MONTHYEARML23325A1432023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNRO-2021-00023, Entergy Operations, Inc. - Supplement to CNRO-2021-00002, Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L2021-10-0606 October 2021 Entergy Operations, Inc. - Supplement to CNRO-2021-00002, Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L ML21272A3032021-09-30030 September 2021 Technology Inclusive Content of Application Project (Ticap) for Non-Light Water Reactors Westinghouse Evinci; Micro-Reactor Tabletop Exercise Report ML21237A0512021-08-25025 August 2021 Follow-on Risk Informed Performance Based Implementation Guidance Needed for Advanced Non-Light Water Reactors ML21081A1922021-06-30030 June 2021 Enclosure - USNRC-CNSC Joint Report Concerning X-Energy's Reactor Pressure Vessel Construction Code Assessment ML21095A3112021-04-0808 April 2021 RB-2021-02 Exam Report Rev 1 ML21095A311 ML21272A3382021-04-0101 April 2021 Technology Inclusive Content of Application Project (Ticap) for Non-Light Water Reactors Versatile Test Reactor Ticap Tabletop Exercise Report ML21090A0332021-03-31031 March 2021 Historical Context and Perspective on Allowable Stresses and Design Parameters in ASME Section III, Division 5, Subsection Hb, Subpart B (ANL/AMD-21/1) ML21063A2372021-03-0303 March 2021 RBS 2020 Annual Assessment Letter ML21075A2672020-10-0909 October 2020 FAQ 20-05 River Bend Uswc - Final Approved RBG-47855, Submittal of Owner'S Activity Report Form for Cycle 202019-08-0808 August 2019 Submittal of Owner'S Activity Report Form for Cycle 20 ML18284A3742018-12-20020 December 2018 NRC Record of Decision for the License Renewal Application for River Bend Unit 1 RBG-47873, License Renewal Application, Revised Updated Safety Analysis Report Supplement, Appendix a, Section A.4, License Renewal Commitment List, Revised Commitment 52018-06-13013 June 2018 License Renewal Application, Revised Updated Safety Analysis Report Supplement, Appendix a, Section A.4, License Renewal Commitment List, Revised Commitment 5 RBG-47870, License Renewal Application, Revised Updated Safety Analysis Report Supplement, Appendix a, Section A.4, License Renewal Commitment List2018-06-0606 June 2018 License Renewal Application, Revised Updated Safety Analysis Report Supplement, Appendix a, Section A.4, License Renewal Commitment List RBG-47770, Focused Evaluation of External Flooding2017-06-28028 June 2017 Focused Evaluation of External Flooding RBG-47729, Resubmittal of Owner'S Activity Report Form2017-01-0909 January 2017 Resubmittal of Owner'S Activity Report Form ML16090A0572016-03-24024 March 2016 Submittal of Regulatory Conference Documents for April 4, 2016. Attachment 2: Engineering Report No. RBS-ME-16-00003, Evaluation of Main Control Room Realistic Heat Load Based on Measured Data ML16090A0592016-03-24024 March 2016 Submittal of Regulatory Conference Documents for April 4, 2016. Attachment 6: Engineering Report No. RBS-ME-15-00036, Main Control Room (MCR) Operator Habitability Under Beyond Design Basis Loss of HVAC Conditions ML16090A0582016-03-24024 March 2016 Submittal of Regulatory Conference Documents for April 4, 2016. Attachment 3: Engineering Report No. RBS-ME-16-00002, Main Control Room Heat-Up Analysis During Loss of HVAC Conditions for 24 Hours ML15212A7272015-09-0404 September 2015 Interim Staff Response to Reevaluated Flood Hazards Submitted in Response to 10 CFR 50.54(f) Information Request Flood-Causing Mechanism Reevaluation RBG-47447, Report 51-9207360-000, Entergy Fleet Fukushima Program Flood Hazard Reevaluation Report for River Bend Station.2014-03-10010 March 2014 Report 51-9207360-000, Entergy Fleet Fukushima Program