MONTHYEARIR 05000413/20240032024-11-0404 November 2024 Integrated Inspection Report 05000413/2024003 and 05000414/2024003 ML24297A6222024-10-11011 October 2024 PCA Letter to NRC Catawba Hurricane Helene IR 05000413/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000413/2024011 and 05000414/2024011 ML24255A8312024-09-23023 September 2024 Project Manager Assignment ML24261B9782024-09-19019 September 2024 Notification of an NRC Fire Protection Team Inspection NRC Inspection Report 05000413-2024010, 05000414-2024010 and Request for Information IR 05000414/20240912024-09-0505 September 2024 Final Significance Determination of a White Finding and Nov and Assessment Followup Letter-NRC Inspection Report 05000414-2024091 IR 05000413/20240052024-08-26026 August 2024 Updated Inspection Plan for Catawba Nuclear Station (Report 05000413/2024005 & 05000414/2024005) ML24235A1542024-08-22022 August 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000413-2024402 and 05000414-2024402) IR 05000413/20240022024-08-0808 August 2024 Integrated Inspection Report 05000413-2024002 and 05000414-2024002 and Apparent Violation IR 05000413/20244032024-08-0101 August 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000413/2024403; 05000414/2024403 ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 ML24178A0552024-06-26026 June 2024 Requalification Program Inspection – Catawba Nuclear Station IR 05000414/20240902024-06-24024 June 2024 NRC Inspection Report 05000414/2024090 and Preliminary White Finding and Apparent Violation ML24170A8632024-06-11011 June 2024 Flowserve June 11, 2024, Part 21 Notification - Redacted Version for Publishing ML24149A1772024-05-28028 May 2024 NRC Response to Duke Energy 2025 FOF Schedule Change Request (Catawba and McGuire) ML24144A1162024-05-28028 May 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc IR 05000413/20240012024-05-10010 May 2024 Integrated Inspection Report 05000413/2024001 and 05000414/2024001 and Apparent Violation ML24095A1072024-04-0808 April 2024 – Review of the Spring 2023 Steam Generator Tube Inspection Report (C1R27) IR 05000413/20243012024-03-12012 March 2024 – Notification of Licensed Operator Initial Examination 05000413/2024301 and 05000414/2024301 ML24017A0652024-03-0808 March 2024 Issuance of Amendment Nos. 319 and 315 to Technical Specification 3.7.11, Control Room Area Chill Water System (Cracws) 05000414/LER-2024-001, Condition Prohibited by Technical Specifications and Loss of Safety Function Due to Failed Damper Controller for the 2A1 Emergency Diesel Generator Room Ventilation Fan2024-03-0404 March 2024 Condition Prohibited by Technical Specifications and Loss of Safety Function Due to Failed Damper Controller for the 2A1 Emergency Diesel Generator Room Ventilation Fan IR 05000413/20230062024-02-28028 February 2024 Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 - (NRC Inspection Report 05000413/2023006 and 05000414/2023006) IR 05000413/20230042024-02-0202 February 2024 – Integrated Inspection Report 05000413-2023004 and 05000414-2023004 ML24005A2512024-01-26026 January 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230102023-10-11011 October 2023 NRC Inspection Report 05000413/2023010 and 05000414/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230052023-08-25025 August 2023 Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2023005 and 05000414/2023005) ML23233A1692023-08-17017 August 2023 EN 56683 - Curtiss Wright, Interim Notification Report for PotentialPurt2l IR 05000413/20230022023-07-25025 July 2023 Integrated Inspection Report 05000413/2023002 and 05000414/2023002 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined IR 05000413/20230012023-05-0505 May 2023 Integrated Inspection Report 05000413/2023001 and 05000414/2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000413/20230112023-04-25025 April 2023 Focused Engineering Inspection Report 05000413/2023011 and 05000414/2023011 ML23107A2542023-04-14014 April 2023 301 Examination Report Letter and Report (Merged) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000413/20234012023-03-0101 March 2023 Security Baseline Inspection Report 05000413 2023401 and 05000414 2023401 IR 05000413/20220062023-03-0101 March 2023 Annual Assessment Letter for Catawba Nuclear Station, Units 1 and 2 (NRC Inspection Report 05000413/2022006 and 05000414/2022006) IR 05000413/20233012023-02-17017 February 2023 Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 IR 05000413/20220042023-01-31031 January 2023 Integrated Inspection Report 05000413/2022004 and 05000414/2022004 IR 05000413/20220112022-12-15015 December 2022 Biennial Problem Identification and Resolution Inspection Report 05000413/2022011 and 05000414/2022011 ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations IR 05000413/20224032022-11-17017 November 2022 Cyber Security Inspection Report 05000413/2022403 and 05000414/2022403 (Public) ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 ML22319A0942022-11-10010 November 2022 EN 56219 - Flowserve. 10 CFR Part 21 Report 38878-8 Solenoid Valve at Duke, Catawba Flowserve Evaluation 105 2024-09-05
