2 to Updated Final Safety Analysis Report, Chapter 14, Appendix 14A, Tables
ML20309A763
Person / Time
Site: Mcguire, McGuire  Duke Energy icon.png
Issue date: 10/08/2020
From:
Duke Energy Carolinas
To:
Office of Nuclear Reactor Regulation
Shared Package
ML20309A875 List: ... further results
References
RA-19-0424
Download: ML20309A763 (4)


Text

McGuire Nuclear Station UFSAR Appendix 14A. Tables Appendix 14A. Tables

McGuire Nuclear Station UFSAR Table 14-1 (Page 1 of 1)

Table 14-1. Preoperational and Startup Test Schedule Unit 1 Unit 2 Begin Preoperational Testing Aug. 1, 1976 May 1, 1978 Begin Hot Functional Testing May 15, 1980 June 1, 1981 Initial Fuel Loading Jan. 28, 1981 Mar. 4, 1983 Moveable Incore Detector Functional Test Incore Thermocouple Functional Test Incore Thermocouple and RTD Cross-Calibration Rod Position Indication Alignment Rod Cluster Control Assembly Drop Time Test Rod Control System Alignment Test Full-Length Rod Drive Mechanism Timing Test Reactor Coolant System Flow Test Reactor Coolant System Flow Coastdown Test RTD Bypass Flow Verification Reactor Protection System Trip Circuits Test Initial Criticality Aug. 8, 1981 May 8, 1983 Begin Low Power Testing Aug. 8, 1981 May 8, 1983 Begin Power Ascension Testing Sept. 11, 1981 May 20, 1983 Commercial Operation Dec. 1, 1981 March 1, 1984 (14 OCT 2000)

McGuire Nuclear Station UFSAR Table 14-2 (Page 1 of 1)

Table 14-2. Power Ascension Test Program Test 0% >10%4 30% 50% 75% 90% 100%

Zero Power Physics Test X Rod Control Cluster at Power X Test Pressurizer Pressure & Level X Control System Test Radiation Shielding Survey X X X X X Nuclear Instrumentation Initial X X X X X Calibration Unit Load Transient Test X X X Effluent Radiation Monitor X Test Power Coefficient & Power X X X X Defect Measurement4 Below Bank Rod Test X Pseudo Rod Ejection Test4 X Incore & Nuclear X Instrumentation Systems Detector Correlation Unit Load Steady State X X X X X X Unit Loss of Electrical Load X X Test Turbine Trip Test X 4

Dynamic Rod Drop Test X Core Power Distribution X X X X X X Loss of Offsite Power Test X Shutdown from Outside X Control Room Test Note:

1. Generator Load
2. k - Indicates test to be performed
3. X - Indicates test the successful completion of which is a pre-requisite for increasing power to the next testing plateau. Otherwise, a safety analysis will be performed for any discrepancies prior to the power increase.
4. Test to performed on Unit 1 only.

(14 OCT 2000)

McGuire Nuclear Station UFSAR Table 14-3 (Page 1 of 1)

Table 14-3. Deleted Per 2009 Update (10 OCT 2009)