Summary of Meeting Between the U.S. Nuclear Regulatory Commission Staff and Strategic Teaming and Resource Sharing Representatives to Discuss License Renewal Activities ML0724704202007-10-0101 October 2007 11/08/2007 Forthcoming Meeting to Discuss the Draft Supplemental Environmental Impact Statement for the License Renewal of Wolf Creek Generating Station ML0724904812007-09-11011 September 2007 Notice of Meeting with Strategic Teaming and Resource Sharing (Stars) for Licensees of Comanche Peak, Diablo Canyon, Palo Verde, South Texas, and Wolf Creek Plants ML0722602142007-08-31031 August 2007 Notice of Category 2 Public Meeting with NEI to Discuss Topical Report WCAP-16308-NP, Pressurized Water Reactor Owners Group 10 CFR 50.69 Pilot Program - Categorization Process - Wolf Creek Generating Station ML0721501532007-08-0202 August 2007 NRC Staff Handout for August 2, 2007, Meeting with Wolf Creek Nuclear Operating Corporation ML0717900072007-07-18018 July 2007 Notice of Meeting with Wolf Creek Nuclear Operating Corporation to Discuss the Licensee'S License Amendment Request Dated March 14, 2006, to Modify the Main Steam and Feedwater Isolation System ML0718702452007-07-0505 July 2007 Notice of Public Meeting Between the NRC Staff and the Expert Panel to Discuss the Wolf Creek Advanced Finite Element Fracture Mechanics Analyses That the Industry Intends to Submit on July 10, 2007 ML0718004572007-06-29029 June 2007 Notice of Meeting Between the Nuclear Regulatory Commission Staff and the Expert Panel for the Wolf Creek Advanced Finite Element Analysis ML0716504002007-06-19019 June 2007 Notice of Meeting with Wolf Creek Nuclear Corp Regarding Nrc'S Request for Additional Information on 2/21/06 Licensee Amendment Request Re SG Tube Surveillance Program, Wolf Creek Generating Station ML0716401312007-06-18018 June 2007 Category 2 Public Meeting with the Nuclear Energy Institute (NEI) to Discuss Topical Report WCAP-16308-NP, Pressurized Water Reactor Owners Group 10 CFR 50.69 Pilot Program - Categorization Process - Wolf Creek Generating Station. ML0716203882007-06-0101 June 2007 06/01/07 - Presentation Material, Advanced Fea Crack Growth Calculations for Evaluation of PWR Pressurizer Nozzle Dissimilar Metal Weld Circumferential Pwscc. 2024-07-02 |
Text
November 09, 2021
Title:
Teleconference with Wolf Creek Nuclear Operating Corporation Regarding the Diesel Generator Completion Time Extension License Amendment Request for Wolf Creek Generating Station, Unit 1 (EPID L-2021-LLA-0173)
Date(s) and Time(s):November 22, 2021, 10:00 AM to 12:00 PM ET
Location: Teleconference
Category: This is an Observation Meeting. This is a meeting in which attendees will have an opportunity to observe the NRC performing its regulatory function or discussing regulatory issues. Attendees will have an opportunity to ask questions of the NRC staff or make comments about the issues discussed following the business portion of the meeting; however, the NRC is not actively soliciting comments towards regulatory decisions at this meeting.
Purpose:
The purpose of this meeting, between Wolf Creek Nuclear Operating Corporation (WCNOC, the licensee) and the U.S. Nuclear Regulatory Commission (NRC) staff, is to provide information to the NRC staff regarding a license amendment request for Wolf Creek Generating Station, Unit 1, that would modify the diesel generator completion time in Technical Specification 3.8.1, "AC [Alternating Current] Sources - Operating" (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21272A369).
Contact:
Samson Lee 301-415-3168 Samson.Lee@nrc.gov
Participants:
NRC External S. Lee, et al., Office of Nuclear Reactor J. Turner, Wolf Creek Nuclear Operating Regulation Corporation
Teleconference: Bridge Number Pass Code (301) 576-2978 903361170
Webinar: URL Meeting Number Password https://teams.microsoft.com/l/meetup-3015762978 903361170 join/19%
3ameeting_NGQ2NzM3NTYtZGI3Ny00NG RmLWIzZDgtZmM0NjhkZGI2MGY2%
40thread.v2/0?context=%7b%22Tid%22%
3a%22e8d01475-c3b5-436a-a065-5def4c64f52e%22%2c%22Oid%22%3a%
22214a7cec-318e-4e30-9a12-d50ff94ad277%22%7d
Docket No: 05000482
The NRC provides reasonable accommodations to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in a meeting or need a meeting notice or the transcript or other information from a meeting in another format (e.g. braille, large print), please contact Anne Silk, NRC Reasonable Accommodations Coordinator, at Anne.Silk@nrc.gov or call directly at 301-287-0745.
Determinations on requests for reasonable accommodation will be made on a case-by-case basis. Ten (10) days advance notice is requested to try to ensure availability; however, every effort will be made to address a request for reasonable accommodations with less notice.
PUBLIC MEETING AGENDA
Teleconference with Wolf Creek Nuclear Operating Corporation Regarding the Diesel Generator Completion Time Extension License Amendment Request for Wolf Creek Generating Station, Unit 1 (EPID L-2021-LLA-0173)
November 22, 2021, 10:00 AM to 12:00 PM ET
Teleconference ADAMS Accession Number: ML21313A013
Distribution:
Office NRR/DORL/LPL4/PM NRR/DORL/LPL4/LA NRR/DORL/LPL4/BC NRR/DORL/LPL4/PM Name SLee PBlechman JDixon-Herrity SLee Date 11/03/2021 11/04/2021 11/04/2021 11/09/2021 OFFICIAL RECORD COPY
Link to meeting details:https://www.nrc.gov/pmns/mtg?do=details&Code=20211433
Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings" 86 FR 14964, March 19, 2021 ADAMS No. ML21050A046 https://www.nrc.gov/reading-rm/doc-collections/commission/policy/index.html