ML20235L972

From kanterella
Jump to navigation Jump to search
Safety Insp Rept 50-219/87-20 on 870601-05.Major Areas Inspected:Licensee Action on Previous Insp Findings, Inservice Testing Program for Pumps & Valves & QA
ML20235L972
Person / Time
Site: Oyster Creek
Issue date: 07/06/1987
From: Bissett P, Blumberg N
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20235L953 List:
References
50-219-87-20, NUDOCS 8707170010
Download: ML20235L972 (9)


See also: IR 05000219/1987020

Text

,

.

.

4

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

50-219/87-20

Docket No.

50-219

License No.

DPR-16

Licensee: GPU Nuclear Corporation

Dyster Creek Nuclear Generating Station

P.O. Box 388

i

Forked River, New Jersey 08731

'

i

Facility Name: Oyster Creek Nuclear Generating Station

l

!

1

Inspection At:

Forked River, New Jersey

Inspection Conducted: June 1-5, 1987

j

Inspectors: Of M ,

N ( // 77

V

.

P. H.AEissett, Reactor Engineer, DRS

7 d' ate

!

Approved by:

8.f,AIqhk.

_

V date

l

6,'If7

N. J. Biumberg, Chief

Operational Programs Section

'

Operations Branch, DRS

Inspection Summary:

Routine, unannounced inspection on June 1-5, 1987

(Report No. 50-219/87-20)

Areas Inspected:

Routine unannounced inspection of licensee action on previous

inspection findings; the inservice testing program for pumps and valves; and

quality assurance.

Result: One violation was identified:

(Failure to follow ASME Section XI code

requirement, specifically IWP 4111, during the testing of the emergency service

water system.)

8707170010 870700

PDR

ADOCK 05000219

G

PDR

,

1

L.

!

.

.

!

.

,

.

DETAILS

1.0 Persons Contacted.

1.1 GpU Nuclear Corporation

J. Barton, Deputy Director

R, Blouch, Manager, Technical Support

P. Crosby, Supervisor, Operations Engineering

V. Foglia, Preventive Maintenance Programs Manager

,

S. Fuller, Operations Quality Assurance (QA) Manager

-

D. MacFarlane, Site QA Audit Manager

D. Robillard, QA Lead Auditor

4

J. Rogers, Licensing Engineer

1.2 USNRC

1

J. Wechselberger, Resident Inspector

'

The inspector also held discussions with other licensee personnel during

the course of the inspection, including operations, engineering, ' quality

,

'

assurance and administrative personnel.

j

All individuals listed above were present at the exit meeting conducted

on June 5, 1987.

!

!

2.0 Licensee Action on Previous Inspection Findings

2.1 (Closed) Unresolved Item (219/85-36-01):

Licensee to revise alarm

response procedures 2000 RAP-3024.1 (B-6-f, B-6-e) to appropriately

alleviste personnel safety concern. The inspector reviewed alarm

response procedures B-6-f and B-6 e and noted that appropriate

procedure changes had been made that alleviated operator exposure

to a hazardous environment.

Based upon this review this item is

closed.

2.2 (Closed) Unresolved Item (219/85-01-03):

Review licensee's.

.

inservice test program. A review of the licensee's inservice

i

test program was performed during inspections 219/85-17 and this

inspection, 219/87-20, which is detailed in Section 3. ' Based upon

this review, this item is closed.

3.0 Inservice Testing of Pumps and Valves

3.1 Scope and Criteria

Administrative contro'1s were reviewed to evaluate the licensee's

program for implementing requirements associated with pump and

valve inservice testing (IST) requirements. The objectives of this.

inspection were to ensure that the licensee's IST program currently.

in place was consistent with the requirements of 10 CFR 50.55a(g),

Technical Specifications and ASME Code,Section XI requirements.

_ _ _ _ _ _ __- . _ _ _ _

_ - _ _ _ _ _ _

_

.

.

'

i

l

3

.

A major portion of this review was an evaluation of the licensee's

IST program with respect to procedures, conduct of testing, and

-analyses of results. Also, a brief review of the licensee's most

!

recent IST program submittal to the NRC was conducted.

3.2 Review / Implementation

i

The inspector reviewed various inservice testing (IST) surveillance

I

proceduresand other related documents (Attachment 1) to ensure that

l

the testing of pumps and valves was being accomplished as detailed

l

in their Inservice Testing program submittal.

The licensee, in March 1987, submitted Revision 5 of their IST-

l

program to the NRC for final review and approval. ' Revision 5

I

reflected changes to Revision _4 based upon a Technical Evaluation

i

Report (TER) sent to the licensee from the NRC in December 1986.

