Exemption from 10CFR50.71(e)(3)(ii),extending Date to 870630 for Util to File Updated Sar.Exemption Contingent Upon Util Ability to Meet Proposed Identified Guidelines
ML20137R001
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 11/22/1985
From: Crutchfield D
Office of Nuclear Reactor Regulation
To:
CONNECTICUT YANKEE ATOMIC POWER CO.
Shared Package
ML20137Q994 List:
References
NUDOCS 8512050407
Download: ML20137R001 (6)


Text

UNITED STATES OF APERICA NUCLEAR REGULATORY COMMISSION In the Pt.tter of CONNECTICUT YANKEE ATOMIC Docket No. 50-213 POWER COMPANY , .

\

j (Haddam Neck Plart)

)

EXEMPTION I.

Connecticut Yankee Atomic Power Company (the licensee) is the holder of Facility Operating License No. DPR-61 which authorizes the operation of the Haddam Neck Plant (the facility) at the steady-state pcwer levels not in excess of 1825 regawatts thermal. The facility is a pressurized water reactor located at the licensee's site in Middlesex County, Connecticut.

The license provides, among other things, that it is subject to all rules, regulations and orders of the Nuclear Regulatory Commission (the Concission) row er bereafter in effect.

II.

J Section 50.71(e)(3)(ii) of 10 CFR Part.50 requires that those plants

~

initially subject to the NRC's systematic evaluation program (SEP) must file a complete updated final safety eralysis ' report within 24 months after receipt of notificatic.) that the SEP has been completed. By letter dated July 20, 1983, the staff informed Ccrrecticut Yankee Atomic Power Company (CYAPCO) that SEP had been completed for the Haddam Neck Plant and that, pursuant to 10 CFR 50.71(e)(3), the licensee was required to file an 8512050407 851122 PDR ADOCK 05000213 <

P PDR

.~

updated Facility Description and Safety Analysis (FDSA). By letter dated February 4,1985 the licensee reevested an exemption to defer submittal of the updated FDSA on the bases that ongoing reviews (e.g., the Integrated Safety Assessment Prcgrar) would directly affect the content of the updated FDSA and that the required submittal would affect the work of the licensee's engineering persenrel on issues of higher safety significance.

The NRC staff reviewed the licensee's request and granted the exemption, by letter dated /pril 11, 1985. However, the staff determined that only a six month exemption from compliance with 10 CFR 50.71 was warranted at that time._ As detailed in the April 11, 1985 exemption, any additional exemptions fren compliance with 10 CFR 50.71 would be granted by the Director of Licensirg enly upon review and approval of a program plan containing schedules or milestones for the submittal of an updated FDSA for the Haddam Neck Plant.

By letter dated September 13, 1985, the licensee requested an additional exemption from the schedular requirements of 10 CFR 50.71 for the submittal date of an updated FDSA. However, the NRC staff, by letter dated October 2, 1985, inforred CYAPCO that this exemption request was not responsive to the

- terms identified in the exemption granted on April 11, 1985, and therefore, the exemption reouest was denied. The denial was based on the licensee's failure to supply the required milestones or schedules, but left open the possibility of further consideration by the staff provided the licensee took certain actions by October 11, 1985.

Py letter dated October 11,1985, CYAPC0 resubmitted a request for ar additional exerption to the schedular requirements of 10 CFR 50.71 for er updated FDSA. In that letter, CYAPC0 stated that the FOSA update would be based largely on the format of Regulatory Guide 1.70, Revision 3, which wculd result ir a r' ore comprehensive document than would result from minimal compliance with 10 CFR 50.71. CYAPC0 also provided milestor.es fer the submittal of component parts of an updated FDSA and a completion schedule for the entire FDSA update. The following are the commitments made and the scheduled completion dates:

PROGRAM SUBMITTAL DATE

1. Provide a concise program description and April 30, 1986 current reference to stand alone documentation for:

a) Radiation Protoction b) Emergency Planning c) Industrial Security d) Ouality Assurance e) Technical Specifications f) Radiclogical Effluent Monitoring and Offsite Dose Calculation Fanual and Plant Process Control Program

2. Provide a complete revision and update of June 30, 1986 the facility accident aralyses 1

L.

f PROGPAM SUBMITTAL DATE

3. Provide current systems descriptions and July 1, 1986 instrumentation drawirgs for all safety-related systems and major balance-of-plant systems 4 Provide updated FDSA Chapters 1, 2, 4, March 31, 1987 7, 8, 10, 11, 12, 13, 15, 16, 17
5. Provide remaining FDSA Chapters with Jure ?0, 1987 some editing of the earlier submittals Based upon these milestones, the licensee requested relief from the completion date reouirement for the updated FDSA until June 30, 1987.

The staff has reviewed the licensee's ' request for an exerption from the Haddam Neck Plant updated FDSA submittal date. The staff finds that the licensee's request meets the reautrements identified in the exemption granted on April 11, 1985 and also finds the proposed and completier schedule to be l

- acceptable.

l The NRC staff considered safety aspects of the requested exemption from tFe updated FDSA submittal date. The proposed exemption affects only the j recuired date for updating the FDSA and does not affect the risk of facility l accidents. Thus, the granting of the requested exemption will have no significant impact on plant safety.

1 I

i I

_ . ~ .

= The public interest will be served by granting the exemption since the licensee can continue to use its personnel to complete other work of higher safety significance sooner than would be the case if personnel or other resources were divertad to update the FDSA immediately.

Based on its review, the staff corcludes that issuance of this exemption will have no significant effect on plant safety. Further, this action is in the public interest and good cause has been shown to support the exemption.

Therefore, an exemption until June 30, 1987 is being granted by the staff for the submittal of an updated FDSA for the Haddam Neck Plant. Any significant deviation from the proposed completion schedule (i.e., failure to supply information within 30 days of the scheduled completion date) will be considered a violatier of the ter.ms of the exemption and may result in the voiding of the exemptier. er.d subsequent enforcement / compliance action. The Director, Divisien of Licensing, ONRR, may grant changes to the scheduled milestores if the licensee's recuest is timely and shows good cause for the proposed change.

However, the staff will not consider any subsequent exemption requests beyond the currently scheduled June 30, 1987 completion date.

Pursuant to 10 CFR 51.32, the Commission has determined that the orantirg of this exemption will have no significant impact on the environment (50 FR 48144, November 21,1985).

I

III.

Accordingly, the Commission has determined that, pursuant to 10 CFR 50.12, an exemption is authorized by law and will rot endanger life or property or the common defense and security and is otherwise in the public interest.

Therefore, the Commission hereby approves the following temporary exemption from compliance with 50.71(e).

An updated FSAR containing those original pages of the FDSA that are still applicable plus updated replacement pages shall be filed under the schedule and conditions described in Section II above. The final completion date for the FDSA update effort shall be June 30, 1987. This updated FDSA shall bring the FDSA up to date as of a maximum of 6 months prior to the date of filing the updated FDSA, with subsequent revisions no less frequently than annually thereafter.

Dated at Bethesda, Maryland, this P2nd day of November 1985.

FOR THE NUCLEAR REGULATORY COMMISSION

, ennis M. 'tchfield Acting Director Division of Licensin Office of Nuclear Reactor Regulation l