[Table view] Category:Status Report
MONTHYEARML24047A2092024-02-22022 February 2024 Calendar Year 2023 Baseline Inspection Completion RA-23-0036, Biennial Decommissioning Financial Assurance Reports2023-03-30030 March 2023 Biennial Decommissioning Financial Assurance Reports IR 05000413/20200062021-03-0303 March 2021 Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 - NRC Inspection Report 05000413/2020006 and 05000414/2020006 RA-19-0159, Stations - Biennial Decommissioning Financial Assurance Reports2019-03-28028 March 2019 Stations - Biennial Decommissioning Financial Assurance Reports RA-17-0018, Duke Energy Carolinas, LLC - Biennial Decommissioning Financial Assurance Reports2017-03-29029 March 2017 Duke Energy Carolinas, LLC - Biennial Decommissioning Financial Assurance Reports CNS-15-080, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-26026 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) CNS-15-071, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-08-0303 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RA-15-0010, Submits Required Biennial Decommissioning Financial Assurance Reports2015-03-30030 March 2015 Submits Required Biennial Decommissioning Financial Assurance Reports CNS-15-013, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-16016 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) CNS-14-086, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) CNS-14-093, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-08-14014 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) CNS-14-020, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-02-28028 February 2014 Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) CNS-14-025, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-02-26026 February 2014 Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML13242A0092013-08-26026 August 2013 Duke Energy - First Six-Month Status Reports in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML13091A0222013-03-28028 March 2013 Submittal of Biennial Decommissioning Financial Assurance Reports ML1214500142012-05-23023 May 2012 NFPA 805 LAR Status Matrix - May 2012 ML1009604182010-03-30030 March 2010 Commitment Change Evaluation Report for 2009 ML0919004522009-03-30030 March 2009 Duke Energy Carolinas, LLC - Oconee Nuclear Station Units 1,2, and 3; McGuire Nuclear Station Units 1 and 2; Catawba Nuclear Station Units 1 and 2 - Decommisionings Financial Assurance Reports ML0505405242005-02-15015 February 2005 January 2005 Monthly Operating Report for Oconee McGuire and Catawba Nuclear Stations ML0224007812002-01-18018 January 2002 E-mail from Jacob Zimmerman, Bulletin 2001-01 Status Report 2024-02-22
[Table view] |
Inspection Report - Catawba - 2020006 |
---|
|
|
Text
March 3, 2021
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 - NRC INSPECTION REPORT 05000413/2020006 AND 05000414/2020006
Dear Mr. Simril:
The NRC has completed its end-of-cycle performance assessment of Catawba Nuclear Station, Units 1 and 2, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2020, through December 31, 2020. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC concluded that overall performance at your facility preserved public health and safety.
The NRC determined the performance at Catawba Nuclear Station Units 1 and 2 during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2022. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, how best to perform on-site portions to minimize personnel health risks and adjust inspection schedules if needed. This is done in accordance with guidance contained in the February 1, 2021 memo, Calendar Year 2021 Inspection Guidance During COVID-19 Telework Restrictions, (ML21027A274). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please call me at 404-997-4611 with any questions you have regarding this letter.
Sincerely,
/RA/
Jared Nadel, Acting Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos.: 50-413, 50-414 License Nos.: NPF-35, NPF-52 Enclosure: Catawba Inspection/Activity Plan (03/01/2021 - 12/31/2022)
cc distribution via ListServ SUBJECT: ANNUAL ASSESSMENT LETTER FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 - NRC INSPECTION REPORT 05000413/2020006 AND 05000414/2020006 DATED: March 3, 2021 DISTRIBUTION:
M. Kowal, RII L. Gibson, RII S. Price, RII OE Mail RIDSNRRDRO PUBLIC RidsNrrPMCatawba Resource ROP Assessment ROP Reports ADAMS Accession No: ML21061A222 OFFICE RII: DRP RII: DRP NAME J. Worosilo J. Nadel DATE 2/24/2021 3/3/2021
IP 22 Inspection Activity Plan Report Catawba 03/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count TI-194, OPEN PHASE CONDITION, REV 2 4 1, 2 01/01/2021 03/31/2021 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)
NFPA 805 TRIENNIAL FIRE PROTECTION INSPECTION 4 1, 2 03/08/2021 03/12/2021 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
