Application for Amend to License NPF-42,requesting Rev to Bases for TS 3.8.1.1 Re Electrical Power Systems - AC Sources
ML20132G982
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 12/20/1996
From: Muench R
WOLF CREEK NUCLEAR OPERATING CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20132G984 List:
References
ET-96-0106, ET-96-106, NUDOCS 9612270102
Download: ML20132G982 (2)


Text

. _

D

?

.c O,.

A Wf#LF CREEK NUCLEAR OPERATING CORPORATION Richard A. Muench Vice President Engineering i

December 20, 1996 t

ET 96-0106 U. S. Nuc2 ear Regulatory Commission i

ATTN: Document Control Desk Mail Station P1-137 Washington, D. C.

20555

Reference:

Letter dated August 9, 1996, from USNRC, to N.

S.

Carns, WCNOC

Subject:

Change to Bases for Technical Specification 3.8.1.1,

" Electrical Power Systems - A. C. Sources" Gentlemen:

The Reference issued Amendment No.

101 to Facility Operating License No.

)

NPF-42 for Wolf Creek Generating Station (WCGS).

Amendment No. 101 revised i

Technical Specification 3/4.8.1, ' Electrical Power Systems-A. C. Sources," and its associated Bases to achieve an overall improvement in emergency diesel generator reliability and availability.

1 WCGS Technical Specification 3.8.1.1, Action b and Action c specify the required actions to be taken with inoperable A.

C.

electrical power sources.

Action b specifies the required actions to be taken within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> with one inoperable diesel generator.

Action c specifies the required actions to be taken within eight hours with one inoperable diesel generator and one offsite power circuit inoperable.

Review of the Bases, issued by the Reference, has identified that the second paragraph of Bases page B 3/4 8-2 should be revised to better define the time restraints associated with Technical Specification 3.8.1.1, Actions b and c.

The verbiage, which had been revised by Wolf Creek Nuclear Operating Corporation (WCNOC) in the Bases, does not make a distinction between the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> requirements of Action b and the eight hour requirements of Action c.

WCNOC is providing the revised Bases change to reflect this difference and i

requests that the NRC issue the revised Bases page change.

I

\\

9612270102 961220

}

PDR ADOCK 05000482 P

PDR P.O. Box 411/ Burhngton, KS 66839 i Phone: (316) 364-8831 An Equal Opporturuty Employer M FHCVET

I l

ET 96-0107 Page 2 of 2 If you should have any questions regarding this response, please contact me at (316) 354-8831, extension 4034, or Mr. Terry S. Morrill at extension 8707.

1 i

very truly yours, M44/

Richard A. Muench RAM /jad Attachment cc: L. -J. Callan (NRC), w/a j

W. D.

Johnson (NRC), w/a j

J.

F. Ringwald (NRC), w/a J. C.

Stone (NRC), w/a f