ML20214M751

From kanterella
Jump to navigation Jump to search
Insp Repts 50-424/87-27 & 50-425/87-27 on 870310-0417. Violations Noted:Failure to Implement Procedure for Placing Auxiliary Feedwater Sys in Standby Readiness & to Establish Procedure to Determine & Evaluate Unidentified Leakage
ML20214M751
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 05/08/1987
From: Livermore H, Rogge J, Schepens R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20214M717 List:
References
50-424-87-27, 50-425-87-27, NUDOCS 8706010418
Download: ML20214M751 (27)


See also: IR 05000424/1987027

Text

.

,

.

- - - _ - - , . ~

-

.

. e(

)

-

'

- .

,

__

  • /uGg

UN'ITED STATES

-

'

NUCLEAR R,EGULATORY COMMISSION

-

-

o.

[

- REGION li

p

'

g,

j

101 MARIETTA STREET.N.W.

ATLANTA, GEORGI A 30323

9 + . . . . [6

'

.

4

s

,

.:

-

-.

,

Report Nos.: ~50-424/87-27 and 50-425/87-12

e

, '

i

-

.

-

~

.

.

.

_ - .. ,

Licensee: Georgia Power Company ? .

2

u

-

'

P.O.-Box 4545

~

' '

'

'

4

'

'

'

. 4

.# . , _

.

(

Atlanta, GA 30302

(

,

,

,

,

Docket Nos.:

50-424 and 50-425

i

. License Nos.': NPF-68,and~CPPR-109

-

,

Facility Name: Vogtle 1 and 2

u

,

Inspection Conducted: March 10 - April'17, 1987,

, , .

Inspectors:

e MM U

[ TF~ 7 _

H. H. Livermore, Senior Resident Inspector,

Date Signed

e

Construction

Wff

LLaurr_ <<

-

ST & - J'

)

a

-J. F. Rogge, Senior Resident Inspector,

Date Signed

Operations

&W vt. "

SI 6'- 7

. /#1

R. J..Schepens, Resident Inspector,

.Date Signed

0perations-

Accompanying Personnel: .C. Burger, Resident--Inspector, Operations

-Approved By: YM

wuu w-

f- k- 7 -

M. V. Sinkule,'Section Chief

Date. Signed

^

Division of Reactor Projects

SUMMARY

Scope: This routine, unannounced inspection entailed Resident Inspection in

the .following areas:

plant operations, radiological controls, maintenance,.

surveillance, fire protection, . security, outage activities, containment and

safety _ related . structures, piping systems and supports, safety ' related '

components,

auxiliary

systems,

electrical

equipment-

and

cables,+

instrumentation, startup test program, and quality programs and administrative

controls affecting quality.

Results: Two violations were identified in the area of Plant Operations. A

,

failure to- implement the procedure for placing the AFW System in standby

readiness and a failure to establish an appropriate procedure to determine and

_

evaluate unidentified leakage.

_ s

,

Q 60 g h [500 [

x

G

.

y

)

--e

'

v-

ge

-

g

--

gii

7

wb

wrw..4

f'T.iT-h----y

w+r--?-+=

e--.

w-rP-F'T--*+

T

--

'1

e

$

f

-

e+=-$r---a"

E- ~

-

...

..

..

REPORT DETAILS

-1.

Persons Contacted

L

Licensee Employees

P. D. Rice, Vice-President, Vogtle Project Director

R. H. Pinson, Vice-President, Project Construction

C. W. Whitney, General Manager, Project Support

  • G. Bockhold, Jr., General Manager Nuclear Operations
  • E. M. Dannemiller, Technical Assistant to General Manager
  • T. V. Greene, Plant Manager

R. M. Bellamy, Plant Support Manager

C. W. Hayes, Vogtle Quality Assurance Manager

  • C. E. Belflower, Quality Assurance Site Manager - Operations

E. D. Groover, Quality Assurance Site Manager - Construction

  • W. E. Mundy, Quality Assurance Audit Supervisor

D. M. Fiquett, Project Construction Manager - Unit 2

G. A. McCarley, Project Compliance Coordinator

W. C. Gabbard, Regulatory Specialist

  • C. L. Cross, Senior Regulatory Specialist

C. F. Meyer, Operations Superintendent

R. M. Odom, Regulatory Compliance Supervisor

C. L. Coursey, Maintenance Superintendent (Startup)

M. A. Griffis, Maintenance Superintendent

G. R. Frederick, Quality Assurance Engineer / Support Supervisor

' *J. F. D' Amico, Nuclear Safety & Compliance Manager

W. F. Kitchens, Manager Operations

V. J. Agro, Superintendent Administration

A. L. Mosbaugh, Assistant Plant Support Manager

M. P. Craven, Nuclear Security Manager

  • J. E. Swartzwelder, Deputy Manager - Operations
  • W. E. Burns, Nuclear Licensing Manager

Other licensee employees contacted included craftsmen, technicians,

supervision, engineers, operations, maintenance, chemistry, inspectors,

and office personnel.

Other Organizations

H. M. Handfinger, Asst. Plant Support Manager - Bechtel

  • Attended Exit Interview

2.

Exit Interviews - Units 1 & 2-(30703) (30703C)

The inspection scope and findings were summarized on April 3,

and

April 16, with those persons indicated in paragraph 1 above.

The

inspector described the areas inspected and discussed in detail the

i

.

_

-

.

..

..

2

inspection results.

No dissenting comments were received from the

licensee.

The licensee did not identify as proprietary any of the

materials provided to or reviewed by the inspector during this inspection.

Region based NRC exit interviews were attended during the inspection

period . by a resident inspector.

The items identified during this

inspection are:

a.

Violation 50-424/87-12-01, " Failure to Place the AFW System in

Standby Readiness" - Paragraph 5.a.

b.

Violation 50-424/87-12-02, " Fail ure to Establish An Appropriate

Procedure to Determine and Evaluate Unidentified Leakage" - Paragraph

5.b.(6).(a).

c.

Unresolved Item 50-424/87-12-03, "Reportability of CRVI Actuations As

a Result of the Chlorine Gas Monitors" - Paragraph 4.

d.

IFI 50-424/87-12-04, " Review Licensee's Progress Toward Synchronizing

the ERF and SOE Clocks." - Paragraph 5.b.(1).

3.

Licensee Action on Previous Enforcement Matters - Units 1 & 2 (92702)

Not inspected.

4.

Unresolved Items - Units 1 & 2 (92701)

Unresolved items are matters about which more information is required to

determine whether they are acceptable or may involve violations or

deviations.

One unresolved item identified during this inspection is

discussed in Paragraph 7.

5.

Operational Safety Verification - Unit 1 (71707) (93702)

The plant began this. inspection period in startup (Mode 2) conducting low

power physics tests. On March 15, the unit dropped rod J3 and was forced

to proceed to cold shutdown (Mode 5) to perform repairs. On March 17, the

unit commenced a return to Mode 2 which was achieved on March 18.

On

March 19, the reactor tripped due to a high positive power rate and

subsequently returned to Mode 2.

Between March 20 and March 23, the unit

experienced three reactor trips related to steam generator level control.

On March 23, at 9:03 P.M. power operation (Mode 1) was obtained for the

first time.

Between March 23 and April 8,

the unit experienced three

reactor trips.related to steam generator level control. On April 8, the

unit was tripped as part of the Remote Shutdown Panel Capability Test and

returned to Mode 1.

On April 10 the unit tripped due to a feedwater check

valve failure and subsequently returned to power. On April 11, the unit

tripped due to steam generator water level problems. A unit outage was

conducted from April 11 through April 14. On April 14, the unit returned

to Mode 1 operation.

During the inspection period a total of ten (10)

_ _ _ _

o

'

-

.

..

..

3

ESFAS Actuations occurred as follows: Five (5) Auxiliary Feedwater System

Actuations of which four (4) were related to tuning problems with the

bypass and main feed reg valves and the steam dump valves and one (1) was

as a result of a procedure error when I&C personnel were installing a

monitoring Jack; four (4) control room ventilation isolations of which

three (3) were as a result of an intake radiogas monitor (1RE-12116) and~

one (1) as a result of the Train

"B"

chlorine gas monitor; and one

(1) fuel handling building isolation as a result of an effluent radiogas

monitor (IRE-2532B). At the end of the inspection period the unit was

performing startup testing at the 50% power plateau.

a.

Control Room Activities

Control Room tours and observations were performed. to verify that

facility operations were being safely conducted within regulatory

requirements.

These inspections consisted of one or more of the

following attributes as appropriate at the time of the inspection.

Proper Control Room staffing

-

-

Control Room access and operator behavior

-

Adherence to approved procedures for activities in progress

-

Adherence to Technical Specification (TS) Limiting Conditions

for Operations (LCO)

-

Observance of instruments and recorder traces of safety related

and important to safety systems for abnormalities

Review of annunciators alarmed and action in progress to correct

-

same.

-

Control Board walkdowns

-

Safety parameter display and the plant safety monitoring system

operability status

-

Discussions and interviews with the On-Shift Operations

Supervisor, Shift Supervisor, Reactor Operators, and the Shift

Technical Advisor to determine the plant status, plans and

assess operator knowledge

Review of the operator logs, unit log and shift turnover sheets

-

Additional inspections conducted consisted of an in-depth review of

the following safety-related clearances:

1-87-998 CCW #1 Train A

1-87-899 Accumulator Isolation Valve Breakers

During an NRC walkdown of the Main Control Board on April 2,1987,

the turbine driven auxiliary feedwater pump speed controller

(PDIC-5180A) was noted to be in the manual in lieu of the required

auto position. Upon notification by the NRC Resident, the licensee

took immediate corrective action to place the controller in the auto

position and completed the required Independent Verification Sheet.

_ __ -

- -_

-

.

..

..

4

The inspector notes that while immediate action was taken to place

the identified mispositioned controller in its correct position, no

action was taken by the licensee to complete independent verification

(IV) sheets for other equipment which had not been previously

documented on IV sheets.

The inspector brought this to the

licensee's attention and IV sheets were to be completed to verify AFW

~

standby readiness. The unit was in Mode 1 power operation at the

time of the discovery.

The inspector conducted further inspection into this matter to

determine if the licensee was in compliance with Techpical

Specification LCO 3.7.1.2.

A review of the completed unit o'perating

procedures (U0P's) (12004-1), the completed independent verification

sheets for placing the auxiliary feedwater system in standby

readiness per system operating procedure (SOP) 13610-1, and the

completed TDAFW pump operability tests per surveillance procedure

14546-1 was performed to determine when the TDAFW pump was last

operated and properly restored to standby readiness.

The inspector

determined that the TDAFW pump was last operated on March 28, 1987,

during the loss of offsite power (LOSP) startup test as documented in

the unit control log and was subsequently secured at 1002 (CST) the

same day.

When securing the TDAFW pump the speed controller is

placed in the manual position and reduced to 15-20% to reduce turbine

speed to 1500-1550 RPM, then the steam supply isolation valve is

closed and the pump is aligned for standby readiness if the unit is

in Modes 1, 2, or 3 per S0P 13610-1. After the LOSP test the unit

was in Mode 3.

The unit then went critical on March 29, 1987, at

0958 (CST) and subsequently entered Mode 1 on March 30, 1987, at 0338

(CST).

During this review the inspector noted that independent

verification sheets which document that certain components are

positioned and then independently verified to be correct had not been

performed for either of the above two evolutions when the TDAFW was

initially secured and then later when Mode 1 was entered as required

by the applicable S0P 13610-1 and UDP 12004-1.

In addition, the

inspector noted that independent verification (IV) sheets had not

been performed for placing the AFW System (i.e. motor and turbine

driven pumps) in standby readiness for the following additional

evolutions:

Evolution Requiring IV of AFW

Date

Procedure

In Standby Readiness

3/20/87

SOP 13610-1

Securing TDAFW Pump

3/25/87

S0P 13610-1

Securing TDAFW Pump

3/25/87

UOP 12004-1

Entering Mode 1

3/27/87

U0P 12004-1

Entering Mode 1

A review was then conducted of the auxiliary feedwater startup test

procedure (1-5AL-01) results to determine the TDAFW pump ability to

supply feedwater to the steam generators with the speed controller in

the manual position and set at approximately 20%. The startup test

data reflected that with the speed controller in manual and set at

50% the turbine speed is 2700 RPM and the pump discharge pressure is

',

.

..

..

5

750 psig.

Therefore, the inspector concluded that the TDAFW pump

would not feed the steam generators which are at approximately

1000 psig.

This information was presentea to the licensee on

April 3, 1987.

The licensee's investigation into this matter revealed that with the

speed controller in manual with a 20*; demand signal that the pump

would have developed a discharge head of approximately 700 psig upon

start and that operator action would have been required to adjust the

speed control unit while in manual or place it in automatic during

response to an accident condition. Relative to the failure to place

the TDAFW pump in standby readiness the licensee determined that this

failure to comply with plant procedures was centered primarily around

one operating crew which has now been counselled as to the

seriousness of this situation and the importance to comply with plant

policy requirements.

Based on the above, the inspector concluded the following: The AFW

system was signed off in the unit control log and in the UOP 12004-1

as being placed in standby readiness on 3/30/87 at 0230 (CST).

Therefore, the maximum amount of time the TDAFW pump would be

considered inoperable based on the above signoffs is 75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> and 25

minutes.

Since TS LCO 3.7.1.2 action statement allows 78 hours9.027778e-4 days <br />0.0217 hours <br />1.289683e-4 weeks <br />2.9679e-5 months <br />

before the unit should be placed in hot standby it does not appear

that the time limit for complying with the TS action statement was

'

violated. However, it should be noted that since the IV sheets were

<

n'ot performed for placing the AFW standby readiness during the

securing of the TDAFW pump after the LOSP test the possibility exists

that the TDAFW pump could have been inoperable since March 28, 1987,

in which case TS LCO 3.7.1.2 action statement time limit would have

been exceeded.

Due to the failure to perform independent verification sheets for

placing the AFW system in standby readiness per S0P 13610-1 the

inspector concluded that TS 6.7.la which requires that written

procedures shall be implemented had been violated.

The foregoing is considered to be in violation of Technical Specification 6.7.la

and will

be

identified as Violation

50-424/87-12-01, " Failure to Place the AFW System in Standby

Readiness."

b.

Facility Activities

Facility tours and observations were performed to assess the

effectiveness of the administrative controls established by direct

observation of plant activities, interviews and discussions with

licensee personnel, independent verification of safety systems status

and LC0's, licensee meetings and facility records.

During these

inspections the following objectives are achieved:

..

.

..

..

6

(1) Safety

System Status (71710) - Confirmation of system

operability was obtained by verification that flowpath valve

alignment, control and power supply alignments, component

conditions, and support systems for the accessible. portions of

the ESF' trains were. proper.

The inaccessible portions' are

confirmed

as

availtbility permits.

Additional

in-depth

inspection of the auxiliary feedwater (AFW) system was performed

to review the_ system lineup procedure with the plant drawings

and as-built configurations, compare valve : remote and local

indications, walkdowns were expanded to include . hangers and

supports, and electrical equipment interiors.

The inspector

verified that the lineup was in accordance with license

requirements for system operability.

During the NRC walkdown of the AFW System Valve Lineup the

inspector questioned the installation of the splice boxes for

motor operator valves 1HV-5113 " Condensate Stor.ne Tank No.2

Supply to TDAFW Pump" and 1HV-5106 "TDAFW Pump Steam Supply

Isolation." A review was conducted of the following documents

to determine the installation requirements:

Document %

Title

X3AR01

Electrical Construction Specification

CX3DF001,

Conduit and Tray General Notes,

2, 3, & 6

Symbols and Details Shts 1 - 4

1X3DH7C4

Conduit Grounding Lighting &

Communications Plan - AFW Pumphouse -

Unit 1

AX2094V050,

Typical Conduit Support Details

51, 52, 53,

Shts 1

-7

54, 55, & 56

1X3D-BC-F02B

Elementary Diagram AFW IHV-5113

1X3D-BC-F02A

Elementary Diagram AFW 1HV-5106

ED-T-02

Raceway Installation

ED-T-08

Cable Termination

ICE 7C4RS119

EE 580 Card for 1HV- 5106

1CE7C4RL120

EE 580 Card for 1HV-5106

1CE7C4RL121

EE 580 Card for 1HV-5113

1CE7C4RS122

EE 580 Card for 1HV-5113

.

. - - _ _ - _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _

.

c-

.

.

. .

7

r

The inspector's concern relative to the installation of the

splice boxes for the subject valves was that they were not

anchored nor supported from a structure but rather were being

supported off of the conduit. Based on the inspector's review

of the above documents the inspector concluded that this was not

an acceptable installation without further engineering review to

ensure that it would meet seismic design criteria.

This

information was presented to the licensee on April 3, 1987.

A followup meeting with the licensee was conducted on April 15,

1987, where the licensee presented the following information to

the inspector.

The licensee had initiated Deficiency Card

No. 1-87-1060 to address the inspector's concern.

This

deficiency card documented the concern and provided engineering

justification consisting of a calculation which qualified the as

installed condition for a use as is disposition.

The above information was considered by the inspector for the

existence

of a violation against 10 CFR 50 Appendix B,

Criterion V.

In addition, the fact that the installed condition

was determined to be acceptable and that the inspector had not

identified any other examples of

improper splice box

installations was taken into consideration. Since the inspector

considers the above an isolated case with no safety significance

it was decided that a violation does not exist.

During the inspection period the inspector inquired about the

progress that was being made to coordinate the Emergency

Response Facility (ERF) computer and Sequence of Events (SOE)

clocks as a result of a deficiency noted in the preoperational

test program.

The inspector was informed that the engineering

request to add a circuit that would maintain the clocks

synchronized had been disapproved. The inspector addressed a

concern to the Plant Support Manager that, based on a human

factor's point of view, the manual correction of time errors

could affect the accuracy of a post event review. The inspector

obtained a commitment to re-review the issue and develop a

resolution either by an administrative program or hardware

change.

During the Remote Shutdown Test the inspector also

noted that the ERF computer time was approximately ten minutes

slower than the control room clock.

The Technical Support

Center was noted as having three clocks with different times.

While the inspector's concern was to synchronize the two clocks

(ERF and SOE) the licensee should develop a program to

synchronize all plant clocks. The following item is identified

to track this item IFI 50-424/87-27-04, " Review Licensee

Progress Toward Synchronizing the ERF and SOE Clocks."

Storage of material and

(2) Plant Housekeeping Conditions

-

components and cleanliness conditions of various

areas

!

,

.

. . . .

. . . . . . . ..

.____

-

.

.

..

..

8

throughout the facility were observed to determine whether

safety and/or fire hazards existed.

(3) Fire Protection - Fire protection activities, staffing and

equipment were observed to verify that fire brigade staffing was

appropriate and that fire alarms, extinguishing equipment,

actuating

controls,

fire

fighting

equipment,

emergency

equipment, and fire barriers were operable.

(4) Radiation Protection - Radiation Control Areas (RCAs) were

observed to verify proper identification and implementation. In

addition, an inspector attended the licensee's respiratory

protection training program which is conducted once a week at

the on-site training center.

The total program was observed

including all lessons, written test, subsequent fit testing and

actual respirator usage.

(5) Security - Security controls were observed to veri fy that

security barriers were intact, guard forces were on duty, and

access to the Protected Area (PA) was controlled in accordance

with the facility security plan.

Personnel within the PA were

observed to verify proper display of badges and that personnel

requiring escort were properly escorted. Personnel within vital

areas were observed to ensure proper authorization for the area.

One item of concern regarding the Badge Island was forwarded to

the Region II office. The inspection also included attendance

at the security meetings being held to improve security

hardware.

(6) Surveillance (61726)(61700) - Surveillance tests were observed

to verify that approved procedures were being used; qualified

personnel were conducting the tests; tests were adequate to

verify equipment operability; calibrated equipment was utilized;

and TS requirements were followed.

The inspectors observed

portions of the following surveillances and reviewed completed

data against acceptance criteria:

Surv. No.

Date

Title

14000

3/25/87

Mode 1 and 2 Shift and Daily

Surveillances

14915

3/25/87

Minimum Temperature for

Criticality - Data Sheet 1

14915

3/25/87

Control Rod Insertion Limits -

Data Sheet 5

24614-102-

4/1/87

Safety Features Sequencer Train B

3009

Analog Channel Operational Test

.

.

-

-

.

..

..

9

'(a)

Independent Measurement of RCS Leak Rates (61728)

This inspection was conducted to independently verify .that

operations procedure 14905-1, "RCS Leakage Calculation

(Inventory Balance)" demonstrated compliance with Technical

Specification LC0 3.4.6.2.

The inspection utilized the

RCSLK9 computer program contained in NUREG-1107.

During the inspection conducted on April 7 the surveillance

data for the licensee tests conducted on April 3 and

April 6,

1987, were reviewed.

From this review the

inspector noted that the licensee had calculated the

,

following results (Note: All values gpm)

1

Total

Test

Previous

Date

Leakage

Identified

Identified

Unidentified

Apr 3

2.61

0

6.2

-3.59

Apr 6

4.874

.327

6.2

-1.653

The NRC calculational results were:

Total

Test

Previous

Date

Leakage

Identified

Identified

Unidentified

Apr 3

2.83

0

6.2*

-3.37

Apr 6

4.48

.07

6.2*

-1.80

  • 6.2 gpm Previous Identified leakage is not calculated as

part of this test.

From the above data the inspector concluded that both GPC

and NRC were in close agreement with what the Total Leakage

should be,- however two concerns were generated. The first

concern pertained to the fact that Unidentified leakages

were being calculated as negative values.

The acceptance

criteria requires action when unidentified leakage exceeds

<1 gpm. Since the licensee was calculating negative values

(e.g. April 3, -3.59 gpm) the true unidentified leakage

would have to increase by 4.59 gpm before the acceptance

criteria would be exceeded. The use of imaginary numbers

is not an acceptable practice and the licensee must

investigate and evaluate the source of negative values to

'

I

ensure that a <1 gpm unidentified leakage can be measured.

!

The second concern, relates to the first, was that the

l

Total Leakage had increased from 2.61 to 4.874 gpm, or a

2.264 gpm change.

This change represented an increase in

t-

l

unidentified leakage which exceeded the <1 gpm limit. This

information was presented to the licensee on April 7, 1987.

l

<

___-__

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

-

..^

,*

..

10

While the licensee developed a course of action to address

these issues the inspector- obtained previous test data.

The inspectors concluded that the major source of error

appeared to be the 6.2 gpm value of previous identified

leakage.

This value was extracted from surveillance

14450-1, "RCS Pressure Isolation Valve Leak Test."

The

inspectors informed the licensee that this data should,

with proper engineering evaluation or methodology be

adjusted to reflect the test configuration appropriate for

the inventory balance conditions. These adjustments should

consider actual Delta P across the leaking valve or the

system valve lineups which might affect the leakrate. The

objective is to recognize that unidentified leakage must be

a number greater than 0 gpm and action taken to identify

the leakage when the leakage exceeds <1 gpm.

On April 9 the licensee computed the following test

results:

Total

Test

Previous

. Leakage

Identified

Identified

Unidentified

6.34

2.5

6.2

-2.36

The NRC results were:

Total

Test

Previous

Leaka_ge

Identified

Identified

Unidentified

6.53

2.88

6.2

-2.55

From the above data the total leakage had increased an

additional 1.466 gpm (6.34-4.874) and identified leakage

had increased 2.173 gpm from the April 6 test results.

The licensee preliminary investigation as of April 14 has

indicated several sources of error where corrective action

is needed. The first source of error appears to be that

the Reactor Collection Drain Tank levels were not being

recorded correctly during the tests. This error results in

larger values of identified leakage which when added to the-

6.2 gpm value would have resulted in unidentified leakage

being more negative than previously calculated.

The

licensee also is continuing to quantify crude tank and

accumulator levels to support making correction to the

previous identified values.

The April 14 test did not

include the 6.2 gpm value of identified leakage as the

licensee now believes that an appropriate adjustments can

be made.

The April 14 data indicates the following:

Total

Test

Previous

Leakage

Identified

Identified

Unidentified

_

_ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

._

.

_

..

. . -

11

,

5.15

3.7

1.95

.5

If the licensee had continued to utilize the 6.2 gpm value,

the 10 gpm identified leakage limit would have been

exceeded. The licensee intends to revise the procedure Lto

incorporate methodology that will ensure that the 1 gpm of

unidentified leakage will be detectable and not masked by-

,

excessively large values of identified leakage. This will

ensure prompt identification of the leakage.

Due to the inadequacy of Surveillance Procedure 14905-1,

"RCS Leakage Calculation (Inventory Balance)" to properly

quantify the amount of unidentifiable leakage.the inspector

concluded that T.S.6.7.la which requires that written

procedures shall be established, implemented and maintained

had been violated.

The following item is identified to track this violation

50-424/87-27-02, " Failure to Establish an Appropriate

Procedure to Determine and Evaluate Unidentified Leakage."

The inspector considered the potential for the existence of.

.

a violation against the Technical Specification LCO 3.4.6.25. but after discussions with the Region II office

and the fact that total leakage was low the violation was

more appropriate to address the procedural aspects of the

problem.

(7) Maintenance Activities (62703)(62700) - The inspector observed

maintenance activities to verify that correct equipment

clearances were in effect; work requests and fire prevention

work permits, as required, were issued and being followed;

quality control

personnel were available for inspection

activities as required; retesting and return of systems to

service was prompt and correct; TS requirements were being

followed. Maintenance backlog was reviewed

I

The

inspector

reviewed

the

following completed / approved

Maintenance Work Orders to verify that required administrative

approvals were obtained before initiating the work; LCO's were

met while the component or system was removed fron service;

inspections were made in accordance with the. licensed

l.

requirements and quality control

records were complete;

'

functional

testing and calibrations, as necessary, were

completed before returning the equipment to service; measuring

i

l

and test equipment used was identified and in calibration and

that parts and materials used were identified and at least met

!

i

the specifications of the original equipment.

l

I

MWO #

Title

l

'

-

-

-.

-.

.

-

-

.

- -. .-

. .

-

-

-

,

,_ .

!

-

.

,

..

..

12

1-87-03393

AFW SG#2 and 3 Valves (1 HV-5132 & 1

HV-5134) Failed to Open on Actuation.

1-87-04377

VCT Outlet Isolation Valve ILV-0112C

Failed to Stroke Fully Closed When

Manually Stroked From QMCB.

1-87-04394

Loop #4 Wide Range Cold Leg Temperature

Indicator ITI-0443B is Reading Approxi-

mately 40 Degrees F. Colder Than Other

Loops.

1-87-04362

Voltage From Turbine Impulse Chamber

Pressure Transmitter 1PT-505 is Reading

Lower Than From the Other IPT-506.

1-87-04221

Main Steam Safety Reliefs Lifted Due To

High Pressure But Failed to Fully Seat.

1-87-04538

While Reactor was At 35% Power NI-32

Re-energized by Itself.

Two violations were identified as discussed above.

6.

Startup Test Program Implementation / Verification - Unit 1 (72302)

The inspector reviewed the present implementation of the Startup Test

Program.

Test Program attributes

inspected

included review of

administrative requirements, document control, documentation of major test

events and deviations to procedures, operating practices, instrumentation

calibrations, and correction of problems revealed by testing.

Periodic facility tours were made to observe Startup Test activities in

progress.

The - inspector verified that procedural prerequisites and

i ni'ti al conditions were met.

Verification was performed by the

inspector's review of records (valve lineup sheets, test equipment

calibration status, system status checklists, or appropriate signoffs

listed in procedure were maintained current) or by direct observation

(monitoring instrumentation indications, valve positions,

equipment

position switches or personnel actions).

Discussions were held with

responsible personnel, as they were available, to determine their

knowledge of the Startup Test Program. Schedules for Startup Test Program

completion and progress reports were routinely monitored.

Specific

. inspections conducted are listed below:

a.

Startup Tests

(1) Loss of Offsite Power Test Procedure Review and Witnessing

(72582)

.

,

..

..

13

The inspector reviewed the loss of offsite power at greater than

10% Power Startup Test. Procedure (1-600-09) for administrative

format and technical adequacy. A review of licensee commitments

from applicable FSAR Chapters, Regulatory Guide 1.68 and the

Safety Evaluation Report was performed and compared with

requirements contained in the test procedure.

This included

verifying that pertinent prerequisites were identified, initial

test conditions and system status were specified, acceptance

-criteria were specified, and management approval and appropriate

committee review were indicated.

The inspector witnessed selected portions of the loss of offsite

power at greater than 10% Power Startup Test Procedure. The

inspection included attendance at briefings held by .the test

supervisor to observe the coordination and general knowledge of

the procedure with the test participants.

Overall crew

performance was evaluated during testing. A preliminary review

of the test results was compared to the inspector's own

observations.

Problems encountered during performance of the

test were verified to be adequately documented, evaluated and

dispositioned. During the performance of the test the inspector

verified that the following occurred:

-

Hot Standby Condition was achieved and maintained, for 30

minutes, using only emergency.on-site power sources.

-

Natural circulation of the Reactor Coolant System.

Reactor Trip, -Turbine Trip, and Reactor Coolant Pumps

-

tripped following loss of offsite power.

-

Transfer from the Reserve Auxiliary Transformer to the

onsite standby power supply occurred and the diesel

generators started and loaded on loss of offsite power.

-

Turbine driven Auxiliary Feedwater Pump started.

(2) Shutdown From Outside the Control Room Procedure Review and Test

Witnessing (72583)

The inspector reviewed the Remote Shutdown Startup Procedure

(1-600-08) for administrative format and technical adequacy. A

review of licensee commitments from applicable FSAR Chapters,

Regulatory Guide 1.68 and the Safety Evaluation Report was

performed and compared with requirements contained in the test

procedure. This included verifying that pertinent prerequisites

were identified, initial test conditions and system status were

specified, acceptance criteria were specified and management

approval and appropriate committee review were indicated.

._ _

-

.

_

,. .

..

14

.

The inspector witnessed the Remote Shutdown Test from the Main

Control Room and the Train "B" Remote Shutdown Panel on: April 9

and 14, 1987. The purpose of this was to verify that the test

was conducted with the minimum shift crew and that no equipment

was used other than that which would normally be available for a

plant cooldown from.outside the Control Room.

A preliminary

review of the test results was compared to the inspector's own

observations.

Problems encountered during performance of the

test were verified to be adequately documented, evaluated and

dispositioned. During the performance of the. test the inspector

verified that the following occurred:

-

The Reactor was tripped from the Remote Shutdown Panel.

-

Control was transferred from the Control Room to the Remote

Shutdown Panel.

-

With stable conditions were achieved the plant was

maintained in a hot standby condition from the Remote

Shutdown Panel for a minimum of 30 minutes.

-

Remote Shutdown Panel

Instrumentation, Controls, and

Interlocks functioned properly.

(3) Ultimate Heat Sink Heat Rejection Capability Test Procedure

Review

The inspector reviewed the Ultimate Heat Sink Heat Rejection

Capability Startup Test Procedure (1-6EF-01) for administrative

format and technical adequacy. A review of licensee commitments

from applicable FSAR Chapters, Regulatory Guide 1.68 and the

Safety Evaluation Report was performed and compared with

requirements contained in the test procedure.

This included

verifying that pertinent prerequisites were identified, initial

test conditions and system status were specified, acceptance

criteria were specified, and management approval and appropriate

committee review were indicated.

No violations or deviations were identified.

7.

Review of Licensee Event Reports - Unit (90712)

Licensee Event Reports (LERS) and Deficiency Cards (DC's) were reviewed

for potential generic impact, to detect trends, and to determine whether

corrective actions appeared appropriate.

Events which were reported

immediately, were reviewed as they occurred to determine if the technical

specifications were satisfied.

During the inspection period the inspector conducted a review of the

licensee's evaluation of reportability per 10 CFR 50.72 and 10 CFR 50.73

.

.

.

. .

15

for Control Room Ventilation Isolation (CRVI) Actuations to date which

were documented in the Unit Control Log and on the following DCs:

DC No~.

Title

Licensee's Evaluation

1-87-746

CRVI on Radiogas Monitor RE12116

Reportable

1-87-782

No CRVI, RE12117 Radiogas Monitor

Not Reportable

Inoperable

1-87-792

CRVI on Radiogas Monitor RE12116

Reportable

1-87-849

CRVI on Chlorine Gas Monitor

Not Reportable

1-87-1012 CRVI on Radiogas Monitor RE12116

Reportable

1-87-1022 CRVI on Radiogas Monitor RE12116

Reportable

1-87-1061 CRVI on Chlorine Gas Monitor AE12110

Not Reportable

1-87-1071 CRVI on Radiogas Monitor RE12116

Reportable

The inspector questioned the licensee concerning their evaluation of

non-reportability of the two (2) CRVI actuations on Chlorine Gas which

occurred on February 20, 1987, and April 4,

1987.

The licensee-informed

the inspector that their present guidance on Engineered Safety Features

'

Actuation System (ESFAS) actuations reportability which is specified in an

internal correspondence letter dated February 2,1987, does not consider

CRVI Actuation as a result of the Chlorine Gas Monitors an ESFAS

Actuation. The licensee further stated that their basis for determining

that CRVI actuations as a result of the Chlorine Gas Monitors were not

reportable was

that Technical

Specification Table

3.3-3,

"ESFAS

Instrumentation Trip Setpoints."

Item 10 Control Room Emergency Mode

Actuation does not list the Chlor.ine Gas Monitors but rather only the

Intake Radiogas Monitors. Therefore, only CRVI actuations as a result of

the Intake Radiogas Monitors are reportable as ESFAS actuations.

The inspector informed the licensee that based on the following criteria

the CRVI actuations which occurred on February 20, 1987, and April 4,

1987, as a result of the Chlorine Gas Monitors should be considered

reportable ESFAS actuations per 10CFR50.72 and 10CRF50.73.

FSAR Sections

6.0,

6.4 and 7.3.6 describe the CRVI System as an Engineered Safety

Features System. NUREG 1022 Supplement No. I which gives guidelines for

reporting states that ESF systems in general are defined in the FSAR and

that actuation of any ESF is reportable. The licensee stated that their

corporate office was presently reviewing their reportable guidelines and

that this issue would be re-reviewed.

Pending the results of the

licensee's review of the reportability of CRVI actuations as a result of

the Chlorine Gas Monitors this item will remain unresolved and be

identified as Unresolved Item 50-424/87-12-03, "Reportability of CRVI

Actuations As A Result of the Chlorine Gas Monitors."

'

l

--, -

,s

m,

- ,

,r-..

,-

r

-

.

.

..

.16

No violations or deviations were identified.

8.

General Construction Inspection - Unit 2 (92706)

Periodic random surveillance inspections were made throughout this

reporting period in the form of general type inspections in different

. areas of the facility.

The areas were selected on the basis of the

scheduled activities and were varied -to provide wide coverage.

Observations were made of activities in progress to note defective items

or items of noncompliance with the required codes and regulatory

requirements.

On these inspections, particular note was made of the

presence of quality control inspectors, supervisors, and quality control

. evidence in the form of available process sheets, drawings, material

identification,

material

protection,

performance

of tests,

and

housekeeping.

Interviews were

conducted

with

craft

personnel,

supervisors, coordinators, quality control inspectors, and others as they

were available in the work areas.

The inspector reviewed numerous

construction deviation reports to determine if requirements were met _in

the areas of documentation, action to resolve, justification, and approval

signatures in accordance with GPC Field Procedure No. GD-T-01.

No violations or deviations were identified.

9.

Fire Prevention / Protection and Housekeeping Measures - Unit 2 (42051C)

The inspector observed fire prevention / protection. measures throughout the

inspection period. Welders were using welding permits with fire watches

and extinguishers.

Fire fighting equipment was in its designated areas

throughout the plant.

The inspector . reviewed and examined portions of procedures pertaining to

the fire prevention / protection measures and housekeeping measures to

determine whether they comply with applicable codes, standards, NRC

Regulatory Guides and licensee commitments.

The inspector observed fire prevention / protection measures in work areas

containing safety related equipment during the inspection period to verify

the following:

(

-

Combustible waste material and rubbish was removed from the work

areas as rapidly as practicable to avoid unnecessary accumulation

of combustibles.

-

Flammable liquids were stored in appropriate containers and in

designated areas throughout the plant.

Cutting and welding operations in progress have been authorized by an

-

appropriate permit, combustibles have been moved away or safely

covered, and a fire watch and extinguisher was posted as required.

Fire protection / suppression equipment was provided and controlled in

-

accordance with applicable requirements.

l

No violations or deviations were identified.

l

i

m

-

w

.

'.

..

17

10.

Structural Concrete - Unit 2 (47053C)

a.

Procedure and Document Review

The inspector. reviewed and examined portions of the following

' procedures pertaining to the placement of concrete to determine

whether they comply with applicable codes, standards, NRC Regulatory

Guides and licensee commitments.

- CD-T-02, Concrete Quality Control

- CD-T-06, Rebar and Cadweld Quality Control

- CD-T-07, Embed Installation and Inspection

b.

Installation Activities

The inspector witnessed portions of the concrete placement indicated

below to verify the following:

(1)

Forms, Embedment, and Reinforcing Steel Installation

Forms were properly placed, secure, leak tight and clean.

-

-

Rebar and 'other embedment installation was installed in

accordance with construction specifications and drawings,

secured, free of concrete and excessive rust, specified

distance from forms, proper on-site .rebar bending (where

applicable) and clearances consistent with aggregate size.

(2) Delivery, Placement and Curing

-

Preplacement inspection was completed and approved prior to

placement utilizing a Pour Card.

-

Construction joints.were prepared as specified.

-

Proper mix was specified and deliverad.

-

Temperature control of the mix, mating surfaces, and

ambient were monitored.

-

Consolidation was performed correctly.

-

Testing at placement location was properly performed in

accordance with the acceptance criteria and recorded on a

Concrete Placement Pour Log.

-

Adequate crew, equipment and techniques were utilized.

-

Inspections during placements were conducted effectively

by a sufficient number of qualified personnel.

-

Curing methods and temperature was monitored.

(3) Rebar Splicing

The inspector witnessed cadwelding operations to verify the

following:

_

.

_

..

..

18

-

Inspections are performed during and after splicing by

qualified QC inspection personnel.

Each splice was defined by a unique number consisting

-

of the bar size, splice type, the position, the

operator's symbol, and a sequential number.

Process and crews are qualified.

-

-

The sequential number and the operator's symbol are marked

on all completed cadwelds.

The inspector also conducted random inspections of completed

cadwelds to verify the following:

-

Tap hole does not contain slag, blow out, or porous metal.

-

Filler metal was visible at both ends of the splice sleeve

and at the tap hole in the center of the sleeve. No voids

were detected at the ends of the sleeves.

-

The sequential number and the operator's symbol are marked

on all completed cadwelds.

No violations or deviations were identified.

11.

Containment (Steel Structures and Supports) - Unit 2 (48053C)

Periodic inspections were conducted to observe containment steel and

support installation activities in progress, to verify the following:

Components were being properly handled (included bending or

-

straightening).

-

Specified clearances were being maintained.

-

Edge finishes and hole sizes were within tolerances.

-

Control, marking, protection and segregation were maintained during

storage.

Fit-up/ alignment meets the tolerances in the specifications and

-

drawings.

No violations or deviations were identified.

12.

Safety-Related Structures (Structural Steel and Supports) - Unit 2

(48063C)

Periodic inspections were conducted to observe construction activities of

safety-related structures / equipment supports for major equipment outside

the containment to verify that:

-

Materials and components were being properly handled to prevent

damage.

-

Fit-up/ alignment t.are within tolerances in specifications and drawing

requirements.

-

Bolting was in accordance with specifications and procedures.

-

Specified clearances from adjacent components were being met.

No violations or deviations were identified.

_ ___________ -.

-

.

..

..

19

13. Reactor Coolant Pressure Boundary and Safety Related Piping - Unit 2

(49053C) (49063C) (37301)

Periodic inspections were conducted to observe construction activities of

the Reactor Coolant Boundary and other safety-related piping installations

inside and outside Containments.

Verifications included but were not

limited to the following:

)

Material and components were being properly handled and stored in

-

order to prevent damage.

Fit-ups and alignments were within tolerances per specifications and

-

drawings.

Specified clearances from pipe to pipe and adjacent components were

-

met.

Piping was installed and inspected in accordance with applicable

-

drawings, specifications, and procedures.

-

Those people engaged in the activity are qualified to perform the

applicable function.

Drawing and specification changes (revisions) are being handled and

-

used correctly.

No violations or deviations were identified.

14. Reactor Coolant Pressure Boundary and Safety Related Piping Welding - Unit

2 (55073C) (55083C)

Periodic inspections were conducted during daily plant surveillances on

safety-related pipe welding at various stages of weld completion.

The

purpose of the inspection was to determine whether the requirements of

applicable specifications, codes, standards, work performance procedures

and QC procedures are being met as follows:

Work was conducted in accordance with a process sheet which

-

identifies the weld and its location by system, references procedures

or instructions, and provides for production and QC signoffs.

-

Welding procedures, detailed drawings and instructions, were readily

available in the immediate work area and technically adequate for the

welds being made.

-

Welding procedure specification (WPS) were in accordance with the

applicable Code requirements and that a Procedure Qualification

Record (PQR) is referenced and exists for the type of weld being

made.

-

Base metals, welding filler materials, fluxes, gases, and insert

materials were of the specified type and grade, have been properly

inspected,

tested and were

traceable

to

test reports or

certifications.

_ _ _ . . .

.

- - - _ ,

-

-

-

_ - - - .

.

.

- -

.

-.

-

,,

,

-h

..

..

20

-

~

. Purge and/or shielding gas flow and composition were as specified in

-

!-

the welding procedure specification and that protection was provided

to shield the welding operation from adverse environmental

l

conditions.

9

Weld joint _ geometry including pipe wall thickness was specified and

-

that surfaces to be welded have been prepared, cleaned and inspected

'

in accordance with applicable procedures or instructions.

. A sufficient . number of adequately qualified QA and QC inspection -

-

personnel were'present at the work site, commensurate with the work

in progress.

The. weld area cleanliness was maintained and that pipe alignment and

-

fit-up tolerances were within specified limits.

Weld . filler material being used was in accordance with welding

-

specifications, unused filler material was separated from other types

'

of material and was stored properly and that weld rod stubs were

!

properly removed from the work location.

i ,-

3~

That there were no evident signs of cracks, excessive heat input,

-

sugaring, or excessive crown on welds.

-

Welders were qualified to the applicable process and thickness, and

that necessary controls and records were in place.

'

No violations or deviations were identified.

- 15 .

Reactor Vessel, -Integrated Head Package, and Internals - Unit 2 (50053C)

(50063C)

,

The inspection consisted of examinations of the Reactor Vessel installed

"

in' containment,- the Reactor Vessel head with the installed control rod

drive mechanisms, and the upper and lower internals in their designated

a

laydown area.

Inspections also determined that proper storage protection

practices were in place and that entry of foreign objects and debris was

. prevented.

'

No violations or deviations were identified.

16.

Safety Related Components - Unit 2 (50073C)

i

The inspection consisted of plant tours to observe storage, handling, and

f

protection; installation; and preventive maintenance after installation of

safety-related components to determine that work is being performed in

accordance with applicable codes, NRC Regulatory Guides, and licensee

commitments.

'

I

During the inspection the below listed areas were inspected at various

j

times during the inspection period to verify the following as applicable:

i

i

k

4

,

. ,.

r-

,-.-----.-_,,,_,..-..._-----,,,,._,,--,.----,_,__,,--,,._~--_.-._----._--..----m.

.

.

-

.

.

-

-

-

_

. .

-

..

. . -

..

21

.

Storage, environment, and protection of components were in accordance

-

with manufacturer's instructions and/or established procedures.

Implementation of special storage and maintenance requirements such

-

as:

rotation of motors, pumps, lubrication, insulation testing

(electrical), cleanliness,etc.

' Performance of licensee / contractor surveillance activities and

-

documentation thereof was being accomplished.

-

Installation requirements were met' such as: proper location,

placement, orientation, alignment, mounting (torquing of bolts and

expansion anchors), flow direction, tolerances, and expansion

clearance.

Appropriate stamps, tags, markings, etc. were in use to - prevent

-

oversight of required inspections, completion of tests, acceptance,

and the prevention of inadvertent operation.

Safety-Related piping, valves, pumps, heat exchangers, and instrumentation

were inspected in the following areas on a random sampling ~ basis

throughout the inspection period:

- Residual Heat Removal Pump Rooms

- Diesel Generator Building

- Auxiliary Feedwater Pumphouse

- Containment Spray Pump Rooms

- Pressurizer Rooms

- Main Coolant Pump Areas

- Steam Generator Areas

,

- Safety Injection Pump Rooms

- RHR and CS Containment Penetration Encapsulation Vessel Rooms

- Component Cooling Water (CCW) Heat Exchangers, Surge Tanks & Pump Rooms

- Cable Spreading Rooms

- Accumulator Tank Areas

- Chemical and Volume Control System (CVCS) Letdown Heat Exchanger

Pump Room

- Battery & Charger Rooms

- Nuclear Grade Piping, Valves & Fittings Storage Areas

- Spent Fuel Pool Heat Exchanger Rooms

- Pressurizer Relief Tank Area

'

- CVCS Centrifugal Charging Pumps & Positive Displacement Pump Rooms

- Bottom Mounted Instrumentation (BMI) Tunnel and Seal Table Area

- BMI and Supports Under Reactor Vessel

- NSCW Tower Pump Rooms and Pipe Tunnels

- Containment, Auxiliary Building, Control Building, and Fuel Handling

Building auxiliary (secondary) areas

No violations or deviations were identified.

,

17.

Safety Related Pipe Support and Restraint Systems - Unit 2 (50090C)

l

4

-

,

, , , _ . . , ,,

, , , ,

. - , - ,

,

,,..,,.,n,

, , , , - , , , , . . , , - - - , - - , - , - . , , . , - - , , - - - - - - - - - , . , . . - , - - . - - - -

-

.

.

.

.

.

22

Periodic random inspections were conducted during the inspection period to

observe construction activities during installation of safety-related pipe

supports to determine that the following work was performed in accordance

with applicable codes, NRC Regulatory Guides, and licensee commitments:

Spring hangers were provided with indicators to show the approximate

-

" hot" or " cold" position, as appropriate.

No deformation or forced bending was evident.

-

-

Where pipe clamps are used to support vertical lines, shear lugs were

welded to the pipe (if required by Installation Drawings) to prevent

slippage.

-

Sliding or rolling supports were provided with material and/or

lubricants suitable for the environment and compatible with sliding

contact surfaces.

-

Supports are located and installed as specified.

-

The surface of welds meet applicable code requirements and are free

from unacceptable grooves, abrupt ridges, valleys, undercuts, cracks,

discontinuities, or other indications which can be observed on the

welded surface.

No violations or deviations were identified.

18.

Electrical and Instrumentation Components and Systems - Unit 2 (51053C)

(52153C)

Periodic inspections were conducted during the inspection period to

observe safety-related electrical equipment in order to verify that the

storage, installation, and preventive maintenance was accomplished in

accordance with applicable codes, NRC Regulatory Guides, and licensee

commitments.

During the inspection period inspections were performed on various pieces

of electrical

equipment during storage,

installation,

and cable

terminating phase in order to verify the following as applicable:

- Location and alignment

- Type and size of anchor bolts

- Identification

- Segregation and identification of nonconforming items

- Location, separation and redundancy requirements

- Equipment space heating

- Cable identification

- Proper lugs used

- Condition of wire (not nicked, etc.), tightness of connection

- Bending radius not exceeded

- Cable entry to terminal point

- Separation

No violations or deviations were identified.

L

_

.

w

.

. .

.

23

19. Electrical and Instrumentation Cables and Terminations - Unit 2 (51063C)

(52063C) (53053C)

a.

Raceway / Cable Installation

The inspector reviewed and examined portions of the following

procedures pertaining to raceway / cable installation to determine

whether they comply with applicable codes, NRC Regulatory Guides and

licensee comm'tments.

- EO-T-02, Raceway Installation

- ED-T-07, Cable Installation

Periodic

inspections were conducted to observe construction

activities of Safety Related Raceway / Cable Installation.

In reference to the raceway installation, the following areas were

inspected to verify compliance with the applicable requirements:

- Identification

- Alignment

Bushings (Conduit)

- Grounding

- Supports and Anchorages

In reference to the cable installation the following areas were

inspected to verify compliance with the applicable requirements:

- Protection from adjacent construction activities (welding, etc.)

- Coiled cable ends properly secured

- Non-terminated cable ends taped

- Cable trays, junction boxes, etc. , reasonably free of debris

!

- Conduit-capped, if no cable installed

- Cable supported

'

I

- Bend radius not exceeded

- Separation

b.

Cable Terminations

The inspector reviewed and examined portions of the following

r

I

procedures pertaining to cable termination to determine whether they

comply with applicable codes, NRC Regulatory Guides and licensee

commitments.

- ED-T-08, Cable Termination

In reference to cable terminations the following areas were inspected

to verify compliance with the applicable requirements.

-

.

_

.

.

-

24

- Cable identification

- Proper lugs used

- Condition of wire (not nicked, etc.)

- Tightness of connection

- Bending radius not exceeded

- Cable entry to terminal point

- Separation

No violations or deviations were identified.

20.

Containment and Safety Related Structural Steel Welding - Unit 2 (55053C)

(55063C)

Periodic inspections were conducted during daily plant surveillances on

safety-related steel welding at various stages of weld completion.

The purpose of the inspection was to determine whether the requirements of

applicable specifications, codes, standards, work performance procedures

and QC procedures are being met as follows:

Work was conducted in accordance with a process sheet or drawing

-

which identifies the weld and its location by system, references,

procedures or instructions, and provides for production and/or QC

signoffs.

Welding procedures, detailed drawings and instructions, were readily

-

available in the immediate work area and technically adequate for the

welds being made.

-

Welding procedure specification (WPS) were in accordance with the

applicable Code requirements and that a Procedure Qualification

Record (PQR) is referenced and exists for the type of weld being

made.

-

Base metals and welding filler materials were of the specified type

and grade, were properly inspected, tested, and were traceable.

Protection was provided to shield the welding operation from adverse

-

environmental conditions.

-

Weld joint geometry including thickness was specified and that

surfaces to be welded were prepared, cleaned and inspected in

accordance with applicable procedures or instructions.

A sufficient number of adequately qualified QA and QC inspection

-

personnel commensurate with the work in progress were present at the

work site.

4

Weld area cleanliness was maintained and that alignment and fit-up

-

tolerances were within specified limits.

- - _ - _ _ _ - - _ - _ _ _

_ _ _ _ _ _ _ - - _ _ _ - _ - - _ _ _ _ _ _ _ _ _ _ _ _ _ _

..

,.

_

.

.

25

Weld - filler material being used was in accordance with welding

-

specifications, unused filler material was separated from other types

of material and was stored and controlled properly, and stubs were

properly removed from the work location.

There were no visual signs of cracks, excessive heat input, or

-

excessive crown on welds.

Welders were qualified to the particular process and thickness; and

-

that necessary controls and records were in place.

No violations or deviations were identified.

21. Allegations - Units 1 & 2

a.

Allegation, RII 86-A-0216, Electrical Splices Inside Penetrations.

Concern

An - alleger stated there were electrical cable splices inside two

penetrations at Plant Vogtle.

Discussion

The alleger could not identify the specific penetrations except that

they were somewhere in the Auxiliary Building.

The inspector

reviewed the GPC Quality Concern files and found that this specific

concern had not been submitted to GPC Quality Concerns, and that

,

there were no other concerns relating to electrical cable splices in

penetrations. A review of procedures and specifications reveals that

4

electrical cable splices are not permitted in field run conduit or

trays (raceways), except on a special case by case basis.

Cable

insulation damage may be replaced with an approved splice when

documented on a Deviation Report (DR) or a Field Change Reouest

(FCR). Specific controls and inspections are delineated in Procedure

ED-T-08 and Specification X3AR01.

The inspector, GPC Quality

Control, and GPC Quality Concerns are unaware of any past or present

problems with unauthorized field run cable splices. The inspector

/

notes that many NRC electrical inspections such as 50-424/87-13 and

85-20 Para. 6 included plant walkdowns and detailed electrical

inspections which did not detect any unauthorized cable splicing

practices.

Conclusion

<-

.

The alleger could not identify or locate the subject penetrations.

Since there have been no prior examples of unauthorized cable

splicing, the inspector can only conclude that the splices seen by

the alleger were authorized and acceptable.

This allegation is

considered closed.

. .

-

- _. .

___________________ _ _ _ - - - - -

--

__-

-

l

-_

- _ _ _

--

...

.

.

26

22.

Followup on Previous Inspection Items - Units 1 & 2 (92701)

(Closed) IFI 50-424/87-12-06, . Review Followup Interview Regarding QCP File

87V0044. Georgia Power Quality Concern personnel interviewed the subject

QC inspector referred to in the tasic Quality Concern. No additional

specific detailed information was provided that affected the conclusion

.

\\.

presented in Inspection Report 50-424/87-12.

i

4

a

h

!

- , , , , , , , , , . . , , , , , , , .