Letter Sequence Draft Other |
---|
EPID:L-2020-SLR-0002, Subsequent License Renewal Application on Aging Management - Request for Additional Information (Rai), Set 4 Response (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: L-2021-129, Ssubsequent License Renewal Application: Aging Management Requests for Confirmation Of/Additional Information (Rci/Rai) Set 1 Responses, L-2021-144, Subsequent License Renewal Application-Aging Management Requests for Additional Information (RAI) Set 2 Responses, L-2021-154, Subsequent License Renewal Application -Aging Management Requests for Confirmation Of/Additional Information (Rci/Rai) Set 3 Responses, L-2021-156, Subsequent License Renewal Application - Aging Management Requests for Additional Information Set 5 Responses, L-2021-157, L-2021-157 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 6 Responses, L-2021-172, Subsequent License Renewal Application - Aging Management Requirement for Additional Information Set 7, Response, L-2021-190, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 2 Responses Revision 1, L-2021-199, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 10 Responses, L-2021-200, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 11 Response, L-2021-222, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 11 Response Revision 1, L-2021-223, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 12 Response, L-2021-224, Subsequent License Renewal Application - First Annual Update, L-2021-248, Subsequent License Renewal Application Aging Management Requests for Additional Information (RAI) Set 14 Response, ML21005A058, ML21015A214, ML21036A217, ML21208A447, ML21214A035, ML21302A019
|
MONTHYEARML20329A2642020-11-16016 November 2020 Enclosure 4, Non-proprietary Reference Documents and Redacted Versions of Proprietary Reference Documents (Public Version) Project stage: Request ML20321A1872020-11-16016 November 2020 Single Positive Test Form Collected on 02/11/2020 Project stage: Request ML20329A2922020-11-16016 November 2020 Application for Subsequent Renewed Facility Operating Licenses Project stage: Request ML21015A2142021-01-15015 January 2021 Subsequent License Renewal Application Acceptance Federal Register Notice FRN Project stage: Other ML21005A0582021-01-15015 January 2021 Subsequent License Renewal Application - Portal Letter Project stage: Other ML21006A4172021-01-15015 January 2021 Subsequent License Renewal Acceptance Letter Project stage: Acceptance Review ML21036A2172021-03-0101 March 2021 SLRA - Proprietary Determination Letter Project stage: Other L-2021-081, Subsequent License Renewal Application - Aging Management Supplement 12021-04-21021 April 2021 Subsequent License Renewal Application - Aging Management Supplement 1 Project stage: Supplement L-2021-113, Subsequent License Renewal Application - Aging Management Supplement 32021-05-27027 May 2021 Subsequent License Renewal Application - Aging Management Supplement 3 Project stage: Supplement ML21161A1192021-06-10010 June 2021 RAIs Set 1 Final Aging Management of Irradiated Concrete and Steel Reactor Vessel Supports Final Project stage: Request L-2021-129, Ssubsequent License Renewal Application: Aging Management Requests for Confirmation Of/Additional Information (Rci/Rai) Set 1 Responses2021-07-0808 July 2021 Ssubsequent License Renewal Application: Aging Management Requests for Confirmation Of/Additional Information (Rci/Rai) Set 1 Responses Project stage: Other L-2021-147, Subsequent License Renewal Application - Aging Management Supplement 3 Revision 12021-07-26026 July 2021 Subsequent License Renewal Application - Aging Management Supplement 3 Revision 1 Project stage: Supplement ML21208A1892021-07-27027 July 2021 SLRA Safety RAIs Set 2 Final Project stage: Request ML21238A2332021-08-0404 August 2021 SLRA Safety RAI Set 4 Final Project stage: Request L-2021-144, Subsequent License Renewal Application-Aging Management Requests for Additional Information (RAI) Set 2 Responses2021-08-11011 August 2021 Subsequent License Renewal Application-Aging Management Requests for Additional Information (RAI) Set 2 Responses Project stage: Other ML21214A0352021-08-16016 August 2021 Subsequent License Renewal Application (SLRA) Compiled Aging Management Audit Breakout Questions Project stage: Other ML21208A4472021-08-16016 August 2021 Subsequent License Renewal Application Aging Management Audit Report Project stage: Other L-2021-154, Subsequent License Renewal Application -Aging Management Requests for Confirmation Of/Additional Information (Rci/Rai) Set 3 Responses2021-08-25025 August 