IR 05000498/2020003

From kanterella
(Redirected from ML21042A051)
Jump to navigation Jump to search
STP2020003-RP-GK (Revised 2), Reissued Integrated Inspection Report 5000498/2020003 and 05000499/2020003
ML21042A051
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 02/17/2021
From: Jeffrey Josey
NRC/RGN-IV/DRP
To: Gerry Powell
South Texas
References
IR 2020003
Download: ML21042A051 (28)


Text

February 17, 2021

SUBJECT:

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION,

UNITS 1 AND 2 - REISSUED INTEGRATED INSPECTION REPORT 5000498/2020003 AND 05000499/2020003

Dear Mr. Powell:

On September 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at South Texas Project Electric Generating Station, Units 1 and 2. The results of this inspection were originally issued in a report, dated October 27, 2019 (Agencywide Document Access and Management System (ADAMS) Accession No. ML20300A591).

The NRC staff subsequently identified inspection activities that were incorrectly listed and reissued the report on January 15, 2021 (Accession No. ML21014A441). Subsequent to the reissued report, NRC staff identified that the item tracking numbers for the two items listed in the report require correction. This reissued inspection report corrects the tracking number error and is enclosed. This change has no impact on the findings documented in this report, but consistent with NRC processes, this report is being reissued in whole.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Jeffrey E. Josey, Chief Reactor Projects Branch A Division of Reactor Projects

Docket Nos. 05000498 and 05000499 License Nos. NPF-76 and NPF-80

Enclosure:

Jeffrey Josey Digitally signed by Jeffrey Josey Date: 2021.02.17 08:50:50 -06'00' As stated

Inspection Report

Docket Numbers:

05000498 and 05000499

License Numbers:

NPF-76 and NPF-80

Report Numbers:

05000498/2020003 and 05000499/2020003

Enterprise Identifier: I-2020-003-0012

Licensee:

STP Nuclear Operating Company

Facility:

South Texas Project Electric Generating Station, Units 1 and 2

Location:

Wadsworth, TX 77483

Inspection Dates:

July 1, 2020 to September 30, 2020

Inspectors:

D. Antonangeli, Health Physicist

M. Chambers, Physical Security Inspector

G. George, Senior Reactor Inspector

G. Kolcum, Senior Resident Inspector

J. ODonnell, Senior Health Physicist

D. Reinert, Reactor Inspector

A. Sanchez, Senior Project Engineer

E. Simpson, Health Physicist

C. Stott, Resident Inspector

Approved By:

Jeffrey E. Josey, Chief

Reactor Projects Branch A

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at South Texas Project Electric Generating Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Remove Plastic Shipping Plug During Auxiliary Feedwater Governor Installation Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000498/2020003-02 Open/Closed

[H.7] -

Documentation 71152 A self-revealed non-cited violation (NCV) of Technical Specification 6.8.1.a was identified when the licensee failed to provide an adequate maintenance procedure to check for and remove all vendor installed shipping plugs from the Unit 1 turbine-driven auxiliary feedwater (AFW) pump governor before installation in the plant.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000498,05000499/2020003-01 Part 37 URI 71124.08 Open

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On August 7, 2020, the unit commenced a load reduction following the trip of the low pressure heater drain pump 11 and isolation of the feedwater heaters 15A/16A due to a level switch failure. Reactor power was reduced to 93.5 percent. Unit 1 returned to 100 percent power on August 8, 2020. On August 16, 2020, Unit 1 reduced power to 95.7 percent due to a main generator gas temperature alarm. Unit 1 was returned to 100 percent power later on August 16, 2020.

Unit 2 operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week, increasing the amount of time on site as local COVID-19 conditions permitted.

As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities; and completed on site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (4 Samples)

(1) The inspectors evaluated readiness for potential impending adverse weather conditions for Hurricane Hanna during the week of July 20, 2020.
(2) The inspectors evaluated response to increased closed loop cooling temperatures of Units 1 and 2, due to high reservoir temperatures combined with heat exchanger fouling during the week of August 9, 2020.
(3) The inspectors evaluated response to Hurricanes Laura and Marco during the week of August 24, 2020.
(4) The inspectors evaluated response to Tropical Storm Beta during the week of September 20, 2020.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1, train D auxiliary feedwater pump following system restoration after maintenance on August 5, 2020
(2) Unit 1, safety injection accumulators configuration during the week of August 30, 2020
(3) Unit 2, essential cooling water system during the week of August 30, 2020
(4) Unit 2, train D auxiliary feedwater pump on September 10, 2020

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Units 1 and 2, auxiliary feedwater during the week of September 20, 2020.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (8 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1, train D auxiliary feedwater pump room and penetration area, Fire Area 51 on August 3, 2020
(2) Auxiliary fuel oil storage tank, Fire Area 99 during the week of August 3, 2020
(3) Unit 2, mechanical auxiliary building roof, Fire Area 79 on August 21, 2020
(4) Unit 1, electrical auxiliary building, Fire Area 76 on August 24, 2020
(5) Fire pump house, Fire Area 59 on August 26, 2020
(6) Unit 1, train A essential cooling water intake structure pump room, Fire Area 53 on August 27, 2020
(7) Unit 1, train B essential cooling water intake structure pump room, Fire Area 54 on August 27, 2020
(8) Unit 1, train C essential cooling water intake structure pump room, Fire Area 55 on August 27, 2020

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (2 Samples)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Unit 1, auxiliary feedwater pump rooms
(2) Unit 2, auxiliary feedwater pump rooms

Cable Degradation (IP Section 03.02) (1 Sample)

The inspectors evaluated cable submergence protection in:

(1) Unit 1, train A manhole AOXYABKEM53 on July 15, 2020 Unit 1, train B manhole BOXYABKEM52 on September 15, 2020 Unit 2, train B manhole BOXYAKKEM54 on September 22, 2020

71111.07T - Heat Sink Performance Triennial Review (IP Section 03.02)

(1) Unit 1, train A essential cooling water intake structure ventilation
(2) Unit 1, train B main steam isolation cubicle ventilation
(3) Unit 2, component cooling water heat exchanger 2B
(4) Unit 2, residual heat removal heat exchanger 2B

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the main control room during auxiliary feedwater turbine governor operation on August 6, 2020.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated an operations crews response to a degraded condition that resulted in fuel damage and led to a general emergency on August 18, 2020.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (4 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 1, train B emergency diesel generator that failed to enter the 5-minute post run cooldown during the week of August 17, 2020
(2) Diesel fire pump 3 during the week of July 20, 2020
(3) Unit 1, train A safety injection accumulator level during the week of August 30, 2020
(4) Units 1 and 2, 125vdc battery cable replacements due to excessive bend radius on September 2, 2020

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Unit 1, train D auxiliary feedwater pump speed drift on July 9, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed;

(1) Unit 2, train C 125vdc battery cable maintenance that resulted in the planned entry into the configuration risk management program on August 4, 2020
(2) Unit 1, train D 125vdc battery cable maintenance that resulted in the planned entry into the configuration risk management program on August 5, 2020
(3) Unit 2, train D 125vdc battery cable maintenance that resulted in the planned entry into the configuration risk management program on August 13, 2020
(4) Unit 1, train B 125vdc battery cable maintenance that resulted in the planned entry into the configuration risk management program on August 19, 2020
(5) Units 1 and 2, auxiliary feedwater system during the week of September 8, 2020
(6) Unit 2, train A yellow risk during the week of September 14, 2020
(7) Unit 2, train B 125vdc battery and inverter maintenance that resulted in the planned entry into the configuration risk management program on September 23, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (9 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 1, train D auxiliary feedwater pump speed drift on July 9, 2020
(2) Unit 1, train B essential chiller was found with an outlet temperature hunting on July 17, 2020
(3) Unit 1, train A power operated relief valve that was found leaking on August 1, 2020
(4) Unit 2, auxiliary airlock inner reactor containment building side door with corrosion found near the door seals on August 3, 2020
(5) Unit 2, train B essential cooling water pump motor due to low oil level found in the sight-glass on August 24, 2020
(6) Unit 1, train A safety injection accumulator level on August 30, 2020
(7) Unit 2, train A essential chilled water pump bearing oil levels during the week of September 14, 2020
(8) Unit 2, quality display processing system link status on September 23, 2020
(9) Unit 1, train D auxiliary feedwater pump trip and throttle valve leak by on September 30, 2020

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit 1, train D auxiliary feedwater pump permanent modification of mechanical overspeed connecting rod with additional threads due to previous failure to latch on April 5, 2020
(2) Temporary modification and restoration for the auxiliary fuel oil storage tank during the week of August 3, 2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (9 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:

(1) Diesel fire pump 1 during the week of July 1, 2020
(2) Unit 1, train D auxiliary feedwater pump following discovery of plugged governor valve bellows on July 9, 2020
(3) Unit 2, train B emergency diesel generator following preventive maintenance performed on the lube oil circulation pump and the standby lube oil pump on July 28, 2020
(4) Unit 1, train D auxiliary feedwater pump following maintenance on August 3, 2020
(5) Unit 2, train C 125vdc batteries following cable replacement on August 4, 2020
(6) Unit 1, train D 125vdc batteries following cable replacement on August 5, 2020
(7) Unit 1, train B emergency diesel generator following fuel oil circuitry repair on August 17, 2020
(8) FLEX diesel generator 11 following maintenance on August 18, 2020
(9) Diesel fire pump 3 during the week of August 20, 2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Unit 2, train D auxiliary feedwater pump on June 18, 2020,
(2) Unit 1, power range neutron flux channel IV actuating channel operational test on July 7, 2020
(3) Unit 1, train D auxiliary feedwater pump on August 6, 2020
(4) Unit 1, train D auxiliary feedwater pump on September 3, 2020
(5) Unit 2, train D auxiliary feedwater pump on September 10, 2020

RCS Leakage Detection Testing (IP Section 03.01) (1 Sample)

(1) Unit 1, unidentified leakage on June 18, 2020

FLEX Testing (IP Section 03.02) (1 Sample)

(1) FLEX diesel generator 22 run on August 27, 2020

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (2 Samples)

The inspectors evaluated:

(1) The inspectors evaluated the licensee's simulator-based licensed operator requalification training evolution that involved a faulted steam generator, loss of reactor coolant accident, and a leak outside of containment on August 19, 2020.
(2) The inspectors evaluated the licensee's simulator-based licensed operator requalification training evolution that involved a reactor coolant leak, loss of an emergency bus, and a loss of reactor coolant accident, on September 22, 2020.

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (10 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Personnel contamination monitoring equipment at the Unit-1 41 access control location: 3 ARGOS-5AB units.
(2) Personnel monitoring equipment at the Unit-1 41 access control location: 2 GEM-5 units.
(3) Small article monitoring equipment at the Unit-1 41access control location:

4 SAM-12 units.

(4) Plant process radiation monitor: Unit 1 Steam Generator Blowdown Detector, 1-RA-RE-8043.
(5) Plant process radiation monitor: Unit 2 Component Cooling Water Transmitter, 2-RA-RT-8040.
(6) Plant process radiation monitor: Unit 2 Safety Injection Train-A Cubicle Indicator, 2-RA-RI-8084.
(7) Radiation monitoring equipment: HP-400-00012-010, Ludlum Model 177 count-rate meter.
(8) Radiation monitoring equipment: HP-400-00097-005, Eberline RO-20 ion chamber.
(9) Radiation monitoring equipment: HP-400-00147-001, Ludlum Model 78 Stretch Scope.
(10) Radiation monitoring equipment: HP-400-00045-002, Ludlum Model 12-4 (neutron)survey meter.

