Proposed Tech Specs,Increasing Storage Capacity of Spent Fuel Racks.Evaluation of Significant Hazards Consideration EnclML20214P039 |
Person / Time |
---|
Site: |
Byron |
---|
Issue date: |
09/03/1986 |
---|
From: |
COMMONWEALTH EDISON CO. |
---|
To: |
|
---|
Shared Package |
---|
ML20214P037 |
List: |
---|
References |
---|
2058K, NUDOCS 8609170233 |
Download: ML20214P039 (5) |
|
Similar Documents at Byron |
---|
Category:TECHNICAL SPECIFICATIONS
MONTHYEARML20209B7411999-06-30030 June 1999 Proposed Tech Specs Section 3.8.5, DC Sources - Shutdown, Correcting LCO & Braidwood TS Section 3.8, Electrical Power Systems, Deleting Various References to At&T Batteries ML20204H9781999-03-23023 March 1999 Proposed Tech Specs,Revising Sections 3.7.15,3.7.16,4.3.1 & 4.3.3 to Support Installation of New Boral high-density SFP Storage Racks at Byron & Braidwood Stations ML20204H4291999-03-22022 March 1999 Proposed Tech Specs 3.9.3,allowing Use of Gamma-Metrics post-accident Neutron Monitors to Provide Neutron Flux Info During Operational Mode 6 ML20198N2041998-12-29029 December 1998 Revised Tech Specs Change,Page 3/4 3-54,providing Early Implementation of Containment Floor Drain Sump Water Level Instrumentation Requirements ML20198N3471998-12-29029 December 1998 Proposed ITS Tables 3.3.1-1 & 3.3.2-1,revising Twelve Allowable Values ML20198A0811998-12-14014 December 1998 Proposed Rev T to Improved Tech Specs Section 3.4, Reactor Coolant Sys ML20196G6611998-11-30030 November 1998 Proposed Rev to Improved Tech Specs Section 3.1 ML20155J2051998-11-0505 November 1998 Proposed TS Converting to Its,Rev R ML20155J0041998-10-30030 October 1998 Proposed Tech Specs Section 5.6.2, Fuel Storage Drainage, to Identify Sf Pool Level Sufficient to Ensure SRP Acceptance Criteria ML20154S5011998-10-18018 October 1998 Proposed Rev N to Improved TS Section 3.7 ML20154M5281998-10-15015 October 1998 Revisions K,O & P of 961213 ITS Submittal ML20154A8881998-10-0202 October 1998 Proposed Rev L to Improved Tech Specs Section 3.8 Closeout ML20153G4331998-09-25025 September 1998 Revs J & M to Tech Specs Sections 3.6 & 5.0,converting to Improved Tech Specs (Its),Final Closeout Package ML20236W5851998-07-31031 July 1998 Proposed Rev G to Sections 3.1 & 3.2 of Improved Tech Specs ML20237B6391998-07-30030 July 1998 Proposed Rev H to Section 3.5 of Improved Tech Specs ML20237E9971998-07-21021 July 1998 Rev I to Proposed Improved Tss,Section 3.9 Re Final Closeout ML20237B7021998-07-0909 July 1998 Proposed Improved TS (ITS) Section 3.3 Issued as Result of Removing Generic Change Traveler TSTF-135,Rev E from ITS Submittal ML20236H6531998-07-0202 July 1998 Rev F to 961213 Improved TS Submittal,Containing Final Package Closeout for Improved TS Sections 1.0,2.0 & 3.0 ML20248M1491998-06-0101 June 1998 Proposed Tech Specs Bases Page B 3.8-58b,converting to Improved Tech Specs ML20248C5511998-05-29029 May 1998 Proposed Tech Specs Bases Section 3/4.4.4, Relief Valves, Specifically Crediting Automatic Function of PORVs to Provide Mitigation for Inadvertent Operation of ECCS at Power Accident ML20216D9431998-04-0909 April 1998 Modified Proposed TS Pages Re 980324 Request for Amends to Licenses NPF-37 & NPF-66 ML20217E1891998-03-24024 March 1998 Proposed Tech Specs Surveillance Sections & Bases Allowing Util to Defer 10CFR50,App J,Type a Testing of Byron Unit 2 Containment Until Next Refuel Outage in 1999 ML20217B2681998-02-14014 February 1998 Proposed Rev D to ITS ML20198C3181997-12-30030 December 1997 Proposed Tech Specs 3.7.1.3 Re Condensate Storage Tank