Revised Monthly Operating Rept for Jul 1991 for North Anna Power Station Unit 2
ML20086B649
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 07/31/1991
From: Mladen C
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
Shared Package
ML20086B609 List:
References
NUDOCS 9111200307
Download: ML20086B649 (1)


Text

.- -

.- . . ~ . , - ~. - . _ - ,

  • . N i

OPERATING DATA REPC21 00CKEY h0.3 50-339 DATE: August 1, 1991 COMPLETED BY: C. Mladen PHONE: (703) 894 2774 (REVISED)

OPERATING STATUS

1. Unit Names................................ North Anna 2
2. . Reporting Periods................,........ July 1991
3. Licensed Thersial Power (MWt) ............. 2893 4 Nameplat e R at ing (Cross MWe): . . . . . . . . . . . . . 947

'5. Design Electrical noting (het MWe):....... 907

6. Maxiam Dependable capacity (Gross MWe):.. 957
7. Mantoun Dependable Capacity (Net MWe) .... 909
8. If changes occur in Capacity Ratings (l' ems No. 3 thru 7) since test report, give reascos:

N/A

9. Power levet to which restricted, if any (Net MWe): _ N/A ,
10. Reasons for restrictions, if any: N/A_,,

This Month T*t D Cumulative

11. Hours in Reporting Period................................ 744.0 5,087.0 93,167.0
12. Nmber of Hours Reactor was Critical..................... 744.0 5,087.0 76,221.3
13. R esc tor R eserve Shutdown Hours . . . . . . . . . . . . . . . . . . . . . . . . . . . 0.0 0.0 5,949.6
14. Hours Generator 0n Line.................................. 744.0 5,087.0 75,321.3 l 15. Unit Reserve Shutdown Hours.............................. 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH)..................... 2,151,780.9 14,708,940.2 201,95E,062.6
17. Gross Electrical Energy Generated (mum).................. 702,472.0 4,857,161.0 66,159,747.0

.18. Net E l ec t r ical Energy Generat ed (HWH ). . . . . . . . . . . . . . . . . . . . 667,3 % .0 4,622,712.0 63,438,192.0f

19. Unit service factor...................................... 100.0% 100.0% 80.8%
20. Unit Availability Factor................................. 100.0% 100.0% 80.8%
21. Unit Cepacity Factor (using MDC Net)..................... 98.7% 100.0% 75.7%
22. Unit Capacity Factor (using DER Net)..................... 98.9% 100.2% 75.1%
23. Forced Outage Rate....................................... 0.0% 0.0% .1.9%
24. Shutdowns Scheduled over Next 6 Months (Type, Date, and Duration of Each): _None l
25. If thutdown at end of Report Period, estimated tinie of Startup N/A

( 26. Units in Test Status (Prior to Coninercial Operation):

t Forecast Achieved

j. INITIAL CRITICALITY l INIf!AL ELECTRICITY COMMERCIAL OPERAlloN 9111200307 911115 l' PDR ADOCK 05000338 l R PDR