Letter Sequence Meeting |
---|
EPID:L-2021-LLA-0173, License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating (Approved, Closed) |
|
MONTHYEARET 21-0004, License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2021-09-29029 September 2021 License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating Project stage: Request ML21309A0332021-11-0505 November 2021 NRR E-mail Capture - Acceptance Review - Wolf Creek Revision of Technical Specification 3.8.1, AC Sources - Operating Project stage: Acceptance Review ML21313A0132021-11-0909 November 2021 Teleconference with Wolf Creek Nuclear Operating Corporation Regarding the Diesel Generator Completion Time Extension License Amendment Request for Wolfcreek Generating Station, Unit 1 Project stage: Meeting ML21333A1312021-12-0707 December 2021 Summary of Meeting with Wolf Creek Nuclear Operating Corporation Diesel Generator Completion Time License Amendment Request for Wolf Creek Generating Station Project stage: Meeting ML22055A1142022-02-23023 February 2022 NRR E-mail Capture - Request for Additional Information - Wolf Creek Request to Revise Diesel Generator Completion Time Project stage: RAI ET 22-0005, Response to Request for Additional Information Regarding License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2022-04-13013 April 2022 Response to Request for Additional Information Regarding License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating Project stage: Response to RAI ML22152A0252022-05-18018 May 2022 Revision 35 to Updated Safety Analysis Report, Cover Letter and Information on Enclosures Project stage: Request ET 22-0012, Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2022-07-12012 July 2022 Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating Project stage: Supplement ML22252A1512022-11-0404 November 2022 Issuance of Amendment No. 234 Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating Project stage: Approval 2022-11-04
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML23303A2182023-11-0606 November 2023 Summary of October 16, 2023, Pre-Submittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding a License Amendment Request to Adopt TSTF-505 for Wolf Creek Generating Station, Unit 1 ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22011A0862022-01-11011 January 2022 Summary of January 10, 2022, Pre-Submittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding a License Amendment Request to Use Portable Lighting for Wolf Creek Generating Station, Unit 1 ML21333A1312021-12-0707 December 2021 Summary of Meeting with Wolf Creek Nuclear Operating Corporation Diesel Generator Completion Time License Amendment Request for Wolf Creek Generating Station ML21200A1102021-07-21021 July 2021 Summary of July 13, 2021, Pre-Submittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding a Temporary Emergency Preparedness Exercise Exemption Request ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21127A1322021-05-11011 May 2021 Summary of April 16, 2021, Conference Call with Representatives of Wolf Creek Generating Station Regarding the Spring 2021 Steam Generator Tube Inspections ML20332A0422020-12-0101 December 2020 Summary of November 19, 2020, Pre-Submittal Teleconference with Wolf Creek Nuclear Operating Corporation an Emergency Response Organization Staffing License Amendment Request ML20332A0462020-11-30030 November 2020 Summary of November 18, 2020, Pre-Submittal Teleconference with Wolf Creek Nuclear Operating Corporation a Risk-Informed Generic Safety Issue (GSI)-191 License Amendment Request ML20189A2832020-07-0707 July 2020 Summary of Region IV Annual Assessment Public Meeting ML19143A4182019-05-21021 May 2019 Summary of Public Meeting with Wolf Creek Nuclear Operation Corporation ML19140A4742019-05-20020 May 2019 Closed Meeting with Wolf Creek Nuclear Operating Corporation to Conduct a Mediation Session Regarding Falsification of Documentation Associated with Licensee Maintenance Activities ML18313A2542018-11-16016 November 2018 Summary of Public Meeting with Wolf Creek Nuclear Operating Corporation Regarding License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses for Wolf Creek Generating Station ML17276B4892017-10-23023 October 2017 9/25/17 Summary of Public Meeting with Wolf Creek Nuclear Operating Corporation Regarding the Proposed LAR for Change in Emergency Plan Staff Augmentation Response Times for Wolf Creek Generating Station (CAC No. MG0174; EPID L-2017-LRM-001 ML16271A4822016-09-27027 September 2016 Summary of Regulatory Conference to Discuss Safety Significance of Wolf Creek Generating Station Emergency Generator Excitation Diode Apparent Violation ML16250A1652016-09-0909 September 2016 8/25/16 Summary of Preapplication Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Amendment Request to Transition to Westinghouse Analyses Methodologies and Alternate Source Term at Wolf Creek Generating Station ML16243A5132016-09-0101 September 2016 Summary of August 25, 2016, Public Meeting with Wolf Creek Nuclear Operating Corporation and Amerenue Regarding a Proposed Application for a New Technical Specification for the Class 1E Electrical Equipment Air Conditioning System (MF8118 a ML16106A1742016-04-22022 April 2016 Summary of Meeting with Wolf Creek Nuclear Operating Company to Discuss the Generic Safety Issue (GSI)-191 Testing Plan/Fiber Penetration and Head Loss Testing Approach for Wolf Creek Generating Station ML15182A0952015-06-30030 June 2015 Summary of Annual Assessment Meeting with Wolf Creek Nuclear Operating Corporation (WCNOC) Regarding Wolf Creek Generating Station 2014 Performance ML14188C4812014-07-0707 July 2014 Summary of Annual Assessment Meeting with Wolf Creek Generating Station ML14134A1842014-05-14014 May 2014 Summary of Public Meeting to Discuss an Apparent Violation Identified at Wolf Creek Generating Station ML14038A3852014-02-0606 