ML20203M5921997-12-17017 December 1997 Proposed Tech Specs,Rev C Changes Improved TSs 3.0,3.3,3.7, 3.8 & 5.0 as Result of Removing Generic Change Traveler TSTF-115 from Improved TS Submittal ML20203D0361997-12-0909 December 1997 Proposed Tech Specs Pages Correcting Errors Discovered in Current TS W/Regards to Total RCS Volume & Correction to Increase in RCS Volume Associated W/Unit 1 Replacement SGs Accounting for Hot Conditions ML20199A4751997-11-0707 November 1997 Proposed Tech Specs Pages Revising TS Surveillance Sections 4.6.1.1.c,4.6.1.2.a,4.6.1.2.c & Bases to Allow Performance of 10CFR50 App J,Type a Testing ML20217K4461997-10-21021 October 1997 Proposed Tech Specs Re Boron Credit in SFP ML20202F4561997-10-10010 October 1997 Proposed Tech Specs,Deleting Lower Flow Rate Requirement Associated W/Nonaccessible Area Exhaust Filter Plenum & Fuel Handling Bldg Ventilation Sys ML20211D9421997-09-24024 September 1997 Proposed Tech Specs Revising Allowable Time Interval for Performing Turbine Throttle Valve & Turbine Valve SRs Requirements from Monthly to Quarterly ML20216G8541997-09-0808 September 1997 Proposed Tech Specs Change to TS 4.5.2.b & Associated Bases Bringing Byron Unit 1 & Braidwood Unit 1 Requirement in Conformance W/Unit 2 Requirements Approved by NRC in ML20217H6071997-08-0707 August 1997 Proposed Tech Specs Pages,Revising Bases for Proposed Improved TS SR 3.8.6.1 & 3.8.6.3,to Indicate That Correction for Level Is Not Required When Battery Charging Current Is Less than 2 Amps for Gould & Less than 3 Amps for C&D ML20148P7721997-06-30030 June 1997 Proposed Tech Specs,Revising TS 3.9.11,5.6.1.1 & 6.9.10 to Allow Util to Permanently Take Credit for Soluble B in Spent Fuel Storage Pool Water to Maintain Acceptable Margin of Subcriticality ML20141F3081997-06-24024 June 1997 Proposed Tech Specs,Changing TS for ECCS Venting ML20141B7781997-06-17017 June 1997 Proposed Tech Specs Revising TS Sections 3/4.6.1.6,4.6.1.2, 6.8.4 & 6.9.1.11 to Support New Requirements in 10CFR50.55a, Which Requires Utils to Update Existing Containment Vessel Structural Integrity Programs ML20148J3231997-06-0909 June 1997 Proposed TS Reflecting Latest Rev of Waste Gas Decay Tank Rupture Accident Dose Calculation ML20140D0081997-05-31031 May 1997 Proposed Tech Specs,Revising TS Surveillance Requirement Re ECCS Pump Casings & Discharge Piping High Points Outside of Containment ML20141K8991997-05-24024 May 1997 Proposed Tech Specs Revising TS Surveillance Requirement 4.5.2.b to Encompass non-operating ECCS Pumps & Discharge Piping Which Are Provided W/High Point Vent Valves ML20141K3381997-05-23023 May 1997 Proposed Tech Specs Requesting Enforcement Discretion from Compliance W/Ts 4.5.2.b.1 Requirements of Venting of Emergency Core Cooling Sys Pump Casings & Discharge Piping High Points Outside of Containment ML20141K0011997-05-21021 May 1997 Proposed Tech Specs Relocating Reactor Vessel Surveillance Program Capsule Withdrawal Schedules IAW GL 91-01 ML20148B6151997-05-0606 May 1997 Proposed Tech Specs,Revising TS 3/4.7.5, Ultimate Heat Sink & Associated Bases to Support SG Replacement & Incorporate Recent UHS Design Evaluations ML20196G0501997-04-25025 April 1997 Proposed Tech Specs Revising Primary Containment & Reactor Coolant Sys Volume Associated W/Unit 1 Steam Generator Replacement ML20137S5341997-04-0707 April 1997 Proposed Tech Specs 3/4.8.2 Re D.C. Sources ML20137P0081997-03-24024 March 1997 Proposed Tech Specs Removing Values of cycle-specific Core Operating Limits from TS & Relocating Values to Operating Limits Rept