Informs That Safety Parameter Display Sys (SPDS) SAR Will Be Submitted by 841114.Preimplementation Audit Results Received 4 Months Later than Expected.Schedule for Submittal of SPDS Info Requested in NRC Will Be Provided
ML20093C080
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 09/19/1984
From: Warembourg D
PUBLIC SERVICE CO. OF COLORADO
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
P-84372, TAC-51242, NUDOCS 8410100350
Download: ML20093C080 (2)


Text

--

i

-o- l public Service Company W On&nado 2420 W. 26th Avenue, Suite 100D, Denver, CO 80211 September 19, 1984 Fort St. Vrain Unit No. 1 P-84372 Regional Administrator Region IV Nuclear Regulatory Commission 'g g g g g 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012 Attention: Mr. E. H. Johnson L

)

DOCKET N0. 50-267

SUBJECT:

Safety Parameter Display System Safety Analysis Report

REFERENCES:

1) PSC Letter Dated 03/09/84, Warembourg to Collins; P-84079
2) NRC Letter Dated 09/14/84, Johnson to Lee; G-84355

Dear Mr. Johnson:

Public Service Company of Colorado pro date for the SPDS Safety Analysis Report (posed SAR) a tentative of September 20,submittal 1984 in Reference 1. The proposed date was based on PSC's understanding that the results of the NRC SPDS Pre-Implementation Audit of March 12, 1984 would be available within 30 days of the audit for PSC to review and take appropriate action. During the audit exit interview, PSC was informed that only the official audit report represented the final position of the NRC, and that information provided during the audit represented the opinion of the auditors only. In this respect, PSC has been hesitant to finalize the SPDS safety analysis report.

In a recent discussion between Mr. Phil Wagner (NRC) and Mr. M.H. Holmes (PSC), Mr. Wagner indicated that PSC should delay submittal of the SPDS SAR until PSC reviews the results of the SPDS

/

B410100350 840919 dgD PDR ADOCK 0D000267 F PDR i

y ' P-84372 Page 2 audit, since NRC coments could impact the SAR. PSC received the.

"SPDS Pre-Implementation Audit Results for Fort St. Vrain" (Reference

2) on September 18, 1984, four months after the date previously specified by the NRC..

Based on the discussion with Mr. Wagner and the recent receipt of the audit results, PSC is proceeding to take appropriate action on the requests contained in Reference 2. PSC hereby commits to submitting the SPDS SAR on or before November 14, 1984 along with the schedule for submitting information on the SPDS requested in Reference 2.

If you have any questions regarding this matter, please call Mr.M.H.Holmesat(303)571-8409.

Very truly yours, b V' Y M A D. W. Warembourg, Man Nuclear Engineering Division DWW/NB:pa 1

1