Calibration and Testing Program (IP Section 03.02) (11 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Ludlum Model 177, HP-400-00012-006, November 4, 2019
(2) Ludlum Model 3, HP-400-00031-059, February 26, 2020
(3) Ludlum Model 9-3, HP-400-00163-040, March 24, 2020
(4) Canberra GEM-5, HP-155-00003-001, September 3, 2020
(5) Canberra Argos-5AB, HP-155-00004-005, December 4, 2019
(6) Eberline EBR-PCM-1C, HP-155-00105-011, February 5, 2020
(7) Eberline AMS-4 Particulate Monitor, HP-400-00099-002, May 13, 2020
(8) Unit 1, Turbine Generator Drain Monitor, 1-RA-RT-8041, November 15, 2019
(9) Unit 2, Condensate Polishing Area Radiation Transmitter, 2-RA-RT-8093, April 30, 2020
(10) Unit 1 Steam Generator Blowdown Radiation Transmitter, 1-RA-RT-8043, September 23, 2019
(11) Unit 1, Containment High Range Area Monitor, 1-RA-RT-8050, April 8-9, 20020

Effluent Monitoring Calibration and Testing Program Sample (IP Sample 03.03) (3 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) WAN 569357, Unit 2 Vent Particulate and Iodine Effluent Monitor, 2-RA-RT-8010A, April 27, 2010
(2) WAN 554121, Unit 2 Vent Wide Range Gas Monitor, 2-RA-RT-8010B, January 20, 2020
(3) WAN 573449, Unit 1 Liquid Waste Processing System Monitor, 1-RA-RT-8038, June 24, 2020

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation

Radioactive Material Storage (IP Section 03.01)

Inspectors evaluated the licensees performance during walk-downs in the Unit-1 Auxiliary Building, Warehouse-44, Metrology Building, and the Unit-2 Yard for controlling, labelling and securing of selected radioactive materials:

(1) Onsite storage containers 1, 23, and 36 in the Unit-2 yard
(2) Sealand containers 529689-1 and 204TLU inside warehouse-44
(3) Decon Jo-boxes 1 and 2 on the 60' walkway of the Unit-1 auxiliary building

Radioactive Waste System Walkdown (IP Section 03.02 (2 Samples)

Inspectors walked down in the Unit 1 Auxiliary Building accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality for the following systems:

(1) Spent resin transfer system
(2) Floor drain system

Waste Characterization and Classification (IP Section 03.03) (2 Samples)

The inspectors evaluated the licensees characterization and classification of radioactive waste of the following:

(1) Dry active waste common 2019
(2) Unit 2, high activity spent resin 2019

Shipment Preparation (IP Section 03.04)

The inspectors were unable to observe preparation of a shipment containing radioactive material according to requirements.

Shipping Records (IP Section 03.05) (3 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review:

(1) STP-1-19-015, Type B dewatered bead resin
(2) STP-2-18-058, LSA -II dewatered bead resin
(3) STP-1-20-013, Type B dewatered bead resin

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 1, July 1, 2019, through June 30, 2020
(2) Unit 2, July 1, 2019, through June 30, 2020

MS07: High Pressure Injection Systems (IP Section 02.06) (2 Samples)

(1) Unit 1, July 1, 2019, through June 30, 2020
(2) Unit 2, July 1, 2019, through June 30, 2020

MS08: Heat Removal Systems (IP Section 02.07) (2 Samples)

(1) Unit 1, July 1, 2019, through June 30, 2020
(2) Unit 2, July 1, 2019, through June 30, 2020

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (3 Samples)

(1) Unit 1, train B emergency diesel generator, Condition Report CR-20-5447
(2) Unit 1, unidentified leakage on June 18, 2020
(3) Unit 1, train D auxiliary feedwater pump speed drift on July 9,

INSPECTION RESULTS

Unresolved Item (Open)

Part 37 URI URI 05000498,05000499/2020003-01 71124.08

Description:

The inspectors, while conducting a public radiation safety baseline inspection, identified several issues of concern regarding the implementation of 10 CFR Part 37 requirements during their review of the controls for a Category 2 radioactive source. The inspection was conducted the week of September 14, 2020, using IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation.

The inspectors informed the licensee of the issues of concern regarding the implementation of the 10 CFR Part 37 requirements, specifically associated with 10 CFR 37.23, 37.43, and 37.49.

These issues of concern regarding the implementation of 10 CFR Part 37 for the control of the Category 2 radioactive source observed require additional information and review to determine whether the licensee performance constituted violations of NRC requirements.

Consequently, we are considering this matter as an unresolved item (URI).

Planned Closure Actions: The inspectors plan to continue their review of documentation provided by the licensee, as it is made available. This review will be a comprehensive assessment of all associated violations and/or findings related to these potential issues identified.

Licensee Actions: The licensee placed this matter into their corrective action program for review and implementation of corrective actions. The licensee used the corrective action program to document their corrective actions already taken and planned. The licensee has already addressed perceived gaps the inspectors identified in the implementation of 10 CFR Part 37 requirements.

Corrective Action References: Condition Report CR 2020-9835

Failure to Remove Plastic Shipping Plug During Auxiliary Feedwater Governor Installation Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000498/2020003-02 Open/Closed

[H.7] -

Documentation 71152 A self-revealed non-cited violation (NCV) of Technical Specification 6.8.1.a was identified when the licensee failed to provide an adequate maintenance procedure to check for and remove all vendor installed shipping plugs from the Unit 1 turbine-driven auxiliary feedwater (AFW) pump governor before installation in the plant.

