TENNESSEE VALLEY AUTHORITY
~
SEQUOYAH NUCLEAR PLANT FUNCTION RESTORATION GUIDELINES FR-H.3 RESPONSE TO' STEAM GENERATOR HIGH LEVEL
.i Revision 1 PREPARED BY:
G. Strictland RESPONSIBLE SECTION: Operations REVISED BY:
Gm t. TespareA SUBMITTED BY:,
,1
/1
- s esponsible Section Supervisor PORC REVIEW DAT.
MAY 191987 APPROVED BY:_
[
Plant Manager
'N I O IS N DATE APPROVED:
L Reason for revision (include all Instruction Change Form Nos.):
Revi;ed to make minor organization name change - step 4 changed HP to RAD CON.
i The last page of this instruction is number:
4
]
1
$h81 O$c $o 27 D
PDR p
n.
f[_.
s SEQUOYAH NUCLEAR PLANT
~
PLANT INSTRUCTION REVISION LOG l
f FUNCTION RESTORATION GUIDELINES FR-H.3 ~
~
REVISION Date Pages REASON FOR REVISION (INCLudC COMMIT-LEVEL Approved Affected MENTS AND ALL ICF FORM NUMBERS)
New instruction written per commitment 0
08/21/85 All to NUREG 0737
[
lgj g jgg7 Revised to make minor organization name 3
3' change - step 4 changed PP to RAD CON.
1.
~
l-t'
- x I
t l
L 4-0264L/pah 1l m
9 m
_m_ _ _ _.
SQNP FR-H.3 Unit 1 or 2 Page 1 of 4 R ev, O f
Ik RESPONSE TO STEAM GENERATOR HIGH LEVEL
~
A.
PURPOSE This guideline provides actions to respond to a steam generator high level B.
SYMPTOMS S/G level greater than 75%
C.
TRANSITION FROM OTHER INSTRUCTIONS 1.
FR-H.2, Response To Steam Generator Overpressure FR-H.4, Response To Loss of Normal Steam Release Capabilities 3.
Status Tree l(
..A e
k e i
SQNP FH-H.3 Unit 1 or 2 Page 2 of 4 Rev. O f
1(
RESP 5NSE TO STEAM GENERATOR HIGH LEVEL S_TEP ACTION / EXPECTED RESPONSE RESPONSE NOT OBTAINED g.-
1 Identify Affected S/G a.
Narrow range S/G '
a.
IF all S/G levels <. 75%,
level > 75%
THEN return to instruction in effect 2
Verify MFW Isolation a.
MFW isolation valves - CLOSED b.
MFW reg valves - CLOSED c.
MFW bypass valves - CLOSED d.
MFW Pumps - TRIPPED 3
Verify AFW Isolation To Affected S/G a.
Motor-driven AFW level control valve - CLOSED b.
Turbine-driven AFW level control valve - CLOSED c.
Affected S/G AFW flow 0 gpm c
- l
SQNP FR-H.3 Unit 1 or 2 Page 3 of 4 Rev. 1 RESPONSE TO STEAM GENERATOR HIGH LEVEL STEP ACTION / EXPECTED RESPONSE RESPONSE NOT OBTkINED i
4 Check Affected S/G Radiation -
IF affected S/G radiation is f
NORMAL
- Eigh, i
THEN consult with TSC to a.
Condenser exhaust monitors evaluate the following bptions:
b.
S/G blowckown monitors Increase supports for the main steamlines Pin or block the pipe hangers I
Drain the main steamlines following Rad Con controls l
Establish S/G blowdown following Rad Con l
controls x
Go to
- E-3, STEAM GENERATOR TUBE RUPTURE l
IF condenser exhaust and 57G blowdown monitors NOT available, i
THEN:
{
Notify Rad Con l
to survey main j
steamlines and S/G blowdown lines l
Notify chem lab to sample a
S/G activity
{
Check RM-90-124 Aux Bldg 690 Y
L~
RESPS/I aac
t SQNP FR-H. 3 Unit 1 or 2 Page 4 of 4 Rev. O RESP 5NSE TO STEAM GENERATOR HIGH LEVEL
^
i i
STEP ACTION / EXPECTED RESPONSE RESPONSE NOT OBTAINED 5
Establish Blowdown From Affected S/G 6
Check Affected S/G Level a.
Narrow range S/G level -
DECREASING f
~
l b.
I_F affected S/G level has
{
reached the main steamline
(> 90% S/G narrow range level),,
THEN:
1 l
- 1) Do NOT depressurize affected S/G
- 2) Close affected S/G MSIV and bypass valve
{
l
- 3) Close steam supply from affected S/G to turbine-driven AFW pump
- 4) Drain main steamline 7
Return To Instruction In Effect i
~
i
- END -