Flood Hazard Reevaluation Report for River Bend Station. ML13365A2812014-02-25025 February 2014 Interim Staff Evaluation Regarding Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) ML14056A1672014-02-25025 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for River Bend Station, Unit 1(PUBLIC) RBG-47386, Attachment 2 to RBG-47386 - Structural Integrity Report No. 1300615.401, Rev. 0, Acceptability of Weir Tricentric Butterfly Valves Having Stainless Steel Seat Fillet Welds Applied with 60 F Preheat.2013-08-19019 August 2013 Attachment 2 to RBG-47386 - Structural Integrity Report No. 1300615.401, Rev. 0, Acceptability of Weir Tricentric Butterfly Valves Having Stainless Steel Seat Fillet Welds Applied with 60 F Preheat. ML13198A0782013-07-18018 July 2013 River Bend Station Seismic Wafkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic ML13130A0682013-05-24024 May 2013 Safety Assessment in Response to Request for Information Pursuant to 10 CFR 50.54(f) - Recommendation 9.3 Communications Assessment RBG-47362, Request for Alternative in Accordance with 10 CFR 50.55a(a)(3)(i) Use of Boiling Water Reactor Vessel and Internals Project (BWRVIP) Guidelines in Lieu of Specific ASME Code Requirements2013-05-16016 May 2013 Request for Alternative in Accordance with 10 CFR 50.55a(a)(3)(i) Use of Boiling Water Reactor Vessel and Internals Project (BWRVIP) Guidelines in Lieu of Specific ASME Code Requirements CNRO-2013-00002, Responses to NRC Request for Additional Information Regarding Application for Order Approving Transfers of Licenses and Conforming License and ESP Amendments2013-01-29029 January 2013 Responses to NRC Request for Additional Information Regarding Application for Order Approving Transfers of Licenses and Conforming License and ESP Amendments RBG-47307, Engineering Report RBS-CS-12-00001, Rev. 000, River Bend Station Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic.2012-11-14014 November 2012 Engineering Report RBS-CS-12-00001, Rev. 000, River Bend Station Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. ML13022A2242012-11-0707 November 2012 Agastat ETR Relay Information RBG-47278, Request for Exemption to 10 CFR 50 Appendix J2012-08-23023 August 2012 Request for Exemption to 10 CFR 50 Appendix J RBG-47190, Letter from Entergy Operations, Inc Additional Information Regarding November 21, 2011, Predecisional Enforcement Conference2011-11-28028 November 2011 Letter from Entergy Operations, Inc Additional Information Regarding November 21, 2011, Predecisional Enforcement Conference ML1127000692011-09-26026 September 2011 Enclosure 2, Mfn 10-245 R4, Description of the Evaluation and Surveillance Recommendations for BWR/2-5 Plants ML1012704392010-05-0505 May 2010 Y020100187 - List of Historical Leaks and Spills at U.S. Commercial Nuclear Power Plants ML0904007952009-02-0404 February 2009 GSI-189 Action Plan, Feb. 09 Update, Publicly Available Version ML0824106442008-08-20020 August 2008 Plume Pathway Exercise Evaluated on June 11, 2008 - Radiological Emergency Preparedness Final Report ML0821900132008-08-0707 August 2008 Monthly Operating Reports Second Quarter 2008 ML0835701932008-07-31031 July 2008 Gnf S-0000-0088-0271, Revision 0, GE14 Thermal Hydraulic Compatibility with River Bend Legacy Fuel, Attachment 5 RBG-46716, Fitness-For-Duty Program Six-Month Performance Data Report for Period January 1, 2007 Through June 30, 20072007-07-25025 July 2007 Fitness-For-Duty Program Six-Month Performance Data Report for Period January 1, 2007 Through June 30, 2007 RBG-46649, Fitness-for-Duty Program Six-Month Performance Data Report2007-02-0808 February 2007 Fitness-for-Duty Program Six-Month Performance