2021 Subsequent License Renewal Application -Aging Management Requests for Confirmation Of/Additional Information (Rci/Rai) Set 3 Responses Project stage: Other L-2021-155, Subsequent License Renewal Application on Aging Management - Request for Additional Information (Rai), Set 4 Response2021-08-30030 August 2021 Subsequent License Renewal Application on Aging Management - Request for Additional Information (Rai), Set 4 Response Project stage: Request L-2021-165, Submittal of Subsequent License Renewal Application - Aging Management Requests for Confirmation Of/Additional Information (Rci/Rai) Set 1 Responses Supplement 12021-09-10010 September 2021 Submittal of Subsequent License Renewal Application - Aging Management Requests for Confirmation Of/Additional Information (Rci/Rai) Set 1 Responses Supplement 1 Project stage: Supplement L-2021-157, L-2021-157 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 6 Responses2021-09-10010 September 2021 L-2021-157 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 6 Responses Project stage: Other L-2021-156, Subsequent License Renewal Application - Aging Management Requests for Additional Information Set 5 Responses2021-09-13013 September 2021 Subsequent License Renewal Application - Aging Management Requests for Additional Information Set 5 Responses Project stage: Other L-2021-173, Subsequent License Renewal Application-Aging Management Request for Additional Information (RAI) Set 8 Response2021-09-16016 September 2021 Subsequent License Renewal Application-Aging Management Request for Additional Information (RAI) Set 8 Response Project stage: Request L-2021-172, Subsequent License Renewal Application - Aging Management Requirement for Additional Information Set 7, Response2021-09-20020 September 2021 Subsequent License Renewal Application - Aging Management Requirement for Additional Information Set 7, Response Project stage: Other L-2021-174, NextEra Energy Point Beach, LLC - Subsequent License Renewal Application - Aging Management Request for Additional Information (RAI) Set 9 Response2021-10-0101 October 2021 NextEra Energy Point Beach, LLC - Subsequent License Renewal Application - Aging Management Request for Additional Information (RAI) Set 9 Response Project stage: Request ML21286A6042021-10-0505 October 2021 SLRA Safety RAIs Set 10 Final Project stage: Request L-2021-200, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 11 Response2021-10-25025 October 2021 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 11 Response Project stage: Other L-2021-190, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 2 Responses Revision 12021-11-0303 November 2021 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 2 Responses Revision 1 Project stage: Other ML21292A1852021-11-0303 November 2021 Letter to Applicant Point Beach Nuclear Plant, Units 1 and 2 Notice of Availability of the Draft Plant-Specific Supplement 23, Second Renewal Project stage: Draft Other L-2021-208, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 9 Response Supplement 12021-11-0404 November 2021 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 9 Response Supplement 1 Project stage: Supplement L-2021-199, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 10 Responses2021-11-0404 November 2021 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 10 Responses Project stage: Other ML21302A0192021-11-10010 November 2021 Maintenance of Reference Material at the Lester Public Library Associated with the Staff'S Review Project stage: Other ML21312A5202021-11-10010 November 2021 Proprietary Determination Letter SLRA Safety RAIs Set 1 Response Project stage: RAI L-2021-221, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 10 Responses Supplement 12021-11-19019 November 2021 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 10 Responses Supplement 1 Project stage: Supplement L-2021-222, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 11 Response Revision 12021-11-23023 November 2021 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 11 Response Revision 1 Project stage: Other L-2021-224, Subsequent License Renewal Application - First Annual Update2021-11-30030 November 2021 Subsequent License Renewal Application - First Annual Update Project stage: Other L-2021-223, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 12 Response2021-12-0909 December 2021 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 12 Response Project stage: Other L-2021-248, Subsequent License Renewal Application Aging Management Requests for Additional Information (RAI) Set 14 