ML20137C6381997-03-14014 March 1997 Proposed Tech Specs,Reducing Allowable Unit 1 RCS Dose Equivalent I-131 from 0.35 Uci/Gram to 0.20 Uci/Gram for Remainder of Cycle 8 ML20137C7991997-03-14014 March 1997 Proposed Tech Specs Deleting 12 License Conditions from Unit 1 Operating License & Two License Conditions from Unit 2 Operating License ML20135E6851997-02-28028 February 1997 Proposed Tech Specs,Replacing Original W D4 SG at Byron & Braidwood W/B&W International SGs ML20136G1461997-02-24024 February 1997 Proposed Tech Specs,Reflecting Conversion to Improved TS to Be Consistent w/NUREG-1431 ML20138N6841997-02-24024 February 1997 Proposed Tech Specs Changing TS from Current TS to Improved TS Consistent w/NUREG-1431,Rev 1, STS - W Plants, Dtd Apr 1995 ML20134N8481997-02-18018 February 1997 Proposed Tech Specs Table 2.2-1 & Table 3.3-4 Re Sys Instrumentation Trip Setpoints,Ts 3.4.1.2 Re Reactor Coolant Sys & TS 4.4.1.2.1 Re Surveillance Requirements 1999-06-30
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML20209B7411999-06-30030 June 1999 Proposed Tech Specs Section 3.8.5, DC Sources - Shutdown, Correcting LCO & Braidwood TS Section 3.8, Electrical Power Systems, Deleting Various References to At&T Batteries ML20211C3311999-04-30030 April 1999 Rev 2.0 to Generic ODCM for Dresden,Quad Cities,Zion, Lasalle,Byron & Braidwood ML20204H9781999-03-23023 March 1999 Proposed Tech Specs,Revising Sections 3.7.15,3.7.16,4.3.1 & 4.3.3 to Support Installation of New Boral high-density SFP Storage Racks at Byron & Braidwood Stations ML20204H4291999-03-22022 March 1999 Proposed Tech Specs 3.9.3,allowing Use of Gamma-Metrics post-accident Neutron Monitors to Provide Neutron Flux Info During Operational Mode 6 ML20202G9361999-01-30030 January 1999 Rev 1.4 to Chapter 10, Radioactive Effluent Treatment & Monitoring, Rev 1.6 to Chapter 11, Radiological Environ Program & Rev 1.6 to Chapter 12, Radioactive Effluent Technical Standards (Rets), for Odcm,Byron Annex ML20198N3471998-12-29029 December 1998 Proposed ITS Tables 3.3.1-1 & 3.3.2-1,revising Twelve Allowable Values ML20198N2041998-12-29029 December 1998 Revised Tech Specs Change,Page 3/4 3-54,providing Early Implementation of Containment Floor Drain Sump Water Level Instrumentation Requirements ML20198A0811998-12-14014 December 1998 Proposed Rev T to Improved Tech Specs Section 3.4, Reactor Coolant Sys ML20196G6611998-11-30030 November 1998 Proposed Rev to Improved Tech Specs Section 3.1 ML20155J2051998-11-0505 November 1998 Proposed TS Converting to Its,Rev R ML20155J0041998-10-30030 October 1998 Proposed Tech Specs Section 5.6.2, Fuel Storage Drainage, to Identify Sf Pool Level Sufficient to Ensure SRP Acceptance Criteria ML20154S5011998-10-18018 October 1998 Proposed Rev N to Improved TS Section 3.7 ML20154M5281998-10-15015 October 1998 Revisions K,O & P of 961213 ITS Submittal ML20154A8881998-10-0202 October 1998 Proposed Rev L to Improved Tech Specs Section 3.8 Closeout ML20153G4331998-09-25025 September 1998 Revs J & M to Tech Specs Sections 3.6 & 5.0,converting to Improved Tech Specs (Its),Final Closeout Package ML20236W5851998-07-31031 July 1998 Proposed Rev G to Sections 3.1 & 3.2 of Improved Tech Specs ML20237B6391998-07-30030 July 1998 Proposed Rev H to Section 3.5 of Improved Tech Specs ML20237E9971998-07-21021 July 1998 Rev I to Proposed Improved Tss,Section 3.9 Re Final Closeout ML20237B7021998-07-0909 July 1998 Proposed Improved TS (ITS) Section 3.3 Issued as Result of Removing Generic Change Traveler TSTF-135,Rev E from ITS Submittal ML20236H6531998-07-0202 July 