Description:

On July 9, 2020, the licensee declared the turbine-driven AFW pump 14 inoperable due to a condition where the pump drifted to slower speeds as the pump was running. Later that same day, the licensee found a vendor plug installed inside the fitting on the pneumatic speed control tubing connection on the governor. The licensee believes the plug was vendor installed and in place until discovery on July 9, 2020. The plug was removed, and a post-maintenance test showed that the turbine-driven AFW pump performed satisfactorily. The pump was then declared operable at 0220 on July 10, 2020.

The governor for AFW pump 14 had been replaced in the spring of 2020 during refueling outage 1RE22. It was tested on April 17, 2020 and put into service. During the test, the pumps speed lowered several rpms. This speed control issue was noted during that initial test but not enough to declare the pump inoperable.

With the plug installed in the turbine-driven AFW governor, air was trapped inside a bellows that could be used for pneumatic speed control. The licensee does not use this pneumatic speed control feature, opting instead for the manual speed setting knob for their speed setpoint control. This setup requires that the bellows for pneumatic speed control be free to pass air as the system runs so the manual speed control knob can properly set the speed vice pneumatic control.

With the bellows plugged, the temperature of the trapped air in the bellows rose which caused increasing air pressure the longer the pump ran. This caused the bellows to depress the speed setting plunger which reduced oil flow to the speed setting piston. This, in turn, changed the spring tension and set a new operating point for the spinning flyweight.

When the licensee found and subsequently removed the plug, they were again able to control the turbine-driven AFW pump with the manual speed setting knob and keep the pump within its normal operating band for speed.

The inspectors reviewed procedure 0PMP04-AF-0002, Auxiliary Feedwater Pump Turbine and Governor Valve Maintenance, Revision 43. The inspectors determined that there was no step in the procedure to remove the vendor plug.

Corrective Actions: The licensee removed the vendor plug from the governor bellows and completed surveillance testing to ensure the governor could maintain pump speed as required. The licensee also found testing documentation from the vendor that shows while the governor with the plug installed would cause the turbine-driven AFW pump to slow down, the pump could still perform its safety function for all accident scenarios.

Corrective Action References: Condition Report CR 2020-7429

Performance Assessment:

Performance Deficiency: The failure to provide adequate procedures for maintenance on safety-related equipment was a performance deficiency. Specifically, the licensee failed to provide an adequate maintenance procedure to check for and remove all vendor installed shipping plugs from the Unit 1 turbine-driven AFW pump governor before installation in the plant.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Procedure Quality attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the plug installed on the turbine-driven AFW governor put the safety-related pump into a degraded condition which limited its speed to a slower speed than required by licensee acceptance criteria. The licensee had to perform calculations using data from previous vendor test reports that the pump was still operable.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Specifically, the turbine -driven AFW pump was able to maintain its operability and therefore screened as Green.

Cross-Cutting Aspect: H.7 - Documentation: The organization creates and maintains complete, accurate and up-to-date documentation. The inspectors determined that the finding had a crosscutting aspect in the area of documentation. Specifically, the licensee could have incorporated warnings that were in the operations procedure since 1995 into maintenance procedures on the turbine-driven AFW pump governor to ensure the control air port was not blocked prior to installation. [H.7].

Enforcement:

Violation: Technical Specification 6.8.1.a requires, in part, that written procedures shall be established, implemented, and maintained in accordance with Appendix A of Regulatory Guide 1.33, Revision 2, February 1978, Section 9.a, maintenance that can affect the performance of safety-related equipment should be properly pre-planned. The licensee established procedure 0PMP04-AF-0002, Auxiliary Feedwater Pump Turbine and Governor Valve Maintenance, Revision 43, to meet Regulatory Guide 1.33 requirement.

Contrary to the above, from 1995 to July 9, 2020, the licensee failed to properly pre-plan maintenance that can affect the performance of safety-related equipment. Specifically, procedure 0PMP-AF-0002 fails to include procedures that ensures the replacement turbine- -driven AFW pump governor is free of all vendor installed plugs and is ready to install in the plant.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 23, 2020, the inspectors presented the triennial heat sink performance inspection results to Mr. J. Connolly and other members of the licensee staff.
  • On September 21, 2020, the inspectors presented the radiation safety inspection results to Mr. G. Powell and other members of the licensee staff.
  • On October 8, 2020, the inspectors presented the integrated inspection results to Mr. J. Connolly and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

0PGP03-ZV-0001

Severe Weather Plan

0PGP03-ZV-0002

Hurricane Plan

0POP02-AF-0001

Auxiliary Feedwater

ZV-0029

Site Preparation for Tropical Storm or Hurricane

71111.04

Miscellaneous

5S-14-9-Z-40131

Motor Driven AFW Pump

5S-14-9-Z-40132

AFW Turbine Steam Inlet Valve

5S-14-9-Z-40134

AFW Crossover Valves

5S-14-9-Z-40135

AFW Pump No. 14(24) Turbine Trip and Throttle Valve

5S-14-9-Z-40136

AFW Turbine Pump Isolation Valve

5S-14-9-Z-40139

AFW Pump 14 (24) Turbine Trip Solenoid

5S139F00063

Feedwater

5S141(2)F00024,

Sheets 1 & 2

Auxiliary Feedwater

5S141(2)F22547

Turbine Driven AFW Pump Lube Oil System

5S149MB1016,

Auxiliary Feedwater

5S199F00020

Condensate Storage

5V-14-9-Z-41634

Main Stm. Iso. Valve Cubicle Vent Fans

Procedures

0POP02-AF-

0001

Auxiliary Feedwater

0IVC51-FP-0400

Fire Preplan Isolation Valve Cubicle, Pump Room Train D

0IVC51-FP-0409

Fire Preplan Isolation Valve Cubicle Penetration Area, Train

D

0PEP07-AF-0001

Auxiliary Feedwater Turbine Overspeed Trip Test

0PMP08-ZI-0025

Pneumatic/Spring Control Valve or Damper Calibration

0POP02-AF-0002 Resetting Auxiliary Feedwater Pump 14(24) Mechanical

Overspeed Trip Device

0POP02-CD-0001 Condensate System

0POP02-SB-0002

Steam Generator Wet Layup Recirc

0PSP03-AF-0007

Auxiliary Feedwater Pump 14(24) Inservice Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0PSP03-XC-0001