'

The licensee has been implementing their IST program based upon

interim approval ~ granted to them in January 1980.

The inspector.also briefly. reviewed various portions of Revision.5-

of their IST program to determine if those conclusions of the 1986

TER had been reflected in Revision 5.

Also, since the licensee

eventually. plans to update their program to a later code edition

(present submittal is based on ASME,Section XI, 1974 Edition-S75),-

the inspector discussed various changes to the present program that

would be needed.

This review of the IST program (Revision 5)

revealed some minor errors which also were brought to the attention

o' the licensee. These errors and various NRC positions are detailed

below.

I

1

'

Core Spray check valves, V20-60, 61, 88 and 89, are not

i

passive v&lves, and therefore should be tested

l

Valve table listing for V16-62 does not agree with Note 3

Valve table listing for V15-27 and 28 does not agree with

Note 9

,

V15-27 and 28 should be categorized as A/C valves

!

Stroke times for applicable valves should be listed within the

IST program submittal

i

Any valve exercised during cold shutdown must also be exercised-

during refueling outages, unless it has been exercised within

the past 3 months.

,

The NRC does not recognize the 9 month testing frequency for

Category 'C' check valves.as stated in the ASME Code Section XI

1974 Edition thru 1975 Summer Addenda.

!

_____ __ - _ - - -

.

.

4

.

Equipment falling within required action ranges is to be

=

declared inoperable as soon as this fact is recognized.

The licensee acknowledged the inspector's comments.

For the core

spray check valves, a Technical Functions Work / Task Request

(ER#E86-81) has been generated to evaluate the necessary

modifications needed to be made to this system to allow testing of

the valves in question without introducing fire water into the

reactor.

The inspector reviewed this task request, generated in

August, 1986 and had no further questions.

Tne inspector also reviewed the testing completed for those valves

designated as Pressure Isolation Valves (PIV).

These valves from a

pressure boundary between those low pressure safety systems that are

connected to the higher pressure reactor coolant system.

These PIVs

are included as part of the licensees IST program and are also

listed on the Technical Specifications, Table 4.3.1.

Testing is

being accomplished as required and as determined by discussions with the

IST Valve Coordinator and a review of applicable records.

The inspector verified the maintainability of the Cold Shutdown Valve

Testing List and the accomplishment of required testing pertaining

to this list. Also reviewed were applicable administrative

procedures and various IST surveillance (listed in Attachment 1).

This review verified the technical adequacy of the procedures and

their compliance with the requirements of Technical Specifications,

Section XI of the ASME Boiler and pressure Vessel Code, and 10 CFR 50.55a(g).

A random sampling of completed IST surveillance verified that the

following attributes were being accomplished with respect to

inservice testing.

Applicable surveillance test procedures were approved and

--

up-to-date

--

Temporary changes were noted within the procedures

Calibrated test equipment utilized during the performance of

--

the surveillance was listed

Acceptance criteria listed within the procedure

--

Appropriate steps were taken,

i.e., increased testing

--

frequency, corrective maintenance, retests were taken if

acceptance criteria were not met

_

_ - - -

(

.

.

..

5

e

Reviews were performed following completion of the test

--

Further reviews of IST program implementation, including evaluation

of test results, trending, recording, etc. is detailed in this report

in paragraph 5.0 Engineering Involvement.

No violations or deviations were identified.

3.3. Test Witnessing

The inspector also observed the performance of two surveillance

tests performed by operator's during the' course of the inspection.

These two surveillance involved flow measurement of the Emergency

Service Water System II and 'A'

and 'B' Control Rod Drive pump

operability tests, including pump vibration measurements. NRC

observation of these surveillance was to verify the following was

accomplished.

Applicable surveillance procedure was approved, up Lo-date, and

.

utilized throughout the conduct of the surveillance.

Appropriate personnel were notified prior to the start of the

test.

Calibrated test equipment was used.

i

Appropriate safety precautions were taken.

Acceptance criteria were met, and if not, appropriate steps

were taken.

Following completion of the test, the system was realigned for

normal operation.

Performance of the Emergency Service Water (ESW) System II flow test

was a retest following an initial test run in which it failed to

meet acceptance criteria. Appropriately, the

'D'

ESW' pump was

declared inoperable due to low flow rate conditions.

System flow

rate measurements have in the past been somewhat erratic for System

II since measurements are taken utilizing a Controlotron "Champitron"

flowmeter. The Controlotron flowmeter is an ultrasonic measuring

i

device and a variety of variables may in effect, produce erroneous'

'

readings.