1998 Rev F to 961213 Improved TS Submittal,Containing Final Package Closeout for Improved TS Sections 1.0,2.0 & 3.0 ML20248M1491998-06-0101 June 1998 Proposed Tech Specs Bases Page B 3.8-58b,converting to Improved Tech Specs ML20248K7361998-05-31031 May 1998 Commonwealth Edison Bnps Unit 1 Cycle 9 Startup Rept ML20248C5511998-05-29029 May 1998 Proposed Tech Specs Bases Section 3/4.4.4, Relief Valves, Specifically Crediting Automatic Function of PORVs to Provide Mitigation for Inadvertent Operation of ECCS at Power Accident ML20217Q8521998-05-0101 May 1998 Rev 9 to Bzp 310-2, Nuclear Accident Reporting Sys Form (Primary Responsibility - Station Director). W/Notes & Comments ML20216D9431998-04-0909 April 1998 Modified Proposed TS Pages Re 980324 Request for Amends to Licenses NPF-37 & NPF-66 ML20217E1891998-03-24024 March 1998 Proposed Tech Specs Surveillance Sections & Bases Allowing Util to Defer 10CFR50,App J,Type a Testing of Byron Unit 2 Containment Until Next Refuel Outage in 1999 ML20217B2681998-02-14014 February 1998 Proposed Rev D to ITS ML20199J7581997-12-31031 December 1997 Rev 1 to IST Plan Pumps & Valves Byron Nuclear Generating Station,Units 1 & 2 ML20198C3181997-12-30030 December 1997 Proposed Tech Specs 3.7.1.3 Re Condensate Storage Tank ML20203M5921997-12-17017 December 1997 Proposed Tech Specs,Rev C Changes Improved TSs 3.0,3.3,3.7, 3.8 & 5.0 as Result of Removing Generic Change Traveler TSTF-115 from Improved TS Submittal ML20203D0361997-12-0909 December 1997 Proposed Tech Specs Pages Correcting Errors Discovered in Current TS W/Regards to Total RCS Volume & Correction to Increase in RCS Volume Associated W/Unit 1 Replacement SGs Accounting for Hot Conditions ML20199A4751997-11-0707 November 1997 Proposed Tech Specs Pages Revising TS Surveillance Sections 4.6.1.1.c,4.6.1.2.a,4.6.1.2.c & Bases to Allow Performance of 10CFR50 App J,Type a Testing ML20216H8241997-10-31031 October 1997 Revs to OCDM for Byron Station,Including Rev 1.3 to Chapter 10,rev 1.5 to Chapters 11 & 12 & Rev 1.3 to App F ML20198M2621997-10-31031 October 1997 Revs to Offsite Dose Calculation Manual,Consisting of Rev 1.5 to Chapter 11 & Rev 1.5 to Chapter 12 ML20217K4461997-10-21021 October 1997 Proposed Tech Specs Re Boron Credit in SFP ML20202F4561997-10-10010 October 1997 Proposed Tech Specs,Deleting Lower Flow Rate Requirement Associated W/Nonaccessible Area Exhaust Filter Plenum & Fuel Handling Bldg Ventilation Sys ML20211D9421997-09-24024 September 1997 Proposed Tech Specs Revising Allowable Time Interval for Performing Turbine Throttle Valve & Turbine Valve SRs Requirements from Monthly to Quarterly ML20216G8541997-09-0808 September 1997 Proposed Tech Specs Change to TS 4.5.2.b & Associated Bases Bringing Byron Unit 1 & Braidwood Unit 1 Requirement in Conformance W/Unit 2 Requirements Approved by NRC in ML20217H6071997-08-0707 August 1997 Proposed Tech Specs Pages,Revising Bases for Proposed Improved TS SR 3.8.6.1 & 3.8.6.3,to Indicate That Correction for Level Is Not Required When Battery Charging Current Is Less than 2 Amps for Gould & Less than 3 Amps for C&D ML20148P7721997-06-30030 June 1997 Proposed Tech Specs,Revising TS 3.9.11,5.6.1.1 & 6.9.10 to Allow Util to Permanently Take Credit for Soluble B in Spent Fuel Storage Pool Water to Maintain Acceptable Margin of Subcriticality ML20141F3081997-06-24024 June 1997 Proposed Tech Specs,Changing TS for ECCS Venting ML20141B7781997-06-17017 June 1997 Proposed Tech Specs Revising TS Sections 3/4.6.1.6,4.6.1.2, 6.8.4 & 6.9.1.11 to Support New Requirements in 10CFR50.55a, Which Requires Utils to Update Existing Containment Vessel Structural Integrity Programs ML20148J3231997-06-0909 June 1997 Proposed TS Reflecting Latest Rev of Waste Gas Decay Tank Rupture Accident Dose Calculation ML20140D0081997-05-31031 May 1997 Proposed Tech Specs,Revising TS Surveillance Requirement Re ECCS Pump Casings & Discharge Piping High Points Outside of Containment ML20141K8991997-05-24024 May 1997 Proposed Tech Specs Revising TS Surveillance Requirement 4.5.2.b to Encompass non-operating ECCS Pumps & Discharge Piping Which Are Provided W/High Point Vent Valves ML20141K3381997-05-23023 May 1997 Proposed Tech Specs Requesting Enforcement Discretion from Compliance W/Ts 4.5.2.b.1 Requirements of Venting of Emergency Core Cooling Sys Pump Casings & Discharge Piping High Points Outside of Containment ML20141K0011997-05-21021 May 1997 Proposed Tech Specs Relocating Reactor Vessel Surveillance Program Capsule Withdrawal Schedules IAW GL 91-01 ML20148B6151997-05-0606 May 1997 Proposed Tech Specs,Revising TS 3/4.7.5, Ultimate Heat Sink & Associated Bases to Support SG Replacement & Incorporate Recent UHS Design Evaluations ML20196G0501997-04-25025 April 1997 Proposed Tech Specs Revising Primary Containment & Reactor Coolant Sys Volume Associated W/Unit 1 Steam Generator Replacement ML20137S5341997-04-0707 April 1997 Proposed Tech Specs 3/4.8.2 Re D.C. Sources 1999-06-30
[Table view] |
Text
_
- DESIGN FEATURES 5.6 FUEL STORAGE CRITICALITY
- 5. 6.1.1 The spent fuel storage racks are designed and shall be maintained with:
- a. k,ff equivalent to less than or equal to 0.95 when flooded with unborated water, which includes a conservative allowance =8"9=99E l MIU!K for uncertainties ' ' - ' " " "
and
- b. m
^
A nominal 14 inch center-to-center distance between fuel assemblies placed in the storage racks.
~
5.6.1.2 The k,7f for new fuel for the first core loading stored dry in the spent fuel storage racks shall not exceed 0.98 when aqueous foam moderation is assumed. .
DRAINAGE 5.6.2 The spent fuel storage pool is designed and shall be maintained to prevent inadvertent draining of the pool below elevation 423 feet.2 inches.
^
CAPACITY .
5.6.3 The spent fuel storage pool is designed and shall be maintained with a storage capacity limited to no more than 198( fuel assemblies.
29Yo 5.7 COMPONENT CYCLIC OR TRANSIENT LIMIT 5.7.1 The components identified in Table 5.7-1 are designed and shall be maintained within the cyclic or transient limits of Table 5.7-1. .
A nominal 10.32 inch north-south and 10.42 inch east-west, center-to-center distance between fuel assemblies placed in Region 1 spent fuel storage racks and a nominal 9.011 inch center-to-center distance between fuel assemblies placed in Region'2 spent fuel storage racks.
8609170233 860903 .
PDR ADOCK 05000454 p PDR BYRON - UNITS 1 & 2 5-5
c-3 ATTAQ9 EDIT B LICENSING REPORT l
l i
I 2058K 1
i
3 ATTAQ94NT C EVALUATION OF SIGNIFICANT HAZARDS CONSIDERATIONS Commonwealth Edison has evaluated this proposed amendment and determined that it involves no significant hazards considerations.
According to 10 CFR 50.92(c), a proposed amendment to an operating license involves no significant hazards considerations if operation of the facility in accordance with the proposed amendment would not:
(1) Involve a significant increase in the probability or consequences of an accident previously evaluated; or (2) Create the possibility of a new or different kind of accident from any accident previously evaluated; or (3) Involve a significant reduction in a margin of safety.
The proposed amendment involves the replacement of the present spent fuel racks with high density racks. This will increase the spent fuel storage capacity at Byron Station from 1060 to 2940 fuel assemblies including six locations for failed fuel storage.
Accidents previously evaluated for radiological consequences are a spent fuel assembly drop onto the spent fuel pit floor and a spent fuel cask drop. Abnormal conditions which have been previously evaluated with respect to potential for criticality are (1) a dropped fuel assembly laying across the top of a fuel rack and (2) a fuel assembly in transport accidently dropped into a position parallel with stored fuel in the most reactive corner of the racks. The effect of a seismic event was also evaluated with respect to potential for criticality.
i All of these events could occur independent of the design and installed configuration of the spent fuel racks. As a result, the probabi-l lity of these events occurring is not affected by replacement of the spent l fuel racks.
l The consequences of the previously evaluated events have been evaluated considering the new spent fuel racks. Our review has concluded
, that the criticality acceptance criterion of maintaining K egg less than or
} equal to 0.95 will not be exceeded for these events.
L
7 The radiological consequences were also evaluated to determine the impact on offsite and onsite doses previously determined. The increase in the storage capacity of the spent fuel pool will neither significantly alter the operating characteristics of the current spent fuel pool nor result in a measurable change in impact on the environment. The design basis fuel handling accidents, described in FSAR Section 15.7.4, were reviewed for possible effects on radiological dose consequences. The review determined that the conclusions in the PSAR will remain valid and that offsite radiological dose consequences will remain within 10 CFR 100 limits. As a result, the consequences of previously ewaluated events will not significantly increase as a result of replacing the spent fuel racks.
With respect to the second standard of 10 CFR 50.92(c), the new spent fuel racks only allow closer spacing of the fuel assemblies. No new 1 or different kind of accidents result from this.
I Although the new spent fuel racks contain two storage regions, the placement of a fuel assembly in the wrong region is not a different kind of accident from the placement of a fuel assembly parallel to stored fuel in the most reactive corner among the current spent fuel racks. Both of these accidents fall within the category of abnormal placement of a fuel
-assembly. For these reasons, the replacement of the spent fuel racks does not create the possibility of a new or different kind of accident from any accidents previously evaluated.
Installation of the new spent fuel racks will not result in a significant reduction in a margin of safety as contemplated by the third standard of 10 CFR 50.92(c). A small increase in the spent fuel pool heat load is expected due to the storage capacity expansion. However, the spent fuel pool cooling system design can handle the increased heat load and maintain the temperature peaks of the pool below design values. Installation of the new spent fuel racks will also result in a small increase in the pool reactivity as measured by the neutron multiplication factor (K gg).
e However, the maximum neutron multiplication factor will be maintained less than or equal to 0.95. For these reasons, increasing the spent fuel pool storage capacity will not significantly reduce a margin of safety.
The NRC has provided guidance concerning the application of the
- standards of 10 CFR.50.92(c) for determining whether significant hazards i considerations exist by providing examples (48 FR 14870 and 51 FR 7751) of amendments that are considered not likely to involve significant hazards considerations. Example (x) relates to an expansion of the storage capacity of a spent fuel pool when all of the following are satisfied
(1) The storage expansion method consists of either replacing existing racks with a design which allows closer spacing between stored spent fuel assemblies or placing additional racks of the original design on the pool floor if space permits, l
l 1
i
T (2) The storage expansion method does not involve rod consolidation or double tiering, (3) The K,gg of the pool is maintained less than or equal to 0.95, and (4) No new technology or unproven technology is utilized in either the construction or the analytical techniques necessary to justify the expansion.
The proposed reracking of Byron Station will replace the existing racks with'a design which allows closer spacing between stored spent fuel assemblies and does not involve rod consolidation or double tiering. The K,gg will be maintained less than or equal to 0.95. Similar analyses and construction techniques have been used previously for plants that have licensed high density spent fuel racks. These plants include Fermi 2, Quad Cities 1 and 2, Rancho Seco, Oyster Creek, Virgil C. Summer, and Diablo Canyon 1 and 2. Therefore, no new technology or unproven technology has been utilized in this case.
Por all the reasons stated above, Commonwealth Edison believes the proposed installation of high density spent fuel racks does not involve any significant hazards considerations.
2058K