Refueling Containment Penetration Status

0PSP05-FW-0501 Steam Generator Wide Range Level Calibration

71111.05

Procedures

0AFO99-FP-0903

Fire Preplan Auxiliary Fuel Oil Storage Tank

0EAB76-FP-0017

Unit 1 Electrical Auxiliary Building, Fire Area 76

0FPH59-FP-0800

Fire Pump House, Fire Area 59

0IVC51-FP-0400

Fire Preplan Isolation Valve Cubicle, Pump Room Train D

0IVC51-FP-0409

Fire Preplan Isolation Valve Cubicle Penetration Area, Train

D

0MAB79-FP-0162

Unit 2 Mechanical Auxiliary Building Roof, Fire Area 79

1ECW53-FP-

0600

Unit 1 Essential Cooling Water Intake Structure Pump Room

Train A, Fire Area 53

1ECW54-FP-

0601

Unit 1 Essential Cooling Water Intake Structure Pump Room

Train B, Fire Area 54

1ECW55-FP-

0602

Unit 1 Essential Cooling Water Intake Structure Pump Room

Train C, Fire Area 55

71111.06

Corrective Action

Documents

CR-YYYY-NNNN

20-2479

Procedures

0PGP03-ZE-0044

Penetration Seals

0PGP03-ZA-0090

Work Process Program

0PGP03-ZA-0514

Controlled System or Barrier Impairment

0PGP03-ZI-0007

Confined Space Entry Program

0PGP03-ZI-0021

Electrical Safety

5E100E2100

General Arrangement Station Underground Duct Banks

Work Orders

Work

Authorization

Number

604560, 593968, 593969

71111.07T Calculations

5V159Z41674

ECW Pump Cub. HVAC Ventilation Fan Logic Diagram

System: HZ

EC05100

Standby Diesel Generator Transient Response Model

MC-5185

Essential Cooling Water Intake Structure (ECWIS) Pressure

Drop

MC-5430

ECWIS Cooling and Heating Loads

MC-6084

Component Cooling Water Heat Exchanger Tube Plugging

01/24/1994

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

MC-6096

Component Cooling Water Heat Exchanger Fouling

MC-6219

Generic Letter 89-013

MC-6498

Essential Cooling Pond Thermal Performance Analysis

MC05047

Component Cooling Water System Heat Loads and Flows

Following a LOCA

MC05181

System Pressure Drop

MC05479

Component Cooling Water System Heat Loads and Flows

for Normal Plant Cooling

MC05908

Instrument Set Points - Component Cooling Water System

05/25/1999

MC06426

IVC/AFW Cooling Load and Room Heat-Up

ZC07020

Area Room Temperature Switches Instrument Uncertainty

and Setpoint Determination

Corrective Action

Documents

CR-YYYY-NNNN

2018-2162, 2018-2921, 2019-1053, 2019-13222

Corrective Action

Documents

Resulting from

Inspection

CR-YYYY-NNNN

20-7775, 2020-7820, 2020-7872

Drawings

00009

EOHC01#1

1VC AFW Pump Cubicle HVAC Supply Fans FN001,

FNO02, & FN003

5R169F20000

Piping and Instrumentation Diagram Residual Heat Removal

System

5V159V00027

Piping & Instrumentation Diagram HVAC Miscellaneous

Buildings Essential Cooling Water Intake Structure &

Electrical Equipment RM - CWIS

5V159Z41674

ECW Pump Cub. HVAC Ventilation Fan Logic Diagram

System: HZ

5V159Z41675

ECW Pump Cub. HVAC Vent Fans Intake & Exh. Dampers

Logic Diagram System: HZ

9-E-HZ01-01

Elementary Diagram ECW HVAC Pump BLDG Vent Fans

FN001, FN003, & FN005

9-E-HZ02-01

Elementary Diagram, ECW HVAC Pump BLDG Vent Fans

FN002, FN004, & FN006

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

9-E-HZ03-01

Elementary Diagram ECW HVAC Intake & Exhaust Air

Dampers, FV-9894, 9895, 9896, 9894A, 9895A, & 9896A

9-E-HZ03-01

Elementary Diagram, ECW HVAC Intake & Exhaust Air

Dampers FV-9894, 9895, 9896, 9894A, 9895A, & 9896A

9-E-HZ04-01

Elementary Diagram ECW Intake Structure HVAC Unit

HTRS HT035 Thru HT040 & HT155 Thru HT160

Engineering

Changes

DCP 99-13150-2

IVC, ECW, and DGB Area Temperature Switch Set-Point

Changes

2/02/1999

Engineering

Evaluations

FAI/20-0513

Evaluation of Gas Void Potential Effects in STP RHR Piping

Miscellaneous

Flow Vibration Analyses for the South Texas (Unit 1 & 2)