UNIT 2 POST-APPROVAL LR PHASE 1 2 2 03/29/2021 04/02/2021 IP 71003 000687 Post-Approval Site Inspection for License Renewal UNIT 2 IN-SERVICE INSPECTION +SG 2 2 03/29/2021 04/02/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP PUBLIC RAD SAFETY INSPECTION 3 1, 2 05/24/2021 05/28/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 05/24/2021 05/28/2021 IP 71124.07 000731 Radiological Environmental Monitoring Program 1, 2 05/24/2021 05/28/2021 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &
Transportation 1, 2 05/24/2021 05/28/2021 IP 71151 000746 Performance Indicator Verification DESIGN BASES ASSURANCE INSPECTION (TEAMS) 6 1, 2 07/26/2021 07/30/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
1, 2 08/09/2021 08/13/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
MATERIAL CONTROL & ACCOUNTING 2 1, 2 08/16/2021 08/20/2021 IP 71130.11 000742 Material Control and Accounting (MC&A)
TARGET SET INSPECTION 2 1, 2 08/16/2021 08/20/2021 IP 71130.14 000743 Review of Power Reactor Target Sets CATAWBA INITIAL LICENSE EXAM 3 1, 2 08/21/2021 08/29/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1, 2 09/19/2021 10/02/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
EMERGENCY PREPAREDNESS PROGRAM INSPECTION 2 1, 2 08/23/2021 08/27/2021 IP 71114.02 000717 Alert and Notification System Testing This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report Catawba 03/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count EMERGENCY PREPAREDNESS PROGRAM INSPECTION 2 1, 2 08/23/2021 08/27/2021 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2 08/23/2021 08/27/2021 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2 08/23/2021 08/27/2021 IP 71114.05 000720 Maintenance of Emergency Preparedness 1, 2 08/23/2021 08/27/2021 IP 71151 001397 Performance Indicator Verification SECURITY BASELINE INSPECTION 3 1, 2 10/04/2021 10/08/2021 IP 71130.02 000734 Access Control 1, 2 10/04/2021 10/08/2021 IP 71130.05 000737 Protective Strategy Evaluation 1, 2 10/04/2021 10/08/2021 IP 71130.09 001656 Security Plan Changes 1, 2 10/04/2021 10/08/2021 IP 71151 001338 Performance Indicator Verification UNIT 1 IN-SERVICE INSPECTION 1 1 10/18/2021 10/22/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP OCCUPATIONAL RAD SAFETY BASELINE INSPECTION 1 1, 2 10/18/2021 10/22/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 10/18/2021 10/22/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 10/18/2021 10/22/2021 IP 71151 000746 Performance Indicator Verification UNIT 1 POST-APPROVAL LR PHASE 1 2 1 10/25/2021 10/29/2021 IP 71003 000687 Post-Approval Site Inspection for License Renewal DUKE CORPORATE AA/FFD BASELINE SECURITY INSPECTION 2 1, 2 01/10/2022 01/14/2022 IP 71130.01 000733 Access Authorization 1, 2 01/10/2022 01/14/2022 IP 71130.08 000740 Fitness For Duty Program SECURITY BASELINE INSPECTION 1 1, 2 01/24/2022 01/28/2022 IP 71130.01 000733 Access Authorization 1, 2 01/24/2022 01/28/2022 IP 71130.08 000740 Fitness For Duty Program FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS 6 1, 2 02/07/2022 02/11/2022 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1, 2 02/28/2022 03/04/2022 IP 71130.03 000735 Contingency Response - Force-On-Force Testing DESIGN BASES ASSURANCE INSPECTION (PROGRAMS) 3 1, 2 05/23/2022 05/27/2022 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report Catawba 03/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count DESIGN BASES ASSURANCE INSPECTION (PROGRAMS) 3 1, 2 06/06/2022 06/10/2022 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements TRIENNIAL HEAT SINK PERFORMANCE 1 1, 2 07/25/2022 07/29/2022 IP 71111.07T 000700 Heat Sink Performance CATAWBA REQUAL INSPECTION 2 1, 2 07/25/2022 07/29/2022 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance EMERGENCY PREPAREDNESS EXERCISE INSPECTION 5 1, 2 08/15/2022 08/19/2022 IP 71114.01 000716 Exercise Evaluation 1, 2 08/15/2022 08/19/2022 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2 08/15/2022 08/19/2022 IP 71151 001397 Performance Indicator Verification UNIT 2 IN-SERVICE INSPECTION +SG 2 2 09/12/2022 09/16/2022 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP OCCUPATIONAL RAD SAFETY BASELINE INSPECTION 3 1, 2 09/12/2022 09/16/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 09/12/2022 09/16/2022 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 09/12/2022 09/16/2022 IP 71124.04 000728 Occupational Dose Assessment 1, 2 09/12/2022 09/16/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2 09/12/2022 09/16/2022 IP 71151 000746 Performance Indicator Verification 1, 2 09/26/2022 09/30/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 09/26/2022 09/30/2022 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 09/26/2022 09/30/2022 IP 71124.04 000728 Occupational Dose Assessment 1, 2 09/26/2022 09/30/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2 09/26/2022 09/30/2022 IP 71151 000746 Performance Indicator Verification SECURITY BASELINE INSPECTION 1 1, 2 10/17/2022 10/21/2022 IP 71130.02 000734 Access Control 1, 2 10/17/2022 10/21/2022 IP 71130.09 001656 Security Plan Changes 1, 2 10/17/2022 10/21/2022 IP 71151 001338 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.