Transmittal Letter for Point Beach Final SE for SLRA Review Rev1
ML22139A229
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/25/2022
From: Beverly Smith
NRC/NRR/DNRL
To: Coffey B
Florida Power & Light Co
Vera Amadiz M
Shared Package
ML22139A228 List:
References
EPID L-2020-SLR-0002
Download: ML22139A229 (3)


Text

May 25, 2022 Mr. Bob Coffey Executive Vice President, Nuclear Division and Chief Nuclear Officer Florida Power & Light Company Mail Stop: EX/JB 700 Universe Blvd.

Juno Beach, FL 33408

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - FINAL SAFETY EVALUATION FOR THE SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW, REVISION 1 (EPID NO. L-2020-SLR-0002)

Dear Mr. Coffey:

By letter dated November16,2020 (Agencywide Documents Access and Management System (ADAMS) Package Accession No.ML20329A292), as supplemented by letters dated April21, 2021 (ADAMS Accession No. ML21111A155), May6, 2021 (ADAMS Accession No. ML21126A239), May27, 2021 (ADAMS Accession No. ML21147A115), July8, 2021 (ADAMS Accession No. ML21189A173), July8, 2021 (ADAMS Accession No. ML21189A174), July26, 2021 (ADAMS Accession No. ML21207A066), August11, 2021 (ADAMS Accession No. ML21223A308), August25, 2021 (ADAMS Accession No. ML21237A055), August30, 2021 (ADAMS Accession No. ML21242A230), September10, 2021 (ADAMS Accession No. ML21253A138), September10, 2021 (ADAMS Accession No. ML21253A140), September 13, 2021 (ADAMS Accession No. ML21256A129), September16, 2021 (ADAMS Accession No. ML21259A153), September20, 2021 (ADAMS Accession No. ML21263A052), October1, 2021 (ADAMS Accession No. ML21274A053), October25, 2021 (ADAMS Accession No. ML21298A090), November3, 2021 (ADAMS Accession No. ML21307A286), November4, 2021 (ADAMS Accession No. ML21308A282), November4, 2021 (ADAMS Accession No. ML21308A283), November 23, 2021 (ADAMS Accession No. ML21327A077), November 30, 2021 (ADAMS Accession No. ML21334A293), December 9, 2021 (ADAMS Accession No. ML21343A294), January 6, 2022 (ADAMS Accession No. ML22006A074), and January 6, 2022 (ADAMS Accession No. ML22006A046), NextEra Energy Point Beach, LLC (NextEra) submitted an application for subsequent renewal of Renewed Facility Operating License Nos. DPR-24 and DPR-27 for Point Beach Nuclear Plant, Units 1 and 2 (Point Beach),

respectively, to the U.S. Nuclear Regulatory Commission (NRC). NextEra submitted the application pursuant to Title 10 of the Code of Federal Regulations Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, for subsequent license renewal.

The NRC staff determined that the application was complete and acceptable for docketing as communicated by email dated January 8, 2021 (ADAMS Accession No. ML21012A365) and by letter dated January 15, 2021 (ADAMS Accession No. ML21006A417), and noticed in the Federal Register on January 22, 2021 (86 FR 6684).

The NRC staff has reviewed the Point Beach Subsequent License Renewal Application (SLRA) and has developed the enclosed Safety Evaluation Related to the Subsequent License

B. Coffey Renewal of Point Beach Nuclear Plant, Units 1 and 2, Revision 1 hereinafter referred to as the Safety Evaluation (SE). The SE reflects the status of the NRC staffs safety review of the SLRA, as supplemented, through January 6, 2022. Revision 1 of the SE corrects errors that were inadvertently introduced into the SE during its final processing.

If you have any questions regarding this matter, please contact the subsequent license renewal project manager, Mr. Bill Rogers, by e-mail at bill.rogers@nrc.gov or Ms. Marieliz Johnson, by e-mail at marieliz.johnson@nrc.gov.

Sincerely,

/RA/

Brian W. Smith, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301

Enclosure:

SE cc w/encl: Listserv

B. Coffey

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - FINAL SAFETY EVALUATION FOR THE SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW, REVISION 1 (EPID NO. L-2020-SLR-0002) MAY 25, 2022 DISTRIBUTION:

E-MAIL:

PUBLIC RidsNrrDnrl Resource RidsNrrPMPointBeach Resource RidsACRS_MailCTR Resource RidsRgn3MailCenter Resource RidsRgn3Dnms Resource RidsRgn3Drp Resource RidsRgn3Drs Resource RidsRgn3Ora Resource RidsRgn3Opa Resource RidsNrrOd Resource RidsNrrPMPointBeach Resource BRogers, NRR/DNRL MJohnson, NRR/DNRL LGibson, NRR/DNRL PClark, NMSS/REFS RElliott, NMSS/REFS BSmith, NRR/DNRL BThomson, NRR/DNRL RHaskell, NRR/DORL NSalgado, NRR/DORL DRoth, OGC JWachutka, OGC TJones, OGC RSkokowski, OEDO MMcCoppin, OEDO SBurnell, HQ/OPA DMcIntyre, HQ/OPA CWolf, OCA LWilkins, OCA VMitlying, RGN III/OPA PChandrathil, RGN III/OPA NFeliz-Adorno, RGN III RNg, RGN III William.Maher@fpl.com Steve.Franzone@fpl.com ADAMS Accession Nos.:

PKG: ML22139A228 LTR: ML22139A229 SE: ML22140A252

  • via-e-mail. **Concurrence on SE issued 2/23/2022 NRR-106 OFFICE DEX/ELTB:BC*

DEX/ESEB:BC*

DSS/SPCB:BC*

DRA/APLB:BC*

NAME JJohnston**

JColaccino**

BWittick**

JWhitman**

DATE 06/02/2021 11/23/2021 06/05/2021 10/08/2021 OFFICE DNRL/NVIB:BC*

DNRL/NPHP:BC*

DNRL/NCSG:BC*

DNRL/NLRP:PM*

NAME DWidrevitz**

MMitchell**

SBloom**

BRogers**

DATE 09/03/2021 11/15/2021 01/26/2022 02/18/2022 OFFICE DNLR/NLRP: BC*

OGC (NLO)*

DNRL: D DNLR/NLRP:PM NAME LGibson**

JWachutka**

BSmith: BThomson for**

MJohnson (ltr)

DATE 02/23/2022 02/23/2022 02/23/2022 05/19/2022 OFFICE DNLR/NLRP:LA OGC (NLO)

DNLR/NLRP:BC DNRL:D NAME YEdmonds (ltr)

JWachutka LGibson BSmith DATE 05/24/2022 05/25/2022 05/25/2022 05/25/2022