Response2022-01-0606 January 2022 Subsequent License Renewal Application Aging Management Requests for Additional Information (RAI) Set 14 Response Project stage: Other L-2021-240, Subsequent License Renewal Application - Aging Management Request for Additional Information Set 13 Response2022-01-0606 January 2022 Subsequent License Renewal Application - Aging Management Request for Additional Information Set 13 Response Project stage: Request ML22041A3342022-02-23023 February 2022 Transmittal Letter for Point Beach Final SE for SLRA Review to AA La 2-9 (3) Project stage: Approval ML22054A1082022-02-23023 February 2022 Subsequent License Renewal Application Safety Evaluation Public Project stage: Approval ML22054A1062022-02-23023 February 2022 Srla Safety Evaluation Documents and Transmittal Letter Project stage: Request ML22139A2292022-05-25025 May 2022 Transmittal Letter for Point Beach Final SE for SLRA Review Rev1 Project stage: Approval ML22139A2282022-05-25025 May 2022 Srla Safety Evaluation Revision 1 Documents and Transmittal Letter Project stage: Request 2021-06-10
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000266/20240032024-11-0505 November 2024 Integrated Inspection Report 05000266/2024003 and 05000301/2024003 ML24295A1142024-10-31031 October 2024 Suppl Env Audit Summary Letter W/Enclosure 1 L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums ML24295A0862024-10-21021 October 2024 Notification of NRC Baseline Inspection and Request for Information Inspection Report 0500026/2025002 L-2024-160, Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41)2024-10-21021 October 2024 Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41) L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-120, LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization2024-10-0808 October 2024 LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000266/2024011 and 05000301/2024011 L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-145, Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency2024-09-0909 September 2024 Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency ML24207A0202024-08-28028 August 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Point Beach Nuclear Plant, Units 1 and 2 (Docket Numbers: 50-0266 and 50-0301) IR 05000266/20240052024-08-21021 August 2024 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2024005 and 05000301/2024005) IR 05000266/20240022024-08-13013 August 2024 Integrated Inspection Report 05000266/2024002 and 05000301/2024002 L-2024-131, Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-08-0909 August 2024 Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review ML24214A3092024-08-0202 August 2024 Confirmation of Initial License Examination ML24194A1802024-07-24024 July 2024 – Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-113, License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections2024-07-24024 July 2024 License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections IR 05000266/20244012024-07-23023 July 2024 Public - Point Beach Nuclear Plant Cyber Security Inspection Report 05000266/2024401 and 05000301/2024401 ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-116, Preparation and Scheduling of Operator Licensing Examinations2024-07-11011 July 2024 Preparation and Scheduling of Operator Licensing Examinations IR 05000266/20240102024-07-10010 July 2024 Age-Related Degradation Inspection Report 05000266/2024010 and 05000301/2024010 L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-105, License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-06-26026 June 2024 License Amendment Request 300, Modify Containment Average Air Temperature Requirements L-2024-107, Schedule for Subsequent License Renewal Environmental Review2024-06-25025 June 2024 Schedule for Subsequent License Renewal Environmental Review ML24176A2242024-06-24024 June 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-093, Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision2024-06-10010 June 2024 Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision IR 05000266/20244202024-06-0505 June 2024 Security Baseline Inspection Report 05000266/2024420 and 05000301/2024420 ML24149A1922024-05-28028 May 2024 Notification of NRC Baseline Inspection and Request for Information ML24141A1382024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection.Docx ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000266/2024301; 05000301/2024301 L-2024-067, Annual Monitoring Report2024-04-26026 April 2024 Annual Monitoring Report ML24116A0402024-04-23023 April 2024 Periodic