Data Report RBG-46615, 10 CFR 50.46(a)(3)(ii) Report2006-08-24024 August 2006 10 CFR 50.46(a)(3)(ii) Report RBG-46609, Fitness-For-Duty Program Six-Month Performance Data Report2006-08-15015 August 2006 Fitness-For-Duty Program Six-Month Performance Data Report RBG-46607, Submittal of Owner'S Activity Report Form (OAR-1)2006-08-10010 August 2006 Submittal of Owner'S Activity Report Form (OAR-1) CNRO-2006-00034, Supplement to Request for Use of Delta Protection Mururoa V4F1 R Supplied Air Suits; Arkansas Nuclear One, Indian Point, Grand Gulf, Waterford, FitzPatrick, River Bend, Pilgrim, Vermont Yankee2006-07-13013 July 2006 Supplement to Request for Use of Delta Protection Mururoa V4F1 R Supplied Air Suits; Arkansas Nuclear One, Indian Point, Grand Gulf, Waterford, FitzPatrick, River Bend, Pilgrim, Vermont Yankee RBG-46568, Thirteenth Fuel Cycle Core Operating Limits Report2006-05-11011 May 2006 Thirteenth Fuel Cycle Core Operating Limits Report CNRO-2006-00023, Request for Alternative CEP-PT-001 Visual Examination of Vent and Drain Connections During System Leakage Tests2006-04-24024 April 2006 Request for Alternative CEP-PT-001 Visual Examination of Vent and Drain Connections During System Leakage Tests ML0607204302006-03-0101 March 2006 March 1, 2006 Public Meeting Slides for Proposed Generic Letter Post-Fire Safe-Shutdown Circuit Analysis Spurious Actuations. RBG-46533, Fitness-For-Duty Program Six-Month Performance Data Report2006-02-10010 February 2006 Fitness-For-Duty Program Six-Month Performance Data Report ML0532604512005-11-14014 November 2005 River Bend, Supplement to Revised License Amendment Request (LAR) 2004-26, Use of the Fuel Building Cask Handling Crane for Dry Spent Fuel Cask Loading Operations. RBG-46468, Transmittal of the Fitness-for-Duty Program Six-Month Performance Data Report2005-08-18018 August 2005 Transmittal of the Fitness-for-Duty Program Six-Month Performance Data Report 2023-11-21
[Table view] Category:Miscellaneous
MONTHYEARML23325A1432023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNRO-2021-00023, Entergy Operations, Inc. - Supplement to CNRO-2021-00002, Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L2021-10-0606 October 2021 Entergy Operations, Inc. - Supplement to CNRO-2021-00002, Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L ML21095A3112021-04-0808 April 2021 RB-2021-02 Exam Report Rev 1 ML21095A311 ML21063A2372021-03-0303 March 2021 RBS 2020 Annual Assessment Letter ML21075A2672020-10-0909 October 2020 FAQ 20-05 River Bend Uswc - Final Approved RBG-47855, Submittal of Owner'S Activity Report Form for Cycle 202019-08-0808 August 2019 Submittal of Owner'S Activity Report Form for Cycle 20 ML18284A3742018-12-20020 December 2018 NRC Record of Decision for the License Renewal Application for River Bend Unit 1 RBG-47729, Resubmittal of Owner'S Activity Report Form2017-01-0909 January 2017 Resubmittal of Owner'S Activity Report Form ML15212A7272015-09-0404 September 2015 Interim Staff Response to Reevaluated Flood Hazards Submitted in Response to 10 CFR 50.54(f) Information Request Flood-Causing Mechanism Reevaluation RBG-47386, Attachment 2 to RBG-47386 - Structural Integrity Report No. 1300615.401, Rev. 0, Acceptability of Weir Tricentric Butterfly Valves Having Stainless Steel Seat Fillet Welds Applied with 60 F Preheat.2013-08-19019 August 2013 Attachment 2 to RBG-47386 - Structural Integrity Report No. 1300615.401, Rev. 0, Acceptability of Weir Tricentric Butterfly Valves Having Stainless Steel Seat Fillet Welds Applied with 60 F Preheat. RBG-47190, Letter from Entergy Operations, Inc Additional Information Regarding November 21, 2011, Predecisional