Component Cooling Water Heat Exchangers

10/05/1987

Meeting Report Regarding Component Cooling Water Flow

Induced Vibration Problem

11/18/1987

System Health Report Component Cooling Water

06/30/2020

06000252

Component Cooling Water Heat Exchanger Thermal

Performance Test PM Template

10/29/2018

3V229VS0002

Specification for Safety Class Fans

3V289VS0008

Specification for Safety Class Dampers

5R289MB01006

Design Basis Document Component Cooling Water System

5V150VQ1004

Essential Cooling Water Intake Structure Ventilation System

Design Criteria

HLAE2400

Final Report Concerning Component Cooling Water Heat

Exchangers

11/05/1987

MM-2-CC-

87001592

CCW Heat Exchanger 2B Inspect/Clean Preventative

Maintenance Activity

10/09/1990

Plan of Action 20-

4781

Unit 1 RH 1B and 1C Header Pressurization Following SI

Accumulator LAR

07/02/2020

ST-HL-AE-3341

Service Water System Problems Affecting Safety-Related

Equipment

01/29/1990

ST-HL-AE-3701

Revised Schedule for NRC Generic Letter 89-13, Service

Water System Problems Affecting Safety-Related Equipment

04/03/1991

ST-HL-AE-3720

Correction of Response to NRC Generic Letter 89-13,

Service Water System Problems Affecting Safety-Related

03/27/1991

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Equipment

ST-HL-AE-3761

Supplemental Response to NRC Generic Letter 89-13,

Service Water System Problems Affecting Safety-Related

Equipment

05/15/1991

VTD-R165-0008

Installation, Operation and Care of Duty Master Nuclear

Service Class 1E Nuclear Service Non Class 1E Integral

Horsepower Induction Motors

VTD-W351-0005

Instruction Manual for Westinghouse NSSS Heat

Exchangers

Operability

Evaluations

11-3756-3

07/12/2012

13-9934-18

07/26/2016

Procedures

0PCP01-ZA-0038

Plant Chemistry Specifications

0PCP03-ZC-0013

Chemical Addition to CW/OC and EW

0PEP07-EW-

0001

Performance Test for Essential Cooling Water Heat

Exchangers

0PGP03-ZE-0080

Essential Cooling Water System Reliability Program

0PMP04-ZG-0011 Heat Exchanger Cleaning (General Guidelines and

Instructions)

0PMP08-ZI-0011

Generic Temperature Switch Calibration (Filled Element)

0POP01-ZO-0004

Extreme Cold Weather Guidelines

0POP02-AF-0001

Auxiliary Feedwater

0POP02-EW-

0001

Essential Cooling Water Operations

0POP09-AN-

2M1

Annunciator Lampbox 22M01 Response Instructions

0PSP03-SP-

0013B

Train B ESF Actuation and Response Time Test

0PSP03-ZQ-0028

Operator Logs

155

Work Orders

Work Activity

Number

23592, 443937, 454609, 454610, 479776, 497442, 508549,

2811, 522812, 533286, 544989, 572382, 572383, 575864,

595316, 595317, 595318

71111.12

Calculations

3689, 3680, 3675, 3686

Corrective Action

Documents

CR-YYYY-NNNN

20-1370, 2020-1860, 2019-3905, 2020-1815, 2020-1854,

2019-8208, 2019-7235, 2019-9047, 2020-4561, 2019-14780,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2019-8208, 2020-7429, 2018-8223, 2018-2084, 2017-17317,

2010-21759, 2020-5447, 2020-4958, 2020-8431,

2014-10004, 2020-2379, 2020-2557, 2020-2553, 2020-7892

Miscellaneous

DCN 1501807

DCP 14-10333-1

Vendor Technical

Documents

VTD-C634-0029, VTD-C634-0004

Procedures

0OOI01-OL-0005

Operations Logs - Diesel Generator

0PGP04-ZE-0313

Maintenance Rule Program

0PMP02-NZ-0013

Cable Terminations

0PMP02-ZG-0004 Bolted Joint Procedure

0POP02-DG-

0002

Emergency Diesel Generator 12(22)