The licensee had just recently modified and installed an

Annubar flow sensor on System II, however, it was not in operation

since the gage was still on order.

The Contolotron is located in

close proximity to the Annubar and it was felt that the Annubar was

creating enough turbulence to produce erroneous flow conditions as

j

sensed by the Controlotion. The licensee subsequently transferred

the gage from the ESW system I Annubar to the ESW system II Annubar

and again performed the flow test.

Resultant flow rates were found

.

!

to be normal and thus acceptable. Following an hour run,

'D'

ESW

pump was declared operable.

,

m

_ . _ _ _ _ _ _ _.._

_ _ _ . . _ _ - _ _ _

3

!

1

'

.

6

.

During observation of the vibration measurements taken on 'A' and. 'B'

control rod drive pumps, the inspector noted a few discrepancies

within the vicinity of these pumps. These discrepancies were

brought to the attention of the operators performing the test and

the Group Shift Supervisor after completion of the test.

The

discrepancies noted included the following:

a valve packing leak -

overdue calibration sticker

an' unsecured pipe stanchion

With the exception of the unsecured pipe. stanchion, all

j

discrepancies were corrected prior to the exit meeting on June 5,

j

1987. A short form (maintenance request) was generated to

eventually correct the pipe stanchion problem. .The calibration

stickers were in actuality not overdue, but-had been marked with

incorrect due dates,' as -a result of calibration frequency changes.

3.4 Findings.

The Emergency Service Water pumps for Systems I and II are subject

to inservice testing requirements per ASME Section XI.

These tests

demonstrate the operational readiness of pumps and valves as well as

providing an indication of any degrading trends that may be

developing. Historically, the licensee has had difficulty in

establishing reference (baseline) values on several of theLESW

pump test quantities, especially pump flow rate. These reference

values are points of pump operation that are readily duplicated

)

during subsequent inservice tests. Deviations, if any, between

(

subsequent tests and established reference values are then. analyzed.

!

The types of corrective action taken depends upon the severity of

)

the deviation, but the analysis of any deviation provides an

indication of the possible development of a degrading trend in pump

j

performance. This enables one to take appropriate corrective action

-

prior to pump failure.

The licensee has been unable to effectively establish any viable

trend data due to frequent establishment of new reference values.

ESW - System II has been especially susceptible-to rebaselining due

to erratic flow rate measurements. These changes have been often

attributable to the 'Contro1otron' flow measuring device's

inability to duplicate results under similar test conditions.

'

ESW - Systems I has shown more test result stability since the

Controlotron flow (ultrasonic) measuring device was replaced with an

Annubar (differential pressure) flow measuring device several years

ago.

ESW - System II has an Annubar in place, however, it still

utilizes the Controlotron, because the Annubar gage is still on order.-

l

During this inspection, the inspector witnessed an operability test

of the 'O' ESW pump (refer to Section 3.3).

The 'D' ESW pump failed

to meet flow rate acceptance criteria.

The validity of the

Controlotron flow rate was questionable, so'the licensee

i

3

.

.

J

..

.

7

j

-.

transferred th'e gage from the ESW - System I Annubar to the

!

ESW - System II Annubar and reran the test. The inspector noted

that the indicated differential pressure was approximately 42 H2O

(subsequently converted to gpm) and that the scale of the gage

,

ranged from 0" - 200 H20. ASME Code Section XI, Article IWP 4111-

'

states that the full scale range of instruments shall not be greater

than four times the reference valve.

Station procedure 125.1"

In-Service Test Program Administration, Section 4.3.3 reiterates

Article IWP 4111.

The full scale of the gage (ESW-1) utilized

-

during the rerun of this test clearly exceeded four times the

'D'

i

ESW pump reference flow rate. A review of completed IST tests for

j

l

System I indicated that gage ESW-1 is routinely used during the

I

performance of inservice tests for

'A'

and 'B' ESW pumps. The

i

reference valves for these pumps are approximately 40" H20.

Failure

to follow AMSE Code Section XI requirements is a. violation

(219/87-20-01).

During the inspector's observation of vibration readings.taken on A

and B CRD pumps,.it was noted that not all measurement reference

points had measurement blocks attached to the pump casing / gear.

box. Discussions with the pump IST Coordination revealed that at one

time, all pumps in the IST program had measurement blocks attached

at the appropriate reference points.