Enforcement Conference2011-11-28028 November 2011 Letter from Entergy Operations, Inc Additional Information Regarding November 21, 2011, Predecisional Enforcement Conference ML1127000692011-09-26026 September 2011 Enclosure 2, Mfn 10-245 R4, Description of the Evaluation and Surveillance Recommendations for BWR/2-5 Plants ML1012704392010-05-0505 May 2010 Y020100187 - List of Historical Leaks and Spills at U.S. Commercial Nuclear Power Plants ML0824106442008-08-20020 August 2008 Plume Pathway Exercise Evaluated on June 11, 2008 - Radiological Emergency Preparedness Final Report RBG-46716, Fitness-For-Duty Program Six-Month Performance Data Report for Period January 1, 2007 Through June 30, 20072007-07-25025 July 2007 Fitness-For-Duty Program Six-Month Performance Data Report for Period January 1, 2007 Through June 30, 2007 RBG-46649, Fitness-for-Duty Program Six-Month Performance Data Report2007-02-0808 February 2007 Fitness-for-Duty Program Six-Month Performance Data Report RBG-46615, 10 CFR 50.46(a)(3)(ii) Report2006-08-24024 August 2006 10 CFR 50.46(a)(3)(ii) Report RBG-46609, Fitness-For-Duty Program Six-Month Performance Data Report2006-08-15015 August 2006 Fitness-For-Duty Program Six-Month Performance Data Report RBG-46607, Submittal of Owner'S Activity Report Form (OAR-1)2006-08-10010 August 2006 Submittal of Owner'S Activity Report Form (OAR-1) CNRO-2006-00034, Supplement to Request for Use of Delta Protection Mururoa V4F1 R Supplied Air Suits; Arkansas Nuclear One, Indian Point, Grand Gulf, Waterford, FitzPatrick, River Bend, Pilgrim, Vermont Yankee2006-07-13013 July 2006 Supplement to Request for Use of Delta Protection Mururoa V4F1 R Supplied Air Suits; Arkansas Nuclear One, Indian Point, Grand Gulf, Waterford, FitzPatrick, River Bend, Pilgrim, Vermont Yankee CNRO-2006-00023, Request for Alternative CEP-PT-001 Visual Examination of Vent and Drain Connections During System Leakage Tests2006-04-24024 April 2006 Request for Alternative CEP-PT-001 Visual Examination of Vent and Drain Connections During System Leakage Tests ML0607204302006-03-0101 March 2006 March 1, 2006 Public Meeting Slides for Proposed Generic Letter Post-Fire Safe-Shutdown Circuit Analysis Spurious Actuations. RBG-46533, Fitness-For-Duty Program Six-Month Performance Data Report2006-02-10010 February 2006 Fitness-For-Duty Program Six-Month Performance Data Report ML0532604512005-11-14014 November 2005 River Bend, Supplement to Revised License Amendment Request (LAR) 2004-26, Use of the Fuel Building Cask Handling Crane for Dry Spent Fuel Cask Loading Operations. RBG-46468, Transmittal of the Fitness-for-Duty Program Six-Month Performance Data Report2005-08-18018 August 2005 Transmittal of the Fitness-for-Duty Program Six-Month Performance Data Report RBG-46403, Submittal of Owner'S Activity Report Forms (OAR-1)2005-02-17017 February 2005 Submittal of Owner'S Activity Report Forms (OAR-1) ML0727008492005-01-31031 January 2005 Caldon Experience in Nuclear Feedwater Flow Measurement ML0532204612004-06-14014 June 2004 Power Reactor Status Report for 6/14/04 ML0402802082004-01-21021 January 2004 Potential Fire Protection Issue at River Bend. RBG-46145, Power Uprate Startup Report2003-08-0707 August 2003 Power Uprate Startup Report RBG-46073, Fitness-for-Duty Program Six-Month Performance Data Report2003-02-14014 February 2003 Fitness-for-Duty Program Six-Month Performance Data Report RBG-45993, Fitness-for-Duty Program Six-Month Performance Data Report2002-08-0101 August 2002 Fitness-for-Duty Program Six-Month Performance Data Report 2023-11-21
[Table view] |
Text
April 8, 2021 Mr. Steven Vercelli, Site Vice President Entergy Operations, Inc.