0PSP03-DG-0003

Standby Diesel 13(23) Operability Test

0PSP06-DJ-0001

25 Volt Class 1E Battery Monthly Surveillance Test

0PSP06-DJ-0002

25 Volt Class 1E Battery Quarterly Surveillance Test

0PSP06-DJ-0003

25 Volt Class 1E Battery Intercell Connection Resistance

Surveillance Test

Work Orders

Work

Authorization

Number

27615, 628622, 614503, 591778, 624890, 624973, 633040,

575409, 605853, 570201, 629593, 629668, 629665, 615379,

636969

71111.13

Calculations

3689, 3686

Corrective Action

Documents

CR-YYYY-NNNN

20-2557, 2020-2553

Procedures

0PMP02-NZ-0013

Cable Terminations

0PMP02-ZG-0004 Bolted Joint Procedure

0PSP06-DJ-0001

25 Volt Class 1E Battery Monthly Surveillance Test

0PSP06-DJ-0002

25 Volt Class 1E Battery Quarterly Surveillance Test

0PSP06-DJ-0002

25 Volt Class 1E Battery Quarterly Surveillance Test

0PSP06-DJ-0003

25 Volt Class 1E Battery Intercell Connection Resistance

Surveillance Test

Work Orders

Work

Authorization

Number

605853, 570201, 629593, 629665, 629668, 581426

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.15

Corrective Action

Documents

CR-YYYY-NNNN

20-8152, 2020-7429, 2020-4958, 2020-9042, 2020-9197,

2016-1252, 2004-2663, 2020-7508, 2020-8188, 2020-6781,

20-5888, 2020-7714, 2020-9943, 2020-10151

Drawings

1F-9031

C

Miscellaneous

Vendor Manual

VTD-B580-0001

Installation, Operation & Maintenance Instructions for

Essential Chilled Water Pumps

Vendor Manual

VTD-B580-0002

Material of Construction

Vendor Technical

Document VTD-

R165-0029

Instruction Manual for Essential Cooling Water Pump Motor

Vendor Technical

Document VTD-

STP1-0001

Rotating Equipment Oil Level Limits and Labels

Procedures

0PGP03-ZA-0133

Fluid Leak Management Program

0PMP05-EW-

0001

Essential Cooling Water Pump Motor Inspection

Work Orders

Work

Authorization

Number

575409

71111.18

Corrective Action

Documents

CR-YYYY-NNNN

2019-975, 2020-8072, 2020-8117, 2020-8339

Drawings

HL-10797-2

04/08/1983

HS-14295-1

04/06/1983

Procedures

0PEP07-AF-0001

Auxiliary Feedwater Turbine Overspeed Trip Test

0POP02-AF-0001

Auxiliary Feedwater

0POP02-AF-0002

Resetting Auxiliary Feedwater Pump 14(24) Mechanical

Overspeed Trip Device

0PSP03-AF-0007

Auxiliary Feedwater Pump 14(24) Inservice Test

Work Orders

Work

Authorization

Number

615462, 564212, 611949, 585036, 568084, 629571

71111.19

Corrective Action

Documents

CR-YYYY-NNNN

20-5447

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Procedures

0POP02-DG-

0002

Emergency Diesel Generator 12(22)

0PSP06-DJ-0003

25 Volt Class 1E Battery Intercell Connection Resistance

Surveillance Test

0PSP06-DJ-0003

25 Volt Class 1E Battery Intercell Connection Resistance

Surveillance Test

Work Orders

Work

Authorization

Number

570201, 605853, 633040, 629593, 590341, 608858, 609351,

71111.22

Corrective Action

Documents

CR-YYYY-NNNN

20-6590, 2020-9196, 2020-9445, 2020-8375, 2019-7521,

2015-5166

Procedures

0POP07-FR-0006

FLEX Diesel Generator Performance Test

0PSP02-NI-0044

Power Range Neutron Flux Channel IV ACOT (N-0044)

0PSP03-AF-0007 Auxiliary Feedwater Pump 14(24) Inservice Test

Work Orders

Work

Authorization

Number

607089, 572074, 607584, 607595, 607585

71114.06

Procedures

0ERP01-ZV-IN01

Emergency Classification

0ERP01-ZV-IN02

Notifications to Offsite Agencies

0POP04-MS-

0001

Excessive Steam Demand

0POP05-EO-

EO00

Reactor Trip or Safety Injection

0POP05-EO-

EO00

Reactor Trip or Safety Injection

0POP05-EO-

EO10

Loss of Reactor or Secondary Coolant

0POP05-EO-

EO10

Loss of Reactor or Secondary Coolant

0POP05-EO-

EO20

Faulted Steam Generator

0POP05-EO-

ES13

Transfer to Cold Leg Recirculation

0POP05-EO-

Transfer to Cold Leg Recirculation

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ES13

IN010ERP01-ZV-

IN02

Notifications to Offsite Agencies

71124.05

Calibration

Records

File #Z05.01

STPNOC Metrology Laboratory Calibration Form

Numerous

Corrective Action

Documents

CR-YYYY-NNNN

2018-09932, 2018-10097, 2018-10300, 2018-11527

2018-11559, 2018-12026, 2019-01116, 2019-00144

2019-00418, 2019-00936, 2019-01040, 2019-01473

2019-04167, 2019-05107, 2019-06344, 2019-07248

2019-07503, 2019-08688, 2019-08843, 2019-09249

2019-09834, 2019-11503, 2019-12317, 2019-13068

2019-13147, 2020-00943, 2020-02190, 2020-02472

20-03730, 2020-03731, 2020-03732, 2020-03863

20-05735, 2020-05863, 2020-06309, 2020-07101

20-07435, 2020-07834

Procedures

0ERP01-ZV-IN07

Offsite Protective Action Recommendations

0PCP01-ZQ-0007

Quality Assurance for Radioanalysis Instrumentation

0PRP10-ZL-0002

Quality Assurance for the Radiological Laboratory

0PSP05-RA-

8010B

MAB Unit Vent Wide Range Gas Monitor Calibration

0PSP05-RA-8038

Liquid Waste Processing System No.1 Monitor Calibration

0PSP05-RA-8050

RCB High Range Area Monitor Calibration

0PTP04-ZC-0002

Calibration of the Eberline 6112 Teletector and the Ludlum

Stretch Scope

0PTP04-ZC-0044

Calibration of Counting Instruments

0PTP04-ZC-0053

Calibration of Handheld Survey Meters/Ion Chambers

0PTP04-ZC-0062

Maintenance Calibration of SAM Series Small Article

Monitors

0PTP04-ZC-0064

Monitor Calibration of Canberra Argos-5AB Whole Body

Monitors

0PTP04-ZC-0067

Calibration of the Ludlum Model 26-1 Friskers

0PTP04-ZC-0068

Calibration of the Mirion Telepole II Telescoping Gamma

Survey Meter

0PTP04-ZC-0069

Calibration of Alpha-Beta Probes

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Self-Assessments 0PGP03-ZX-0003