However, because of pump

overhauls, pump replacement or lack of adhesion, many of the

measurement blocks had not been replaced. The inspector stated that

measurement points need to be clearly identified, especially for.

those pumps on which the measurement blocks were missing. The

licensee acknowledged the inspectors concern and stated that-

vibration measuring points would be clearly identified.

j

.

4.0 Quality Assurance / Quality Control Interface

l

l

Discussions were held with the Quality Assurance (QA) audit group and the

I

Operations QA (0QA) group to ascertain the extent of _their involvement

with the conduct of the inservice testing program.

It was noted that the

QA audit group performs a yearly audit of Engineering activities which

includes inservice testing of pumps and valves. The latest completed

i

audit was reviewed by the inspector.

No significant findings were

identified within the IST areas during this audit which was completed in

September, 1986. Another audit of the IST area is scheduled for June of

1987. The inspector also briefly reviewed a Gilbert / Commonwealth review

I

of the Oyster Creek pump and valve test program.

This report was issued

j

in August, 1986 and was a comprehensive review of the appropriateness.'of

the present program and those changes that would be necessary when the

.

' licensee eventually updated to a more recent version'of the ASME code.

l

Several of the changes recommended in'this program review were reflected

in the licensee's most recent IST program submittal to the NRC, dated

March 12, 1987.

Discussions were also held with the Operations QA (0QA) group. 0QA

routinely monitors onsite activities, including the performance of IST

-)

l

.

_

____-____ - - - -

.

.

.

~

8

.

surveillance.

Observation of these activities are documented in "QA

Monitoring Reports".

Examples of these monitoring reports were reviewed

by the inspection, together with " Monitoring Effectiveness Evaluations"

and " Monitoring Effectiveness Evaluation".

These reports are the

mechanism in which the 00A group solicits constructive feedback from a

previously monitored group so as to improve upon their overall monitoring

effectiveness.

The inspection had no further questions in this area.

5.0 Engineering Involvement

As noted previously, engineering is primarily responsible for controlling

the conduct of IST activities.

They also perform reviews of all

completed IST tests and subsequently track, document and trend components

performance.

The inspector discussed with both the IST Pump and IST

Valve Coordinators, various aspects of the IST program implementation.

Also reviewed were Pump Operability Test Summary Sheets, Cold Shutdown

and Refueling Test Lists, Valve Test Summary Sheets, Valve Trend Analysis

Sheets, etc.

The inspector found these records being maintained and

up-do-date.

6.0 Exit Interview

The inspector met with licensee representatives on June 5, 1987, to

summarize the scope and findings of the inspection.

At no time during the inspection was written material provided to the

licensee by the inspectors.

The licensee did not indicate that any

proprietary information was contained within the scope of this

inspection.

.

_ , _ _ , . , _ _ , _ _ , _ _

_ , _ _ - - - - - _

_

_

- _ _ - - _ _ -

_-

. _ _ .

~

.

..:

i

-

]

.

1

-

Attachment 1

]

i

Documents Reviewed

]

Administrative Procedure 112.1, Technical Specification Supporting

Installed Instrumentation, Rev. 24.

Ad.ninistrative Procedure 116, Surveillance Test Program, Rev. 26.

'

Administrative Procedure 104, Control of Nonconformances and Corrective

,

l

Action, Rev. 10.

Inservice Testing Program Submittal, Rev.,~5, March 12, 1987.

'

Administrative Procedure 108, Equipment Control, Rev. 37.

i

Gilbert Commonwealth " Review of Oyster Creek Pump and Valve Test

Program", August 11, 1986.

i

QA Audit S-0C-86-08.

Standing Order 36, Rev. 2.

QA Monitoring Effectiveness Evaluation, January,1987.

Temporary Change Notice Procedure Book 'and Index.

,

Safety Evaluation Report (Interim Report), Pump and Valve Inservice

..

Testing Program, Oyster Creek Nuclear Generating Station, April, 1982.

Reactor Building Closed Cooling Water System Valve Test, Pro'cedure No.

642.4.002, Rev. 5.

Containment Spray and ESW IST, Procedure No. 607.4.003, Rev. 14.

CR0 Pump Operability Test, Procedure No. 617.4.001, Rev. 10.

I

Shutdown Cooling Valve Operability and IST Valve Test, Procedure No.

I

613.4.002, Rev. 3, 4.

.i

Emergency Service Water Valve Operability Test Procedure No. 608.4.001,

!

Rev. 2.

Excess Flow Check Valves Functional Test, Procedure No. 604.3.008.

j

,

!

}

Control Rod Scram Insertion Time Test and Valve IST Test, Procedure No.

I

L

617.4.003, Rev. 8.

!

..