River Bend Station 5485 U.S. Highway 61N St. Francisville, LA 70775
SUBJECT:
River Bend Station - NRC EXAMINATION REPORT 05000458/2021301
Dear Mr. Vercelli:
On March 12, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an initial operator license examination at River Bend Station. The enclosed report documents the examination results and licensing decisions. The preliminary examination results were discussed on February 11, 2021 with you and other members of your staff. A telephonic exit meeting was conducted on March 12, 2021, with Mr. G. Kimish, lead examination writer, who was provided the NRC licensing decisions.
The examination included the evaluation of six applicants for reactor operator licenses, four applicants for instant senior reactor operator licenses, and five applicants for upgrade senior reactor operator licenses. The license examiners determined that all the 15 applicants satisfied the requirements of 10 CFR Part 55 and the appropriate licenses have been issued. There were no post-examination comments submitted by your staff. The enclosure contains details of this report.
No findings were identified during this examination.
S. Vercelli 2 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Gregory E. Werner, Chief Operations Branch Division of Reactor Safety Docket No. 005000458 License No. NPF-47
Enclosure:
Examination Report 05000548/2021301, w/attachment: Supplemental Information cc: Electronic Distribution to River Bend Station
ML21095A311 SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002 By: mnk Yes No Publicly Available Sensitive OFFICE SOE:R2/DRS/OB OE:DRS/OB SRI:DRS/EB2 SOE:DRS/OB OE: R2/DRS/OB NAME MKennard MDoyle JDrake COsterholtz JBundy SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/
DATE 04/01/2021 04/05/2021 04/05/2021 04/05/2021 04/05/2021 OFFICE C:DRP/C C:DRS/OB NAME JKozal GWerner SIGNATURE JWK GEW DATE 04/08/2021 04/08/2021 U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000458 License Number: NPF-47 Report Number: 05000458/2021301 Enterprise Identifier: L-2021-OLL-0010 Licensee: Entergy Operations, Inc.
Facility: River Bend Station Location: Saint Francisville, Louisiana Inspection Dates: February 8, 2021, to March 12, 2021 Inspectors: M. Kennard, Senior Operations Engineer, Chief Examiner C. Osterholtz, Senior Operations Engineer M. Doyle, Operations Engineer J. Bundy, Operations Engineer J. Drake, Senior Reactor Inspector Approved By: Gregory E. Werner Chief, Operations Branch Division of Reactor Safety Enclosure
SUMMARY
Examination Report 05000458/2021301; February 8 to March 12, 2021; River Bend Station; Initial Operator Licensing Examination Report The NRC examiners evaluated the competency of six applicants for reactor operator licenses, four applicants for instant senior reactor operator licenses and five applicants for an upgrade senior reactor operator licenses at River Bend Station.
The licensee developed the examinations using NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 11. The written examination was administered by the licensee on February 19, 2021. The NRC examiners administered the operating tests on February 8-11, 2021.
The NRC examiners determined that all of the applicants satisfied the requirements of 10 CFR Part 55, and the appropriate licenses have been issued.