February 2014 1/22/2014 - Summary of Public Meeting to Discuss Corrective Actions Implemented to Address the Chilling Effect Letter ML13221A2132013-08-12012 August 2013 8/7/2013 - Summary of Preapplication Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Long-Term Corrective Actions for Water Hammer Events in the Essential Service Water System at Wolf Creek ML13221A2152013-08-12012 August 2013 7/30/2013 - Summary of Preapplication Meeting with Wolf Creek Nuclear Operating Company to Discuss Proposed Transition to Westinghouse Methodologies for Core Design and Non-LOCA Safety Analyses at Wolf Creek Generating Station ML13121A4892013-05-0101 May 2013 End of Cycle Meeting Summary 4-18-13 ML13077A0732013-04-0101 April 2013 Summary of 2/28/13 and 3/11/13 Conference Calls with Licensee and Its Contractors Ongoing Steam Generator Tube Inspection Activities During Refueling Outage 19 ML12355A6922012-12-20020 December 2012 Summary of Public Meeting with Wolf Creek Nuclear Operating Corp Re Improved Station Performance ML12276A2652012-11-0101 November 2012 Meeting Summary with Wolf Creek Nuclear Operating Corporation to Discuss Transition from Current to NRC-Approved Westinghouse Methodologies for Performing the Core Design and Non-LOCA Safety Analysis at Wolf Creek ML12191A1742012-07-0909 July 2012 6/25/2012 Summary of Public Meeting with Wolf Creek Nuclear Operating Corporation ML12191A1462012-07-0606 July 2012 6/26/2012 - Summary of Public Meeting to Discuss Performance of Wolf Creek Nuclear Operating Corporation ML13246A3802012-05-0808 May 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Tuesday, May 8, 2012 ML1207601012012-03-16016 March 2012 Summary of Public Meeting with Wolf Creek Nuclear Operating Corporation ML13246A3782012-02-16016 February 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Thursday, February 16, 2012 ML13246A3772012-01-31031 January 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Tuesday, January 31, 2012 ML13246A3762012-01-23023 January 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Monday, January 23, 2012 ML12011A1012012-01-19019 January 2012 Summary of Meeting with NEI and to Address Di&C Issues ML13246A3742012-01-17017 January 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Tuesday, January 17, 2012 ML1110104292011-04-11011 April 2011 Summary of Annual Performance Assessment Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Wolf Creek Generating Station Performance for the NRC Inspection Period Ending December 31, 2010 ML1024506282010-09-0202 September 2010 Summary of Public Meeting with Wolf Creek Nuclear Operating Corporation ML1013404892010-05-14014 May 2010 Summary of Annual Performance Assessment Meeting with Wolf Creek Nuclear Operating Corporation to Discuss the Wolf Creek Generating Station Performance for the NRC Inspection Period from January 1 Through December 31, 2009 ML0933805662009-12-17017 December 2009 Summary of Meeting with Union Electric Company and Wolf Creek Nuclear Operating Company to Discuss NRC Requests for Additional Information on Generic Letter 2004-02 Sent 7/31/2009 and 8/27/2009, Respectively ML0933702032009-12-0303 December 2009 Summary of Public Meeting for Wolf Creek Generating Station ML0924607142009-09-28028 September 2009 Summary of Meeting with Union Electric Co., and Wolf Creek, to Discuss Draft Requests for Additional Information on GL 2004-02 for Callaway, Unit 1, and Wolf Creek ML0911205282009-04-21021 April 2009 Summary of Annual Performance Assessment Meeting for Wolf Creek Generating Station ML0902102062009-01-23023 January 2009 Summary of Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Changes to Post Fire Shutdown Unresolved Items Analysis Methods Pre-Application for Wolf Creek Generating Station ML0829607972008-10-22022 October 2008 Summary of Meeting with Wolf Creek, Discussing Several Initiatives Being Implemented to Improve Plant Performance ML0817706682008-06-25025 June 2008 Summary of Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Several Initiatives That Were Being Implemented to Improve Plant Performance at Wolf Creek ML0813606472008-06-10010 June 2008 05/01/2008-Summary of Public Meeting on Safety Evaluation Report with Open Items Regarding the Wolf Creek Generating Station License Renewal Review ML0812803052008-05-0808 May 2008 Summary of Conference Call with Wolf Creek Nuclear Operating Corporation Spring 2008 Steam Generator Tube Inspections During Refueling Outage 16 at Wolf Creek Generating Station ML0807904692008-04-10010 April 2008 Summary of Teleconference with Wolf Creek Nuclear Operating Corporation, Ameren Union Electric Company for Callaway Plant, and Performance Contracting, Inc. Containment Sump Head Loss Testing 2023-11-06
[Table view] |
Text
December 7, 2021 LICENSEE: Wolf Creek Nuclear Operating Corporation FACILITY: Wolf Creek Generating Station, Unit 1
SUBJECT:
SUMMARY
OF NOVEMBER 22, 2021, PUBLIC TELECONFERENCE WITH WOLF CREEK NUCLEAR OPERATING CORPORATION REGARDING THE DIESEL GENERATOR COMPLETION TIME EXTENSION LICENSE AMENDMENT REQUEST FOR WOLF CREEK GENERATING STATION, UNIT 1 (EPID L-2021-LLA-0173)
On November 22, 2021, an observation public teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Wolf Creek Nuclear Operating Corporation (the licensee). The purpose of the teleconference was to provide information to the NRC staff regarding a license amendment request (LAR) for Wolf Creek Generating Station, Unit 1 (Wolf Creek), that would modify the diesel generator (DG) completion time in Technical Specification (TS) 3.8.1, AC [Alternating Current] Sources - Operating (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21272A369). No presentation slides were used at the teleconference. The meeting notice and agenda, dated November 9, 2021, are available in ADAMS at Accession No. ML21313A013. A list of attendees is provided in the Enclosure.