Assessment/Benchmark Report, High Range Radiation and

Effluent Monitor Assessment

07/16/2018

MN-18-0-107381

Quality Monitoring Report

11/29/2018

MN-18-1-107149

Quality Monitoring Report

10/09/2018

MN-18-1-107197

Quality Monitoring Report

10/15/2018

MN-18-1-107205

Quality Monitoring Report

10/15/2018

MN-19-0-107592

Quality Monitoring Report

07/10/2019

MN-19-0-107910

Quality Monitoring Report

11/13/2019

MN-19-2-107700

Quality Monitoring Report

10/05/2019

MN-20-0-108151

Quality Monitoring Report

07/21/2020

71124.08

Corrective Action

Documents

CR-YYYY-NNNN

2018-05496, 2018-11245, 2018-14956, 2018-14957

2018-14958, 2018-14959, 2018-14963, 2019-04181,

2019-07874, 2019-13300, 2019-13584, 2019-13585,

2019-13586, 2019-14086, 2019-14087, 2020-00407,

20-01683, 2020-02198, 2020-06679

Miscellaneous

Typical Part 61 Sampling and Analysis Waste Stream - DAW

Common

2/12/2019

Typical Part 61 Sampling and Analysis Waste Stream -

HASR

2/26/2019

Jan. 2020 Source Inventory and Leak Testing

July 2020 Source Inventory and Leak Testing

Procedures

0PG03-Z0-0017

Radioactive Waste Process Control Program

0PGP03-ZR-0053

Radioactive Material Control Program

0POP02-WS-

0002

High Integrity Container (HIC) Dewatering for Shipment and

Burial

0PRP03-ZR-0001

Determination of Radioactive Material Curie Content,

Reportability, DOT Sub-Type, and Waste Classification

0PRP03-ZR-0001

Determination of Radioactive Material

0PRP03-ZR-0002

Radioactive Waste Shipments

0PRP03-ZR-0004

Inventory and Leak Testing of Radioactive Sources

0PRP03-ZR-0009

10CFR61 Sampling and Analysis Program

0PRP03-ZR-0011

Shipment of Radioactive Material

0PRP03-ZR-0014

Onsite Staging Facility Operations

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0PRP07-ZR-0025

Preparation and Shipment of High Integrity Containers or

Reusable Polyethylene Waste Containers

Radiation

Surveys

Survey #111242

OSSC Quarterly Routine Survey

08/24/2020

Survey #111369

Characterization Survey of Intermodal Container

09/03/2020

Self-Assessments

Snap-Shot SA Inspection Procedure 71124.08

05/21/2020

NRC Snapshot Assessment for Inspection Procedure (IP) 71124-05, 71124-06, 71124-07, and 71124-08

07/30/2020

Audit Report

Number 20-02

(RC)

Radiological Controls Quality Audit Report

03/11/2020

MN-18-0-107403

CFR Part 37 Program Review

2/13/2018

MN-19-0-107916

CFR Part 37 Program Review

11/12/2019

Shipping Records Shipment # STP-

1-19-015

Radioactive Waste Shipment Document Package, Part 1

04/10/2019

Shipment # STP-

1-19-015

Radioactive Waste Shipment Document Package, Part 2

04/10/2019

Shipment # STP-

1-20-013

Radioactive Waste Shipment Document Package

2/26/2020

Shipment # STP-

2-18-058

Radioactive Waste Shipment Document Package

11/28/2018

71152

Corrective Action

Documents

CR-YYYY-NNNN

2018-09932, 2018-10097, 2018-10300, 2018-11527

2018-11559, 2018-12026, 2019-01116, 2019-00144

2019-00418, 2019-00936, 2019-01040, 2019-01473

2019-04167, 2019-05107, 2019-06344, 2019-07248

2019-07503, 2019-08688, 2019-08843, 2019-09249

2019-09834, 2019-11503, 2019-12317, 2019-13068

2019-13147, 2020-00943, 2020-02190, 2020-02472

20-03730, 2020-03731, 2020-03732, 2020-03863

20-05735, 2020-05863, 2020-06309, 2020-07101

20-07435, 2020-07834

71152

Procedures

0ERP01-ZV-IN07

Offsite Protective Action Recommendations

71152

Miscellaneous

0PCP01-ZQ-0007

Quality Assurance for Radioanalysis Instrumentation

71152

Procedures

0PRP10-ZL-0002

Quality Assurance for the Radiological Laboratory

71152

Procedures

0PSP05-RA-

MAB Unit Vent Wide Range Gas Monitor Calibration

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

8010B

71152

Procedures

0PSP05-RA-8038

Liquid Waste Processing System No.1 Monitor Calibration

71152

Work Orders

0PSP05-RA-8050

RCB High Range Area Monitor Calibration

0PTP04-ZC-0002

Calibration of the Eberline 6112 Teletector and the Ludlum

Stretch Scope

0PTP04-ZC-0044

Calibration of Counting Instruments

0PTP04-ZC-0053

Calibration of Handheld Survey Meters/Ion Chambers

0PTP04-ZC-0062

Maintenance Calibration of SAM Series Small Article

Monitors

0PTP04-ZC-0064

Monitor Calibration of Canberra Argos-5AB Whole Body

Monitors

0PTP04-ZC-0067

Calibration of the Ludlum Model 26-1 Friskers

0PTP04-ZC-0068

Calibration of the Mirion Telepole II Telescoping Gamma

Survey Meter

0PTP04-ZC-0069

Calibration of Alpha-Beta Probes

Self-Assessments 0PGP03-ZX-0003

Assessment/Benchmark Report, High Range Radiation and

Effluent Monitor Assessment

07/16/2018

MN-18-0-107381

Quality Monitoring Report

11/29/2018

MN-18-1-107149

Quality Monitoring Report

10/09/2018

MN-18-1-107197

Quality Monitoring Report

10/15/2018

MN-18-1-107205

Quality Monitoring Report

10/15/2018

MN-19-0-107592

Quality Monitoring Report

07/10/2019

MN-19-0-107910

Quality Monitoring Report

11/13/2019

MN-19-2-107700

Quality Monitoring Report

10/05/2019

MN-20-0-108151

Quality Monitoring Report

07/21/2020