Update of the Updated Final Safety Analysis Report ML24071A0912024-04-22022 April 2024 Issuance of Relief Request I6-RR-03 - Extension of the Unit 2 Steam Generator Primary Nozzle Dissimilar Metal Welds Sixth 10-Year Inservice Inspection Program Interval IR 05000266/20240012024-04-11011 April 2024 Integrated Inspection Report 05000266/2024001 and 05000301/2024001 L-2024-030, Supplement to Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-03-27027 March 2024 Supplement to Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements L-2024-043, Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules2024-03-25025 March 2024 Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules L-2024-011, And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications IR 05000266/20230062024-02-28028 February 2024 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2023006 and 05000301/2023006) ML24053A3732024-02-22022 February 2024 Operator Licensing Examination Approval Point Beach, March 2024 L-2024-020, Refueling Outage Owners Activity Report (OAR-1) Unit 1 for Inservice Inspections2024-02-22022 February 2024 Refueling Outage Owners Activity Report (OAR-1) Unit 1 for Inservice Inspections ML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 IR 05000266/20230042024-02-0101 February 2024 Integrated Inspection Report 05000266/2023004 and 05000301/2023004 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 2024-09-09
[Table view] |
Text
November 3, 2021 Mr. Michael Strope Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241
SUBJECT:
POINT BEACH NUCLEAR PLANT, UNIT NOS. 1 AND 2 - NOTICE OF AVAILABILITY OF THE DRAFT PLANT-SPECIFIC SUPPLEMENT 23, SECOND RENEWAL, TO THE GENERIC ENVIRONMENTAL IMPACT STATEMENT FOR LICENSE RENEWAL OF NUCLEAR PLANTS (EPID NO. L-2020-SLR-0002)
Dear Mr. Strope:
The U.S. Nuclear Regulatory Commission (NRC) staff has completed the draft plant-specific Supplement 23, Second Renewal, to NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GElS), regarding the proposed subsequent renewal of Renewed Facility Operating License Nos. DPR-24 and DPR-27 for an additional 20 years of operation for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (Point Beach), respectively. The NRC staff has prepared a Federal Register Notice of Availability (86 FR 62220) to advise the public that the draft supplement is publicly available from the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC website at https://www.nrc.gov/reading-rm/adams.html. The ADAMS accession number for the draft Supplement 23, Second Renewal, to the GElS is ML21306A226. In addition, the draft Supplement 23, Second Renewal, to the GEIS will be available to the public near the site at the following location: Lester Public Library, 1001 Adams Street, Two Rivers, WI 54241.
As discussed in Chapter 4 of the draft supplement, the NRC staffs preliminary recommendation is that the adverse environmental impacts of subsequent license renewal for Point Beach are not so great that preserving the option of subsequent license renewal for energy-planning decisionmakers would be unreasonable. This recommendation is based on: (1) the analysis and findings in the GElS; (2) the Environmental Report submitted by NextEra Energy Point Beach, LLC; (3) the NRC staffs consultation with Federal, State, Tribal, and local governmental agencies; (4) the NRC staffs independent environmental review; and (5) the NRC staffs consideration of public comments.
A public meeting will be held to present an overview of the draft supplement and to accept public comment on the draft supplement. An NRC meeting notice will be published to provide more details about this public meeting.
A separate Notice of Availability of the draft supplemental environmental impact statement will be placed in the Federal Register through the U.S. Environmental Protection Agency (EPA).
The 45-day public comment period end date is calculated from the date on which the EPA notice is published in the Federal Register.
M. Strope Should you have any questions concerning the NRC staffs environmental review of this subsequent license renewal application, please contact the Project Manager, Phyllis M. Clark, by e-mail at Phyllis.Clark@nrc.gov.
Sincerely, Signed by Elliott, Robert on 11/03/21 Robert B. Elliott, Chief Environmental Review License Renewal Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards Docket Nos. 50-266, 50-301 cc: Distribution via Listserv
OFFICE LA:ERMB:REFS LA:ERMB:REFS OGC BC:ELRB:REFS NAME SImboden SFigueroa JWachutka RElliott DATE 10/19/2021 10/20/2021 10/27/2021 11/03/2021