A. NRC-Identified and Self-Revealing Findings None.
B. Licensee-Identified Violations None.
2
REPORT DETAILS OTHER ACTIVITIES - INITIAL LICENSE EXAMINATION
.1 License Applications
- a. Scope The NRC examiners reviewed all license applications submitted to ensure each applicant satisfied relevant license eligibility requirements. The NRC examiners also audited three of the license applications in detail to confirm that they accurately reflected the subject applicants qualifications. This audit focused on the applicants experience and on-the-job training, including control manipulations that provided significant reactivity changes.
- b. Findings No findings were identified.
.2 Examination Development
- a. Scope The NRC examiners reviewed integrated examination outlines and draft examinations submitted by the licensee against the requirements of NUREG-1021. The NRC examiners conducted an onsite validation of the operating tests.
- b. Findings The NRC examiners provided outline, draft examination, and post-validation comments to the licensee. The licensee satisfactorily completed comment resolution prior to examination administration.
The NRC examiners determined the written examinations and operating tests initially submitted by the licensee were within the range of acceptability expected for a proposed examination.
.3 Operator Knowledge and Performance
- a. Scope On February 19, 2021, the licensee proctored the administration of the written examinations to all 15 applicants. The licensee staff graded the written examinations, analyzed the results, and presented their analysis to the NRC on February 22, 2021.
The NRC examination team administered the various portions of the operating tests to all applicants on February 8 - February 11, 2021.
3
- b. Findings No findings were identified.
All applicants passed the written examination and all parts of the operating tests. The final written examinations and post-examination analysis may be accessed in the ADAMS system under the accession numbers noted in the attachment. There were no post-examination comments as indicated in the licensee submittal.
The examination team noted no generic weaknesses associated with applicant performance on the operating tests. Post examination analysis revealed four generic weaknesses associated with applicant performance on the written examination:
- The definition of high energy systems - 11 0f 15 missed Question 68
- The basis and limit for the Drywell-to-Primary Containment differential pressure - 6 of 9 missed Question 77
- The time requirement to declare the Unusual Event for a single fire alarm - 6 of 9 missed Question 81
- The applicability of the generic tech Spec SR 3.0.3 - 5 of 9 missed Question 91 These deficiencies were captured in the licensees gap training program and lessons learned document to ensure all applicants understand the concepts. Copies of all individual examination reports were sent to the facility training manager for evaluation and determination of appropriate remedial training.
.4 Simulation Facility Performance
- a. Scope The NRC examiners observed simulator performance with regards to plant fidelity during examination validation and administration.
- b. Findings No findings were identified.
.5 Examination Security
- a. Scope The NRC examiners reviewed examination security for examination development during both the onsite preparation week and examination administration week for compliance with 10 CFR 55.49 and NUREG-1021. Plans for simulator security and applicant control were reviewed and discussed with licensee personnel.
4
- b. Findings No findings were identified.
EXIT MEETINGS AND DEBRIEFS Exit Meeting Summary The chief examiner presented the preliminary examination results to Mr. S. Vercelli, Site Vice President, and other members of the staff on February 11, 2021. A telephonic exit was conducted on March 12, 2021, between Mr. M. Kennard, chief examiner, and Mr. G. Kimish, lead examination writer. The licensee did not identify any information or materials used during the examination as proprietary.
5
SUPPLEMENTAL INFORMATION KEY POINTS OF CONTACT Licensee Personnel S. Peterkin, Training Manager G. Kimish, Lead Examination Writer G. Gardner, Nuclear Training Instructor T. Laporte, Nuclear Initial Training Supervisor M. McCue, Operations Superintendent T. Schenek, Regulatory Assurance Manager NRC Personnel R. Kumana, Senior Resident Inspector ADAMS DOCUMENTS REFERENCED Accession No. ML21088A202 - FINAL REACTOR OPERATOR (RO) WRITTEN EXAMINATION Accession No. ML21088A203 - FINAL SENIOR REACTOR OPERATOR (SRO) WRITTEN EXAMINATION Accession No. ML21095A053 - FINAL OPERATING TEST Accession No. ML21095A054 - POST-EXAMINATION ANALYSIS