In response to NRC staff questions on the LAR concerning details on removing Sharpe Station from the TS and the alignment of gensets at the station as a backup to the DGs, the licensee indicated that the Wolf Creek LAR would extend the completion time for one inoperable DG from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 14 days based on the availability of a supplemental power source (i.e., station blackout (SBO) DG system) and remove the credit for the Sharpe Station. The Sharpe Station is offsite and has a special application to support pre-planned DG maintenance, as needed.
The licensee indicated that the Sharpe Station was available before the SBO DGs, which were installed onsite in 2013 and provide operational flexibility and control. The licensee was planning to upgrade its switchyard in the next few years and afterwards, transformer connections would not be available for the Sharpe Station to the safety buses. With the SBO DGs, the licensee indicated that the Sharpe Station would not be needed to extend the completion time as proposed in the LAR and could be removed from the TS. The licensee would follow the Title 10 of the Code of Federal Regulations Section 50.59, Changes, tests, and experiments, process to evaluate the Sharpe Station in the switchyard modification, which is separate from this LAR.
In response to NRC staff questions about the SBO DGs, the licensee indicated that the SBO DGs were installed after the completion of the licensing basis SBO coping time analysis. The SBO DGs are not qualified as alternate AC sources per Regulatory Guide 1.155, Station Blackout (ADAMS Accession No. ML003740034) but are consistent with Branch Technical Position 8-8, Onsite (Emergency Diesel Generators) and Offsite Power Sources Allowed
Outage Time Extensions (ADAMS Accession No. ML113640138). The licensee also indicated that the Sharpe Station is not described in the Wolf Creek Final Safety Analysis Report.
The NRC staff planned to submit requests for additional information to the licensee as part of the LAR review process.
Two members of the public were in attendance. The public did not provide any comments. No regulatory decisions were made at this meeting.
Please direct any inquiries to me at 301-415-3168 or Samson.Lee@nrc.gov.
/RA/
Samson S. Lee Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-482
Enclosure:
List of Attendees cc: Listserv
LIST OF ATTENDEES NOVEMBER 22, 2021, PUBLIC TELECONFERENCE REGARDING DIESEL GENERATOR COMPLETION TIME EXTENSION LICENSE AMENDMENT REQUEST WOLF CREEK NUCLEAR OPERATING CORPORATION WOLF CREEK GENERATING STATION, UNIT 1 U.S. Nuclear Regulatory Commission S. Lee, Office of Nuclear Reactor Regulation (NRR)
A. Foli, NRR H. Kodali, NRR G. Curran, NRR M. Hamm, NRR S. Alferink, NRR S. Vasavada, NRR K. Martin, NRR R. Wolfgang, NRR J. Dixon-Herrity, NRR Wolf Creek Nuclear Operating Corporation R. Benham, Director Nuclear and Regulatory Affairs D. Wirth, Senior Manager Nuclear Engineering J. Turner, Manager Licensing D. Alford, Manager Probabilistic Risk Assessment (PRA)
D. Sullivan, Manager Electrical Design Engineering T. Slenker, Superintendent Operations D. Vu, PRA Engineer J. Lee, PRA Engineer C. Medlen, PRA Engineer Public M. Wiwel, PSEG Nuclear Enclosure
ML21333A131 OFFICE NRR/DORL/LPL4/PM NRR/DORL/LPL4/LA NRR/DORL/LPL4/BC NRR/DORL/LPL4/PM NAME SLee PBlechman JDixon-Herrity SLee DATE 12/1/2021 12/1/2021 12/7/2021 12/7/2021