Letter Sequence Other |
|---|
|
Results
Other: ML20079Q405, ML20079Q414, ML20082F335, ML20093C080, ML20099J326, ML20099J334, ML20137L067, ML20137L073, ML20137N914, ML20141N187, ML20141N189, ML20203P944
|
MONTHYEARML20079Q4141983-09-30030 September 1983 Safety Parameter Display Sys Program Plan, in Response to Generic Ltr 82-33,Suppl 1 to NUREG-0737 Project stage: Other ML20082F3351983-11-0404 November 1983 Requests Info Re NRC Schedule for Preimplementation Review of Safety Parameter Display Sys.Nrc Review Needed to Enable Further Implementation of NUREG-0737,Suppl 1 Requirements Per Generic Ltr 82-33 Project stage: Other ML20079Q4051984-01-20020 January 1984 Forwards Safety Parameter Display Sys Program Plan & Responds to NRC Re Control Room Design Review in-progress Audit.Audit Proposed to Take Place During Wk of 840312 Project stage: Other ML20137L0731984-08-31031 August 1984 Rev 0 to Procedure EIP-24, Test Procedure for Performance & Isolation Testing of 1E Analog & Digital Isolators Project stage: Other ML20093C0801984-09-19019 September 1984 Informs That Safety Parameter Display Sys (SPDS) SAR Will Be Submitted by 841114.Preimplementation Audit Results Received 4 Months Later than Expected.Schedule for Submittal of SPDS Info Requested in NRC Will Be Provided Project stage: Other ML20099J3161984-11-13013 November 1984 Forwards Response to NRC 840914 Request for Addl Info Re SPDS Sar,Rev 0 to SAR, Fort St Vrain SPDS & Revised SPDS Program Plan Project stage: Request ML20099J3341984-11-13013 November 1984 Revised SPDS Program Plan Project stage: Other ML20099J3261984-11-15015 November 1984 Rev 0 to Fort St Vrain SPDS Sar Project stage: Other ML20141N1891984-12-0707 December 1984 Rev 2 to Procedure EIP-30, Isolator Circuit Differential High Voltage Fault Test Procedure Project stage: Other ML20107C1021985-01-31031 January 1985 Responds to 850131 Request for Addl Info Re SPDS Isolators. Description of Measures Taken to Protect Safety Sys from Electrical Interference Generated by SPDS Will Be Provided by Aug 1985 Project stage: Request ML20137L0671985-08-0101 August 1985 Rev 0 to Procedure PSCC-1-EIP-24, Test Procedure for Qualification of Fort St Vrain Electrical Isolation Sys for Public Svc Co of Co Project stage: Other ML20137L0561985-08-26026 August 1985 Forwards PSCC-1-EIP-24, Test Procedure for Qualification of Fort St Vrain Electrical Isolation Sys... & Rev 0 to EIP-24, Test Procedure for Performance & Isolation Testing..., Per NRC Request for SPDS Review Project stage: Request ML20137N9141985-09-0505 September 1985 Forwards Test Plan Used in Testing SPDS Isolation Equipment from Interference & Provides Action Taken Re Info Needed for NRC Review Project stage: Other ML20141N1871986-02-19019 February 1986 Forwards Response to 860103,14 & 15 Requests for Addl Info Re SPDS Project stage: Other ML20203P9441986-04-29029 April 1986 Clarifies to NRC Re Spds.Forwards Rev 2 to Procedure EIP-30, Isolator Circuit Differential High Voltage Fault Test Procedure Project stage: Other 1984-08-31
[Table View] |
Text
q s
Y
- i pul9ie Service Company f M 2
')g C
1 November 4, 1983 Fort St. Vrain Unit No. 1 P-83360 I
Mr. John T. Collins l@ h Regional Administrator R I 81983 U. S. Nuclear Regulatory Commission
')
Region IV M
611 Ryan Plaza Drive, Suite 1000
. -t Arlington, Texas 76011
^ -W.6 - u
SUBJECT:
NRC Pre-implementation Review of the Safety Parar::ter Display System
REFERENCE:
PSC Letter P-83147 Dated April 14, 1983 Lee to Denton
Dear Mr. Collins:
On April 14, 1983, Public Service Company of Colorado (PSC) provided the NRC with our response to NRC Generic Letter 8C-33 (Supplement I to Nureg 0737).
Included in this letter was our estimated schedule integration and implementation of the Nureg requirements. This schedule was predicated on several factors some of which are not directly controllable by PSC. The reque:ted NRC pre-implementation review of the Safety Parameter Display System (SPDS) is one of these items. This review was requested to take place during September, 1983, but has yet to take place.
Due to the unique technical characteristics of the Fort St. Vrain High Temperature Gas Cooled Reactor, PSC opted to develop our own plant specific SPDS rather than attempt to retrofit a SPDS designed around a PWR or BWR. This project is requiring a substantial effort in terms of manpower and equipment. The schedule for the SPDS also has an impact on the integration and implementation of the other Nureg 0737, Supplement I activities.
It is important that this review take place as soon as possible to avoid future schedule and resource impacts on PSC.
Please contact us regarding the NRCs schedule for providing this review.
b g :D N
l 6 5
)
i 0311280518 831104 PDR ADOCK 05000267
_/
F PDR
=
1 i
I e ;
If you have any questions regarding this matter please call Mr.
Michael Niehoff at (303) 785-2223, extension 403.
Sincerely, l
5%ww I 8
H. L. Brey, Manager Nuclear Engineering Division HLB / MEN /sem i
i f
l f
l l
[
l
_ _ ~ _. _.. _. _ _ _.
_