Informs That Plant QA Plan Has Been Approved & Implemented
ML20107B416
Person / Time
Site: 05000363
Issue date: 08/04/1971
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Howard E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML18039A986 List: ... further results
References
FOIA-95-258 NUDOCS 9604160301
Download: ML20107B416 (2)


Text

-

.3 UNITED STATES 8.g.

,,,,ou i ATOMIC ENERGY COMMISSION omsion or coseuanes 201 e4s 3960 l

970 BROAD STREET NEWARK. NEW JERSEY 07101 AUG 41971 E. M. Howard, Senior Reactor Inspector Region I~, Division of Compliance JERSEY CENTRAL POWER AND LIGHT C0.

FORKED RIVER 1 C0 REPORT 71-02 The Forked River QA Plan has been approved and implemented. The major contractors have developed detailed procedures and instructions covering the activities now in progress and scheduled in the near future. A schedule for completion of the remaining portions appear commensurate with the project status.

The JCP&L/CE contract has not been signed; however, the QA plan, which will be referenced in the contract, has been approved by GPU/JCP&L.

A site visit will be scheduled when a~ctivities start onsite.

The management exit interview was held on July 23, 1971.

R. Hgward and B. G. Avers were receptive and stated their inten-tions regarding documentation of quality. Documentation require-ments allow for the use of Certificates of Compliance; however, l

GPU stated their intentions were to have all documentation regarding quality on site prior to installation or use.

. F. Heishman Reactor Inspector

)

9604160301 960213 r

PDR FOIA DEKOK95-258 PDR

r:

x

.1

A c.

d,.

3960 AUG 41971 E. M. Howard, Senior Reactor Inspector Region'I, Division of Compliance JER$EY CENTRAL POWER AND LIGHT CO.

FORKED RIVER 1 C0. REPORT 71-02 The Forked River QA Plan has been approved and implemented. The major contractors'have developed detailed procedures and instructions covering the activities now in progress and scheduled--in the near future. A schedule for completion of the remaining portions appear comensurate with the projact status.

The JCP&L/CE contract has not been signed; however, the QA plan, which will be referenced in the contract, has bc::n approved by GPU/JCP&L.

^

A site visit will be scheduled when activities start cnsite.

The management exit interview was held on July 23,1971.

R. Howard and.B. G. Avers were' receptive and stated their inten-tions regarding documentation of quality.

Documentation require-ments allow for the use of Certificates of Compliance; however, I

i GPU stated their intentions were. to have all documentation regarding quality on site prior to installation or use.

R. F. Heishman Reactor Inspector 4