Letter Sequence Acceptance Review |
|---|
EPID:L-2021-LRO-0031, Revised Transcript for Public Meeting Held on July 29, 2021, in Tarrytown, Ny, Regarding Indian Point Energy Center Post-Shutdown Decommissioning Activities Report (Approved, Closed) |
Administration
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
|
MONTHYEARML21162A0012021-06-15015 June 2021 Transmittal Letter, Notification of the Availability of the Post-Shutdown Decommissioning Activities Report in the Federal Register Project stage: Other ML21162A0022021-06-15015 June 2021 Individual Federal Register Notice, Notification of the Availability of the Post-Shutdown Decommissioning Activities Report Project stage: Other ML21188A2112021-07-0707 July 2021 Acceptance of Submittal Post-Shutdown Decommissioning Activities Report Project stage: Acceptance Review ML21181A0282021-07-12012 July 2021 Individual Federal Register Notice, Notification of Public Meeting for Public Comments on Post-Shutdown Decommissioning Activities Report Project stage: Meeting PMNS20210905, (IPEC) Post-Shutdown Decommissioning Activities Report (PSDAR) Public Meeting2021-07-13013 July 2021 (IPEC) Post-Shutdown Decommissioning Activities Report (PSDAR) Public Meeting Project stage: Request Press Release-I-21-007, NRC to Hold Public Meeting to Receive Comments on Indian Point Nuclear Power Plant Decommissioning Activities Report2021-07-19019 July 2021 Press Release-I-21-007: NRC to Hold Public Meeting to Receive Comments on Indian Point Nuclear Power Plant Decommissioning Activities Report Project stage: Request ML21207A0292021-07-29029 July 2021 Public Meeting Agenda - Post Shutdown Decommissioning Activities Report, 07/29/2021 PSDAR Public Meeting Project stage: Meeting ML21221A3112021-07-29029 July 2021 Transcript for Public Meeting Held on July 29, 2021, in Tarrytown, New York Regarding Indian Point Energy Center Post-Shutdown Decommissioning Activities Report Project stage: Meeting ML21214A1402021-07-29029 July 2021 Updated Indian Point Public Meeting Presentation Slides - Post Shutdown Decommissioning Activities Report, 07/29/2021 PSDAR Public Meeting Project stage: Meeting ML21207A0262021-07-29029 July 2021 Public Meeting Presentation Slides - Post Shutdown Decommissioning Activities Report, 07/29/2021 PSDAR Public Meeting Project stage: Meeting ML21238A0102021-08-18018 August 2021 Transcript for Virtual Public Meeting Held on August 18, 2021, Regarding Indian Point Energy Center Post-Shutdown Decommissioning Activities Report Project stage: Meeting ML21217A1992021-08-18018 August 2021 Virtual Public Meeting Presentation Slides - Post Shutdown Decommissioning Activities Report, 08/15/2021 PSDAR Public Webinar Meeting Project stage: Meeting ML21232A2362021-08-20020 August 2021 Enclosure 2 - Summary of NRC Staff Edits to the July 29, 2021 Public Meeting Transcript Project stage: Meeting ML21232A2302021-08-20020 August 2021 Revised Transcript for Public Meeting Held on July 29, 2021, in Tarrytown, Ny, Regarding Indian Point Energy Center Post-Shutdown Decommissioning Activities Report Project stage: Request ML21232A2342021-08-20020 August 2021 Memo - Revised Transcript for Public Meeting Held on July 29, 2021, in Tarrytown, Ny, Re IP Energy Center Post-Shutdown Decommissioning Activities Report Project stage: Meeting ML21232A2352021-08-20020 August 2021 Enclosure 1 - Official Transcript for the Public Meeting on Holtec Indian Point Post-shutdown Decommissioning Project stage: Meeting ML21342A1372021-12-0909 December 2021 Summary of Public Meeting in Tarrytown, Ny, to Discuss Indian Point Nuclear Generating Unit Nos. 1, 2, and 3 Post-Shutdown Decommissioning Activities Report Project stage: Request ML21342A1412021-12-0909 December 2021 Enclosure - List of Attendees for the Public Meeting in Tarrytown, Ny, Re Indian Point Units 1, 2, and 3 PSDAR Project stage: Meeting ML21342A1402021-12-0909 December 2021 Summary of Public Meeting in Tarrytown, Ny, to Discuss Indian Point Units 1, 2, and 3 (IPEC) Post-shutdown Decommissioning Activities Report Project stage: Meeting ML22006A0342022-01-0505 January 2022 Request for Additional Information - HDI Indian Point Post-Shutdown Decommissioning Activities Report Project stage: Request ML22034A6032022-02-0303 February 2022 Response to Request for Additional Information - Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E for Low-level Radioactive Waste Shipments Project stage: Response to RAI ML22034A7882022-02-0303 February 2022 Response to Requests for Additional Information - Related to Post Shutdown Decommissioning Activities Report Project stage: Response to RAI ML22082A2202022-05-0202 May 2022 Review of Post Shutdown Decommissioning Activities Report Project stage: Approval 2021-07-29
[Table View] |
Text
From:
Guzman, Richard To:
Andrea Sterdis Cc:
RidsNRRLIC109 Resource; Danna, James; Sturzebecher, Karl; Matthew Johnson; Watson, Bruce
Subject:
Indian Point Nuclear Generating, Unit Nos. 1, 2, and 3 - Acceptance of Submittal Re: Post-Shutdown Decommissioning Activities Report (EPID L-2021-LRO-0031)
Date:
Wednesday, July 07, 2021 1:00:58 PM Attachments:
image003.png
SUBJECT:
ACCEPTANCE OF SUBMITTAL RE: POST-SHUTDOWN DECOMMISSIONING ACTIVITIES REPORT (EPID L-2021-LRO-0031)
On December 19, 2019, Holtec Decommissioning International, LLC (HDI) submitted to the U.S. Nuclear Regulatory Commission (NRC) the Post-Shutdown Decommissioning Activities Report (PSDAR) for the Indian Point Nuclear Generating, Unit Nos. 1, 2, and 3 (IPEC), contingent upon the transfer of the IPEC licenses to HDI (ADAMS Accession No. ML19354A698). Paragraph 50.82(a)(4)(i) of title 10 of the Code of Federal Regulations (10 CFR) states that a PSDAR must contain a description of the planned decommissioning activities along with a schedule for their accomplishment, a discussion that provides the reasons for concluding that the environmental impacts associated with site-specific decommissioning activities will be bounded by appropriate previously issued environmental impact statements, and a site-specific decommissioning cost estimate (DCE), including the projected cost of managing irradiated fuel. The IPEC license transfer transaction closed on May 28, 2021. Accordingly, pursuant to 10 CFR 50.82(a)(4)(ii), the NRC noticed receipt of the PSDAR, including the DCE, for IPEC and made it available for public comment on June 24, 2021 (86 FR 33383).
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this submittal. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the submittal in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> to complete. The NRC staff expects to complete this review by June 30, 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date (greater than a month) or significant changes in the forecasted hours (greater than 25%), the reasons for the changes, along with the new estimates, will be communicated during the routine
interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information and unanticipated addition of scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.
If you have any questions, please contact me.
Richard V. Guzman Senior Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Office: O-9C7 l Phone: (301) 415-1030 Richard.Guzman@nrc.gov