Notice of Meeting with Wolf Creek Nuclear Operating Corporation to Present an Update on the Initiatives Being Implemented to Improve Station Performance
ML102180065
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 08/06/2010
From: Geoffrey Miller
NRC/RGN-IV/DNMS/NMSB-B
To:
References
Download: ML102180065 (6)


Text

UNITED STATES NU CLE AR RE GUL AT OR Y C O M M I S S I O N R E GI ON I V 611 R YAN PLAZA D R I V E, SU ITE 400 AR LI N GTON , TEXAS 76011-4005 August 6, 2010

SUBJECT:

MEETING WITH WOLF CREEK NUCLEAR OPERATING CORPORATION FACILITY: Wolf Creek Generating Station DOCKET: 05000482 DATE & TIME: Wednesday, August 25, 2010 12:00 p.m. (CDT)

LOCATION: Region IV Office Executive Conference Room 612 E Lamar, Suite 400 Arlington, TX 76011 PURPOSE: The purpose of the meeting is for Wolf Creek Nuclear Operating Corporation to present an update on the initiatives being implemented to improve station performance. Specifically, the licensee will address performance in the area of Problem Identification & Resolution and their preparations for an upcoming 95002 supplemental inspection.

CATEGORY: This is a Category 1 meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the Nuclear Regulatory Commission after the business portion, but before the meeting is adjourned.

The Nuclear Regulatory Commission provides reasonable accommodation to individuals with disabilities where appropriate.

If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or the transcript of other information from the meeting in another format (e.g., Braille or large print), please notify the Nuclear Regulatory Commissions meeting contact listed below. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.

A telecommunications bridge will be available for the public. The number of lines is limited and interested parties should contact the NRCs meeting contact listed below for directions.

Wolf Creek Generating Station PARTICIPANTS: NRC Elmo Collins, Regional Administrator Chuck Casto, Deputy Regional Administrator Anton Vegel, Acting Director, Division of Reactor Projects Troy Pruett, Acting Deputy Director, Division of Reactor Projects Roy Caniano, Director, Division of Reactor Safety Jeffrey Clark, Acting Deputy Director, Division of Reactor Safety Geoffrey Miller, Chief, Reactor Projects Branch B Chris Long, Senior Resident Inspector UTILITY Matt Sunseri, President & Chief Executive Office Steve Hedges, Site Vice President Steve Henry, Plant Manager Gary Pendergrass, Director Plant Engineering Jenny Yunk, Manager of Preparation for IP 95002 Inspection MEETING CONTACT: Geoffrey Miller, Branch Chief Project Branch B (817) 860-8141 Geoffrey.Miller@nrc.gov

cc:

Matthew W. Sunseri, President and Chief Executive Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 Site Vice President Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 Jay Silberg, Esq.

Pillsbury Winthrop Shaw Pittman LLP 2300 N Street, NW Washington, DC 20037 Supervisor Licensing Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 Chief Engineer Utilities Division Kansas Corporation Commission 1500 SW Arrowhead Road Topeka, KS 66604-4027 Office of the Governor State of Kansas Topeka, KS 66612-1590 Attorney General 120 S.W. 10th Avenue, 2nd Floor Topeka, KS 66612-1597 Chairman Coffey County Courthouse 110 South 6th Street Burlington, KS 66839 Chief, Radiation and Asbestos Control Section Bureau of Air and Radiation Kansas Department of Health and Environment 1000 SW Jackson, Suite 310 Topeka, KS 66612-1366

Wolf Creek Generating Station Chief, Technological Hazards Branch FEMA, Region VII 9221 Ward Parkway Suite 300 Kansas City, MO 64114-3372

Wolf Creek Generating Station E-Mail To:

NRC Attendees PMNS Resource, Mtg Announcement Coordinator Elmo Collins, RA Chuck Casto, DRA Anton Vegel, D:DRP Roy Caniano, D:DRS Troy Pruett, DD:DRP Jeff Clark, DD:DRS Mark Haire, C:DRS/OB Sue Bogle (OEWEB Resource)

OEMAIL, D/OE Margie Kotzalas, RIV OEDO Coordinator Jack Giessner, RIV OEDO Coordinator Paul Bonnett, NRR/DIRS/IPAB Balwant Singal, Project Manager, NRR Geoffrey Miller, Branch Chief, PBB Rick Deese, Senior Project Engineer, PBB Chris Long, Senior Resident Inspector Charles Peabody, Resident Inspector Victor Dricks, Region IV PAO Ray Kellar, Region IV Enforcement Specialist Lucy Owen, Region IV RA Administrative Assistant Anita Tannenbaum, Region IV RA Administrative Assistant Deborah Harrison, Region IV DRP Administrative Assistant Shirley Allen, Region IV DRS Administrative Assistant Kimberly Brewton, Region IV DRS Administrative Assistant Dana Lackey, Region IV DRP Administrative Assistant Tracy Karl, Region IV DRS Administrative Assistant Dawn Yancey, Region IV DRP Administrative Assistant Bub Mueller, IRMB Phil Longdo, Receptionist Ann Mattila, Security Advisor Jenny Weil, OCA mortensengk@INPO.org Lara Uselding, Region IV PAO Bill Maier, Region IV RSLO Karla Fuller, Region IV RC William Jones, Region IV ACES Verlyn Jenkins, Region IV DRP Administrative Assistant Denise Freeman, Region IV DNMS Administrative Assistant Earnestine Clay, DRMA, TL Harold McKelvey, IRMB

Wolf Creek Generating Station ML102180065 SUNSI Review Completed: Yes ADAMS: Yes No Initials: RWD Publicly Available Non-Publicly Available Sensitive Non-Sensitive RIV:SPE:DRP/B C:DRP/B RSLO RDeese GBMiller WAMaier

/RA/ RWD for /RA/

8/6/2010 8/6/2010 8/5/2010 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax