Text
'.
,a..
UNITED STATES
[
8,j NUCLEAR REGULATORY COMMISSION 5
<j wAsumorow, p. c. rosss O
./
November 28, 1986 Docket No. 50-219 Mr. P. B. Fiedler Vice President and Director Oyster Creek Nuclear Generating Station Post Office Box 388 Forked River, New Jersey 08731
Dear Mr. Fiedler:
SUBJECT:
DEFERMENT OF NRC REQUIRED MODIFICATIONS FROM CYCLE 11 REFUELING OUTAGE (TAC 59400&61327)
~
Re:
Oyster Creek Nuclear Generating Station In your letter dated July 26, 1985, you requested the staff to consider the defement of eight NRC required modifications from the Cycle 11 Refueling (Cycle 11R) outage to either operating Cycle 11 or to the Cycle 12R outage.
These modifications are the following:
safety parameter display system (SPDS) implementation, unlation condenser makeup pump, intake canal level instrumen-tation, masonry wall modifications, torus attached piping supports that do not require a plant shutdown, torus bulk water temperature indication, thermal-overload protect <on for motors fo-motor-operated valves (MOV), and airborne particulate and pseous radioactivity monitors. You requested that the above modifications be defereed to operating Cycle 11 or to the Cycle 12R outage.
The Cycle 12R outage is scheduled to begin in 1988.
As stated in your letter, there have been discussions between the staff and GPU Nuclear (the licensee) on defement of low safety priority work from the Cycle 11R outage. This began with a meeting on April 23, 1985. The intent of these deferments was for the licensee to complete the most important safety work in the Cycle 11R outage with the resources available, to manage the outage work as best as possible and to restart Oyster Creek within a reasonable time.
The Cycle 11R outage has always been scheduled to be 6 to 9 months, the second longest outage for the plant. The staff has been in agreement with these goals and it was our intent to complete our evaluation of your request before the commencement of the outage.
In the staff's letter to you dated October 6, 1986, we addressed the above eight modifications in that we approved deferring five modifications, we l
acknowledged that you had completed one modification and we deferred action on i
two modifications. The five modifications are SPDS, masonry wall modification, torus attached piping supports, torus bulk water indication and airborne particulate and gaseous radioactivity monitors. The one modification completed is the MOV thermal-overload protection. The last two mcdifications, isolation condenser makeup pump and the intake canal level instrumentation, are the subject of this letter.
l 8612170195 861128 l
PDR ADOCK 05000219 P
~ - -.. - -. - -
November 28, 1986 Mr. P. B. Fiedler For the isolation condenser makeup pump, the staff also reviewed your submittal dated April 21, 1936. As discussed in the enclosed Safety Evaluation (SE), the staff concludes that it is acceptable to defer this to Operating Cycle 11 but not later than the restart from the Cycle 12R outage on the basis of improving outage manageability, controlling person rem exposures and completing higher priority safety improvements during the Cycle 11R outage.
For the intake canal level instrumentation, the staff also reviewed your submittal dated April 21, 1986. This submittal changed your request for a deferment to a request for cancellation of your commitment to install automatic water level instrumentation in the intake canal with readout in the control room in the Cycle 11R outage. Your submittals on this issue, however, did not address the use of this instrumentation for measuring the water level at the intake structure to determine if it is near or below the service water pump suction elevation. This is discussed in Section 4.1(5) of the Integrated Plant Safety Assessment Raport for Oyster Creek, NUREG-0822, dated January 1983. You are requested, within 60 days of receipt of this letter, to provide a discussion on the administrative controls to monitor the canal water for low water level near or below the service water pump suction eleva-tion and the actions to be taken by the control room operators. The staff con-cludes that it is acceptable to defer this installation to Operating Cycle 11 but no later than the restart from the Cycle 12R outage. This is what you requested in your letter dated July, 26, 1985. The issue of cancelling the installation of this instrumentation will be addressed later after we have reviewed your response to our request for additional information. This has been discussed with the licensee on November 19, 1986, and is acceptable to them.
The reporting and/or recordkeeping requirements contained in thi's letter affect fewer than ten respondents; therefore, OMB clearance is not required under P.L. 96 511,
- incerely, I
(M IM
(
Jack N. Dongew, Jr., Project Manager BWR Project Directorate #1 Division of BWR Licensing
Enclosure:
DISTRIBitTION:
CGrimes EJordan MSrinivasan Safety Evaluation Docket File GHulman BGrimes RDiqqs NRC PDR PDLiaw JPartlow OC File cc w/ enclosure:
BWD1 R/F Glainas JDonohew NCho'.shi local PDR RBernero CJamerson FEltawila CSEE PREVIOUS PAGES OGCB-BETH ACRS(10)
JZwolinski HShaw FOR CONCURRENCE RVestcott NThompson GHolahan s
OFC : DBL:BWD1*
)1
- DPLB;ISAPD*: DBL:PSB*
- DBL:AD*
, %
- DB ~
L
..... :............ :..hl,:k,..:............:............:............:.
f ho w:we CGrimes GHulman
- Glainas Lolinski rnero NAME :CJamerson 114d86 10/30/a6 11/18/86
- 11/18/86 11886 DATE :10/28/86
Mr. P. B. Fiedler For the isolation condenser makeup pump, the staff also reviewed your su ittal dated April 21, 1986. As discussed in the enclosed Safety Evaluation E),the staff concludes that it is acceptable to defer this to Operating Cyc1 11 but not later than the restart from Cycle 12R outage on the basis of im oving outage manageability, controlling person rem exposures and completi g higher priority safety improvements during the Cycle 11R outage.
For the intake canal level instrumentation, the staff also rey ewed your submittal dated April 21, 1986. This submittal changed you tequest for a deferment to a request for cancellation of your commitment install automatic water level instrumentation in the intake cana/d your request l
ith readout in the control room in the Cycle 11R outage. The staff has fou acceptable and, based on the enclosed SE, concludes that administrative controls to monitor the canal water level are sufficiint to protect the plant and the installation of automatic canal water level indication in the control room is not required.
Sincerely, Jakk N Donohew, Jr., Project Manager
,PWR Project Directorate #1
/ Division of BWR Licensing p
Enclosure:
/
Safety Evaluation j
cc w/ enclosure:
/
See next page
/
Enclosure:
OkSTRIRUTION CGrimes EJordan MSrinivasan Safety Evaluation f Docket File GHulman BGrimes RDiqqs
/ NRC PDR BDLiaw JPartlow OCFile cc w/ enclosure:
/
PD#1 R/F Glainas JDonohew NChokshi See next page
/
Local PDR RBernero CJamerson FEltawila OGC.BETH ACRS(10)
JZwolinski HShaw
/
RWestcott NThompson GHolanan
/
/
- SEEPREy!0USPAGEFORCONCURRENCE DFC : DBL:BWD#1*
- DBL:BWD#1*
- DPLB:15APDy-:DB :P5B
- D AD
- DBL:BWD#1
- DBL:D NAME :CJamerson:go JDonohew
- CGrimes
- GHQan
- G as
- JZwolinski
- RPernero
.....:............:............:............:...........:o.'_.y.......:............:...........
DATE :11/13/86
- 11/13/86
/ /86 e ll/ dE6
/ [J/A6
/ /86 e
/ /R6 0FFICIAL RECORD COP"'
L m
Mr. P. B. Fiedler 2
For the isolation condenser makeup pump, the staff also reviewed your submi tal dated April 21, 1986. AsdiscussedintheenclosedSafetyEvaluation(SET,the staff concludes that it is acceptable to defer this to Operating Cycle 11 but not later than the restart from Cycle 12R outage.
/
/
For the intake canal level instrumentation, the staff also reviewed your submittal dated April 21, 1986. This submittal changed your requ'est for a deferment to a request for cancellation of your commitment to, install automatic water level instrumentation in the intake canal with readout in the control room in the Cycle 11R outage. The staff has found your request acceptable and, based on the enclosed SE, concludes that administrative controls to monitor the canal water level are sufficient to protect the plant and the installation of automatic canal water level indication in the control room is not required.
p Sincereli,
/
Jack N Donohew, Jr., Project Manager
,'BWR Project Directorate #1 Division of BWR Licensing
Enclosure:
Safety Evaluation cc w/ enclosure:
See next page
/
1
Enclosure:
/
DISTRIBUTION CGrimes EJordan MSrinivasan Safety Evaluation Docket File Shulman BGrimes RDiggs NRC PDR 180Liaw JPartlow OCFile cc w/ enclosure:'
PD#1 R/F
'Glainas JDonohew NChokshi See next page local PDR
JZwolinski HShaw RWestcott Nihompson GHolahan l
p'
/
/
); e o,
. w
%4 4
ed,
non
/
yo m er e f 04 en (a
> a M.*[
,iDRg QA (Ahrib'er&c14 a I ^ i 404-d f,, h T j d 0,T.,h h.
OFC :DUL:BWDf1 ) :DBt: 911
- D LB:I PD : DBL I B,
- DUL:An
- 05L':PWD#1
- DBL:D L....:......
NAME :CJamerson. j...
J
- CGrime i :GHu
- Glainoi
- JZwolinski
- RBernero
. :..........:............:.. 7........:............:........................
DATE : 40 / AV/86
% /.ed86
- to /24/86
- H/11/86
/ /86
/ /86
/ /86 P"'
0FFICIAL RECORD COPY A.
e e
Mr. P. B. Fiedler Oyster Creek Nuclear Oyster Creek Nuclear Generating Station Generating Station CC:
Mr. Ernest L. Blake, Jr.
Resident Inspector Shaw, Pittman, Potts and Trowbridge c/o U.S. NRC 2300 N Street, NW Post Office Box 445 Washington, D.C.
20037 Forked River, New Jersey 08731 J.B. Liberman, Esquire Comissioner Bishop, Liberman, Cook, et al.
New Jersey Department of Energy 1155 Avenue of the Americas 101 Commerce Street New York, New York 10036 Newark, New Jersey 07102 Mr. David M. Scott, Acting Chief Regional Administrator, Region I Bureau of Nuclear Engineering U.S. Nuclear Regulatory Comission Department of Environmental Protec. tion 631 Park Avenue CN 411 King of Prussia, Pennsylvania 19406 Trenton, New Jersey 08625 BWR Licensing Manager GPU Nuclear Corporation 1 Upper Pond Road Parsippany, New Jersey 07054 Deputy Attorney General State of New Jersey Department of Law and Public Safety 36 West State Street - CN 112 Trenton, New Jersey 08625 Mayor lacey Township 818 West lacey Road Forked River, New Jersey 08731 Licensing Manager Oyster Creek Nuclear Generating Station Mail Stop: Site Emergency Bldg.
P. O. Box 388 Forked River, New Jersey 08731
. _. _. _ _ _ _ _ -. _ _.. _ _,. _ _ _ _